Quarterly Update on Construction and Commissioning Activities

 

Firestone Diamonds plc, the AIM-quoted Diamond company, is pleased to provide its quarterly update on construction and commissioning activities at its Liqhobong Diamond Mine ("Liqhobong" or the "Project") for the quarter ended December 2016. Liqhobong is owned 75% by Firestone and 25% by the Government of Lesotho.

 

Highlights for the quarter ended 31 December 2016

?        Project construction 100% complete and ramping up to nameplate capacity

?        First Diamond recoveries commenced in late October 2016

?        Recovery of over 20 special stones larger than 10.8 carats, with the largest being a 37 carat white Diamond, as well as several fancy yellow diamonds

?        Processing of lower grade stockpiles and diluted ore in the quarter produced 58,000 carats at a grade of 14.4 carats per hundred tonnes

?        402,000 tonnes treated by the processing plant and nameplate capacity achieved on multiple occasions

?        Strong operating cost management of US$12 per tonne treated at bottom end of guidance

?        Zero lost time injury record maintained, with approximately 3.6 million man hours worked

?        Strong financial position with cash and available facilities of US$18 million, alongside a further US$15 million standby facility available

?        First sale of Liqhobong diamonds will be held in Antwerp, Belgium from 6-10 February 2017

 

Stuart Brown, Chief Executive Officer, commented:

 

"Construction activities at Liqhobong were completed early in the quarter and we are currently in the commissioning and ramp up stage of the Project. We have been pleased with the tonnes processed by the plant, which has already seen nameplate production reached on multiple occasions at this early stage of ramp up.

 

As previously guided, the commencement of commissioning has seen the processing of historic low grade stockpiles, diluted ore and low grade ore from the main pit which at the end of December had produced 58,000 carats. Pleasingly, we have recovered over 20 special stones (larger than 10.8 carats) including a 37 carat white stone and numerous smaller yellow and fancy yellow stones, with no breakages of larger stones to date. At this stage of the ramp up, we have encountered the normal commissioning challenges and these are being addressed by our team in a methodical way.

 

We look forward to providing further updates on the ramp up programme, as well as the Diamond sale next month."

 

Project and Commissioning Update

 

As at 31 December 2016, construction was 100% completed at Liqhobong and first ore was treated through the plant at the end of October 2016, which was well within the revised delivery target.. By the end of December 2016, 402,000 tonnes of ore (being from historic low grade stockpiles, diluted ore and low grade ore from the main pit) had been treated through the plant with a total of 58,000 carats having been recovered, including over 20 special stones larger than 10.8 carats, with the largest being a 37 carat white Diamond, as well as several fancy yellow diamonds.

 

As is normal during the commissioning phase of a new plant, we have had to modify or change certain operating parameters. The current grade of 14.4 carats per hundred tonnes has been below the initial commissioning estimates and the Company is currently focused on making adjustments and investigating potential causes for the under recovery of lower value finer diamonds.

 

During the commissioning process we will continue mining in the lower quality ore areas until the recoveries have reached required levels, following which we will then move into the better quality ore areas within the main pit, where the higher value diamonds are expected to be recovered. The recovery tailings from the commissioning phase are being stored separately and will be retreated once the commissioning adjustments have been made.

 

Operations at the plant have seen good volumes being treated, and on a few occasions during the ramp up stage, the plant has already met the nameplate capacity target of 500 tonnes per hour for 24 consecutive hours. The Company remains on target to achieve nameplate production by the beginning of Q2 2017.

 

During the commissioning phase we have been careful to manage costs in line with the planned tonnage volumes, at US$12 per tonne treated, we are at the bottom end of the guidance of US$12-14 per tonne.

 

The rainy season has also begun and water is being collected and stored in the various water storage facilities for future operations in the dry season.

 

Health & Safety

 

At the end of the quarter, the Project maintained its outstanding health and safety record, having reached 3.6 million man hours worked without a single Lost Time Injury.

 

Financial

 

The Company continues to manage its cash prudently. At the end of the year, cash on hand was US$4 million with US$14 million available under the ABSA debt facility and a further US$15 million available under the standby facility.

 

At the end of December 2016, 95% of the capital budget had been spent on the project with the remaining US$8 million to be spent in Q1 2017.

 

Diamond Sales

 

Firestone has scheduled its first Diamond sale to take place in Antwerp in the week of 6-10 February 2017. Results are expected to be announced during the week commencing 13 February 2017. Thereafter, the Company expects to host two sales per quarter with the second auction due late Q1 2017.

 

The information contained within this announcement is deemed by the Company to constitute inside information as stipulated under the Market Abuse Regulations (EU) No. 596/2014 ("MAR").

 

For more information contact:

 

Firestone Diamonds plc

+44 (0)20 8741 7810

Stuart Brown




Strand Hanson Limited (Nomad)

+44 (0)20 7409 3494

Stuart Faulkner


Richard Tulloch


James Dance




Macquarie Capital (Europe) Limited (Joint Broker)

+44(0)20 3037 2000

Raj Khatri


Nick Stamp




Mirabaud Securities LLP (Joint Broker)


Rory Scott

+44 (0)20 7878 3360

Ed Haig-Thomas

+44 (0)20 7878 3447



Tavistock (Public and Investor Relations)

+44 (0)20 7920 3150

Emily Fenton

+44 (0)7788 554 035

Jos Simson


Barney Hayward


 

Background information on Firestone

 

Firestone is an international Diamond mining company with operations focused on Lesotho. Firestone is currently in the process of commencing production at the Liqhobong Diamond Mine in Lesotho to become a one million carat per annum producer.

 

Lesotho is emerging as one of Africa's significant new Diamond producers, hosting Gem Diamonds' Letseng Mine, Firestone's Liqhobong Mine and Namakwa Diamonds' Kao Mine.

 

For more information please visit: www.firestonediamonds.com.

 

**ENDS**


This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
UPDBRGDBLGDBGRU

To unsubscribe or to change your subscriber options, go to:

http://www.firestonediamonds.com/investors/new-alerts/email-alerts
.
Data and Statistics for these countries : Belgium | Lesotho | All
Gold and Silver Prices for these countries : Belgium | Lesotho | All

Firestone Diamonds PLC

DEVELOPMENT STAGE
CODE : FDI.L
ISIN : GB0003915336
Follow and Invest
Add to watch list Add to your portfolio Add or edit a note
Add Alert Add to Watchlists Add to Portfolio Add Note
ProfileMarket
Indicators
VALUE :
Projects & res.
Press
releases
Annual
report
RISK :
Asset profile
Contact Cpy

Firestone D is a diamonds exploration company based in United kingdom.

Firestone D holds various exploration projects in Botswana.

Its main asset in development is BK11 in Botswana and its main exploration property is TSABONG in Botswana.

Firestone D is listed in Germany, in United Kingdom and in United States of America. Its market capitalisation is GBX 101.0 millions as of today (US$ 110.1 millions, € 100.9 millions).

Its stock quote reached its highest recent level on October 22, 2004 at GBX 1 000.00, and its lowest recent point on March 20, 2020 at GBX 0.05.

Firestone D has 505 113 970 shares outstanding.

Your feedback is appreciated, please leave a comment or rate this article.
Rate : Average note :0 (0 vote) View Top rated
 
Financings of Firestone Diamonds PLC
7/21/2016Issue of shares
Nominations of Firestone Diamonds PLC
6/2/2009Appointment of Joint Brokers
6/19/2008Joint broker appointment
Project news of Firestone Diamonds PLC
7/20/2016(Liqhobong)Liqhobong Diamond Mine Construction Update
9/25/2009(Tsabong)Botswana operations update
6/26/2008(Tsabong)Botswana operations update
2/25/2008(Tsabong)Encouraging results from MK1 kimberlite, Tsabong
2/18/2008(Tsabong)Tsabong Evaluation Update
Corporate news of Firestone Diamonds PLC
7/25/2016NOTIFICATION OF MAJOR INTEREST IN SHARES
7/25/2016Holding(s) in Company
3/27/2013Hemscott News Alert - Firestone Diamonds PLC
1/29/2013Hemscott News Alert - Firestone Diamonds PLC
11/6/2012Hemscott News Alert - Firestone Diamonds PLC
10/25/2012Hemscott News Alert - Firestone Diamonds PLC
10/8/2012Hemscott News Alert - Firestone Diamonds PLC
9/27/2012Hemscott News Alert - Firestone Diamonds PLC
5/14/2012(AIM: FDI) operational update Q1 2012
5/14/2012Hemscott News Alert - Firestone Diamonds PLC
4/2/2012Hemscott News Alert - Firestone Diamonds PLC
3/15/2012Hemscott News Alert - Firestone Diamonds PLC
2/28/2012Hemscott News Alert - Firestone Diamonds PLC
2/1/2012Hemscott News Alert - Firestone Diamonds PLC
1/17/2012Hemscott News Alert - Firestone Diamonds PLC
12/30/2011Hemscott News Alert - Firestone Diamonds PLC
12/5/2011Hemscott News Alert - Firestone Diamonds PLC
10/10/2011Hemscott News Alert - Firestone Diamonds PLC
9/14/2011[AIM: FDI] diamond sales results
9/14/2011Hemscott News Alert - Firestone Diamonds PLC
8/30/2011Hemscott News Alert - Firestone Diamonds PLC
7/20/2011[AIM: FDI] Operations update
5/3/2011Hemscott News Alert - Firestone Diamonds PLC
4/21/2011Hemscott News Alert - Firestone Diamonds PLC
3/24/2011Hemscott News Alert - Firestone Diamonds PLC
3/4/2011..cal Testwork using AmmLeach\256 on Firestone's...
3/2/2011Extends Expiry Date of Outstanding Warrants
7/24/2009Result of General Meeting
7/8/2009Update on Botswana operations and placing
2/19/2009Selected by Debswana as preferred bidder for Jwaneng Modular...
2/9/2009Buffels River Toll Treatment Update
7/16/2008Placing raises £5 million
6/18/2008Additional Listing
5/20/2008NOTIFICATION OF MAJOR INTERESTS IN SHARES
3/31/2008Unaudited interim results for the six months to 31 December ...
10/29/2007Update on Tsabong evaluation programme, Botswana
10/8/2007Hemscott News Alert - Firestone Diamonds PLC
Comments closed
 
Latest comment posted for this article
Be the first to comment
Add your comment
LSE (FDI.L)Other OTC (FRDIF)
0.200+53.85%0.006-40.00%
LSE
GBX 0.200
03/25 16:45 0.070
53.85%
Prev close Open
0.130 0.180
Low High
0.150 0.300
Year l/h YTD var.
 -  -
52 week l/h 52 week var.
- -  0.200 -%
Volume 1 month var.
1,384,451 -%
24hGold TrendPower© : 2
Produces
Develops Diamonds
Explores for
 
 
 
Analyse
Interactive chart Add to compare
Interactive
chart
Print Compare Export
You must be logged in to use the porfolio and watchlists (free)
Top Newsreleases
MOST READ
Annual variation
DateVariationHighLow
2020-70.59%1.100.05
 
5 years chart
 
3 months chart
 
3 months volume chart
 
 
Mining Company News
Plymouth Minerals LTDPLH.AX
Plymouth Minerals Intersects Further High Grade Potash in Drilling at Banio Potash Project - Plannin
AU$ 0.12-8.00%Trend Power :
Santos(Ngas-Oil)STO.AX
announces expected non-cash impairment
AU$ 7.71-0.39%Trend Power :
Oceana Gold(Au)OGC.AX
RELEASES NEW TECHNICAL REPORT FOR THE HAILE GOLD MINE
AU$ 2.20+0.00%Trend Power :
Western Areas NL(Au-Ni-Pl)WSA.AX
Advance Notice - Full Year Results Conference Call
AU$ 3.86+0.00%Trend Power :
Canadian Zinc(Ag-Au-Cu)CZN.TO
Reports Financial Results for Q2 and Provides Project Updates
CA$ 0.12+4.55%Trend Power :
Stornoway Diamond(Gems-Au-Ur)SWY.TO
Second Quarter Results
CA$ 0.02+100.00%Trend Power :
McEwen Mining(Cu-Le-Zn)MUX
TO ACQUIRE BLACK FOX FROM PRIMERO=C2=A0
US$ 11.11+2.21%Trend Power :
Rentech(Coal-Ngas)RTK
Rentech Announces Results for Second Quarter 2017
US$ 0.20-12.28%Trend Power :
KEFIKEFI.L
Reduced Funding Requirement
GBX 0.55-0.90%Trend Power :
Lupaka Gold Corp.LPK.V
Lupaka Gold Receives First Tranche Under Amended Invicta Financing Agreement
CA$ 0.06-8.33%Trend Power :
Imperial(Ag-Au-Cu)III.TO
Closes Bridge Loan Financing
CA$ 2.47+3.78%Trend Power :
Guyana Goldfields(Cu-Zn-Pa)GUY.TO
Reports Second Quarter 2017 Results and Maintains Production Guidance
CA$ 1.84+0.00%Trend Power :
Lundin Mining(Ag-Au-Cu)LUN.TO
d Share Capital and Voting Rights for Lundin Mining
CA$ 15.25-3.42%Trend Power :
Canarc Res.(Au)CCM.TO
Canarc Reports High Grade Gold in Surface Rock Samples at Fondaway Canyon, Nevada
CA$ 0.24+0.00%Trend Power :
Havilah(Cu-Le-Zn)HAV.AX
Q A April 2017 Quarterly Report
AU$ 0.19+0.00%Trend Power :
Uranium Res.(Ur)URRE
Commences Lithium Exploration Drilling at the Columbus Basin Project
US$ 6.80-2.86%Trend Power :
Platinum Group Metals(Au-Cu-Gems)PTM.TO
Platinum Group Metals Ltd. Operational and Strategic Process ...
CA$ 1.79-3.76%Trend Power :
Devon Energy(Ngas-Oil)DVN
Announces $340 Million of Non-Core Asset Sales
US$ 52.57+0.84%Trend Power :
Precision Drilling(Oil)PD-UN.TO
Announces 2017Second Quarter Financial Results
CA$ 8.66-0.35%Trend Power :
Terramin(Ag-Au-Cu)TZN.AX
2nd Quarter Report
AU$ 0.04+5.88%Trend Power :