RNS Number : 4679A
Ormonde Mining PLC
12 September 2018
� 

12 September 2018

� 

Ormonde Mining plc

� 

("Ormonde" or "the Company")

� 

Barruecopardo Tungsten Project Update

� 

� 

The Board of Ormonde ("the Board") is pleased to provide an update on the Barruecopardo Tungsten Project in Salamanca, Spain ("Barruecopardo" or "the Project"), where construction is well-advanced and commissioning activities have commenced.

� 

Key progress updates include:

� 

·� � � �  The Project team achieved a major milestone during August with the commencement of commissioning of the turnkey crush and screen plant, the first trial of waste rock through the primary crusher having been successfully carried out;

·� � � �  The construction of the rest of the crush and screen circuit is complete, and installation of the associated electrical circuitry is presently in progress and due for completion by the second half of September;

·� � � �  Initial commissioning of the water treatment plant has also been carried out, and will continue on the imminent completion of the water management system pipework and pump installation to feed water from the old open pit;

·� � � �  The installation of major equipment and structures at the process plant is also well-advanced;

·� � � �  Process plant commissioning is now expected to commence at the start of December, a number of weeks later than originally envisaged; plant commissioning is then expected to run through into January 2019, with first production of tungsten concentrates from the beginning of February;

·� � � �  Projected construction costs remain within the Project's Construction Budget of €53.6 million;

·� � � �  Recent site photos of the construction activity can be seen on Ormonde's website at the following link http://ormondemining.com/timeline-in-pictures/.

� 

Michael Donoghue, Ormonde's Chairman and Interim Managing Director, commented:

� 

"It is very pleasing to have achieved another major project milestone during the quarter, with the on-target commencement of commissioning of the crush and screen plant and the water treatment plant, taking the Project into its mine commissioning phase. This major advancement accompanied progress on the construction of the process plant where most of the major equipment has been installed and structural works are well advanced.�  � 

� 

"The commissioning of the process plant is now due to commence in early December, slightly later than originally planned, with first tungsten expected to be produced from early February 2019, to commence a new secure supply to the global markets."

� 

� 

Enquiries to:

� 

Ormonde Mining plc Tel:� +353 (0)1� 8014184

Paul Carroll, Chief Financial Officer

Fraser Gardiner, Chief Operating Officer

� 

Davy (Nomad, ESM Adviser and Joint Broker)

John Frain Tel: +353 (0)1 6796363

� 

SP Angel Corporate Finance LLP (Joint Broker)

Ewan Leggat� Tel:� +44 (0)20 34700470

� 

Capital� M Consultants

Simon Rothschild� Mob:� +44 (0)77 03167065

� 

Murray Consultants

Mark� Brennock Tel:� +353� (0)1� 4980300� Mob:� +353� (0)87� 2335923

� 

� 

Details

� 

Construction:

The construction of the turnkey crush and screen plant is complete, with only electrical circuitry remaining to be finalised, such that by the second half of September commissioning of the entire crushing circuit will commence.

� 

At the process plant, the installation of major equipment and structural installation are 70 per cent completed: jigs, cyclones, spirals, hydrosizer, shaking tables, mills, concentrate thickeners, concentrate dryer and cooler, tailings dewatering screens, fines thickener and filter press are all fully installed or in position. However, a number of factors including detailed engineering, equipment delivery and contractor scheduling have combined towards the latter stages of the project to delay the completion of some installations such as the preconcentration screen structure, process piping and electrical works, when compared to the original June 2017 construction schedule.

� 

In the meantime, details such as walkways, the process plant control room, external cladding, roofing, and water tanks are well advanced. Other developments in hand include the installation of the water management system pipework, and completion of site services and infrastructure, including the site laboratory, canteen and changing rooms. The underground High Tension ("HT") powerline, the main HT substation and yard, and the Medium Tension electrical ring main have all been installed.

� 

Commissioning:

The Project team achieved a major milestone during August with the commencement of initial commissioning of the primary crusher. To-date, several hundred tonnes of waste rock have been successfully fed through the crusher and conveyed to the coarse ore stockpile for use in commissioning the rest of the crush and screen circuit during the second half of September. This will be the focus of the commissioning program while the process plant is being completed.

� 

Initial commissioning of the water treatment plant has been carried out, and will be finalised on the imminent completion of the water management system pipework and pump installation to feed water from the old open pit.

� 

Commissioning of the process plant is now due to commence at the start of December (compared to previous guidance of end-September). The current commissioning plan sees first production of tungsten from the beginning of February 2019.

� 

� 

Tungsten Market:

The Board notes that APT tungsten prices have seen a period of weakness over the last couple of months, with prices reducing from US$352 per metric tonne unit ("mtu") in late June to a current range of US$275-290 per mtu. This correction appears to be attributable to a combination of Chinese APT smelters coming back online following closures related to environmental inspections, and traditional weak trading demand during the summer period. Despite this short-term variability, the Board remains of the view that supply-demand fundamentals will continue to support prices over the medium to long term.

� 

� 

� 

� 

� 

Notes:

This announcement includes certain statements that may be deemed "forward-looking statements". Although the Company believes the forward-looking statements are based on reasonable assumptions, such statements should not be in any way construed as guarantees of future performance and actual results or developments may differ materially from those in the forward-looking statements.

� 

Risk factors are typical of a mining project development and include (but are not limited to): the availability and / or delivery of equipment and contractor services to complete mine construction on schedule and on budget; plant performance during and after commissioning; rates of metal recovery in the process plant; mined ore tonnages and grade in comparison to estimated ore reserves; cost overruns and the potential for future additional funding requirements; and tungsten concentrate sales prices.

� 

Barruecopardo is a fully permitted and funded mining project currently being developed through a US$99.7 million funding package agreed with Oaktree Capital Management (70% interest). Ormonde's participation in the Project is held through its 30 per cent minority interest in Barruecopardo Joint Venture BV, a company which is governed by a Shareholder Agreement between Ormonde and its partner which provides for certain rights and obligations for each party.� 

� 

For more information, visit www.ormondemining.com� 


This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.
� 
END
� 
� 
UPDQFLFFVKFBBBF

==

Ormonde Mining Email Alerts
Brought to you by Brighter IR

To unsubscribe,

To change your preferences, click here to log in

.
Data and Statistics for these countries : Spain | United Kingdom | All
Gold and Silver Prices for these countries : Spain | United Kingdom | All

Ormonde Mining PLC

DEVELOPMENT STAGE
CODE : ORM.L
ISIN : IE0006627891
Follow and Invest
Add to watch list Add to your portfolio Add or edit a note
Add Alert Add to Watchlists Add to Portfolio Add Note
ProfileMarket
Indicators
VALUE :
Projects & res.
Press
releases
Annual
report
RISK :
Asset profile
Contact Cpy

Ormonde Mining is a zinc and lead exploration company based in Ireland.

Ormonde Mining develops zinc, lead, copper, gold, silver and tungsten in Spain, and holds various exploration projects in Spain.

Its main assets in development are LA ZARZA and BARRUECOPARDO in Spain and its main exploration property is SALAMANCA & ZAMORA in Spain.

Ormonde Mining is listed in United Kingdom. Its market capitalisation is GBX 3.3 millions as of today (US$ 4.0 millions, € 3.5 millions).

Its stock quote reached its highest recent level on September 10, 2004 at GBX 9.97, and its lowest recent point on May 26, 2023 at GBX 0.01.

Ormonde Mining has 472 507 482 shares outstanding.

Your feedback is appreciated, please leave a comment or rate this article.
Rate : Average note :0 (0 vote) View Top rated
 
Project news of Ormonde Mining PLC
3/16/2011(Salamanca & Zamora)Salamanca-Zamora Gold Exploration Update
3/2/2011(Barruecopardo)Barruecopardo Drilling Progress
5/27/2010(Barruecopardo)Doubling and major upgrade of tungsten Mineral Resource
10/27/2009(La Zarza)JV with Antofagasta on La Zarza
2/19/2010(La Zarza)Update on activities in Joint Venture with Antofagasta on La...
7/13/2009(La Zarza)Exploration deal with Major on La Zarza
7/15/2008(Barruecopardo)Issue of equity to fund Barruecopardo Tungsten Project
6/17/2008(Barruecopardo)New resource estimate trebles the size of the Barruecopardo ...
4/1/2008(Barruecopardo) Best drilling intersection to-date from the Barruecopardo T...
2/26/2008(Barruecopardo)Further drilling success at Salamanca Tungsten ProjectConten...
1/24/2008(Barruecopardo) Tungsten Resource & Preliminary Economic Evaluation
12/6/2007 Tungsten Drilling ResultsContent-class: urn:content-classes...
11/8/2007(La Zarza) Reports Thick zinc intersections from La Zarza drilling
9/27/2007Tungsten Drilling Results
8/7/2007Reports high grade gold drilling intercepts at its Salamanca...
5/10/2007reports high-grade tungsten in Salamanca drilling
5/2/2006(Salamanca & Zamora)extends new Salamanca gold zone to 2,5 km
Corporate news of Ormonde Mining PLC
9/16/2016Notification of Interest
6/28/2016Declaration of Urgent Occupation - Approved
6/28/2016Publication of Annual Report
6/17/2016Aurum Mining PLC - Convertible Loan and Trading Update
6/16/2016Final Results 2015
6/15/2016Barruecopardo Update
6/7/2016Barruecopardo Drilling Results
5/25/2016Drilling Update
4/15/2015Placing
3/24/2015Directorate Change
11/23/2014Barruecopardo - Granting of Mining Concession
4/10/2013Hemscott News Alert - Ormonde Mining PLC
2/22/2013Hemscott News Alert - Ormonde Mining PLC
2/4/2013Hemscott News Alert - Ormonde Mining PLC
1/23/2013Hemscott News Alert - Ormonde Mining PLC
11/9/2012Hemscott News Alert - Ormonde Mining PLC
10/15/2012Hemscott News Alert - Ormonde Mining PLC
9/17/2012Hemscott News Alert - Ormonde Mining PLC
7/4/2012Hemscott News Alert - Ormonde Mining PLC
6/6/2012Hemscott News Alert - Ormonde Mining PLC
3/28/2012Hemscott News Alert - Ormonde Mining PLC
3/12/2012Hemscott News Alert - Ormonde Mining PLC
2/28/2012Hemscott News Alert - Ormonde Mining PLC
2/13/2012Hemscott News Alert - Ormonde Mining PLC
12/6/2011Hemscott News Alert - Ormonde Mining PLC
9/29/2011Hemscott News Alert - Ormonde Mining PLC
5/16/2011Hemscott News Alert - Ormonde Mining PLC
4/14/2011Hemscott News Alert - Ormonde Mining PLC
6/30/2010Issue of Equity
4/12/2010Signs Option Agreement over Tharsis Project, Spain
9/28/2009Interim Results
7/20/2009Issue of Equity
5/26/2009Preliminary Results 2008
9/22/2008Interim Results
6/12/2008AGM operational update
5/13/2008Final results for the year ending 31 December 2007
5/12/2008 Related tungsten news
5/9/2008Ormonde Mining Announcement
4/16/2008 Steve Nicol joins Ormonde BoardContent-class: urn:content-c...
11/13/2007Multi-vein nature of Spanish tungsten project
11/1/2007 Wide gold intersection in Salamanca
7/12/2007Consolidates 100% interest in La Zarza Copper-Gold Project
7/4/2007Upgrades Barruecopardo Tungsten Prospec
5/16/2007Final Results for the year ended 31 December 2006
Comments closed
 
Latest comment posted for this article
Be the first to comment
Add your comment
LSE (ORM.L)
0.007-98.83%
LSE
GBX 0.007
05/26 09:00 -0.590
-98.83%
Prev close Open
0.600 0.007
Low High
0.007 0.007
Year l/h YTD var.
 -  -
52 week l/h 52 week var.
0.007 -  0.007 -98.83%
Volume 1 month var.
0 -%
24hGold TrendPower© : -15
Produces
Develops Copper - Gold - Lead - Silver - Tungsten - Zinc
Explores for Gold
 
 
 
Analyse
Interactive chart Add to compare
Interactive
chart
Print Compare Export
Last updated on : 6/7/2010
You must be logged in to use the porfolio and watchlists (free)
Top Newsreleases
MOST READ
Annual variation
DateVariationHighLow
20240.00%
2023-99.00%0.840.01
2022-22.22%1.100.41
2021-48.57%3.400.73
2020-32.69%2.740.42
 
5 years chart
 
3 months chart
 
3 months volume chart
 
 
Mining Company News
Plymouth Minerals LTDPLH.AX
Plymouth Minerals Intersects Further High Grade Potash in Drilling at Banio Potash Project - Plannin
AU$ 0.12-8.00%Trend Power :
Santos(Ngas-Oil)STO.AX
announces expected non-cash impairment
AU$ 7.75+0.52%Trend Power :
Oceana Gold(Au)OGC.AX
RELEASES NEW TECHNICAL REPORT FOR THE HAILE GOLD MINE
AU$ 2.20+0.00%Trend Power :
Western Areas NL(Au-Ni-Pl)WSA.AX
Advance Notice - Full Year Results Conference Call
AU$ 3.86+0.00%Trend Power :
Canadian Zinc(Ag-Au-Cu)CZN.TO
Reports Financial Results for Q2 and Provides Project Updates
CA$ 0.12+4.55%Trend Power :
Stornoway Diamond(Gems-Au-Ur)SWY.TO
Second Quarter Results
CA$ 0.02+100.00%Trend Power :
McEwen Mining(Cu-Le-Zn)MUX
TO ACQUIRE BLACK FOX FROM PRIMERO=C2=A0
US$ 11.03-0.72%Trend Power :
Rentech(Coal-Ngas)RTK
Rentech Announces Results for Second Quarter 2017
US$ 0.20-12.28%Trend Power :
KEFIKEFI.L
Reduced Funding Requirement
GBX 0.56+1.09%Trend Power :
Lupaka Gold Corp.LPK.V
Lupaka Gold Receives First Tranche Under Amended Invicta Financing Agreement
CA$ 0.06-8.33%Trend Power :
Imperial(Ag-Au-Cu)III.TO
Closes Bridge Loan Financing
CA$ 2.45-0.81%Trend Power :
Guyana Goldfields(Cu-Zn-Pa)GUY.TO
Reports Second Quarter 2017 Results and Maintains Production Guidance
CA$ 1.84+0.00%Trend Power :
Lundin Mining(Ag-Au-Cu)LUN.TO
d Share Capital and Voting Rights for Lundin Mining
CA$ 15.45+1.31%Trend Power :
Canarc Res.(Au)CCM.TO
Canarc Reports High Grade Gold in Surface Rock Samples at Fondaway Canyon, Nevada
CA$ 0.24-2.08%Trend Power :
Havilah(Cu-Le-Zn)HAV.AX
Q A April 2017 Quarterly Report
AU$ 0.19+0.00%Trend Power :
Uranium Res.(Ur)URRE
Commences Lithium Exploration Drilling at the Columbus Basin Project
US$ 6.80-2.86%Trend Power :
Platinum Group Metals(Au-Cu-Gems)PTM.TO
Platinum Group Metals Ltd. Operational and Strategic Process ...
CA$ 1.76-1.68%Trend Power :
Devon Energy(Ngas-Oil)DVN
Announces $340 Million of Non-Core Asset Sales
US$ 51.84-1.38%Trend Power :
Precision Drilling(Oil)PD-UN.TO
Announces 2017Second Quarter Financial Results
CA$ 8.66-0.35%Trend Power :
Terramin(Ag-Au-Cu)TZN.AX
2nd Quarter Report
AU$ 0.04+0.00%Trend Power :