Avnel Announces New Mineral Resource Estimate and Preliminary Economic Assessment for its Kalana Gold Project in Southwest Mali
Published : March 24, 2014
( 0 vote, 0/5 ) Print article
  Article Comments Comment this article Rating Follow Company  
0
Send
0
comment

Avnel Announces New Mineral Resource Estimate and Preliminary Economic Assessment for its Kalana Gold Project in Southwest Mali

/NOT FOR DISTRIBUTION TO U.S. NEWSWIRE SERVICES OR FOR DISSEMINATION IN THE UNITED STATES/

ST. PETER PORT, GUERNSEY, March 24, 2014 /CNW/ - Avnel Gold Mining Limited ("Avnel" -  TSX: AVK) is pleased to announce the results of a Mineral Resource Estimate ("MRE") and Preliminary Economic Assessment ("PEA") on its Kalana gold deposit located in the northwest of its 387.4 kmKalana Exploitation Permit in Southwest Mali.

"The robustness of the results of the MRE and PEA indicates the potential for the development of a new mine at Kalana and Avnel intends to immediately commence a pre-feasibility study and, assuming that to be positive, a feasibility study" commented Howard Miller, CEO of Avnel.  "The MRE demonstrates a viable project with 1.25 million ozs. at a grade of 4.53 g/t in the Indicated Resource category and 0.25 million ozs. at a grade of 3.76 g/t in the Inferred Resource category.  Whilst the PEA is by definition a preliminary assessment, the 2 year payback and project NPV (10% discount) of US$194 million after tax and imputed interest is very encouraging".

HIGHLIGHTS:

In-situ Mineral Resource estimate:

  • Indicated Resource 8.5 million tonnes with a gold grade of 4.53 g/t for contained gold of 1.25 million ozs. (cut-off grade of 0.9 g/t).
     
  • Inferred Resource 2.1 million tonnes at a gold grade of 3.76 g/t for contained gold of 0.25 million ozs. (cut-off grade of 0.9 g/t).

Preliminary Economic Assessment:

  • Gold production averaging 138,000 ozs. gold per year for the first 4 years and then 98,000 ozs. of gold per year over the remaining life of mine.
     
  • After tax and imputed interest net present value (10%) of US$194 million with a 53% project internal rate of return.
     
  • All in project costs including capital cost (excluding taxes for the project and imputed interest) of US$679 per oz.
     
  • 14 year mine life at a throughput rate of 1,200,000 tonnes p.a. at a head grade of 3.1g/t Au.
     
  • Based on a cut-off grade of 0.9 g/t and a gold price of US$1,110 per oz.
     
  • Recovered gold production of 1.46 million ozs.
     
  • Total tonnes of waste to be mined 128 million.
     
  • Conventional gravity and CIL process plant achieving 93% recovery for the pit and 83% for tailings.
     
  • Total capital of US$188 million.

Both of the studies were undertaken by Snowden Mining Industry Consultants Pty Ltd. and an NI 43-101 Technical Report  is in the course of being completed and will be filed on or before March 31, 2014.  The Snowden qualified persons are Mr. Ivor Jones in respect of the MRE and Mr. Allan Earl in respect of the PEA.  Both are independent of Avnel and have reviewed and approved their respective content of this press release.

Avnel reported in a March 2013 press release that IAMGOLD had indicated that its exploration program has identified an unconstrained resource in the indicated and inferred categories of 1.5 million ozs. above the 150m level and a potentially viable open pit resource in excess of 1.0 million ozs. of gold at an average grade of approximately 2.1 g/t. This was based on a gold price of US$1,600 per oz. and a cut-off grade of between 0.5 g/t and 0.6 g/t.

Snowden has completed the MRE utilising approximately 25% additional drillhole data that was not available to IAMGOLD when completing their preliminary resource estimate. In addition Avnel has completed a re-assay program in 2013/2014 utilising the LeachWell method using 2kg samples that was recommended by Snowden, and acknowledged by IAMGOLD, as an appropriate methodology to address the underestimation of gold grades using conventional 50g fire assays. The results show an improvement in grades of between 25% and 50% compared to the 50g fire assays. Snowden used the new assay results and complete drill data to generate a robust resource model. Snowden used multiple indicator kriging ("MIK") to estimate grades. To calculate the MRE, the cut-off grade used was 0.9 g/t based on an assumed gold price of US$1,110/oz. The MRE shows the positive impact of the additional data and the higher cut-off grade.

On March 18, 2014 Snowden reported to Avnel that:

"The Mineral Resources for the in-situ Kalana Main Project gold deposit (0.9 g/t gold cut-off) total:

  • 1.25 million ounces of gold in the Indicated Mineral Resource category (8.5 million tonnes grading 4.53 grams of gold per tonne).
     
  • 0.25 million ounces of gold in the Inferred Mineral Resource category (2.1 million tonnes grading 3.76 grams of gold per tonne).

The Mineral Resources for the Kalana tailings (no grade cut-off applied) totals:

  • 0.04 million ounces of gold the Indicated Mineral Resource category in historic and active tailings (0.7 million tonnes grading 1.80 grams of gold per tonne).

The Mineral Resource estimate for the Kalana Main Project incorporates data from all exploration drilling completed to date.  Table 1 and Table 2 summarise the 2014 Kalana Main Project Mineral Resource estimate.

The Preliminary Economic Assessment (PEA) of the Kalana Main Project Mineral Resources identified the potential for a mine life of 14 years recovering 1.46 million ounces:

  • a two year construction period, with first production anticipated in H2 2017
     
  • gold production averaging 138,000 ounces gold per year for the first four years and then 98,000 ounces gold per year over the remaining life of mine
     
  • total capital of US$188 million
     
  • all-in sustaining cost of US$577 per ounce (including total operating costs and sustaining capital costs)
     
  • all-in cost for the project of US$679 per ounce (including total operating costs and total capital costs)
     
  • after tax net present value after tax (NPV 10%) of US$194 million with a 53% project internal rate of return
     
  • a payback period of about 2 years after the start of production.

Mineral Resource modelling and estimation – the in-situ deposit

Mineralisation at the gold deposit occurs over an area of approximately 1,200 m in an east–west direction by 1,000 m in a north-south direction.  The attitude of the veins varies from north-south to northeast-southwest and dips at low to moderate angles respectively to the east or the south.

Avnel and Snowden used Avnel's interpretation of the mineralisation at Kalana as the basis of the resource estimate.  The deposit has been divided into a number of structural domains and vein packages which comprise varying amounts of gold mineralisation.  Mineralisation within these domains is characterised by a mix of barren rock with variably mineralised parts including continuous veins and stockwork mineralisation.

The input data for the resource estimate comprises information from 185 Diamond drillholes, 19 underground Diamond drillholes and 567 RC drillholes totalling 132,391 m.

All data was composited to the nominal sample length of 1 m prior to analysis and estimation.  Grade estimation was completed using Multiple Indicator Kriging into 10 m by 10 m by 5 m blocks.  Indicator variograms were modelled up to the 95th percentile of the data with a mathematical model used to define the top end of the grade distribution.  The result of this estimation method is that, while no top cut is used to limit the higher grades, the higher grades are limited in their influence by using a mathematical model for the higher grades in the dataset.

Following the MIK estimation, the results were post-processed to provide a proportion of the block and the grade of this portion above the 0.9 g/t Au cut-off grade (which was defined separately as a part of the preliminary economic assessment).  Subsequently the estimate was depleted for historic production tonnes using a manual deduction, even though the estimate did account for this through the modelling where the reef was not represented in the drilling (drilling through stopes).

The March 2014 Mineral Resource estimate for the Kalana Main Project gold deposit was completed by Snowden on behalf of Avnel.  The Mineral Resources are classified as Indicated and Inferred Resources in accordance with the CIM Standards on Mineral Resources and Reserves, Definitions and Guidelines prepared by the CIM Standing Committee on Reserve Definitions and adopted by CIM Council.

Classification of the Mineral Resource comprised an evaluation of data quality, confidence in the geological interpretation, a test of the reasonableness of the assumption of economic extraction, review of statistical information and comparisons of model grade estimates versus input data grades.  Where grades were estimated in the first search pass (90 m by 60 m by 10 m) and more than 10% of the block was estimated as above the cut-off grade, it was considered that the confidence in the model was sufficient to define an Indicated Mineral Resource.  The remainder of the estimates within the pit optimisation shell were classified as an Inferred Mineral Resource.

The Mineral Resources are reported above a cut-off grade of 0.9 g/t Au.  This cut-off grade was defined as an output of the preliminary economic assessment based on a gold price of US$1,110 per ounce.

The tailings Mineral Resource

The quantity and grade of tailings is compiled from a combination of the evaluation of the tailings mineral resource in June 2004, with the addition of tailings since 2005 (tonnes and grade as measured from production).  In May 2004, a sampling programme was completed on the 1985 to 1991 Russian tailings dam.  The sampling was performed by using an auger and taking 1 m vertical samples on a grid of 10 m by 10 m.  The tonnage of the tailings dam has been estimated from the historical production records with the addition of the tailings from ore milled in the period January to June 2004.  No survey measure of the tailings dam is possible as there is no survey record of the original topographic base for the dam.  The average sample gold grade for the tailings dam was used for the June 2004 resource estimate.  The tailings resource at that time was reported as 234,000 tonnes at 1.9 g/t Au in the Measured category.

Since July 2004, the tonnes and grade of added material to the tailings dam has been measured from the output from production.  This has been reported as 421,000 tonnes at 1.73 g/t Au.

In 2012, IAMGOLD sampled the tailings dams on a grid of between 10 m by 10 m and 20 m by 20 m (depending on location) with an average depth of 3.6 m and maximum depth of 5 m.  Whilst this sampling did not always reach the base of the tailings, the assays for the samples indicated the grade for the tailings mineral resource are conservative and support the confidence that the grades in the mineral resource can be achieved.

Snowden is therefore of the opinion that the confidence in the estimation of the tailings Mineral Resource is sufficient so that it can be classified as an Indicated Mineral Resource.

Kalana Main Project Mineral Resource

The Mineral Resource estimate has been based on information collated from extensive drilling and underground workings at the Kalana Gold Mine.  The mineralisation is hosted in narrow shallow dipping quartz and associated inter-vein mineralisation defining together a vein package.  It is a Paleoproterozoic orogenic gold deposit emplaced in Birimian terranes of the West African Craton.

Table 1            Kalana Main Project in-situ Mineral Resource estimate - March 2014

Classification

Tonnes

(millions)

Gold Grade

(g/t)

Contained

Gold

(million ounce)

Indicated Resource

8.5

4.53

1.25

Inferred Resource

2.1

3.76

0.25

(1) Mineral Resources which are not Mineral Reserves do not have demonstrated economic viability.  The estimate of Mineral Resources may be materially affected by environmental, permitting, legal, marketing, or other relevant issues.  The Mineral Resources in this news release were estimated using the Canadian Institute of Mining, Metallurgy and Petroleum (CIM), CIM Standards on Mineral Resources and Reserves, Definitions and Guidelines prepared by the CIM Standing Committee on Reserve Definitions and adopted by CIM Council.
(2) The quantity and grade of reported Inferred resources in this estimation are uncertain in nature and there has been insufficient exploration to define these Inferred Resources as an Indicated or Measured Mineral Resource and it is uncertain if further exploration will result in upgrading them to an Indicated or Measured Mineral Resource category.
(3) Contained metal figures and totals may differ due to rounding of figures.
(4) Based on a cut-off grade of 0.9 grams of gold /tonne.

Table 2            Kalana Gold Mine tailings Mineral Resource estimate - March 2014

Category

Tonnes

(millions)

Gold Grade

(g/t)

Contained

Gold

(million ounce)

Indicated Resource

0.7

1.80

0.04

Note: Footnotes (1), (2), (3) as per Table 1.  No cut-off grade applied.

Preliminary Economic Assessment

The Kalana Main Project PEA is a study which includes an economic analysis of the potential viability of the Kalana Main Project Mineral Resources.  It is not a pre-feasibility study (PFS) or feasibility study (FS) and cannot be used to support mineral reserves.  It is preliminary in nature and includes the use of Inferred Mineral Resources that are considered too speculative geologically to have reliable technical and economic considerations applied to them that would enable them to be categorised as Mineral Reserves.  There is no certainty that the PEA will be realised and actual results may vary, perhaps materially.  Mineral Resources that are not Mineral Reserves do not have demonstrated economic and technical viability.

The Kalana Main Project PEA is subject to a number of important assumptions, including, among others, that a competent mining contractor can mine the mineralisation in a selective manner that achieves, or betters, the assumed dilution and recovery factors, that suitable locations can be identified for waste dumps and tailings storage facilities, that further test work will confirm the metallurgical recoveries, that there is no material increase in capital and operating costs, forecast construction schedules can be achieved, an adequate supply of water is available and can be exploited, environmental and social impact studies will be completed in an acceptable timeframe, all required permits will be obtained in a timely manner and the Company will continue to have the support of local communities and regulators.

The March 2014 PEA for the Kalana Main Project was completed by Snowden on behalf of Avnel.  The findings of Snowden's assessment are:

  • A 14 year mine life recovering 1.46 million ounces and comprising:
     
    • a three stage open pit containing 15.1 million tonnes at 3.2 grams of gold per tonne and 128 million tonnes of waste.
       
    • 655,000 tonnes of tailings at 1.8 grams of gold per tonne.
       
    • a 1.2 million tonnes per year of conventional gravity and CIL process plant achieving 93% recovery for saprolite, saprock and fresh material and 83% for tailings.
       
  • About a two year construction period, with first production anticipated in H2 2017.
     
  • Gold production averaging 138,000 ounces gold per year for the first four years and then 98,000 ounces gold per year over the remaining life of mine.
     
  • Total capital of US$188 million comprising:
     
    • US$134 million plant, mine services and infrastructure.
       
    • US$15 million pre-strip.
       
    • US$29 million sustaining capital and community.
       
    • mine closure US$10 million.
       
  • All-in sustaining cost for the project of US$577 per ounce (based on total operating costs, sustaining capital and mine closure costs).
     
  • All-in cost for the project of US$679 per ounce (based on total operating and total capital costs).
     
  • After tax net present value after tax (NPV 10%) of US$194 million with a 53% project internal rate of return.
     
  • Payback on construction capital and pre-production costs is expected to be 2 years after the start of production.

The Kalana Main Project PEA is based on open pit mining using small-scale mining equipment to selectively mine the economic quartz and associated inter-vein mineralisation with larger equipment used in waste.  The processing method will be conventional gravity concentration and CIL.  The open pit will be mined in three stages with preferential processing of higher grades and lower grade material stockpiled for later processing.  To account for dilution and losses during the mining process, the mineral resource had a 50% tonnage modifying factor and a mining recovery modifying factor between 92.5% and 95% applied in the mine production schedule.  Only Inferred and Indicated Mineral Resources (which were constrained by the optimised open pit) were included in the mine production schedule.  A tailings Mineral Resource from historic operations will be recovered and processed in the first year of production.

Test work and historic operations show the work index for saprolite and fresh rock will be in a range of 11 kwh/t to 17 kwh/t.  Metallurgical tests have shown gravity gold recoveries in the range 40% up to 95% in saprolite and fresh rock.  Operating experience has shown gravity recoveries of between 80% and 92%.  Cyanide leach test work of saprolite and fresh mineralisation has achieved up to 95% gold recovery from mineralisation ground to 80% passing 75 micron.  Gold recovery of 93% using a combination of gravity recovery and CIL has been used in the PEA.

The optimised pit shell was defined using standard optimisation software, a gold price of US$1,110 per ounce, mining and processing costs that reflect the weathering profiles and general and administrative (G&A) costs.  Overall pit-slope angles range from 37º to 45º depending on the weathering profile.  The production schedule was constrained to an advance rate of 30 vertical meters per year.

Over the life of mine, mining costs are estimated to average US$3.32 per total tonne mined.  Processing and administration costs are estimated to average US$20.87 per tonne processed.  Using a discount rate of 10%, the Kalana Main Project open pit has an estimated project NPV (after allowance for tax and interest) of about US$194 million and a project internal rate of return (IRR) of 53% after accounting for all operating costs, capital expenditures, tax, imputed interest and royalty payments.  Pre-feasibility and feasibility study costs of about US$16 million have not been included in the financial analysis.  The base case results of the Kalana Main Pit PEA are summarised in Table 3 and sensitivity to metal price and discount rate in Table 4.

Table 3            Kalana Main Project PEA results – base case

Item

Value

Tonnes processed (kt)

15,753

Au grade (g/t)

3.1

Au contained (koz)

1,578

Recovery

93%

Au recovered (koz)

1,464

Revenue (US$M)

1,625

Royalty (US$M)

49

Selling cost (US$M)

16

Net revenue (US$M)

1,560

Mining cost (US$M)

477

Process cost (US$M)

258

G&A (US$M)

71

Total operating cost (US$M)

806

Capital plant and infrastructure (US$M)

134

Pre-strip (US$M)

15

Sustaining capital (US$M)

29

Closure cost ($M)

10

Total capital cost (US$M)

188

Net cash flow (US$M)

566

NPV after tax and interest (US$M)

194

IRR after tax and interest

53%

Table 4            Kalana Main Project Sensitivity (gold price and discount rate)

Metal price (US$/oz)

NPV (5%)

NPV (10%)

IRR

1,110

US$276 million

US$194 million

53%

1,300

US$424 million

US$306 million

74%

ABOUT THE COMPANY

Avnel is a producing gold mining company operating the Kalana Mine in south-west Mali and is engaged in the exploration of the 30-year Kalana Exploitation Permit encompassing 387.4 sq km around and to the south of the Kalana Mine as well as on Avnel's abutting Fougadian Exploration Permit.

Avnel's principal asset is an 80% interest in Société d'Exploitation des Mines d'Or de Kalana ("SOMIKA") which is the holder of the Kalana Exploitation Permit.  The Kalana Project is situate in south west Mali.  The 387.4 sq km exploitation permit has a NI-43-101 compliant resource of 1,020,000 oz (at an average grade of 10.4 g/t) in the measured and indicated category, and 249,000 oz (at an average grade of 3.4 g/t) in the inferred category prepared by Snowden in 2004 in respect of the existing Kalana underground mine (name plate capacity 60,000 tonnes per year narrow vein underground mine in fresh rock).  Avnel intends to file a new NI 43-101 Technical Report on or before March 31, 2014 in respect of the MRE and PEA described in this press release.  During the period of the pre-feasibility study and feasibility study it is anticipated the present underground mine as described above will continue.  If the feasibility study is positive it is contemplated that the underground mine will close. The infrastructure of the underground mine sits atop the conceptual new open pit.

Avnel also holds the Fougadian Exploration Permit covering an area of 75 sq. km. to the south of the main Kalana Exploitation Permit area and abutting it.  Avnel and IAMGOLD have entered into a joint venture arrangement agreement whereby IAMGOLD has the option to acquire up to an initial 51% in Avnel's interest in the Fougadian Exploration Permit and in an additional 75 sq. kms to the south of Avnel's Fougadian Exploration Permit area for which IAMGOLD has an exploration permit which is subject to that joint venture arrangement.

The PEA is preliminary in nature and includes the use of indicated and inferred resources that are considered too speculative geologically to have the economic considerations applied to them that would enable them to be categorised as mineral reserves.  Thus, there is no certainty that the PEA will be realised.  Actual results may vary, perhaps materially.  Mineral resources that are not mineral reserves do not have demonstrated economic viability.  The PEA is subject to a number of assumptions, including, among others that an Environmental Impact Assessment will be completed within the required timeline, all required permits will be obtained in a timely manner, the company will continue to have the support of local community, a constant regulatory environment and no material increase occurs to the estimated costs.

Technical Information and Qualified Person/Quality Control Notes

Information in this release arising subsequent to the date of the 2005 Snowden Technical Report regarding the Kalana Gold Mine and exploration activity is provided by Avnel management under the supervision of Roy Meade (a director of the Company) who is a non-independent "Qualified Person" as such term is defined in National Instrument 43-101. Portions of the information are based on assumptions, qualifications and procedures which are not fully described herein.

Forward-Looking Information

This release includes certain statements that may be deemed "forward-looking statements". All statements in this release, other than statements of historical facts are forward-looking statements. Forward-looking statements in this release include, among other things, statements about the potential development and operation of an open-pit mine based on the PEA, the completion of a pre-feasibility study and feasibility study on the Kalana Main Project and the continued operation of the existing underground gold mine at Kalana.  Although Avnel believes the expectations expressed in such forward-looking statements are based on reasonable assumptions, such statements are not guarantees of future performance and actual results or developments may differ materially from those in the forward-looking statements. Factors that could cause actual results to differ materially from those in forward looking statements include market prices, gold prices, continued availability of capital and financing and general economic, market, political or business conditions. Investors are cautioned that any such statements are not guarantees of future performance and actual results or developments may differ materially from those projected in the forward-looking statements. Avnel does not assume any obligation to update or revise its forward- looking statements, whether as a result of new information, future events or otherwise

SOURCE AVNEL GOLD MINING LTD.

For further information: Howard Miller, Chief Executive Officer, Phone: +44 207 589 9082; Fax +44 207 589 8507, UK Mobile: +44 07768 696129, Canadian Mobile: +1 416 726 8174, Email: howard@hbmiller.co.uk, www.avnelgold.com; Roy Meade, Executive Director, Technical and Operations, Phone: +223 6674 7679, Email: rmeade@avnelgold.com; Dr Olivier Féménias, EurGeol, Vice President Geology, Phone: +44 7572 457 888, Email: ofemenias@avnelgold.com; Public Relations Consultant: Ari Todd, President, FronTier Consulting, 1 King Street West - Suite 1411, Toronto, Canada, M5H 1A1, Direct: +1 416 800 9156, Mobile: +1 647 999 9734, Email: ari@frontiermcg.com, www.frontierconsultingltd.com
Data and Statistics for these countries : Canada | Guernsey | Mali | All
Gold and Silver Prices for these countries : Canada | Guernsey | Mali | All

Avnel Gold Mining Ltd.

EXPLORATION STAGE
CODE : AVK.TO
ISIN : GB00B09Y5410
Follow and Invest
Add to watch list Add to your portfolio Add or edit a note
Add Alert Add to Watchlists Add to Portfolio Add Note
ProfileMarket
Indicators
VALUE :
Projects & res.
Press
releases
Annual
report
RISK :
Asset profile
Contact Cpy

Avnel Gold Mining is a gold producing company based in United kingdom.

Its main exploration properties are KALANA GOLD MINE and FOUGADIAN PERMIT in Mali.

Avnel Gold Mining is listed in Canada. Its market capitalisation is CA$ 162.1 millions as of today (US$ 133.0 millions, € 111.4 millions).

Its stock quote reached its highest recent level on December 13, 2006 at CA$ 1.25, and its lowest recent point on December 19, 2008 at CA$ 0.02.

Avnel Gold Mining has 376 989 984 shares outstanding.

Your feedback is appreciated, please leave a comment or rate this article.
Rate : Average note :0 (0 vote) View Top rated
 
Annual reports of Avnel Gold Mining Ltd.
Announces 2007 Annual Results - Period Ended December 31, 20...
Nominations of Avnel Gold Mining Ltd.
11/25/2013appoints Dr. Olivier Féménias as Vice President Geology
5/23/2013announces election of directors
8/5/2008Announces Appointment of Chief Financial Officer
3/27/2008Announces Appointment of Chief Operating Officer
10/16/2007Announces Appointment of VP Exploration
Financials of Avnel Gold Mining Ltd.
8/14/2008Announces Second Quarter 2008 Results
5/15/2008Announces First Quarter 2008 Results - Period ended March 31...
11/14/2007Announces Third Quarter 2007 Results
8/13/2007Announces Second Quarter 2007 Results - Period ended June 30...
5/14/2007Announces First Quarter 2007 Results
Project news of Avnel Gold Mining Ltd.
3/24/2014Avnel Announces new mineral resource estimate preliminary ec...
1/21/2011(Kalana Gold Mine)- KALANA UPDATE
3/26/2008(Fougadian Permit) has commenced drilling program on the major gold anomaly di...
Corporate news of Avnel Gold Mining Ltd.
5/26/2016Avnel Reports Results of Annual General Meeting
5/11/2016Avnel Reports Files First Quarter 2016 Financial Statements ...
5/6/2016Avnel Gold Files NI 43-101 Technical Report for the Kalana M...
3/30/2016Avnel Announces Definitive Feasibility Study Results for Kal...
3/30/2016Avnel Announces Filing of AIF and Year-End Consolidated Fina...
10/5/2015Avnel Reports That Measured Plus Indicated Resource Increase...
9/15/2015Avnel Successfully Concludes its 30,143 m Over 181 Holes Dri...
8/12/2015Avnel Reports Second Quarter 2015 Financial Results
7/20/2015Avnel Drills 174.0 g/t over 3 m, 6.0 g/t over 15 m, and 7.8 ...
7/16/2015Avnel Drills 174.0 g/t over 3 m, 6.0 g/t over 15 m, and 7.8 ...
4/17/2015Avnel Gold Mining Limited Announces C$12 Million Bought Deal...
4/17/2015IIROC Trade Resumption - CWT.UN; AVK
4/16/2015IIROC Trading Halt - AVK
3/31/2015Avnel Confirms Commencement of Drilling at Kalana Main and A...
3/30/2015Avnel Appoints Mr. Andrew King and Mr. Keith McCandlish to t...
3/26/2015Avnel Reports that Diluted Pit-Constrained Indicated Resourc...
3/26/2015Reports That Diluted Pit-Constrained Indicated Resources Inc...
2/5/2015Avnel Gold Announces Commencement of Definitive Feasibility ...
11/13/2014Avnel Gold Provides Kalana Main PFS Update and Reports Third...
11/13/2014Avnel Gold Provides Kalana Main PFS Update and Reports Third...
10/30/2014TSX Delisting Review - Avnel Gold Mining Limited (Symbol: AV...
10/15/2014Avnel Gold Reports that Indicated Resources Increased 55% to...
7/17/2014Avnel Announces Closing of Approximately C$9.9 Million Priva...
7/7/2014TSX Delisting Review - Avnel Gold Mining Limited (Symbol: AV...
6/26/2014Avnel Announces Proposed Private Placement of up to C$13.5 M...
5/23/2014Avnel Gold Announces 2014 AGM Results
5/14/2014Avnel Gold Mining Limited (AVK: TSX) announces first quarter...
4/1/2014Avnel Gold Mining (TSX:AVK) Files NI 43-101 Technical Report...
3/31/2014Avnel Gold Mining Limited (AVK: TSX) Announces 2013 Annual R...
3/24/2014Announces New Mineral Resource Estimate and Preliminary Econ...
3/24/2014Avnel Announces New Mineral Resource Estimate and Preliminar...
10/16/20072007 Toronto Resource Investment Conference
10/15/2007 Receives Recommendations for Extensive Drill Program to Inv...
9/17/2007Announces Strategic Review
7/18/2007Announces Exceptional Soil Geochemistry Results at its Fouga...
4/2/2007Production at the Kalana Gold mine increases
Comments closed
 
Latest comment posted for this article
Be the first to comment
Add your comment
TORONTO (AVK.TO)
0.430-2.27%
TORONTO
CA$ 0.430
09/15 14:58 -0.010
-2.27%
Prev close Open
0.440 0.440
Low High
0.430 0.440
Year l/h YTD var.
 -  -
52 week l/h 52 week var.
- -  0.430 -%
Volume 1 month var.
200,500 -%
24hGold TrendPower© : 24
Produces
Develops
Explores for Gold - Silver
 
 
 
Analyse
Interactive chart Add to compare
Interactive
chart
Print Compare Export
Last updated on : 11/25/2010
You must be logged in to use the porfolio and watchlists (free)
Top Newsreleases
MOST READ
Annual variation
DateVariationHighLow
 
5 years chart
 
3 months chart
 
3 months volume chart
 
 
Mining Company News
Plymouth Minerals LTDPLH.AX
Plymouth Minerals Intersects Further High Grade Potash in Drilling at Banio Potash Project - Plannin
AU$ 0.12-8.00%Trend Power :
Santos(Ngas-Oil)STO.AX
announces expected non-cash impairment
AU$ 7.82+1.69%Trend Power :
Oceana Gold(Au)OGC.AX
RELEASES NEW TECHNICAL REPORT FOR THE HAILE GOLD MINE
AU$ 2.20+0.00%Trend Power :
Western Areas NL(Au-Ni-Pl)WSA.AX
Advance Notice - Full Year Results Conference Call
AU$ 3.86+0.00%Trend Power :
Canadian Zinc(Ag-Au-Cu)CZN.TO
Reports Financial Results for Q2 and Provides Project Updates
CA$ 0.12+4.55%Trend Power :
Stornoway Diamond(Gems-Au-Ur)SWY.TO
Second Quarter Results
CA$ 0.02+100.00%Trend Power :
McEwen Mining(Cu-Le-Zn)MUX
TO ACQUIRE BLACK FOX FROM PRIMERO=C2=A0
US$ 11.04+1.38%Trend Power :
Rentech(Coal-Ngas)RTK
Rentech Announces Results for Second Quarter 2017
US$ 0.20-12.28%Trend Power :
KEFIKEFI.L
Reduced Funding Requirement
GBX 0.54-2.53%Trend Power :
Lupaka Gold Corp.LPK.V
Lupaka Gold Receives First Tranche Under Amended Invicta Financing Agreement
CA$ 0.06+0.00%Trend Power :
Imperial(Ag-Au-Cu)III.TO
Closes Bridge Loan Financing
CA$ 2.52+6.78%Trend Power :
Guyana Goldfields(Cu-Zn-Pa)GUY.TO
Reports Second Quarter 2017 Results and Maintains Production Guidance
CA$ 1.84+0.00%Trend Power :
Lundin Mining(Ag-Au-Cu)LUN.TO
d Share Capital and Voting Rights for Lundin Mining
CA$ 16.05+2.62%Trend Power :
Canarc Res.(Au)CCM.TO
Canarc Reports High Grade Gold in Surface Rock Samples at Fondaway Canyon, Nevada
CA$ 0.24+2.13%Trend Power :
Havilah(Cu-Le-Zn)HAV.AX
Q A April 2017 Quarterly Report
AU$ 0.19-7.32%Trend Power :
Uranium Res.(Ur)URRE
Commences Lithium Exploration Drilling at the Columbus Basin Project
US$ 6.80-2.86%Trend Power :
Platinum Group Metals(Au-Cu-Gems)PTM.TO
Platinum Group Metals Ltd. Operational and Strategic Process ...
CA$ 1.90+1.60%Trend Power :
Devon Energy(Ngas-Oil)DVN
Announces $340 Million of Non-Core Asset Sales
US$ 51.43-0.46%Trend Power :
Precision Drilling(Oil)PD-UN.TO
Announces 2017Second Quarter Financial Results
CA$ 8.66-0.35%Trend Power :
Terramin(Ag-Au-Cu)TZN.AX
2nd Quarter Report
AU$ 0.03+0.00%Trend Power :