African Eagle Resources PLC

Publié le 21 juin 2011

(UK) - Mid-year progress report

( 0 vote, 0/5 ) Imprimer l'article
  Article Commentaires Commenter Notation Suivre la société  
0
envoyer
0
commenter
Mots clés associés :   Aluminium | Cobalt | Copper | Manganese | Nickel |
   

Published: 09:00 CEST 21-06-2011 /Thomson Reuters /Source: African Eagle Resources PLC /XLON: AFE /ISIN: GB0003394813

Mid-year progress report


African Eagle Resources plc

MID-YEAR PROGRESS REPORT

Dutwa

  • Second bulk ore sample drilling nears completion
  • Geotechnical testwork completed on first bulk ore sample
  • Mineralogical study conducted by London Natural History Museum
  • Metallurgical testwork progressing well at labs in Australia and South Africa
  • Environmental baseline and social impact assessment started
  • Significant progress on logistics and reagents studies

Other Projects

  • JV partner BrightStar commences 10,000m drilling programme at Miyabi gold project, Tanzania
  • Zambian copper spin-out company Cobra Copper incorporated
  • Board reorganisation well advanced


Dutwa is a unique nickel project with a JORC resource of 99 million tonnes at 0.93% Ni, easily mined from two hilltop deposits and amenable to simple, low acid consumption atmospheric leaching, leading to world class economics. The updated independent financial modelling prepared for the feasibility study by Simulus in March 2011 indicated a net present value for a 3Mtpa project of $870M at today's nickel price of $10/lb, with cash operating costs of approximately $3.40/lb and a projected capital payback of between three and five years.

The African Eagle board's intention is to deliver a definitive feasibility study ("DFS") on Dutwa by the end of Q4 2012 - the pre-feasibility stage of this is on track for late 2011. Mineral processing and metallurgical testwork, key components of the DFS, are currently underway on carefully chosen bulk samples of each of the ore types. The new testwork will build on the results of past tests which demonstrated that the Dutwa ore can be treated by simple atmospheric leaching at low acid consumption, with no requirement to employ costly and challenging HPAL (high pressure acid leaching) technology. The new tests will help to optimise the process flow-sheet and investigate various ways to cut operating costs to improve the favourable economics already demonstrated by our scoping studies.

Several elements of the DFS are already underway in parallel with the pre-feasibility work, including drilling a second bulk ore sample for pilot-plant testwork and the environmental and social impact assessment.

African Eagle's Managing Director Mark Parker comments: "We are pleased to report good progress on our Dutwa DFS. Geotechnical tests have been completed on Bulk Ore Sample 1; metallurgical test programmes are well underway; and diamond drilling to obtain Bulk Ore Sample 2 is almost complete. We expect to recommence drilling for the resource upgrade at the Ngasamo part of Dutwa in early July. We have made a start on the baseline work for our environmental and social impact assessment and advanced our logistics and reagents studies. We are on schedule with the DFS and expect to establish the preferred treatment process for Dutwa ore and complete the pre-feasibility stage of the study in late 2011.

"Our management reorganisation, which is intended to put in place the skills and expertise we will need for the finance and construction of the Dutwa project, is making good progress. The spin out of our Zambian copper projects into a new company, Cobra Copper, is advancing well. In Tanzania, our partner BrightStar Resources has begun a major drill programme at the Miyabi gold project."


Dutwa progress

Tests are well underway on Bulk Ore Sample 1 ("BOS1"), which was shipped to the ALS AMMTEC lab in Perth WA in Q1 2011. BOS1 consists of about 10 tonnes of large diameter mineralised drill core, from holes carefully selected to be representative of the averages and variations of the principal ore types from both Wamangola and Ngasamo. Testwork so far has focused on investigating the properties of the ore in crushing and grinding prior to leaching, and on geotechnical tests to determine the rock parameters for mining engineering and pit design. The test data have been incorporated into a request to quote for accurate mining cost estimates for input to the feasibility study, sent to international mining contractors. Beneficiation tests now underway on BOS1 employ commonly used laterite ore processing steps such as crushing, drum scrubbing, attritioning and screening to determine the upgrade potential of the various types of ore, ahead of integrated feed slurry preparation and leaching tests.

This testwork has been complimented by a mineralogical study by the London Natural History Museum ("NHM"), which is giving valuable insights into the style and nature of the nickel and cobalt mineralisation. Understanding the mineralogy of nickel laterites is vital in developing the optimum ore treatment method. The information from the NHM study will help us to design a process flow-sheet which minimises the amount of acid required to leach the nickel and reduce the process energy requirements, reducing the operating cost per pound of nickel.

Atmospheric agitated tank leaching tests by Mintek, Johannesburg, on composite samples from Ngasamo covering a wide range of lithologies returned encouraging results, confirming that the leach performance of Dutwa ores is superior to many nickel laterites elsewhere in the world. The ferruginous siliceous ore from Ngasamo, which accounts for about 20% of the total Dutwa resource, does not leach quite as well as its equivalent at Wamangola, but nickel can still be recovered easily from this ore with extractions approaching 80% at a low acid consumption of 375 kg/t after 8 hours at 90-95 Celsius. Ngasamo transition ore averaged 75% extraction with 425 to 440 kg/t acid, while even the saprolitic ore required only 550-660kg/t acid to extract 75 to 80% of the nickel. Such ores from other laterite deposits are characteristically high acid consumers, needing up to 900-1000 kg/t. As the Dutwa ores are generally low in iron, aluminium and manganese, we expect that extraction of nickel and cobalt from the liquors produced by atmospheric leaching will be relatively straight forward.

The financial models for the DFS are now fully built and checked. Inputs will be modified and improved as better data become available, such as the mining and processing costs noted above. The models will also be used to test the economic impact of potential cost-saving measures such as using rail instead of road transport or using magnesium-bearing saprolite ore in place of some of the limestone needed to neutralise residual acid after leaching.

Well ahead of schedule, diamond drilling, for bulk ore sample 2 ("BOS2") is nearing completion. BOS2 consists of a further 15 tonnes of material from the two Dutwa deposits and will be shipped to Perth for use as feedstock for our first pilot-scale metallurgical tests later this year or early 2012. Results from this will inform the detailed plant design engineering and costing for the DFS, and will provide product samples for potential off-take buyers.

The mineral resources at Dutwa have been almost completely defined to JORC standards, but some drilling is still needed, mostly at Ngasamo, to extend the resource and upgrade it from inferred to indicated category. This will commence in early July, using a new track-mounted drill rig which has been designed to operate safely on the relatively steep slopes of Ngasamo hill. Flooding of the drill rig factory in Brisbane early in the year delayed this start of this drilling programme somewhat and due to the specialised nature of the rig, it was not practical to source an alternative, but we expect to complete the programme in time to finish the pre-feasibility phase of the DFS in late 2011.

We are making good progress with other elements of the feasibility study: our studies of logistics, infrastructure and reagents are well advanced and our contractor has started the baseline surveys for the environmental and social impact assessment, which will be conducted to full Equator Principles standards.


Miyabi Gold project

BrightStar Resources Limited ("Brightstar"), who signed a joint venture over the Miyabi gold project in April, has already begun operations on the ground, commencing a 10,000 metre drilling programme which will cover a three kilometer strike length of a highly prospective zone along the granite contact, as well as other promising targets. BrightStar's announcement can be found on its web site, www.brightstar.com.au


Corporate reorganisation

The Company is advancing its plan to reorganise its board of directors, in order to put in place the skills it will need to take Dutwa through construction and into production, and to spin out its non-core legacy projects. The search for a new CEO is making good progress and the Company is on track for Mark Parker to shift to a new opportunities role at the year end. Our part time Finance Director, Bevan Metcalf, will step aside once a full time replacement has been appointed, with input from the new CEO. Chris Davies has been mandated to steer AFE's copper division to full independence, and Julian McIntyre joined the Board as a non-executive director in May.

African Eagle's plan to divest its legacy assets in order to focus on the Dutwa project is advancing well. Under the guiding hand of Chris Davies, AFE's copper division is well on the way to being spun out into a new company, Cobra Copper. Cobra represents a fully integrated copper exploration and development company in one of the great copper producing regions of the world, and we expect it to realise the value of AFE's copper assets.


Qualified Person

Information in this report relating to metallurgical test results is based on data reviewed by Chad Czerny PhD, Project Manager, Metallurgy for African Eagle Resources, who is a Member of the Australasian Institute of Mining and Metallurgy, has more than 20 years' relevant experience in the mining and metallurgical industry, and is a Qualified Person under AIM guidelines. Dr Czerny consents to the inclusion of the information in the form and context in which it appears.


For further information about the Company, see the Company's web site www.africaneagle.co.uk or contact one of the following:

African Eagle Resources plc
Mark Parker (Managing Director)
Euan Worthington (Chairman)
Sandra Spencer (PR Consultant)
+44 20 7248 6059
+44 77 5640 6899
+44 75 1535 7790

Canaccord Genuity Limited
Andrew Chubb
Bhavesh Patel
+44 20 7050 6500

Ocean Equities Limited
Guy Wilkes
+44 20 7786 4370

Russell & Associates, Johannesburg
Charmane Russell
Marion Brower
+27 11 8803924
+27 82 8928052





You are receiving this email because you have previously expressed an interest in receiving news about African Eagle Resources plc. If you are receiving this email in error or you do not wish to receive such emails from the Company in future please reply inserting UNSUBSCRIBE in the subject line and I will not email you again.



.

African Eagle Resources PLC

EN DÉVELOPPEMENT
CODE : AFE.L
ISIN : GB0003394813
Suivi et investissement
Add to watch list Add to your portfolio Add or edit a note
Ajouter une alerte Ajouter aux Watchlists Ajouter au portefeuille Ajouter une note
ProfilIndicateurs
de Marché
VALEUR :
Projets & res.
Communiqués
de Presse
Rapport
annuel
RISQUE :
Profile actifs
Contactez la cie

African Eagle est une société développant des projet miniers de nickel et d'or basée au Royaume-Uni.

African Eagle est en développement de projets de nickel, d'or et de cuivre en Tanzanie et en Zambie.

Ses principaux projets en développement sont FAIDA - MIYABI PROJECT et KILIMANI - MIYABI PROJECT en Tanzanie et MKUSHI PROJECT en Zambie et ses principaux projets en exploration sont MAJELE, SENA et KING SOLOMON au Mozambique, NDOLA, SASARE EAGLE EYE, MOKAMBO, LUNGA et MKUSHI en Zambie et ZANZUI, IGURUBI, DUTWA et MIYABI en Tanzanie.

African Eagle est cotée au Royaume-Uni et en Allemagne. Sa capitalisation boursière aujourd'hui est 243,9 millions GBX (409,4 millions US$, 306,2 millions €).

La valeur de son action a atteint son plus haut niveau récent le 08 juillet 2011 à 9,98 GBX, et son plus bas niveau récent le 05 juillet 2013 à 0,10 GBX.

African Eagle possède 871 160 000 actions en circulation.

Votre avis nous interesse, merci de laisser un commentaire ou de noter cet article.
Evaluer : Note moyenne :0 (0 vote) Voir les mieux notés
 
Nominations de African Eagle Resources PLC
15/09/2011(UK) - Appointment of new CEO
05/05/2011(UK) - Appointment of Non-executive Director
09/03/2010(Dutwa)Appoints project manager at Dutwa
15/10/2009Appointment of New Chairman
Projets de African Eagle Resources PLC
20/09/2011(Miyabi)(UK) - Miyabi drilling update
14/03/2011(Dutwa) Dutwa economic model update
01/03/2011(Dutwa)- Dutwa whittle optimisation report.
10/06/2010(Dutwa) Dutwa Nickel Project - Drilling Results
07/04/2010(Igurubi)Vends interest in Igurubi gold project to Peak Resources
17/03/2010(Dutwa)Drilling results from Ngasamo Hill
21/01/2010(Dutwa)Continues to Yield Positive Results
30/11/2009(Dutwa)Further Drilling Results
01/12/2009(Dutwa)Update on Metallurgical Tests
22/02/2010(Dutwa)Drill Results from Ngasamo Hill
20/10/2009(Dutwa)Dutwa Progress Summary
03/08/2009(Zanzui)Zanzui Nickel Leach Tests
29/07/2009(Dutwa)Dutwa Nickel Project Scoping Study
14/02/2009(Dutwa)Nickel Leach testwork results.
26/11/2008(Zanzui)Zanzui Nickel Project First Drill results
02/12/2008(Mokambo)Mokambo Copper Project
27/11/2008(Dutwa)Dutwa (7) The Resource statement
11/11/2008(Dutwa)DRILL RESULTS RECEIVED
26/08/2008(Dutwa)Dutwa Nickel Discovery
31/07/2008(Miyabi)Miyabi Project update
Communiqués de Presse de African Eagle Resources PLC
26/09/2011(UK) - Investor Presentation, Press & Research Links & Updat...
04/08/2011(Dutwa)(UK) - Dutwa mineralogical results
27/06/2011(UK) - 'Riches beyond gold' - The Sunday Telegraph
21/06/2011(UK) - Mid-year progress report
21/04/2011(UK) - Preliminary results
20/05/2010Communication with Shareholders & Notice of AGM
30/04/2010PRELIMINARY RESULTS FOR THE YEAR ENDED 31 DECEMBER 2009
25/09/2009Interim Report & Accounts
07/08/2009Open Offer Financing Oversubscribed
21/07/2009Open Offer to Shareholders
14/05/2009Igurubi Gold Resource and Dutwa Nickel Project Report
09/01/2009Strategic plan
25/09/2008Interim results
Publication de commentaires terminée
 
Dernier commentaire publié pour cet article
Soyez le premier à donner votre avis
Ajouter votre commentaire
LSE (AFE.L)BERLIN (EB1.BE)
0,280+0.00%0,013+0.00%
LSE
GBX 0,280
11/08 07:30 -
0%
Cours préc. Ouverture
0,280 0,280
Bas haut
0,280 0,280
Année b/h Var. YTD
 -  -
52 sem. b/h var. 52 sem.
- -  0,280 -%
Volume var. 1 mois
0 -%
24hGold TrendPower© : -8
Produit
Développe Copper - Gold
Recherche Cobalt - Copper - Gold - Iron - Nickel - Platinum - Uranium
 
 
 
Analyse
Interactive chart Add to compare
Graphique
interactif
Imprimer Comparer Exporter
Dernière mise à jour le : 23/02/2010
Vous devez être connecté pour accéder au portefeuille (gratuit)
Top Newsreleases
LES PLUS LUS
Variation annuelle
DateVariationMaxiMini
 
Graphique 5 ans
 
Graphique 3 mois
 
Graphique volume 3 mois
 
 
Nouvelles des Sociétés Minières
Plymouth Minerals LTDPLH.AX
Plymouth Minerals Intersects Further High Grade Potash in Drilling at Banio Potash Project - Plannin
0,12 AU$-8,00%Trend Power :
Santos(Ngas-Oil)STO.AX
announces expected non-cash impairment
7,68 AU$+0,33%Trend Power :
OceanaGold(Au)OGC.AX
RELEASES NEW TECHNICAL REPORT FOR THE HAILE GOLD MINE
2,20 AU$+0,00%Trend Power :
Western Areas NL(Au-Ni-Pl)WSA.AX
Advance Notice - Full Year Results Conference Call
3,86 AU$+0,00%Trend Power :
Canadian Zinc(Ag-Au-Cu)CZN.TO
Reports Financial Results for Q2 and Provides Project Updates
0,12 CA$+4,55%Trend Power :
Stornoway Diamond(Gems-Au-Ur)SWY.TO
Second Quarter Results
0,02 CA$+100,00%Trend Power :
McEwen Mining(Cu-Le-Zn)MUX
TO ACQUIRE BLACK FOX FROM PRIMERO=C2=A0
11,88 US$-2,74%Trend Power :
Rentech(Coal-Ngas)RTK
Rentech Announces Results for Second Quarter 2017
0,20 US$-12,28%Trend Power :
KEFIKEFI.L
Reduced Funding Requirement
0,53 GBX+1,53%Trend Power :
Lupaka Gold Corp.LPK.V
Lupaka Gold Receives First Tranche Under Amended Invicta Financing Agreement
0,06 CA$+0,00%Trend Power :
Imperial(Ag-Au-Cu)III.TO
Closes Bridge Loan Financing
2,58 CA$-2,27%Trend Power :
Guyana Goldfields(Cu-Zn-Pa)GUY.TO
Reports Second Quarter 2017 Results and Maintains Production Guidance
1,84 CA$+0,00%Trend Power :
Lundin Mining(Ag-Au-Cu)LUN.TO
d Share Capital and Voting Rights for Lundin Mining
16,12 CA$-2,15%Trend Power :
Canarc Res.(Au)CCM.TO
Canarc Reports High Grade Gold in Surface Rock Samples at Fondaway Canyon, Nevada
0,26 CA$+4,08%Trend Power :
Havilah(Cu-Le-Zn)HAV.AX
Q A April 2017 Quarterly Report
0,23 AU$+0,00%Trend Power :
Uranium Res.(Ur)URRE
Commences Lithium Exploration Drilling at the Columbus Basin Project
6,80 US$-2,86%Trend Power :
Platinum Group Metals(Au-Cu-Gems)PTM.TO
Platinum Group Metals Ltd. Operational and Strategic Process ...
1,86 CA$-2,11%Trend Power :
Devon Energy(Ngas-Oil)DVN
Announces $340 Million of Non-Core Asset Sales
52,10 US$-1,86%Trend Power :
Precision Drilling(Oil)PD-UN.TO
Announces 2017Second Quarter Financial Results
8,66 CA$-0,35%Trend Power :
Terramin(Ag-Au-Cu)TZN.AX
2nd Quarter Report
0,04 AU$+5,56%Trend Power :