Minemakers Limited-Sandpiper Phosphate Project: Resource Upgrade
Published : February 29, 2012
( 0 vote, 0/5 ) Print article
  Article Comments Comment this article Rating Follow Company  
0
Send
0
comment
Keywords :   Market | Namibia | Phosphate |

TORONTO, ONTARIO--(Marketwire - Feb. 29, 2012) - Minemakers Limited (TSX:MAK)(News - Market indicators)(NSX:MMS) -

HIGHLIGHTS

  • A recently completed resource development programme of gravity core sampling in the northern half of the initial 8km x 20km target recovery area has resulted in an upgraded mineral resource estimate with:

    • An increase in Indicated Mineral Resource to 220.3Mt at 20.13% P2O5.
    • Initial delineation of Measured Mineral Resource of 4.1Mt at 20.45% P2O5.
             
15%
cut-off
Inferred
Total
(dry)
P2O5
 Grade
Indicated
Total
(dry)
P2O5
 Grade
Measured
Total
(dry)
P2O5
 Grade
Aug 2011 1.717 Bt 19.0% 73.9 Mt 20.57% - -
Feb 2012 1.607 Bt 18.9% 220.3 Mt 20.13% 4.1 Mt 20.45%
  • The resource development sampling programme has delineated sufficient resources in the Indicated Resource category to support a mine development plan for the definitive Feasibility Study, as planned.

There is a very high rate of conversion from Inferred Resource to the higher confidence categories of Indicated and Measured Resource. Within the sampled area, the previous 109.5Mt Inferred Resource estimate has been replaced by estimates of 146.4Mt Indicated Resource and 4.1Mt Measured Resource. This greater than 100% conversion rate can be attributed to a 1:1 conversion of the Inferred to Indicated category Resource combined with a greater thickness of the resource due to deeper penetration into the mineralized sediments by an improved gravity coring system. It increased penetration from the previous 1.45m to 1.93m depth in the recent programme. Phosphate mineralization is generally still open at depth to the west and south of this newly tested resource area.

Background

Minemakers Limited (TSX:MAK)(News - Market indicators)(NSX:MMS) ("Minemakers" or "the Company"), is pleased to announce an important upgrade of phosphate resources in the Sandpiper Phosphate Project offshore Namibia. The Company advises that the results of the definitive Feasibility Study ("FS") resource sampling programme in the initial target recovery area of the Sandpiper Project area have resulted in a substantial upgrade to the Indicated Resource Category as well as an overall increase of the total mineral resource tonnage estimate.

The Sandpiper Project is owned by Namibian Marine Phosphate (Pty) Limited ("NMP"), a Joint Venture between Minemakers, UCL Resources Limited (ASX:UCL) and Namibian partner Tungeni Investments cc.

The latest resource upgrade sampling programme in the initial target recovery area of the Sandpiper Project area (Figure 1) has resulted in a substantial increase in the Indicated Resource category estimate as well as an increase of the total mineral resource estimate. The overall results continue to meet high project expectations, particularly with respect to consistent grade and the high conversion rate to the higher resource categories. The world class dimension of the Sandpiper Project has been further confirmed.

To view Figure 1: Project Location Map, please visit the following link: http://media3.marketwire.com/docs/Figure_1Project_Location.pdf.

Resource Upgrade

The revised estimate of the phosphate mineral resource by independent geostatistical consultant Dr Alwyn E Annels, FIMMM, C.Eng. now stands at: 

Resource 15% Cut off
Category Million tonnes P205 Grade
Measured 4.093 20.45%
Indicated 220.349 20.13%
Inferred 1,607.8 18.9%

As previously announced, the Sandpiper deposit comprises two main layers with phosphate mineralisation. The upper layer (Layer 1) tends to be relative shelly, grading downwards into a second generally higher grade sandy layer (Layer 2) which overlies a poorly mineralized footwall clay.

Indicated and Measured Mineral Resources have been calculated for the initial target recovery area in ML170 using combined assay and thickness data for Layers 1 and 2.

2D Inverse Distance Weighting (IDW) methods (to the power 3) were used to interpolate thicknesses, grade, specific gravities and moisture content for 200 m N-S x 200 m E-W blocks. Extrapolation has been constrained by the search parameters used. The dimensions of the search areas were controlled by examination of the distribution and trends of data, the numbers of samples captured and by the results of current geostatistical studies.

Sample Programme

Gravity cores were recovered from 398 new sample sites on a 400 x 400m sample grid located in the northern half of the initial target recovery area of the Sandpiper Project Area with the objective of upgrading the confidence in the resource base to support the definitive FS. This area lies in water depths of less than 225m which is targeted for dredging using Jan De Nul's vessel MV Christobal Colon. The improved gravity coring system achieved an overall greater penetration than the previous phases of the regional resource sampling completed in 2009, 2010 and 2011 with an average sampling penetration depth of 1.93m (previously 1.45m) and maximum penetration of just over 3 metres. Sub-samples were taken from the new cores and submitted for P2O5 assay analysis in accordance with standard procedures which include duplicate samples as well as comparative testing by independent laboratories. (Sample sites are shown on Figure 2.)

To view Figure 2: Sample Locations Map, please visit the following link: http://media3.marketwire.com/docs/Figure_2Sample_Locations.pdf.

Future Work

The next phase of resource development sampling will focus on further upgrading the current Indicated Mineral Resource in this initial target recovery area to the Measured Resource category for further support to the definitive FS financial modelling and feasibility assessment. This work is currently in progress and comprises closer spaced infill sampling and analysis.

Andrew Drummond, Executive Chairman

The qualified person in relation to this press release is Andrew Drummond, who is Executive Chairman of the Company and a Fellow of The Australian Institute of Mining and Metallurgy and a Member of the Australian Institute of Geoscientists. Mr Drummond has sufficient experience deemed relevant to the style of mineralisation and type of deposit under consideration and to the activity which he is undertaking to qualify as a Competent Person as defined in the 2004 Edition of the 'Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves' and a 'Qualified Person' as defined in National Instrument 43-101 - Standards of Disclosure for Mineral Projects ("NI43-101"). Mr Drummond consents to the inclusion in the report of the matters based on his information in the form and context in which it appears.

For further information regarding the Sandpiper Marine Phosphate Programme, please refer to Minemakers' NI43-101 compliant technical report entitled "Updated Estimation of Phosphate Resources for the Sandpiper Project in EPLs 3415 and 3323, Namibia", dated March 11, 2011 and available on SEDAR at www.sedar.com.

Cautionary Statement Regarding Forward-Looking Information

All statements, trend analysis and other information contained in this report relative to markets for Minemakers' trends in resources, recoveries, production and anticipated expense levels, as well as other statements about anticipated future events or results constitute forward-looking statements. Forward-looking statements are often, but not always, identified by the use of words such as "seek", "anticipate", "believe", "plan", "estimate", "expect" and "intend" and statements that an event or result "may", "will", "should", "could" or "might" occur or be achieved and other similar expressions. Forward-looking statements are subject to business and economic risks and uncertainties and other factors that could cause actual results of operations to differ materially from those contained in the forward-looking statements. Forward-looking statements are based on estimates and opinions of management at the date the statements are made. Minemakers does not undertake any obligation to update forward-looking statements even if circumstances or management's estimates or opinions should change. Investors should not place undue reliance on forward-looking statements.

ABN 48 116 296 541



Minemakers Limited
Mr Andrew Drummond
Executive Chairman
+61 8 9264 7000
+61 8 9264 7099 (FAX)
www.minemakers.com.au
or
Magnus Investor Relations & Corporate Communication
Mr John Gardner
+61 413 355 997
Data and Statistics for these countries : Namibia | All
Gold and Silver Prices for these countries : Namibia | All

MineMakers Limited

DEVELOPMENT STAGE
CODE : MAK.AX
Follow and Invest
Add to watch list Add to your portfolio Add or edit a note
Add Alert Add to Watchlists Add to Portfolio Add Note
ProfileMarket
Indicators
VALUE :
Projects & res.
Press
releases
Annual
report
RISK :
Asset profile
Contact Cpy

MineMakers is a tin and tungsten exploration company based in Australia.

MineMakers develops tin, tungsten, diamonds and phosphate in Australia, in Namibia and in South Africa, and holds various exploration projects in Australia, in Namibia and in South Africa.

Its main assets in development are SAVANNA in South Africa, SANDPIPER/MEOB JV in Namibia and WONARAH in Australia and its main exploration properties are ANCHOR ( TASMANIA), MOINA, VAAL RIVER ALLUVIAL and BRONKHORSTFONTEIN in South Africa and ABERFOYLE, STOREY'S CREEK, LUTWYCHE, ROYAL GEORGE, GREAT PYRAMID, CASTLE CAREY, TASMANIA UNITED URANIUM and LUDERITZ PROJECT - ML111 DFI JV in Namibia.

MineMakers is listed in Australia and in Germany. Its market capitalisation is AU$ 34.4 millions as of today (€ 32.4 millions).

Its stock quote reached its highest recent level on April 18, 2008 at AU$ 2.95, and its lowest recent point on March 20, 2015 at AU$ 0.06.

MineMakers has 275 360 000 shares outstanding.

Your feedback is appreciated, please leave a comment or rate this article.
Rate : Average note :0 (0 vote) View Top rated
 
Corporate Presentations of MineMakers Limited
5/27/2008Article on MAK - Resource Stocks
Annual reports of MineMakers Limited
Annual Report to Shareholders
2009 Annual Report
Nominations of MineMakers Limited
7/11/2013Changes of Registered Office and Appointment of Joint Compan...
5/8/2013Resignation of Non-Executive Chairman
4/30/2012Appoints Cliff Lawrenson as CEO and Managing Director
2/9/2009Investor Relations Manager Appointed
6/23/2008Senior Executive Appointment
2/14/2008(Wonarah)Wonarah Study Managers Appointed
Financials of MineMakers Limited
9/23/2013and Controlled Entities Annual Financial Report
Project news of MineMakers Limited
9/24/2015Baobab Project acquisition completes
6/3/2013(Wonarah)Market Update-Progress on Wonarah Project and with JDCPhosph...
9/7/2011Progressing Two hosphate Projects
3/15/2011(Wonarah)Wonarah Phosphate Project Positive Dry Kiln Testwork Progres...
2/28/2011(Wonarah)Wonarah Phosphate Project Historic Mining Agreement Signed
3/11/2009(Wonarah)Wonarah Permitting Application Lodged, More Extensive DSO Gr...
2/27/2009(Wonarah)Outstanding Drill Results Continue at Wonarah
1/9/2009(Wonarah)MOU Signed on Wonarah Railway Study
12/18/2008(Wonarah)Wonarah Phosphate Project Resource Increase, Mine Planning a...
8/29/2008(Wonarah)Wonarah resource drilling completed
8/26/2008(Wonarah)Wonarah Granted Major Project Status by NT Government
8/14/2008High Grade Phosphate Price
7/17/2008(Wonarah)Audio Stream Wonarah Phosphate Project Update
7/14/2008(Wonarah)Successful Arruwurra Drilling Results Open Development Alter...
6/17/2008(Wonarah)Settlement of Purchase of Wonarah Clawback
6/3/2008(Wonarah)Secures 100% Equity and Control of Development of the Wonara...
5/13/2008(Wonarah)Concerns About Trading Practices in Minemakers and Wonarah P...
4/14/2008(Wonarah)Wonarah Drilling Update
3/14/2008(Wonarah)Wonarah Drilling Approvals Secured Drilling to Begin on Sche...
2/18/2008(Wonarah)Early Start to Metallurgical Testwork at Wonarah
1/9/2008(Wonarah)Rock Phosphate Price Rockets to US$200/tonne - Feasibiity Pl...
Corporate news of MineMakers Limited
11/26/2015Change of Director's Interest Notice
11/2/2015Final Share buy-back notice - Appendix 3F
10/26/2015Quarterly Activities Report
9/30/20152015 Annual Report
9/28/2015Initial Director's Interest Notice
9/28/2015Appendix 3B
9/28/2015Notice under section 708A(5)(e) of Corporations Act
9/25/2015Initiation of research coverage by Foster Stockbroking
9/22/2015Baobab Project Update
9/2/2015Africa Down Under Presentation
8/13/2015Corporate Video Presentation
7/30/2015Fourth Quarter Activities Report
7/29/2015Minemakers Limited: Incentive Structure for Advisors
7/20/2015Notice of General Meeting/Proxy Form
7/16/2015Minemakers Limited: Sale of South African Legacy Assets
7/16/2015Sale of South African Legacy Assets
7/2/2015Baobab Project - Local Community Engagement
6/29/2015Minemakers Limited: Appointment of Advisor
6/29/2015Appointment of Advisor
6/16/2015Investor Update
4/7/2015Appendix 3B - Expiry of unlisted options
4/7/2015Market Update
3/17/2015Half Year Accounts
2/2/2015Quarterly Activities Report
10/17/2014Minemakers Announces On-Market Share Buy-Back
10/16/2014Quarterly Activities Report
3/12/2014Appendix 3Y
3/6/2014Additional Investment in JDCPhosphate, Inc.
10/30/2013Quarterly Activities and Cashflow Reports
10/15/2013Notice of Annual General Meeting and Proxy Form
9/9/2013Progress on commissioning of JDCPhosphate's IHP Demonstratio...
6/25/2013Completion of Sale of Unmarketable Parcels of Shares
6/20/2013TNT Mines Limited and Niuminco Group Limited
5/3/2013Sale of Unmarketable Parcels of Shares
4/24/2013Releases Quarterly Activities Report
4/16/2013(Wonarah)Updated Mineral Resource Statement in Connection With its Wo...
1/31/2013December 2012 Quarterly Activities Report
9/24/2012Exchange Release-Request for Trading Halt
8/13/2012(Wonarah)Wonarah Strategic Partnership Process-Appointment of Indian ...
6/7/2012(Wonarah)Update on Wonarah-Strategic Partnership Process Commenced
6/7/2012(Wonarah): Update on Wonarah-Strategic Partnership Process Commenced
4/18/2012Audio Broadcast: Minemakers releases positive Feasibility r...
4/16/2012Request for Trading Halt-Minemakers Limited
4/10/2012Extension of Minemakers' Offer Update-ASIC Relief Obtained
4/4/2012Extension of Minemakers' Offer
3/19/2012Clarification of Press Speculation Regarding NMDC
3/6/2012Bidders Statement Completion of Despatch and BRR Interview
2/29/2012-Sandpiper Phosphate Project: Resource Upgrade
2/21/2012Takeover by Minemakers Limited-Bidders Statement
2/9/2012-New Board Appointment: Mr Dick Block
2/3/2012Response to ASX Query
1/13/2012Sandpiper Phosphate Project Namibia Lodgement of Environment...
11/28/2011Investor Presentation Annual General Meeting
10/5/2011(Wonarah)-Wonarah Phosphate Deposit: Significant Resource Additions f...
7/19/2011Audio Broadcast
7/4/2011Record Date for "In-Specie" Distribution of TNT Mines Limite...
6/8/2011Sandpiper Joint Venture Definitive Feasibility Study Progres...
6/2/2011(Wonarah)Wonarah Phosphate Development MOU Signed with India's NMDC L...
5/24/2011Termination of Verte Mandate
5/18/2011(Wonarah)Media Speculation Regarding an Indian MOU for Wonarah
12/22/2009Audio Broadcast First Phosphate Mined at Wonarah
3/5/2009Announces Scrip Offer for Bonaparte Diamond Mines
1/20/2009Quarterly Activites Report
9/17/2008(Audio) broadcast with Mr Andrew Drummond, Managing Director
7/29/2008June 2008 Quarterly Report
5/29/2008Tasmanian Tin and Tungsten Update
4/2/2008Clarifications Concerning Company Presentation dated 31/3/08
3/17/2008Further Strong Increases in Rock Phospate Prices
3/10/2008Raises $11.55M to Advance Work on its Projects
2/29/2008Tay-Munglinup Project Update
2/27/2008Response to ASX Share Price Query
1/9/2008Audio Stream - Rock Phosphate Price Rockets to US$200/Tonne
12/13/2007Moina Fluorspar-Tungsten-Tin Base Metals Project Update
11/28/2007Audio Stream - Uranium Exploration
11/27/2007Positive Results from Tasmanian Uranium Exploration
10/24/2007 Quarterly Activities Report Sept 2007
10/5/2007Issue Closes Over Subsribed
9/20/2007(Audoi) Stream Encouraging First Drill Testing of Tasmanian ...
9/19/2007Encouraging First Drill Testing of Tasmanian Castle Carey Ur...
8/6/2007Audio Stream Final Magnetite Assays for West Southdown and F...
8/2/2007Final Magnetite Assays, West Southdown and Frankland Magneti...
7/24/2007Highly encouraging uranium assays from Rossarden district ur...
7/16/2007First Magnetite Assays, West Southdown Iron Ore Project
7/3/2007Drill Testing Storeys Creek & Wolfram Bergbau MOU Extension
Comments closed
 
Latest comment posted for this article
Be the first to comment
Add your comment
AUSTRALIA (MAK.AX)BERLIN (WTP.BE)
0.125-10.71%0.010+0.00%
AUSTRALIA
AU$ 0.125
11/25 07:58 -0.020
-10.71%
Prev close Open
0.140 0.140
Low High
0.125 0.140
Year l/h YTD var.
 -  -
52 week l/h 52 week var.
- -  0.125 -%
Volume 1 month var.
437,256 -%
24hGold TrendPower© : -1
Produces
Develops Diamonds - Phosphate
Explores for Fluorite - Tin - Tungsten - Uranium
 
 
 
Analyse
Interactive chart Add to compare
Interactive
chart
Print Compare Export
Last updated on : 12/9/2010
You must be logged in to use the porfolio and watchlists (free)
Top Newsreleases
MOST READ
Annual variation
DateVariationHighLow
 
5 years chart
 
3 months chart
 
3 months volume chart
 
 
Mining Company News
Plymouth Minerals LTDPLH.AX
Plymouth Minerals Intersects Further High Grade Potash in Drilling at Banio Potash Project - Plannin
AU$ 0.12-8.00%Trend Power :
Santos(Ngas-Oil)STO.AX
announces expected non-cash impairment
AU$ 7.44-0.53%Trend Power :
OceanaGold(Au)OGC.AX
RELEASES NEW TECHNICAL REPORT FOR THE HAILE GOLD MINE
AU$ 2.20+0.00%Trend Power :
Western Areas NL(Au-Ni-Pl)WSA.AX
Advance Notice - Full Year Results Conference Call
AU$ 3.86+0.00%Trend Power :
Canadian Zinc(Ag-Au-Cu)CZN.TO
Reports Financial Results for Q2 and Provides Project Updates
CA$ 0.12+4.55%Trend Power :
Stornoway Diamond(Gems-Au-Ur)SWY.TO
Second Quarter Results
CA$ 0.02+100.00%Trend Power :
McEwen Mining(Cu-Le-Zn)MUX
TO ACQUIRE BLACK FOX FROM PRIMERO=C2=A0
US$ 10.36+0.97%Trend Power :
Rentech(Coal-Ngas)RTK
Rentech Announces Results for Second Quarter 2017
US$ 0.20-12.28%Trend Power :
KEFIKEFI.L
Reduced Funding Requirement
GBX 0.63-1.87%Trend Power :
Lupaka Gold Corp.LPK.V
Lupaka Gold Receives First Tranche Under Amended Invicta Financing Agreement
CA$ 0.05+0.00%Trend Power :
Imperial(Ag-Au-Cu)III.TO
Closes Bridge Loan Financing
CA$ 2.19+3.30%Trend Power :
Guyana Goldfields(Cu-Zn-Pa)GUY.TO
Reports Second Quarter 2017 Results and Maintains Production Guidance
CA$ 1.84+0.00%Trend Power :
Lundin Mining(Ag-Au-Cu)LUN.TO
d Share Capital and Voting Rights for Lundin Mining
CA$ 14.70-0.88%Trend Power :
Canarc Res.(Au)CCM.TO
Canarc Reports High Grade Gold in Surface Rock Samples at Fondaway Canyon, Nevada
CA$ 0.25+2.04%Trend Power :
Havilah(Cu-Le-Zn)HAV.AX
Q A April 2017 Quarterly Report
AU$ 0.16-2.94%Trend Power :
Uranium Res.(Ur)URRE
Commences Lithium Exploration Drilling at the Columbus Basin Project
US$ 6.80-2.86%Trend Power :
Platinum Group Metals(Au-Cu-Gems)PTM.TO
Platinum Group Metals Ltd. Operational and Strategic Process ...
CA$ 2.29-0.43%Trend Power :
Devon Energy(Ngas-Oil)DVN
Announces $340 Million of Non-Core Asset Sales
US$ 45.56-0.44%Trend Power :
Precision Drilling(Oil)PD-UN.TO
Announces 2017Second Quarter Financial Results
CA$ 8.66-0.35%Trend Power :
Terramin(Ag-Au-Cu)TZN.AX
2nd Quarter Report
AU$ 0.03+0.00%Trend Power :