| Reserves and resources of the Boddington Project |
| Tonnage | Grade | Reserves and resources |
| Gold | Gold |
| g/t | oz |
| Proven | 45,735,000 | 0.94 | 1 382 190 |
| Probable | 125,581,000 | 0.78 | 3 149 268 |
| Proven and Probable | 171,316,000 | 0.82 | 4 531 457 |
| Measured | 52,384,000 | 0.88 | 1 482 083 |
| Indicated | 202,688,000 | 0.69 | 4 496 434 |
| Mesured and Indicated | 255,072,000 | 0.73 | 5 978 516 |
| Inferred | 226,651,000 | 0.59 | 4 299 329 |
| Total | 653 039 000 | | 14 809 303 |
|
|
|
Definitions
|
| Reserves and resources of the Boddington Project |
| Metal | Total | Reserves | Mineralized Material | Unit | In situ value |
| | Proven | Probable | Proven and Probable | Measured | Indicated | Mesured and Indicated | Inferred | | |
| Gold | 14 809 303 | 1 382 190 | 3 149 268 | 4 531 457 | 1 482 083 | 4 496 434 | 5 978 516 | 4 299 329 | oz | 20 270 529 567 US$ |
|
|
|
|
|
| Production history |
| Metal | 2009 | 2008 | 2007 | 2006 | 2005 | 2004 | 2002 | 2001 | 2000 | 1999 |
| GOLD (oz) | | | | | | | 4,235 | 227,171 | 228,859 | 231,695 |
|
| Production Objectives |
| Metal | 2013 | 2014 | 2015 | 2016 | 2017 | 2018 | 2019 | 2020 |
| GOLD (oz) | 1,000,000 | 1,000,000 | 1,000,000 | 1,000,000 | 1,000,000 | 1,000,000 | 1,000,000 | 1,000,000 |
|
|
|
|