Colossus Minerals Provides Development Update
Published : September 23, 2013
( 0 vote, 0/5 ) Print article
  Article Comments Comment this article Rating Follow Company  
0
Send
0
comment

TORONTO, ONTARIO--(Marketwired - Sept. 23, 2013) - Colossus Minerals Inc. (the "Company" or "Colossus") (News - Market indicators)(OTCQX:COLUF) provides a development update for its 75% owned Serra Pelada gold-platinum-palladium Mine. The Serra Pelada Mine is a joint venture between Colossus and Cooperativa de Mineração dos Garimpeiros de Serra Pelada ("COOMIGASP") located in the State of Pará, Brazil. 

HIGHLIGHTS

  • The Company is on track with its dewatering program expansion. As of September 17, 2013, six of the originally planned ten wells are pumping and total dewatering output is approximately 800 m3 per hour. Currently, total output exceeds the recharge rate by approximately 75% and total output is expected to reach approximately 1,500 m3 per hour by December 2013.
     
  • Underground development has progressed according to the plan detailed in the Company's July 15, 2013 press release. In August, the Company advanced on four separate development faces achieving advance in the main decline, ventilation access drift, the north access and a permanent pumping station. The Company achieved 85 metres of development in August over 24 days resulting in an advance rate in excess of 3.5 metres per day. According to plan, the Company stopped development for a period of 7 days to complete the first phase of the ventilation system expansion.
     
  • The Company plans to continue the decline development to have multiple access drives ready for mining in 2014. Five access drives will be developed to commence feeding the process plant late in the fourth quarter of 2013. Commissioning of individual unit operations commenced in August and will continue throughout September and early into the fourth quarter.
     
  • The bulk sample will be processed once management is satisfied with process plant operating effectiveness.
     
  • The first phase of ventilation expansion is complete. The second phase of the expansion is 55% complete with shaft sinking progressing well.
     
  • Tailings dam construction is progressing well with 85% of the project complete to date. The tailings dam is expected to be complete ahead of process plant start-up.

Claudio Mancuso, Chief Executive Officer commented, "After the setback related to dewatering experienced in July, the Company's dewatering and underground development activities are progressing according to the remediation plan communicated in mid-July. Completion of the first phase of the ventilation system expansion provides a four-fold increase in underground airflow and allows us to begin ramping up development with increased manpower and equipment in September. The underground team achieved development on four separate faces in August and we remain on track to have five access drives ready to enter the Central Mineralized Zone in December."

CONSTRUCTION AND DEVELOPMENT ACTIVITIES

Underground Development

As of September 19, 2013, the Company had completed approximately 2,200 metres of total development; 1,400 primary and 800 metres of secondary development. In August, the Company completed 85 metres of development over a 24 day period advancing on four separate faces. The Company ceased development for a seven day period to complete the first phase of the ventilation system expansion (discussed below). The 85 metres of development in August consisted of 37 metres in the main decline, 30 metres of secondary excavation for a permanent pumping station, three metres in the northern access and 15 metres in the ventilation access drift and other secondary development. Over the 24 day period prior to the shutdown to complete the ventilation system expansion, the Company averaged approximately 3.5 metres per day.

As previously announced, some dewatering wells and pumps were not performing to design specifications and, as a result, the Company required additional dewatering capacity in order to mine the Central Mineralized Zone ("CMZ") in a sustainable, effective and efficient manner. As a result, the Company is expanding its dewatering capacity. As of September 17, 2013, six of the originally planned ten wells are pumping and total dewatering output is approximately 800 m3 per hour. Currently, total output exceeds the recharge rate by approximately 75% and total output is expected to reach approximately 1,500 m3 per hour by December 2013. A new 250 m3 per hour well is currently being drilled and is expected to be operational by the end of October. To provide additional contingency, the Company has recently initiated an additional 250 m3 per hour well. Contractors have been mobilized and the additional well will be operational by the end of December. Since the previous development update, the Company has also decided to refurbish three of the original wells which were planned to be abandoned. These three refurbished wells will provide an additional 100 m3 per hour of contingency capacity. Excavation for a permanent underground pumping station was completed in August and civil work and mechanical installation will continue throughout the end of September and early October. Once completed, the permanent pumping station will provide 800 m3 per hour of pumping capacity from underground, which is over three times the current underground inflow of 250 m3 per hour.

As previously disclosed, the ventilation system requires expansion to provide sufficient air to support four crews and sets of equipment. The expansion work includes widening and concrete lining the artisanal shaft which will be used as a ventilation raise and development of a drift to tie the ramp to this ventilation raise at depth. The project to upgrade the ventilation system is approximately 55% complete.

The first phase of the ventilation system expansion was completed in August. The first phase involved moving vent fans from surface to the current ramp access to the artisanal shaft, and civil works involved with installing the fans in this new location. This first phase expansion has increased airflow underground from 10m3/s to 45m3/s by drawing air through the artisanal shaft with increased fan and reticulation capacity. This first phase expansion allows the Company to begin ramping-up development crews and equipment to remain on track with its previously disclosed development objectives.

The Company anticipates it will begin feeding the process plant late in the fourth quarter of 2013 and continues to make progress in its mine planning activities. Management previously laid out the month by month schedule for development for the remainder of 2013. Specifically, the Company's schedule for the advancement of development at the Serra Pelada Mine for July and August, with the actual results for the respective months, is laid out in the following table:

Month   Activity - Set out July 15, 2013   Result
July 2013   Progress decline, and advance pump station and vent access.   • Decline development - 47 metres
• Pump station development - 12 metres
• North access - 11 metres
• Vent access and other secondary development - 14 metres
         
August 2013   Continue to progress decline, advance development of pump station, and continue to advance vent access. Install interim expansion (Phase I) of the ventilation system.   • Decline development - 37 metres
• Pump station development - 30 metres
• North access - 3 metres
• Vent access and other secondary development - 15 metres
• Development stopped 7 days & the first phase of the ventilation system expansion was completed
• Ventilation expansion increased air flow from 10m3/s to 45m3/s and allows for ramp-up of crews and equipment to begin in September

Process Plant

The various phases of the process plant construction, along with respective percentages complete are presented in the table below.

  August 13 Sept. 17
Total Project 90% 92%
Process Plant    
  Engineering 99% 100%
  Procurement 99% 99%
  Civil construction 99% 100%
  Structural steel fabrication 100% 100%
  Structural, mechanical, piping & electrical installation 85% 88%
Commissioning   15%
Power house 100% 100%
Ventilation Upgrade Phase I 50% 100%
Ventilation Upgrade Phase II 50% 55%
Tailings impoundment facility 65% 80%
Rehabilitation of dewatering bore field 70% 85%
Expansion of dewatering capacity 20% 30%

Process plant construction is progressing well. Significant milestones achieved since the last development update include:

  • Inspection of buildings for the purpose of signing off handover of facilities to the Company is advanced. Commissioning of unit operations is underway.
     
  • The primary crusher area's structural steel, platework and associated equipment installation is 100% complete. Electrical and instrumentation installations are approaching completion. Commissioning of the primary crusher continued in August.
     
  • The reagent handling area structural steel, platework and associated equipment installation is 100% complete. Electrical and instrumentation installations are progressing.
     
  • All of the structural steel and platework is 100% erected.
     
  • Mechanical installations and piping in the grinding building are progressing well with this area now 90% complete.
     
  • Significant progress has been made in erecting the conveyor systems. Conveyor belts are installed and ready for commissioning.
     
  • The primary screen, scrubber and a number of tanks have been installed in the Scrubbing & Screening building. Installation of pipe and electrical equipment has been advanced to +50%.
     
  • Civil construction of the gold room is complete. Erection of tanks and other mechanical installations in the gold room area are progressing. 

Infrastructure

Other infrastructure construction is progressing as planned. The power house is complete and commissioned. The Company is currently running two of the four generators and electrical reticulation across the project site is complete. Connection to the grid has been achieved and commissioning of the power line was started the second week of August 2013. This facility will go live September 26, 2013. 

Construction of the tailings dam was slowed due to issues of payment and contractor access. Nonetheless, as of September 17, 2013, this component of the project is 80% complete with the clearing, diversion structures, spillway, and foundation complete. Bulk earthworks are advanced and project completion is now scheduled for late September 2013.

Denver Gold Forum

Colossus will be presenting at the Denver Gold Forum to be held September 22 to 25, 2013 at the Hyatt Regency, Denver, Colorado, USA.

Mr. Claudio Mancuso, Chief Executive Officer, is scheduled to speak on Wednesday, September 25, 2013 at 11:45 am MT. The presentation will be available on Colossus' website on September 23, 2013 and the webcast will be available from a link from the Company's home page on September 25, 2013.

About Colossus:

Colossus is a development-stage mining company focused on bringing its 75% owned Serra Pelada gold-platinum-palladium Mine into production. The Serra Pelada Mine is a joint venture between Colossus and COOMIGASP located in the State of Pará, Brazil. Serra Pelada, located in the mineral prolific Carajas region in the State of Pará, is host to one of the highest grade gold and platinum group metals deposits in the world. Between 1980 and 1986 Serra Pelada was host to the largest precious metals rush in Latin American history. Colossus Minerals Common Shares, warrants and notes trade on the Toronto Stock Exchange (TSX) under the symbols CSI, CSI.WT.A, CSI.WT.B and CSI.NT respectively and in the United States its Common Shares trade on the OTCQX under the symbol COLUF. The Company is headquartered in Toronto, Canada.

Qualified Person:

David Anthony, P. Eng., President and Chief Operating Officer of Colossus, is a "qualified person" as such term is defined in National Instrument 43-101 and has reviewed and approved the technical information and data included in this press release.

CAUTIONARY STATEMENT REGARDING FORWARD-LOOKING INFORMATION

Forward-looking statements in this press release include statements regarding the timing and nature of future exploration and development programs that are dependent on projections that may change as drilling continues, or if unexpected ground conditions are encountered. The Company does not currently have any mineral properties that are in production or that contain a reserve as defined by National Instrument 43-101. In addition, areas of exploration potential are identified which will require additional drilling to determine whether or not they contain similar mineralization to areas that have been explored in more detail. Significant additional drilling is required at Serra Pelada to fully understand system size.

Except for statements of historical fact relating to Colossus, certain statements in this press release relating but not limited to the Company's exploration and development plans, activities and intentions, constitute "forward-looking information" within the meaning of the Securities Act (Ontario) or "forward-looking statements" within the meaning of the United States Private Litigation Reform Act of 1995. These forward-looking statements represent management's best judgment based on current facts and assumptions that management considers reasonable. Forward-looking statements are frequently characterized by words such as "target", "plan", "expect", "project", "intend", believe", "anticipate" and other similar words, or statements that certain events or conditions "appear to", "may" or "will" occur. Forward-looking statements are based on the opinions and estimates of management at the date the statements are made, and are subject to a variety of risks and uncertainties and other factors that could cause actual events or results to differ materially from those projected in the forward-looking statements. The factors include but are not limited to risks related to the Company's relationship with COOMIGASP and/or those seeking to control it, the joint venture operation, actual results of exploration activities, the inherent risks involved in the exploration and development of mineral properties, changes in project parameters as plans continue to be refined, delays in obtaining government approvals, the uncertainties of project cost overruns or unanticipated costs and expenses, uncertainties relating to the availability and costs of financing needed in the future, the uncertainties inherent to conducting business in Brazil and the rest of Latin America, the availability of equipment and supplies, unexpected adverse climate conditions, the reliance on only a few key members of management, as well as those factors discussed in the section entitled "Risk Factors" in the Company's most recent Annual Information Form filed with Canadian provincial securities regulatory authorities and other regulatory filings which are posted on SEDAR at www.sedar.com. Unless required by law, Colossus undertakes no obligation to update forward-looking statements if circumstances or management's estimates or opinions should change. The reader is cautioned not to place undue reliance on forward-looking statements.



Colossus Minerals Inc.
Ann Wilkinson
VP, Investor Relations
(416) 643-7655
awilkinson@colossusminerals.com
www.colossusminerals.com
Data and Statistics for these countries : Brazil | Canada | All
Gold and Silver Prices for these countries : Brazil | Canada | All

Colossus Minerals Inc

EXPLORATION STAGE
CODE : CSI.TO
ISIN : CA19681L1094
Follow and Invest
Add to watch list Add to your portfolio Add or edit a note
Add Alert Add to Watchlists Add to Portfolio Add Note
ProfileMarket
Indicators
VALUE :
Projects & res.
Press
releases
Annual
report
RISK :
Asset profile
Contact Cpy

Colossus Minerals is a gold and palladium exploration company based in Canada.

Its main exploration properties are SERRA PELADA and NATIVIDADE in Brazil.

Colossus Minerals is listed in Canada. Its market capitalisation is CA$ 4.3 millions as of today (US$ 3.8 millions, € 2.8 millions).

Its stock quote reached its highest recent level on December 03, 2010 at CA$ 9.87, and its lowest recent point on January 17, 2014 at CA$ 0.03.

Colossus Minerals has 106 978 000 shares outstanding.

Your feedback is appreciated, please leave a comment or rate this article.
Rate : Average note :0 (0 vote) View Top rated
 
Financings of Colossus Minerals Inc
11/30/2009Expiry of Warrants
11/25/2009’s Final Reminder to Holders of Unexercised $2.70 Common Sha...
10/26/2009Provides Notice of Early Expiry of Warrants
3/10/2009Announces Closing Of $24.7 Million Bought Deal Financing
2/12/2009Announces Cdn$21,500,000 Bought Deal Financing
Nominations of Colossus Minerals Inc
10/16/2013Names David Massola as New Chief Financial Officer
3/28/2013Provides Development Update and Announces the Addition of J....
12/11/2012Announces Management Appointments and Board Changes
11/8/2012Announces Search for Chief Operating Officer
10/12/2012Appoints John Frostiak as Chairman Following Planned Departu...
7/16/2012Appoints Lyle Pritchard as Vice President, Operations and Pr...
8/2/2011Appoints Antenor Silva and Mel Leiderman to its Board of Dir...
5/18/2011Appoints David Anthony to the Board of Directors
5/9/2011Appoints Paulo de Tarso Serpa Fagundes Chief Operating Offic...
3/3/2011Appoints Claudio Mancuso as Chief Financial Officer
9/28/2009Appoints Randy Reichert as President & COO
Project news of Colossus Minerals Inc
2/7/2013' Development Remains On Schedule for Initial Production In ...
12/15/2011(Serra Pelada)Extends High Grade Subzones in the CMZ and Expands the GT Zo...
3/24/2011(Serra Pelada)Drills 7.81 Metres at 136.43 g/t Gold, 249.20 g/t Platinum a...
12/17/2009(Serra Pelada)Approval of the Final Exploration Report for the Serra Pelad...
11/2/2009(Serra Pelada)Media Coverage: “Colossus Delivers More Monster Holes at Ser...
11/3/2009(Serra Pelada)Commences Metallurgical Testing on Gold-Platinum-Palladium M...
9/3/2009(Serra Pelada)Drills 4.15 Metres @ 8.04 g/t Gold, 154.5 g/t Platinum and 2...
6/1/2009(Serra Pelada)Sponsors First Essay Writing Contest in Serra Pelada
2/11/2009(Serra Pelada)7.88M @ 98.4 g/t Platinum, 115.7 g/t Palladium, 2.74 g/t Rho...
Corporate news of Colossus Minerals Inc
10/25/2013Announces Board Change
9/23/2013Provides Development Update
9/10/2013to Present at the Bank of America Merrill Lynch 19th Annual ...
8/26/2013(Serra Pelada). Clarifies Events at Serra Pelada
8/13/2013. Completes C$37,950,000 Million Bought Deal Financing
7/23/2013. Announces Overnight Marketed Offering
7/15/2013Provides Development Update
7/8/2013Intersects Gold and Copper in its Phase 1 Drilling Program o...
7/8/2013Intersects Gold and Copper in its Phase 1 Drilling Program o...
6/18/2013Provides Development Update
6/12/2013. Completes C$28.75 Million Bought Deal Financing
5/21/2013Announces Voting Results
5/15/2013Provides Development Update
4/16/2013to Present at the European Gold Forum 2013
2/25/2013to Present at the BMO Capital Markets 22nd Global Metals & M...
1/25/2013to Present at the 2013 TD Securities Mining Conference
1/10/2013Intersects High Grade Gold Values in Diamond Drilling at Ele...
9/19/2012and Sandstorm Agree to a US$75 Million Long-Term Precious Me...
9/10/2012to Present at the 2012 Denver Gold Forum
8/20/2012Provides Update on Exploration on Elefante Area
6/18/2012Drills 3.30 Metres at 54.48 g/t Gold, 0.69 g/t Platinum and ...
5/29/2012to Present at Euro Pacific Global Investment Conference
5/15/2012Provides Update and Reminder of Annual General Meeting
4/30/2012to Present at Macquarie's "Making the Grade" Mining Conferen...
4/25/2012Drills 109.89 g/t Gold, 0.75 g/t Platinum and 15.51 g/t Pall...
4/10/2012Announces Significant Achievement in Metallurgical Recoverie...
4/2/2012(Serra Pelada)Provides Operations and Development Update for Serra Pelada
3/12/2012Expands the Elefante Mineralization, Intersects Gold in Uppe...
3/1/2012. Joins OTCQX
2/23/2012to Present at BMO Capital Markets 2012 Global Metals & Minin...
1/24/2012to Present at TD Securities 2012 Mining Conference
1/16/2012Acquires Cutia Property
12/2/2011to Present at Clarus Securities Inc. "Top of the Rocks" Inve...
10/11/2011Continues Strategic Evolution Toward Producer Status
9/7/2011Drilling Extends the GT Zone and High-Grade Subzones in the ...
4/26/2011Drills 7.30 Metres at 1494.7 g/t Gold, 516.6 g/t Platinum an...
1/24/2011Announces Results of AGM and Expiry of Warrants
11/23/2009Earning a 75% Interest in Serra Pelada Project
11/12/2009Listed on Van Eck’s Junior Miners ETF Index
11/12/2009Announces an Amendment to the Partnership Agreement with Coo...
10/28/2009Media Coverage: Steve Palmer, President & CEO of Alpha North...
10/7/2009Announces Filing Of Preliminary Prospectus
10/1/2009Announces $57.5 Million Bought-Deal Financing and Adopts Sha...
9/30/2009Drills 70.70 metres @ 53.59 g/t gold, 20.77 g/t platinum and...
8/10/2009Announces Change of Auditors
8/4/2009’s Check Assays Yield Higher Precious Metal Grades
7/3/2009Media Coverage: Mining Journal’s Feature on Brazil Highlight...
7/2/2009Media Coverage: Sprott Asset Management's Charles Oliver and...
6/15/2009Media Coverage: John Embry, Chief Investment Strategist at S...
6/4/2009Drills 27.9 metres @ 35.49 g/t gold, 19.89 g/t platinum and ...
2/11/2009Media Coverage: Steve Palmer, President & CEO of Alpha North...
Comments closed
 
Latest comment posted for this article
Be the first to comment
Add your comment
TORONTO (CSI.TO)
0.040+0.00%
TORONTO
CA$ 0.040
02/21 15:47 -
0%
Prev close Open
0.040 0.040
Low High
0.030 0.040
Year l/h YTD var.
 -  -
52 week l/h 52 week var.
- -  0.040 -%
Volume 1 month var.
1,866,075 -%
24hGold TrendPower© : -11
Produces
Develops
Explores for Gold - Palladium
 
 
 
Analyse
Interactive chart Add to compare
Interactive
chart
Print Compare Export
Last updated on : 10/8/2010
You must be logged in to use the porfolio and watchlists (free)
Top Newsreleases
MOST READ
Annual variation
DateVariationHighLow
 
5 years chart
 
3 months chart
 
3 months volume chart
 
 
Mining Company News
Plymouth Minerals LTDPLH.AX
Plymouth Minerals Intersects Further High Grade Potash in Drilling at Banio Potash Project - Plannin
AU$ 0.12-8.00%Trend Power :
Santos(Ngas-Oil)STO.AX
announces expected non-cash impairment
AU$ 7.72-0.19%Trend Power :
Oceana Gold(Au)OGC.AX
RELEASES NEW TECHNICAL REPORT FOR THE HAILE GOLD MINE
AU$ 2.20+0.00%Trend Power :
Western Areas NL(Au-Ni-Pl)WSA.AX
Advance Notice - Full Year Results Conference Call
AU$ 3.86+0.00%Trend Power :
Canadian Zinc(Ag-Au-Cu)CZN.TO
Reports Financial Results for Q2 and Provides Project Updates
CA$ 0.12+4.55%Trend Power :
Stornoway Diamond(Gems-Au-Ur)SWY.TO
Second Quarter Results
CA$ 0.02+100.00%Trend Power :
McEwen Mining(Cu-Le-Zn)MUX
TO ACQUIRE BLACK FOX FROM PRIMERO=C2=A0
US$ 10.87-3.12%Trend Power :
Rentech(Coal-Ngas)RTK
Rentech Announces Results for Second Quarter 2017
US$ 0.20-12.28%Trend Power :
KEFIKEFI.L
Reduced Funding Requirement
GBX 0.56+0.00%Trend Power :
Lupaka Gold Corp.LPK.V
Lupaka Gold Receives First Tranche Under Amended Invicta Financing Agreement
CA$ 0.06-8.33%Trend Power :
Imperial(Ag-Au-Cu)III.TO
Closes Bridge Loan Financing
CA$ 2.38-4.03%Trend Power :
Guyana Goldfields(Cu-Zn-Pa)GUY.TO
Reports Second Quarter 2017 Results and Maintains Production Guidance
CA$ 1.84+0.00%Trend Power :
Lundin Mining(Ag-Au-Cu)LUN.TO
d Share Capital and Voting Rights for Lundin Mining
CA$ 15.79-0.32%Trend Power :
Canarc Res.(Au)CCM.TO
Canarc Reports High Grade Gold in Surface Rock Samples at Fondaway Canyon, Nevada
CA$ 0.24+0.00%Trend Power :
Havilah(Cu-Le-Zn)HAV.AX
Q A April 2017 Quarterly Report
AU$ 0.19+0.00%Trend Power :
Uranium Res.(Ur)URRE
Commences Lithium Exploration Drilling at the Columbus Basin Project
US$ 6.80-2.86%Trend Power :
Platinum Group Metals(Au-Cu-Gems)PTM.TO
Platinum Group Metals Ltd. Operational and Strategic Process ...
CA$ 1.86+0.54%Trend Power :
Devon Energy(Ngas-Oil)DVN
Announces $340 Million of Non-Core Asset Sales
US$ 52.13+0.58%Trend Power :
Precision Drilling(Oil)PD-UN.TO
Announces 2017Second Quarter Financial Results
CA$ 8.66-0.35%Trend Power :
Terramin(Ag-Au-Cu)TZN.AX
2nd Quarter Report
AU$ 0.04+5.88%Trend Power :