Orezone Gold Corp.

Published : April 28th, 2015

Announces Positive Feasibility Study for Bombore

( 0 vote, 0/5 ) Print article
  Article Comments Comment this article Rating Follow Company  
0
Send
0
comment


 

View this email in your browser
Orezone Announces Positive Feasibility Study for Bombor�
Mine Life increased to 11 years, 24.4% after tax IRR and AISC of US$678/oz

(Download PDF)

April 28, 2015, Orezone Gold Corporation (ORE-TSX) is pleased to announce the highlights of the independent Feasibility Study (the �Study�) for its wholly owned Bombor� Gold Project in Burkina Faso, West Africa. The study envisions a shallow open pit mining operation with a processing circuit that combines heap leaching and carbon-in-leach (CIL) without any grinding to process the soft and mostly free digging oxidized ores. The eleven-year mine plan, based on a mineral reserve using an US$1,100 gold price, is designed to deliver higher grade ore in the early years (0.88 g/t over the first eight years of production at a strip ratio of 1:1).  Lower grade stockpiles will be processed in the final three years.  The financial model with revenues based on a US$1,250 gold price, yields a robust 24.4% after tax internal rate of return to the Company (based on 90% ownership, 10% Gov�t) with a net present value of US$196 M at a 5% discount rate.  Project payback is estimated at 2.7 years with all in sustaining costs averaging $678/oz.  Initial capital is estimated at $250.0 M including contingencies, all working capital and a $10.5 M credit for gold revenues generated during the pre-production period. Capital costs include the mining fleet, a much larger water storage reservoir and higher resettlement costs than envisioned in the March 2014 Preliminary Economic Assessment (PEA).  Sustaining capital is estimated at $75.2 M, taking into account the additional three years of mine life and higher resettlement costs than estimated in the PEA. Total reclamation and closure costs are estimated at $22.5 M including $8.7 M of heap rinsing costs expensed in year 12.
 
�The results of the Study are compelling and the project benefits from size, location, low reagent consumption, rapid leaching kinetics and low all-in operating costs,� said Ron Little, CEO of Orezone.  �Bombor� is one of the largest and most advanced undeveloped gold deposits in the region that lends itself to phased development.  The initial 11 year phase requires less capital and has lower operating costs to process the shallow and softer oxidized ores.  A second phase, at slightly higher gold prices (>US$1,400) could expand the standard CIL circuit with the addition of grinding to process the well-defined sulphide resource (73 Mt at 1.1 g/t for 2.6 Moz).�
 
The Study was completed by Kappes, Cassiday and Associates of Reno (�KCA�, Processing and Study Manager), Golder Associates, Inc. of Reno and Montreal, (�Golder�, Geotechnical), RPA Inc. of Toronto (�RPA�),  Reserves and Mining) and WSP Canada Inc. of Montreal (�WSP�) in conjunction with Socrege and BEGE of Burkina Faso (Social & Environmental). 
 
Summary of Financials
The Base Case assumptions include mineral reserves using an average gold price of $1,100/oz and revenues based on $1,250/oz along with current prices for fuel, reagents and labor. Capital is based on quotes received from potential equipment and service providers between Q3 2014 to present.  The financial highlights are as follows:

Base Case Highlights
 
   
Mine Plan Contained Gold at $1,100 Au (ounces) 1,465,000
Average Gold Grade (g/t) LOM  0.76  /  Years (1-8)  0.88
Processing Throughput (Mt/yr) 5.5
Mine Life (years) 10.7
Average Annual Gold Production (ounces) LOM 116,000  /  Years (1-8)  135,000
Gold Production (ounces recovered) 1,275,000
Waste to Ore Strip Ratio     (incl. pre-strip, water OCR) 1.07: 1.0
Gross Revenue ($M) using $1,250 Au 1,589
Direct Cash Cost ($/oz) 554
Operating Cost ($/oz) 603
Initial Capital ($M)             (incl. $10.5M capital credit) 250.0
Sustaining Capital ($M) 75.2
Closure Costs ($M)      (incl. $8.7M of expensed costs) 22.5
Attributable to Orezone (1)  
NPV after tax (0%) ($M) 323.9
NPV after tax (5%) ($M) 196.1
IRR after tax 24.4%
Attributed to Government (2)  
NPV (0%) with taxes ($M) 214.8
NPV (5%) with taxes ($M) 152.7
  1. Represents Orezone�s Burkina Faso subsidiary cash flows net of royalties and local taxes.  
  2. The Government of Burkina Faso benefits from its 10% free-carried interest, royalties (4% NSR), corporate tax (18.3%) and withholding taxes.
Exchange Rates:  USD : XOF = 550;     Euro : USD =  $1.19;   Euro : XOF = 655.957
Fuel price delivered to site (USD/L): Diesel $1.20, HFO $0.77
 
The Mineral Resource and Mineral Reserve
The Mineral Reserve estimate prepared by RPA, is based on the 2013 Mineral Resource estimate prepared by SRK Consulting (Canada) Inc., which includes 139.9 Mt of M&I resources grading 1.01 g/t for 4.6 Moz plus 18.4 Mt Inferred resources grading 1.22 g/t for 0.7 Moz. The Study mineable reserve is limited to only the measured and indicated near-surface saprolite (oxide) and transitional (semi-oxidized) resources to an average depth of 45 m. 
  
The Mineral Resource estimate consists of three separate block models:
  • The North model, which consists of the KT, Maga, CFU, OCR, and P8P9 zones.
  • The South model, which consists of the P11, Siga E, and Siga W zones.
  • The Southeast model, which is to the south and southeast of the South model and consists of the P16 and P17 zones
 
Mineral Resource Estimate � SRK Consulting (Canada) Inc., April 26, 2013
 
                                  Measured Mineral Resource               Indicated Mineral Resource           Inferred Mineral Resource
 
 
Cut off 
Gold

 

Tonnage 


Grade
 
 Contained
Gold

Tonnage 

 Grade
 Contained
Gold
 
Tonnage
 
Grade
 Contained
Gold
North:  g/t Mt  g/t  koz   Mt g/t   koz  Mt g/t  koz 
Laterite/Oxide 0.45 13.57 0.95 417 14.20 0.82 375 2.04 0.88 57
Transitional 0.45 9.22 0.93 275 5.84 0.92 173 0.79 1.00 25
Fresh 0.50 22.04 1.00 711 11.98 1.29 497 4.42 1.63 232
Sub-total   44.83 0.97 1,402 32.02 1.02 1,046 7.25 1.35 315
South:                    
Laterite/Oxide 0.45 8.11 0.94 246 4.53 0.86 125 1.66 0.89 48
Transitional 0.45 7.49 0.89 214 2.97 0.96 92 1.35 0.96 41
Fresh 0.50 20.58 1.02 674 15.26 1.19 584 5.46 1.26 222
Sub-total   36.17 0.98 1,134 22.76 1.10 801 8.46 1.14 311
Southeast:                    
Laterite/Oxide 0.45 0.24 1.33 10 0.37 1.05 12 0.30 0.97 9
Transitional 0.45 0.25 1.53 12 0.34 0.97 11 0.24 0.97 7
Fresh 0.50 1.53 1.44 71 1.32 1.43 61 2.18 1.15 81
Sub-total   2.03 1.44 94 2.02 1.28 83 2.71 1.12 97
Combined:                  
Laterite/Oxide 0.45 21.92 0.95 673 19.10 0.84 513 4.00 0.89 115
Transitional 0.45 16.96 0.92 501 9.14 0.94 275 2.37 0.97 74
Lat/Ox/Tr Total 0.45 38.88 0.94 1,174 28.24 0.87 789 6.37 0.92 189
Fresh 0.50 44.14 1.03 1,456 28.55 1.24 1,142 12.05 1.38 534
Total All Material  83.03 0.99 2,630 56.79 1.06 1,930 18.42 1.22 723
Total M+I All Material 139.82 1.01 4,560            
Total M+I Oxidized 67.12 0.91 1,963            
 
*  Mineral resources are not mineral reserves and do not have a demonstrated economic viability. All figures have been rounded to reflect the relative accuracy of the estimates. The gold price of US$1,400 and the cut-off grades from the previous resource estimation (2012) have been retained for comparison purposes.  Reported within conceptual open pit shells optimized considering a carbon in leach CIL process option.

 
For the Mineral Reserve estimate, RPA developed reserve block models, for each of the three resource block models, by applying modifying factors for conversion of Mineral Resources to Mineral Reserves.  Those factors included amongst others, weathering profiles, operating costs, metallurgical recoveries, mining dilution & extraction and pit slopes.

Mineral Reserve Estimate � RPA, March 20, 2015
 
Category Proven Probable Proven & Probable
Tonnes Grade Ounces Tonnes Grade Ounces Tonnes Grade Ounces
Mt g/t koz Mt g/t koz Mt g/t koz
North 25.32 0.77 627 15.11 0.69 333 40.43 0.74 960
South 12.96 0.81 339 6.15 0.92 173 19.13 0.80 491
Southeast 0.18 1.17 7 0.18 1.18 7 0.36 1.18 14
Total 38.48 0.79 973 21.44 0.71 493 59.92 0.76 1,465
CIM definitions were followed for Mineral Reserves.  Mineral Reserves are estimated using a variable gold cut-off grade based on ore type and location; estimated cut-off grades range from 0.30 g/t to 0.45 g/t gold.  Mineral Reserves are estimated using an average long-term gold price of US$1,100 per ounce.  A minimum mining width of five metres was used.  Bulk density is estimated in the Mineral Resource model by block; the average density of ore is 1.8 t/m3.  Numbers may not add due to rounding.  Mineral Reserves are included in the mineral resource. 
 
 
Estimated Annual Gold Production
The Study assumes during years 1 through 8 an average annual mining rate of 13.9 Mt, including 5.5 Mt of ore.  The ore is composed almost equally of +/- 212 micron material and is processed via the heap leach pad (+212 micron) and CIL (-212 micron) circuits.  Average gold produced and average diluted grades for each year are summarized in the table below.  Some gold is recovered during the pre-production period as a result of mining and processing the ore contained within the water storage facility (OCR).  During years 9 to 11 ore is only processed from the lower grade stockpiles.
 
Year -1 1 2 3 4 5 6 7 8 9 10 11 Total
Gold (Koz) 11.1 186 168 146 135 135 112 115 89 65 65 48 1,275
Grade (g/t) 0.45 1.21 1.09 0.95 0.88 0.87 0.73 0.75 0.58 0.42 0.42 0.42 0.76
 
 
Summary of Operating Costs (excluding pre-production period)
 
Category Total Costs
$M
Average Cost
$/t processed
Average Cost
$/oz
Mining 299 5.06 234
Processing 293 4.97 230
General Services 111 1.88 87
Transport & Refining 3.2 0.05 2.5
Cash Cost 706 11.96 554
Royalties 63 1.07 50
Total Cash Cost 770 M 13.03 603
 
 
Initial Project Capital Cost Estimates 
 Initial capital costs are based on quotes of equipment and services from potential providers.
 
Project Capital Area
 
US$M
Infrastructure 7.5
Power Plant 7.8
Mining and Support Equipment 24.8
Process Plant (incl. water system) 98.7
Indirects * 14.1
Resettlement 10.3
EPCM, Commissioning and Owner�s Cost * 29.3
Pre-production * (w/OCR and preproduction Gold credit**) 30.5
Working Capital 10.2
Contingencies 16.7
Total Initial Capital Costs $250.0
* Including contingency
** Excluding VAT
*** Gold credit is for gold produced during the pre-production period of commissioning equipment and amounts to approximately 8,400 ounces.
 
 
Sustaining Capital & Closure Cost Estimates
 
Project Sustaining & Closure Capital Area US$M
Mining and G&A 23.1
Plant & Nested Tails 36.1
Resettlement 9.9
Contingencies 6.1
Total Sustaining Capital Costs 75.2
Reclamation and Closure* 13.8
Total Sustaining and Closure Capital 89.0
*Total closure cost estimated at $22.5M.  $8.7M of expensed costs for heap rinsing not included in closure capital as gold production is associated with the process.
 
Sustaining capital costs were estimated on the basis of quotes on equipment from potential providers. Taxes and freight are included along with the individual items. The closure and reclamation plan includes work to be conducted from the closure of the mine at the end of operating activities, as well as progressive rehabilitation work during the life of the mine.  The goal is to return the site to a satisfactory state as quickly as possible in terms of reducing the risks for health and safety, controlling erosion and developing a profile compatible with the future uses of the site. 
 
Total LOM reclamation and closure costs are estimated to be $22.5 M including $8.7 M in expensed operating costs for heap rinsing in year 12.  The additional $13.8 M in capital and $8.7 M in expenses are included in the LOM AISC estimate of $678/oz.  An estimated equipment salvage value of $9.6 M has been included as a credit.
 
Project Sensitivities
The project is sensitive to gold price as demonstrated in the following table:
 
Gold Price (per oz) $1000 $1100 Base Case
$1250
$1400 $1500
To Orezone          
NPV (0%) After tax ($M) 121.2 198.5 323.9 437.1 519.8
NPV (5%) After tax ($M) 49.1 105.1 196.1 278.2 338.1
IRR After tax 10.4% 16.1% 24.4% 31.3% 36.2%
           
To Gov�t Burkina Faso
(incl taxes, dividends and royalties)
         
NPV (0%) After tax ($M) 99.1 149.1 214.8 292.6 337.3
NPV (5%) After tax ($M) 69.8 105.7 152.7 208.5 240.6
 
The project is also sensitive to operating costs, in particular fuel (diesel and HFO) which accounts for approximately 25% of expenses.  Diesel pricing is set by the government of Burkina Faso. The Study uses the conservative delivered to site fuel prices of $1.20/L for diesel and $0.77/L for HFO. Although diesel prices are lower than those used in the 2014 PEA, they are not as low as the current price in Burkina Faso or the free market price.  The project economics and other mining operations in the country would benefit if the government were to change their policy to allow free market pricing and direct supply.
 
Mine Plan and Pit Optimization Studies
The Company has worked with RPA to develop a mine plan and production schedule (based on the April 2013 resource model).  Scheduling has been optimized for project returns by processing the higher grade ore in the early years and stockpiling the lower grade ore for processing after mining is complete in year 8.  Initial process grade for years 1 through 3 averages 1.08 g/t, with the years 1 through 8 averaging 0.88 g/t.  A fleet of 32 tonne haul trucks, such as Volvo or Scania rear-dump units, will be used to provide increased versatility, as the mine plan consists of a large number of shallow pits of varying tonnage. 

Total ore processed, including the lower grade stockpiles, will be 59.9 Mt of oxide and semi-oxidized ore grading an average of 0.76 g/t.  The life of mine strip ratio is approximately one tonne of waste per tonne of ore.    
 
 Metallurgical Test Results
KCA has completed all of the metallurgical testing associated with the Bombor� project Study and have reviewed the historical data.  Results indicate that the overall recovery for the combined heap leach and CIL processing circuit is expected to be 87%.  The circuit separates the fine ore (-212 micron) from the coarse ore in a cyanide solution via a rotary scrubber, screen and classifiers.  The slurried fine ore (49% of the total) is pumped to a CIL circuit for gold recovery without any grinding. The CIL tails are sent to a lined tailings facility that utilizes the heap leach as part of the containment system in order to reduce the footprint and liner costs. The tails facility is designed to be zero discharge.  The coarse (+0.212 mm) fraction is conveyed to a standard heap leach pad, where it is leached with a cyanide solution. With the majority of the fines removed from the coarser heap leach ore, there is no requirement for cement agglomeration or inter-lift liners for a stacking height of up to 60 m.  The pregnant liquor from the heap leach is sent to the CIL circuit for gold recovery.  Gold is recovered in a standard carbon desorption plant, finishing with electrowinning and smelting to produce gold dor� bars.
 
Maximum power requirement will be 7.2 kWh/t ore.  Overall reagent consumptions are given in the table below. 
 
Reagent Consumption
 
Reagent Consumption
Cyanide 0.4 kg/t Heap; 0.165 kg/t CIL
Lime 1.24 kg/t
Caustic 25.9 t/yr
Carbon 52 t/yr
 
Development Timetable
Estimated time to construct the Bombor� operation (pre-production) is 21 months, including time to excavate the Off Channel Reservoir (OCR) to be used for project water storage, and time to commission the process plant equipment. 
 
Water for the operation will be collected by gravity feed into the OCR from about 10% of the annual rainy season runoff from the Nobsin River drainage basin.  The OCR usable volume design capacity is 3 M cubic meters, and significantly larger than those designs presented in the 2014 PEA (0.9 M cubic meters).  Annual water consumption for the project is calculated to be, on average, between 2.6 M and 2.9 M cubic meters per year and considers recycle of tailings solution.  The increase in annual water consumption as compared to the 2014 PEA is due to the change in the process from 100% Heap Leach to a combined Heap Leach/CIL process. 
 
 
Environmental Studies and Social Responsibility
The Environmental Baseline Studies for the Bombor� Project began in 2011 and were completed at the end of 2014. Local consultants have conducted archaeological studies and a comprehensive range of environmental and social impact studies. Their work is supported by WSP who were retained by Orezone early in 2014 to support and audit the Bombor� ESIA study and resettlement action plan (�RAP�).
 
Over the past 5 years the Company has recognized and accepted its social responsibility by actively supporting local communities by sponsoring over 50 initiatives which included improvements and additions to local schools, clinics, water wells and supply inventories. Orezone have on staff technically qualified personnel, sociologists and managers experienced with mining and resettlement projects in Burkina Faso. With the help of our employees, consultants and community leaders the Company is currently developing plans to pursue these community projects in the coming weeks, months and years. 
 
The Company continues to hold formal and informal information meetings with the community leaders to update them regularly on the status of the Bombor� study. In order to ensure safe operations, the project will require the relocation of over 500 local households (approximately 3,700 residents) from several communities and two artisanal mining sites over the initial 5 years of construction and operation.  The program for this relocation has been the object of joint discussions involving the communities affected, their representatives, the Company and its local consultants Socrege.  A detailed analysis based on these discussions has led to a substantial increase in relocation and resettlement cost as compared to the 2014 PEA.  The main areas where estimated costs increased were building replacement, artisanal miner compensation, infrastructure crop and tree compensation and livelihood compensation.  Pre-production costs for the resettlement program are now estimated at $10.3 M, with life of mine costs estimated at   $20.2 M. 
 
Full details of the Feasibility Study in the form of a NI 43-101 technical report will be filed on SEDAR within the next 45 days.  The Company is also in the process of updating the 2013 Mineral Resource estimate with the inclusion of an additional 50,000 m of drilling.  The update will be completed by Q3 2015 and if warranted, an update to the Mineral Reserve and mine plan will be completed prior to any production decision.
 
About Orezone Gold Corporation
Orezone is a Canadian company with a gold discovery track record of +12 Moz and recent mine development experience in Burkina Faso, West Africa.  The Company owns a 100% interest in Bombor�, the largest undeveloped oxide gold deposit in West Africa which is situated 85 km east of the capital city, adjacent to an international highway.  The Company is the process of updating the Mineral Resource estimate, completing the Feasibility Study and filing an application for a mining permit on Bombor� in H1 2015.

For further information please contact Orezone at (613) 241-3699 or Toll Free: (888) 673-0663

Carl Defilippi of Kappes, Cassiday & Associates; Glen Ehasoo of RPA Inc.; Todd Minard of Golder Associates Inc., Craig Wood of WSP, Glen Cole of SRK Consulting (Canada) Inc., Tim Miller, COO, Pascal Marquis, SVP and Ron Little, CEO of Orezone, are Qualified Persons under National Instrument 43-101 and have reviewed the information in this release. 

FORWARD-LOOKING STATEMENTS AND FORWARD-LOOKING INFORMATION: This news release contains certain �forward-looking statements� within the meaning of applicable Canadian securities laws. Forward-looking statements and forward-looking information are frequently characterized by words such as �plan�, �expect�, �project�, �intend�, �believe�, �anticipate�, �estimate�, �potential�, �possible� and other similar words, or statements that certain events or conditions �may�, �will�, �could�, or �should� occur. Forward-looking statements in this release include statements regarding, among others; completing a full feasibility study for Bombor� and applying for a mining permit in H1 2015, updating the Bombor� resource estimate by Q3 2015 and if warranted update to the mineral reserve and mine plan prior to a production decision, the Government of Burkina Faso making changes to fuel price policies that might benefit the project, and a second phase could expand the standard CIL circuit with the addition of grinding to process the well-defined underlying sulphide resource.

FORWARD-LOOKING STATEMENTS are based on certain assumptions, the opinions and estimates of management at the date the statements are made, and are subject to a variety of risks and uncertainties and other factors that could cause actual events or results to differ materially from those projected in the forward-looking statements. These factors include the inherent risks involved in the exploration and development of mineral properties, the uncertainties involved in interpreting drilling results and other geological and geotechnical data, fluctuating metal prices, the possibility of project cost overruns or unanticipated costs and expenses, the ability of contracted parties (including laboratories and drill companies to provide services as contracted); uncertainties relating to the availability and costs of financing needed in the future and other factors. The Company undertakes no obligation to update forward-looking statements if circumstances or management�s estimates or opinions should change. The reader is cautioned not to place undue reliance on forward-looking statements. Comparisons between any resource model and estimates with the subsequent drill results are preliminary in nature and should not be relied upon as potential qualified changes to any future resource updates or estimates.

Readers are advised that National Instrument 43-101 of the Canadian Securities Administrators requires that each category of mineral reserves and mineral resources be reported separately. Readers should refer to the annual information form of Orezone for the year ended December 31, 2014 and other continuous disclosure documents filed by Orezone since January 1, 2015 available at www.sedar.com, for this detailed information, which is subject to the qualifications and notes set forth therein.
 
Copyright � 2015 Orezone Gold Corp., All rights reserved.
You registered to receive Orezone Gold Corp. updates via email on their website at: http://www.orezone.com or provided your contact details

Our mailing address is:
Orezone Gold Corp.
290 Picton Avenue, Suite 201
Ottawa, Ontario K1Z 8P8
Canada

Add us to your address book


     

Email Marketing Powered by MailChimp
Data and Statistics for these countries : Burkina Faso | Canada | All
Gold and Silver Prices for these countries : Burkina Faso | Canada | All

Orezone Gold Corp.

EXPLORATION STAGE
CODE : ORE.TO
Follow and Invest
Add to watch list Add to your portfolio Add or edit a note
Add Alert Add to Watchlists Add to Portfolio Add Note
ProfileMarket
Indicators
VALUE :
Projects & res.
Press
releases
Annual
report
RISK :
Asset profile
Contact Cpy

Orezone Gold is a gold exploration company based in Canada.

Its main exploration properties are ZELINE 1 & ZELINE 4 and KOSSA in Niger and BOMBORE, SEGA and BONDI in Burkina Faso.

Orezone Gold is listed in Canada. Its market capitalisation is CA$ 93.9 millions as of today (US$ 68.4 millions, € 63.9 millions).

Its stock quote reached its highest recent level on April 08, 2011 at CA$ 5.26, and its lowest recent point on November 27, 2015 at CA$ 0.22.

Orezone Gold has 117 350 000 shares outstanding.

Your feedback is appreciated, please leave a comment or rate this article.
Rate : Average note :0 (0 vote) View Top rated
 
Annual reports of Orezone Gold Corp.
2009 Annual Report
2008 Annual Report
Annual report 2006
Financings of Orezone Gold Corp.
11/13/2013Closes C$5M Non-Brokered Private Placement
10/30/2013Arranges C$5M Non-Brokered Private Placement
6/23/2010Arranges C$5M Private Placement for Brighton Energy
1/2/2009 Closes Private Placement, Updates Timing of Transaction wit...
Financials of Orezone Gold Corp.
11/15/2008 Third Quarter Update
Project news of Orezone Gold Corp.
3/27/2013(Bombore)Positive Progress Report for Bombore Feasibility Study and R...
11/13/2012(Bombore)Positive Drill Results Support Further Growth at Bombore
9/4/2012(Bombore)35,000 m of Positive Drill Results Support Further Growth at...
8/27/2012(Bombore)Bombore Gold Project Reaches World Class Size
2/22/2012(Bombore)Provides Positive Update on its Bombore Gold Project
2/3/2012(Sega)Sells Sega Project to Cluff Gold for $29.6M
1/10/2012(Bombore)Reports Continued Positive Results at Bombore Gold Project
11/28/2011Brighton Expands Niger Uranium Discovery to 14 km2 of Minera...
8/18/2011Orezone Confirms Heap Leach Potential of Sulphide Resources ...
8/18/2011(Sega)Confirms Heap Leach Potential of Sulphide Resources at Sega
8/8/2011Orezone Expands Bombor\303\251 Gold Project ...
8/8/2011(Bombore)Expands Bombore Gold Project Area 60% With New Permit
7/26/2011(Bombore)Reports Higher Gold Grades and Improved Continuity at Bombor...
6/21/2011(Bombore)Bombor=E9 Gold Project Has PositivePreliminary Economic Asse...
6/20/2011Orezone Bombor\303\251 Gold Project ...
4/11/2011(Sega)Confirms Positive Metallurgical Results for Sega Gold Deposi...
3/24/2011(Bombore)Positive Drill Results at Bombore Continue to Confirm Model
3/23/2011(Bombore)Positive Drill Results at Bombore Continue to Confirm Model
2/24/2011(Zeline 1 & Zeline 4)/Brighton Makes Significant New Uranium Discovery in Niger: ...
7/6/2010(Bombore)Fourth Round of Positive Drill Results at Bombore
6/16/2010(Bombore)Positive Results Continue From Bombore Infill and Expansion ...
5/13/2010Additional PositiveInfill and Expansion Drilling Results at ...
3/25/2010(Bombore)Bombore Auger Drilling Results Indicate Possible 2.5km of Ex...
1/28/2010(Bombore)Commences $2 Million Drill Program at Bombore
1/5/2010(Sega)Increases Sega Project Gold Resources
12/8/2009(Bombore)Improves on Final Bombore Metallurgical Results
10/14/2009(Bombore)Confirms Bombore Gold Deposit is Amenable to Heap Leaching
7/29/2009(Bombore)Completes Drilling Below Surface Resources at Bombore
6/24/2009(Bombore)Orezone Confirms Mineralization at Bombore Below Surface Res...
11/10/2008(Bombore)Almost Triples Gold Resource at Bombore Project
6/30/2008(Essakane)2008 Technical report
Corporate news of Orezone Gold Corp.
12/4/2015Orezone Approved to Move from TSX to TSX-V
9/16/2015Orezone Provides Update on Bomboré Permitting and Bondi Proj...
9/16/2015Orezone Provides Update on Bombore Permitting and Bondi Proj...
7/21/2015Orezone Closes C$6.5M Investment
7/6/2015Orezone Arranges C$6.5M Investment that Includes Ross Beaty
1/27/2015Sandstorm Gold Announces 10 Royalty Agreements
1/27/2015Orezone Closes US$3 Million Financing and Secures an Additio...
1/27/2015Sandstorm Gold Announces 10 Royalty Agreements
1/27/2015Orezone Closes US$3Million Financing
11/24/2014Bombore Gold Project Feasibility Study Update
11/10/2014Orezone update on Operations in Burkina Faso
11/10/2014Orezone Update on Operations in Burkina Faso
11/3/2014Orezone update on Bomboré and Burkina Faso
11/3/2014Orezone Update on Bombore and Burkina Faso
10/14/2014Bombore Gold Project Feasibility Study Update
9/8/2014Bombore Gold Project Feasibility Study Update
7/10/2014Positive Metallurgical and Drilling Results at Bombore
6/4/2014Positive Metallurgical Test Results at Bombore
5/23/2014Orezone Gold Corporation: Results of Annual General Meeting
5/21/2014Orezone Appoints Chief Operating Officer
6/20/2013News Release
6/20/2013(Bombore)Shifts Focus of Bombore Study to Heap Leach Scenario
6/4/2013(Bondi)Positive Metallurgical and Drill Results from the Bondi Proj...
5/24/2013Results of Annual General Meeting
5/24/2013Results of Annual General Meeting
4/29/2013(Bombore)Increases and Upgrades the Bombore Gold Project Resource
2/4/2013(Bombore)Bombore FS and Resource Update Will Include +400,000m of Dri...
5/31/2012(Bombore)Bombore Drill Program Continues with Positive Results
5/23/2012(Sega)Completes the Sale of Sega to Cluff Gold for $26.5M
3/30/2012(Bombore)Completes 215,000 Drill Program at Bombore
2/7/2012to Consolidate Brighton Energy Corporation
12/7/2011Brighton Energy Makes Another Near-Surface Uranium Discovery...
9/12/2011(Bombore)Positive Results Continue at Bombore With Seven Drills Opera...
5/26/2011(Bombore)Reports Additional Positive Drill Results at Bombore Gold Pr...
5/16/2011.: Brighton Energy Discovers Additional Uranium Mineralizati...
4/6/2011Expands Board and Management Team
3/7/2011Burkina Faso is Ra
2/17/2010Brighton Energy Limited Receives Niger Uranium Permit Approv...
7/8/2009Ron Little named Ernst & Young Entrepreneur of the Year Fina...
2/25/2009IAMGOLD Completes Acquisition of Orezone
2/20/2009Obtains Final Court Approval for IAMGOLD Transaction
2/19/2009Shareholders Approve Arrangement with IAMGOLD
2/13/2009 Updates Status of Shareholder Vote
9/29/2005An emerging producer in Burkina Faso, West Africa
Comments closed
 
Latest comment posted for this article
Be the first to comment
Add your comment
TORONTO (ORE.TO)
0.800-1.23%
TORONTO
CA$ 0.800
04/24 13:34 -0.010
-1.23%
Prev close Open
0.810 0.800
Low High
0.800 0.800
Year l/h YTD var.
0.690 -  0.900 -5.88%
52 week l/h 52 week var.
0.690 -  1.61 -48.05%
Volume 1 month var.
15,155 -4.76%
24hGold TrendPower© : -19
Produces
Develops
Explores for Copper - Gold - Molybdenum - Uranium
 
 
 
Analyse
Interactive chart Add to compare
Interactive
chart
Print Compare Export
Last updated on : 2/10/2010
You must be logged in to use the porfolio and watchlists (free)
Top Newsreleases
MOST READ
Annual variation
DateVariationHighLow
2024-19.19%
2023-21.43%1.650.82
20222.44%1.811.08
 
5 years chart
 
3 months chart
 
3 months volume chart
 
 
Mining Company News
Plymouth Minerals LTDPLH.AX
Plymouth Minerals Intersects Further High Grade Potash in Drilling at Banio Potash Project - Plannin
AU$ 0.12-8.00%Trend Power :
Santos(Ngas-Oil)STO.AX
announces expected non-cash impairment
AU$ 7.75+0.52%Trend Power :
Oceana Gold(Au)OGC.AX
RELEASES NEW TECHNICAL REPORT FOR THE HAILE GOLD MINE
AU$ 2.20+0.00%Trend Power :
Western Areas NL(Au-Ni-Pl)WSA.AX
Advance Notice - Full Year Results Conference Call
AU$ 3.86+0.00%Trend Power :
Canadian Zinc(Ag-Au-Cu)CZN.TO
Reports Financial Results for Q2 and Provides Project Updates
CA$ 0.12+4.55%Trend Power :
Stornoway Diamond(Gems-Au-Ur)SWY.TO
Second Quarter Results
CA$ 0.02+100.00%Trend Power :
McEwen Mining(Cu-Le-Zn)MUX
TO ACQUIRE BLACK FOX FROM PRIMERO=C2=A0
US$ 10.92-1.71%Trend Power :
Rentech(Coal-Ngas)RTK
Rentech Announces Results for Second Quarter 2017
US$ 0.20-12.28%Trend Power :
KEFIKEFI.L
Reduced Funding Requirement
GBX 0.55+0.00%Trend Power :
Lupaka Gold Corp.LPK.V
Lupaka Gold Receives First Tranche Under Amended Invicta Financing Agreement
CA$ 0.06-8.33%Trend Power :
Imperial(Ag-Au-Cu)III.TO
Closes Bridge Loan Financing
CA$ 2.38-3.64%Trend Power :
Guyana Goldfields(Cu-Zn-Pa)GUY.TO
Reports Second Quarter 2017 Results and Maintains Production Guidance
CA$ 1.84+0.00%Trend Power :
Lundin Mining(Ag-Au-Cu)LUN.TO
d Share Capital and Voting Rights for Lundin Mining
CA$ 15.32+0.46%Trend Power :
Canarc Res.(Au)CCM.TO
Canarc Reports High Grade Gold in Surface Rock Samples at Fondaway Canyon, Nevada
CA$ 0.24-2.08%Trend Power :
Havilah(Cu-Le-Zn)HAV.AX
Q A April 2017 Quarterly Report
AU$ 0.19+0.00%Trend Power :
Uranium Res.(Ur)URRE
Commences Lithium Exploration Drilling at the Columbus Basin Project
US$ 6.80-2.86%Trend Power :
Platinum Group Metals(Au-Cu-Gems)PTM.TO
Platinum Group Metals Ltd. Operational and Strategic Process ...
CA$ 1.77-1.12%Trend Power :
Devon Energy(Ngas-Oil)DVN
Announces $340 Million of Non-Core Asset Sales
US$ 52.10-0.89%Trend Power :
Precision Drilling(Oil)PD-UN.TO
Announces 2017Second Quarter Financial Results
CA$ 8.66-0.35%Trend Power :
Terramin(Ag-Au-Cu)TZN.AX
2nd Quarter Report
AU$ 0.04+0.00%Trend Power :