Publié le 24 janvier 2008

Key Project Milestones Achieved, Wetar Project

( 0 vote, 0/5 ) Imprimer l'article
  Article Commentaires Commenter Notation Suivre la société  
0
envoyer
0
commenter

 

 

 

 

January Update

Finders Logo

Wetar Geo Map

Kali Kuning X Section

 

January 2008

 

On behalf of the board and employees of Finders Resources, thank you for your continued support of our company, and may 2008 be prosperous for us all.

December and January have been extremely busy times for the Finders Team, and we would like to take this opportunity to bring you up to date on key items. Several announcements have been made to the ASX and AIM markets:

  1. Key Project Milestones Achieved, Wetar Project
  2. Completion of Financing
  3. Broker Research Reports
  4. Shareholding Changes


1. Key Project Milestones Achieved, Wetar Project

Highlights

Finders Resources
� definitive feasibility study to asses 20-25,000t per year copper cathode production at the Wetar Copper project, is progressing according to schedule with the following key project milestones achieved for the Kali Kuning Demonstration Plant:

    Major capital items ordered: first equipment shipment has departed for site by landing craft.
    Key operational staff appointed.
    Receipt of principal permits.

Finders� is targeting copper cathode production from a 5tpd SX-EW plant from June 2008.

All key elements of engineering design work for the test heaps and demonstration plant have been completed, enabling the company to issue orders for capital items in a timely fashion; such as the rectifier, anodes and cathodes, which have longer lead times.

Plant and equipment for the development will be mobilised to the project area in two main shipments, the first of which departed Surabaya on January 17th. This shipment includes contract earthmoving equipment, generators and fuel and water tanks. Initial work will focus on road refurbishment, environmental protection measures and construction of the heap pad area.

The Company has expanded its senior project team with experienced appointments in key disciplines. The technical team for the project is now largely in place.

    Mine Superintendant
    Construction Supervisor
    Processing Superintendant
    Purchasing Supervisor
    Environmental Officer

 
On the 4th January 2008, the Company received notification that the Environment Impact Control Committee (BAPEDALDA) of Maluku had approved the Company
�s environmental management and control plans (UKL/URL) for the demonstration plant after review by the provincial AMDAL commission on December 12th 2007. 

On the 14th January 2008, further permits for a 100,000t bulk sample and pilot-scale processing were received from the Regency of Maluku Tenggara Barat.

Managing Director, Chris Farmer said:

�The first shipment of equipment to Wetar marks the start of an exciting phase for the Company as we make the transition towards being a copper producer.  Our ability to hire quality staff in a highly competitive market is a strong endorsement of both the project quality and Finders� corporate culture.

With the principal permits in place, we remain on track to meet our targets for copper production and look forward to reporting the outcomes of a very busy year ahead for us we attempt to build a profitable project which has tangible benefits for all stakeholders



2. Completion of A$15.8 million Financing

Finders Resources Limited (�Finders�) is pleased to advise of the completion of its previously announced financing arrangement with metals trading company, Tennant Metals Pty Ltd and its associated shareholder, Meridian International Capital Limited, by the issue of a total of 5,165,339 shares at A$1.10 per share (raising A$5.68 million), and the provision of a secured loan facility for US$5.0 million.

This transaction, together with the recent placement of 4 million shares at A$1.10 per share (raising A$4.4 million) arranged by Southern Cross Equities, completes the A$15.8 million financing, which will be used to construct the Wetar Copper Project
�s  demonstration plant (expected capital cost of US$6.25 million) and to provide the company with additional working capital.

Finders Executive Chairman Dr Russell Fountain said:

�Completion of this financing during a period of market uncertainty is a major success for Finders, and leaves the company in a very strong financial position to take advantage of strong copper prices as we benefit from the 5 tonne per day copper cathode demonstration plant coming on stream mid year and move towards the completion of a definitive feasibility study at Wetar by year end.


3. Broker Research Reports

In December John Macdonald of Greeen Leader Equities Research completed and published a Brokers Report on the Company. This report can be viewed by click ing here:

 
http://www.greenleader.com.au/framework/documents/frame.asp?doc=529.pdf

Hoodless Brennan have also included Finders in their AIM Mining Companies Review. A copy of this doscumnet can be downloaded from:

http://www.hoodlessbrennan.com/stock-research-prices/mining-review/


4. Shareholding Changes

As a consequence of the recently undertaken fund raising and share placements Finders has been required to make several statutory reports to the ASX. Copies of these reports are available from the ASX website, and shortly will also be available from the companies website.


For further information please contact:

Finders Resources Ltd:
Russell Fountain, Executive Chairman, +61 (0) 2 9211 8299
Chris Farmer, Managing Director, cbf@findersresources.com

Financial PR:
Doug Macdonald, +61 (0) 424 255 959, Capital Group (in Australia)
Paddy Blewer or Nick Elwes, 020 7457 2020, College Hill (in the UK)

RFC Corporate Finance Ltd (Finders
� Nominated Adviser for the AIM market):
Rob Adamson, +61 (0)2 9250 0000
Stuart Laing, +61 (0)8 9480 2506, stuartl@rfc.com.au


Competent Person Statement

The Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves (the �JORC Code�) sets out minimum standards, recommendations and guidelines for Public Reporting in Australasia of Exploration Results, Mineral Resources and Ore Reserves. The information contained in this announcement has been presented in accordance with the JORC Code and references to �Indicated� and �Inferred Resources� are to those terms as defined in the JORC Code.

Geological and Mineral Resource information in this announcement is based on information compiled by Dr R Fountain who is a Fellow of the Australasian Institute of Geoscientists and a Director of Finders. Dr Fountain has sufficient experience that is relevant to the styles of mineralisation and types of deposits under consideration and to the activity that he is undertaking to qualify as Competent Person as defined in the JORC Code. He consents to the inclusion in this announcement of the matters based on his information in the form and context in which they appear.


Statements by Finders Resources Ltd

Geological information in this announcement is based on information compiled by Dr R Fountain who is a Fellow of the Australasian Institute of Geoscientists and a Director of Finders. Dr Fountain has sufficient experience that is relevant to the styles of mineralisation and types of deposits under consideration and to the activity that he is undertaking to qualify as Competent Person as defined in the JORC Code. He consents to the inclusion in this announcement of the matters based on his information in the form and context in which they appear.
Statements in this document that are forward-looking and involve numerous risks and uncertainties that could cause actual results to differ materially from expected results are based on the Company
�s current beliefs and assumptions regarding a large number of factors affecting its business. Actual results may differ materially from expected results. There can be no assurance that (i) the Company has correctly measured or identified all of the factors affecting its business or the extent of their likely impact, (ii) the publicly available information with respect to these factors on which the Company�s analysis is based is complete or accurate, (iii) the Company�s analysis is correct or (iv) the Company�s strategy, which is based in part on this analysis, will be successful.

Background

Finders, listed on AIM and ASX, is the operator of the Wetar Copper (~73% and earning), and Ojolali Gold-Silver Projects (72% with option) in Indonesia, and holds an investment in Geopacific Resources NL, an ASX-listed company with active exploration programs for gold and copper in Fiji.

At the Wetar Copper Project, Finders has previously announced Measured, Indicated and Inferred Resources at a 0.5% copper cut-off grade, of 9.8 million tonnes at 2.5% copper for 248,000 tonnes contained copper in two deposits, Kali Kuning and Lerokis. The company is planning to develop an open cut heap leach SX-EW copper mining operation to produce 20-25,000 tonnes of cathode copper per year from mid 2009. A key component of the feasibility study for this project is the construction of a semi-commercial scale test heap and pilot plant, designed to produce 5 tonnes per day of copper cathode from July 2008, with an estimated capital cost of US$6.25 million.

At the Ojolali Project, Finders has previously announced Inferred Resources at the Jambi Oxide gold deposit (3.2 Mt @ 1.0 g/t Au, 6.9 g/t Ag at a 0.5 g/t Au cut-off, and including mining dilution) and Inferred Resources at the Tambang Prospect (7.9 Mt @ 167g/t Ag and 0.7 g/t Au at a 1 g/t Au equivalent cut-off using drilling data from a previous explorer).

Finders� believes that the Ojolali project has strong potential to generate short-term cash flow through open pit CIL/CIP development of the gold resource at the Jambi Oxide gold deposit. Other prospects have outstanding potential for the discovery of additional resources using modern geophysical techniques to optimize drill targeting.

For further information on results previously reported and a full resource statement please visit our website www.findersresources.com

 

powered by 

http://www.itsinthemail.com.au/

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 


This email was sent to newsrelease@24hgold.com by dpb@findersresources.com |
Print / PDF version | Read our Privacy Policy.
Finders Resources Limited - Suite 51 Level 3, 330 Wattle St, Ultimo, Australia

Finders Resources Ltd

CODE : FND.AX
ISIN : AU000000FND9
Suivi et investissement
Add to watch list Add to your portfolio Add or edit a note
Ajouter une alerte Ajouter aux Watchlists Ajouter au portefeuille Ajouter une note
ProfilIndicateurs
de Marché
VALEUR :
Projets & res.
Communiqués
de Presse
Rapport
annuel
RISQUE :
Profile actifs
Contactez la cie

Finders est une société d’exploration minière de cuivre basée en Australie.

Finders détient divers projets d'exploration en Indonesie.

Ses principaux projets en exploration sont WETAR COPPER et OJOLALI en Indonesie.

Finders est cotée au Royaume-Uni et en Australie. Sa capitalisation boursière aujourd'hui est 2,0 milliards AU$ (1,3 milliards US$, 1,2 milliards €).

La valeur de son action a atteint son plus bas niveau récent le 04 mars 2016 à 0,11 AU$, et son plus haut niveau récent le 19 avril 2024 à 2,64 AU$.

Finders possède 761 270 016 actions en circulation.

Votre avis nous interesse, merci de laisser un commentaire ou de noter cet article.
Evaluer : Note moyenne :0 (0 vote) Voir les mieux notés
 
Présentations des Compagnies de Finders Resources Ltd
16/09/2016Updated Investor Presentation September 2016
14/09/2016Investor Presentation September 2016
Dans les médias de Finders Resources Ltd
04/06/2019Orefinders to resample historical drilling at Knight propert...
Rapports annuels de Finders Resources Ltd
Annual Report & Notice of Meeting
2008 Annual Report
Financements de Finders Resources Ltd
28/07/2011(Wetar Copper)to raise US$138m project finance for Wetar Copper Project
Nominations de Finders Resources Ltd
04/06/2009appoints Michael Stirzaker as Finance Director
07/01/2009appoints Rob Thomson as an Executive Director with prime res...
01/10/2008Appoints Robert Thomson - Resend
27/07/2007Appoints Project Manager and Releases Quarterly Report
Projets de Finders Resources Ltd
12/09/2016(Wetar Copper)Wetar Copper Project Update
19/07/2012(Wetar Copper)Wetar Copper Project Permitting Update
18/05/2012(Wetar Copper)Wetar Copper Project Updated Feasibility Study
16/03/2012(Wetar Copper)Secures off take partner for Wetar Copper Project
26/10/2011(Wetar Copper)Interim Funding for Capital Equipment, Wetar Copper Project
27/06/2011(Wetar Copper)announces Wetar Copper Project Bankable Feasibility Study
15/06/2011(Wetar Copper)announces Key Mining Permits for Wetar Copper Project
09/09/2009(Wetar Copper)progress on Wetar Copper Definitive Feasibility Study
30/07/2009(Wetar Copper)Wetar Copper Project Progress
29/06/2009(Wetar Copper)Wetar Copper Project Progress of Definitive Feasibility Stud...
01/06/2009(Wetar Copper)(FND) takes option to acquire processing plant for Wetar Cop...
11/07/2008(Wetar Copper)Wetar initial pilot plant production late September - feasib...
02/06/2008(Ojolali)33% INCREASE IN GOLD CONTENT IN UPGRADED RESOURCE ESTIMATE F...
24/01/2008(Wetar Copper) Key Project Milestones Achieved, Wetar Project
Communiqués de Presse de Finders Resources Ltd
26/07/2016Finders Resources Investors Presentation July 2016
01/07/2016Plant Commissioning Update
14/06/2016First Copper Stripped at Wetar Expansion Project
01/06/2016Wetar Expansion Project - First Copper Plated
31/05/2016May 2016 Results of Annual General Meeting
22/04/2016Annual Report 2015
04/04/2016Financial Report 2015
29/03/2016Finders Resources Investor Presentation November 2015
01/02/2016Quarterly Activities and Cashflow Report 31 December 2015
16/12/2015Appendix 3F Final Share Buy-back Notice
30/10/2015Quarterly Activities Report September 2015
23/10/2015Change of Director's Interest Notice Barry Cahill
23/10/2015Change of Director's Interest Notice Gary Comb
30/07/2015Quarterly Activities Report June 2015
15/04/2015Full Year Statutory Accounts CY2014
19/03/2014Notice of General Meeting 16 April 2014 and Proxy Form
31/01/2012Quarterly Activities Report December 2011
08/12/2011Whim Creek SX/EW Plant Arrives in Indonesia
28/09/2009repays US$5m loan ahead of schedule
21/08/2009Straits sale of Whim Creek to have no effect on Finders’ opt...
04/08/2009RAISES A$20 MILLION IN OVERSUBSCRIBED PLACEMENT
09/03/2009' Maiden Shipment of Copper Cathode from Wetar
16/01/2009CONVERTIBLE NOTE FACILITY TO RAISE UP TO US$1.5 MILLION
01/08/2008commercial scale pilot plant tracking for late September
08/04/2008 April Update
26/02/2008 December Quarterly Report & Appendix 5B
03/07/2007Selects Heap Leach with Onsite SXEW for Wetar Copper Project
07/06/2007Lists on ASX Friday 8 June 2007
31/05/2007Raising will be used to progress Finders’ advanced copper an...
31/05/2007successful A$6 million raised
15/05/2007PROSPECTUS OFFER OPENS WITH STRONG INTEREST AND EXPECTED T...
Publication de commentaires terminée
 
Dernier commentaire publié pour cet article
Soyez le premier à donner votre avis
Ajouter votre commentaire
AUSTRALIA (FND.AX)LSE (FND.L)
2,64+0.00%24,25-2.02%
AUSTRALIA
AU$ 2,64
19/04 15:25 -
0%
Cours préc. Ouverture
2,64 2,74
Bas haut
2,56 2,74
Année b/h Var. YTD
0,920 -  3,35 153,85%
52 sem. b/h var. 52 sem.
0,380 -  3,35 378,26%
Volume var. 1 mois
198 966 -3,65%
24hGold TrendPower© : 44
Produit
Développe
Recherche
 
 
 
Analyse
Interactive chart Add to compare
Graphique
interactif
Imprimer Comparer Exporter
Vous devez être connecté pour accéder au portefeuille (gratuit)
Top Newsreleases
LES PLUS LUS
Variation annuelle
DateVariationMaxiMini
2024528,57%
2023-25,00%0,690,40
 
Graphique 5 ans
 
Graphique 3 mois
 
Graphique volume 3 mois
 
 
Nouvelles des Sociétés Minières
Plymouth Minerals LTDPLH.AX
Plymouth Minerals Intersects Further High Grade Potash in Drilling at Banio Potash Project - Plannin
0,12 AU$-8,00%Trend Power :
Santos(Ngas-Oil)STO.AX
announces expected non-cash impairment
7,82 AU$+1,69%Trend Power :
Oceana Gold(Au)OGC.AX
RELEASES NEW TECHNICAL REPORT FOR THE HAILE GOLD MINE
2,20 AU$+0,00%Trend Power :
Western Areas NL(Au-Ni-Pl)WSA.AX
Advance Notice - Full Year Results Conference Call
3,86 AU$+0,00%Trend Power :
Canadian Zinc(Ag-Au-Cu)CZN.TO
Reports Financial Results for Q2 and Provides Project Updates
0,12 CA$+4,55%Trend Power :
Stornoway Diamond(Gems-Au-Ur)SWY.TO
Second Quarter Results
0,02 CA$+100,00%Trend Power :
McEwen Mining(Cu-Le-Zn)MUX
TO ACQUIRE BLACK FOX FROM PRIMERO=C2=A0
11,04 US$+1,38%Trend Power :
Rentech(Coal-Ngas)RTK
Rentech Announces Results for Second Quarter 2017
0,20 US$-12,28%Trend Power :
KEFIKEFI.L
Reduced Funding Requirement
0,56 GBX+4,63%Trend Power :
Lupaka Gold Corp.LPK.V
Lupaka Gold Receives First Tranche Under Amended Invicta Financing Agreement
0,06 CA$+0,00%Trend Power :
Imperial(Ag-Au-Cu)III.TO
Closes Bridge Loan Financing
2,52 CA$+6,78%Trend Power :
Guyana Goldfields(Cu-Zn-Pa)GUY.TO
Reports Second Quarter 2017 Results and Maintains Production Guidance
1,84 CA$+0,00%Trend Power :
Lundin Mining(Ag-Au-Cu)LUN.TO
d Share Capital and Voting Rights for Lundin Mining
16,05 CA$+2,62%Trend Power :
Canarc Res.(Au)CCM.TO
Canarc Reports High Grade Gold in Surface Rock Samples at Fondaway Canyon, Nevada
0,24 CA$+2,13%Trend Power :
Havilah(Cu-Le-Zn)HAV.AX
Q A April 2017 Quarterly Report
0,19 AU$-7,32%Trend Power :
Uranium Res.(Ur)URRE
Commences Lithium Exploration Drilling at the Columbus Basin Project
6,80 US$-2,86%Trend Power :
Platinum Group Metals(Au-Cu-Gems)PTM.TO
Platinum Group Metals Ltd. Operational and Strategic Process ...
1,90 CA$+1,60%Trend Power :
Devon Energy(Ngas-Oil)DVN
Announces $340 Million of Non-Core Asset Sales
51,43 US$-0,46%Trend Power :
Precision Drilling(Oil)PD-UN.TO
Announces 2017Second Quarter Financial Results
8,66 CA$-0,35%Trend Power :
Terramin(Ag-Au-Cu)TZN.AX
2nd Quarter Report
0,03 AU$+0,00%Trend Power :