Sabina Gold & Silver Reports Positive Results From Early 2011 Drilling at the Back River Project, Nunavut
Published : April 27, 2011

Hole 11GSE002 (Goose) returns 18.99 g/t Au over 27.2m including 63.51 g/t Au over 4.1m

Hole 11GSE009 (Umwelt) returns 10.14 g/t Au over 25.0m including 16.62 g/t Au over 10.0m

Umwelt mineralization extended a further 200m South

( 0 vote, 0/5 ) Imprimer l'article
  Article Commentaires Commenter Notation Suivre la société  
0
envoyer
0
commenter
Mots clés associés :   Canada | Precious Metals | Zinc |

VANCOUVER, BRITISH COLUMBIA--(Marketwire - April 27, 2011) - Sabina Gold & Silver Corp (News - Market indicators) is pleased to announce significant assay results from the first holes drilled as part of the 2011 exploration program on its Umwelt and Goose deposits at its 100% owned Back River Project in Nunavut, Canada. 

The 2011 drilling campaign at Back River started on the Goose claim block in March. To date, a total of 39 holes and 7,872 metres of core have been completed or are in progress, with most assays still pending.

The focus of work in 2011 is to extend and expand the new deposits at Llama and Umwelt, as well as, identify potential new deposits not only on the Goose claim block but elsewhere on the Back River property. 

A total of four rigs are currently drilling at the Goose claim block, generating approximately 300 metres of core per day. The four drill rigs are focusing on resource expansion at Llama and Umwelt. Each deposit has one drill completing aggressive 100 metre step outs to the south with a second drill following up with 50 metre infill holes.

2010 drilling had extended the Umwelt corridor of mineralization approximately 750 m along strike. However, only 535 m of strike length had been drilled sufficiently to enable a resource calculation on that deposit. The new drill holes reported today now extend the Umwelt mineralized zone by a further 200m to the south along strike. Hole 11GSE009 drilled 100 m south of last year's drilling returned 10.14 g/t Au over 25.0 m including 16.62 g/t Au over 10.0 m. Hole 11GSE016 drilled 100 m south of Hole 11GSE009 returned 5.55 g/t Au over 19.2 m including 25.39 g/t Au over 2.2 m at a vertical depth of 340 m. Most assays remain pending however it is encouraging to note that grades and widths to date are similar to those encountered in the 2010 drilling program. Both Llama and Umwelt remain open along strike.

Initial 2011 drilling also targeted the Goose deposit to aid in the geological/resource modelling interpretation in support of a calculation of an open pit resource. Most significantly, hole 11GSE002 returned 18.99 g/t Au over 27.2m including 63.51 g/t Au over 4.1m at a vertical depth of 170 metres in a central area of the deposit that was originally thought to be barren. The historical Goose resource is being recalculated to include recent drilling and new resource modelling to determine its potential as an open pit. This calculation is nearing completion and is expected within the next 3-4 weeks.

A fifth rig will be operational shortly and will begin testing regional targets at the Goose claim block.

"Our 2011 drilling campaign is off to a good start," said Tony Walsh, President & CEO, "While 70% of our $30 million Back River budget is focussed on extending the deposits at Llama and Umwelt, we are also very excited about applying our exploration tool box to find new discoveries. At the Goose claim block there are over 15 such targets alone and we have started to direct some of our resources to these anomalies."

The new deposits and target areas at Goose are within a 5 km corridor that have been identified using an exploration tool box developed by Sabina's geological team. This new tool box is based on a set of assumptions that specifically target large buried alteration and mineralized features in folded iron formation units. These types of folded units have the potential to be extracted by open pit methods.

Initial exploration drilling is also underway at the George claim block where two drills are testing large, shallow but covered alteration and mineralization targets similar to that at Llama and Umwelt. The George deposit contains an existing indicated resource of 590,000 oz of Au and an additional inferred resource of 866,000 oz of Au at an average grade of 10.5 g/t Au. While the George deposit itself is more amenable to underground mining methods, the development and application of the new tool box has identified numerous opportunities to find additional large shallow open pit deposits close to the existing resource. 

UMWELT

Drilling at Umwelt is planned to extend and expand the mineralized zone both along strike and down plunge. 

To date a total of eight holes totalling 3,773m have been drilled or are in progress on the Umwelt target. Assay results have been returned for four holes.

New results include step-out holes 11GSE009 located 100 metres south of the drilling completed in 2010 and 11GSE016 located a further 100 metres south of 11GSE009. Hole 11GSE009 returned 10.14 g/t Au over 25.0m including 16.62 g/t Au over 10.0m. Hole 11GSE016 returned 5.55 g/t Au over 19.2m including 25.39 g/t Au over 2.2m at a vertical depth of 340 metres within the Main Zone.

In addition, results have been returned for holes 11GSE001 and 11GSE006 which targeted the Main Zone immediately below the southern extent of the 2010 drilling. Hole 11GSE001 returned 5.62 g/t Au over 23.3m including 13.70 g/t Au over 5.2m in Main Zone East limb and 15.27 g/t Au over 3.0m in Main Zone West limb. Hole 11GSE006 returned 6.72 g/t Au over 12.5m within a broader zone of 3.40 g/t Au over 31.33m.

The mineralized zones are hosted within a turbiditic sedimentary sequence containing silicate and oxide facies iron formations. Gold dominantly occurs with quartz +/- carbonate veining and arsenopyrite +/- pyrite +/- pyrrhotite in the iron formation. Drilling at Umwelt has identified an anti-form structure with a fold hinge that plunges to the south. Thick zones of gold mineralization are associated with the fold hinge in what is now known as the Main Zone. Mineralization also occurs along a separate iron formation horizon immediately to the west known as the West Zone. The relationship between the Main and West zones is uncertain but the West Zone may be a refolded limb of the Main zone.

Table 1: Umwelt deposit – 2011 assay results.
Hole Id Area Section From (m) To (m) Length (m) Au (g/t)   Comment/Mineral Zone
11GSE001 Umwelt 4600 325.50 326.50 1.00 7.99   Main Zone East
      333.50 356.75 23.25 5.62   Main Zone East
including     351.60 356.75 5.15 13.70   Main Zone East
      402.00 405.00 3.00 15.27   Main Zone West
                 
11GSE006 Umwelt 4550 355.00 367.50 12.50 6.72   Main Zone East
      355.00 386.33 31.33 3.40   Main Zone East
including     360.00 364.50 4.50 15.12   Main Zone East
      Additional assays pending          
                 
11GSE009 Umwelt 4450 314.00 339.00 25.00 10.14   Main Zone Centre
including     317.00 320.00 3.00 22.67   Main Zone Centre
and     329.00 339.00 10.00 16.62   Main Zone Centre
including     330.00 332.70 2.70 35.08   Main Zone Centre
      Additional assays pending          
                 
11GSE016 Umwelt 4350 368.00 387.20 19.20 5.55   Main Zone Centre
including     375.00 379.00 4.00 8.32   Main Zone Centre
and     385.00 387.20 2.20 25.39   Main Zone Centre

True widths are estimated to be 70% of the drill widths. Interpretation is currently in progress to confirm the geological relationships at the Umwelt deposit.

Llama Deposit

Initial drilling at Llama focussed on gaps in the resource model and going forward, the plan is to extend and expand the mineralized zone both along strike and down plunge. 

To date, a total of 13 holes totalling 2,939m have been drilled or are in progress on the Llama deposit target. Assay results are still pending.

Goose Deposit

A total of 3 holes totalling 590 metres were drilled on the Goose deposit. The holes were drilled to provide information for the ongoing geological / resource modelling interpretation in support of an open pit resource estimate.

Hole 11GSE002, located on local grid section 5180N, was drilled to validate the interpretation that an early hole drilled on this section is inappropriately located due to erroneous down hole deviation tests. Hole 11GSE002 returned 18.99 g/t Au over 27.2m including 63.51 g/t Au over 4.1m at a vertical depth of 170 metres. Both the geology and mineralized zones correlates very well with adjacent holes confirming the interpretation.

Hole 11GSE004B, located on local grid section 4730N targeted a gap in the drilling of the greywacke core within the folded iron formation. The hole intersected numerous gold bearing mineralized zones within the greywacke unit including 9.57 g/t Au over 3.0m at a vertical depth of 55 metres. Currently the known mineralization within the greywackes represents only a small portion of the overall Goose deposit resource. There is excellent potential to expand this greywacke component of the resource with further drilling particularly in an open pit scenario.

Table 2: Goose deposit – 2011 assay results.
Hole Id Area Section From (m) To (m) Length (m) Au (g/t)   Comment/Mineral Zone
11GSE002 Goose 5180 156.25 170.50 14.25 2.60   Goose Main
including     156.25 157.20 0.95 9.72   Goose Main
      193.70 196.60 2.90 5.30   Goose Main
including     195.60 196.60 1.00 13.68   Goose Main
      204.80 232.00 27.20 18.99   Goose Main
including     215.80 219.90 4.10 63.51   Goose Main
and     225.00 226.00 1.00 75.87   Goose Main
and     229.00 230.10 1.10 102.00   Goose Main
                 
11GSE004B Goose 4730 28.00 33.00 5.00 5.95   Greywacke
      35.80 38.80 3.00 1.39   Greywacke
      43.20 43.70 0.50 8.78   Greywacke
      48.30 54.50 6.20 3.38   Goose Main
including     48.30 49.40 1.10 9.88   Greywacke
      63.20 66.20 3.00 9.57   Greywacke

RESOURCE UPDATES

The Company has retained RPA to prepare a new resource estimate for the original Goose deposit based on an open pit model. This estimate is due shortly and if positive, the Company anticipates moving to a scoping study in mid-2011.

GEORGE LAKE DRILLING

Diamond drilling started at George in mid April using two rigs to explore for near surface open pitable targets. No assay results have yet been received. A total of six initial high priority target areas have been defined using Sabina's toolbox with the intention of discovering another Banded Iron Formation gold hosted deposit comparable to Goose, Llama or Umwelt. Approximately 4,000 to 6,000m of drilling is planned as part of the initial phase of exploration drilling. The George property is located 60 km northwest of the Goose property. 

SABINA GOLD & SILVER CORP.

Sabina Gold & Silver Corp. is an emerging precious metals company with district scale, world class undeveloped assets in one of the world's newest, most politically stable mining jurisdictions: Nunavut, Canada.

The properties consist of the Hackett River silver-zinc Project, the Back River Gold Project, both advanced exploration properties, as well as the Wishbone Claims, a vastly prospective grass roots project. 

The combined holdings total approximately 3,000 square kilometres and cover the largely unexplored Wishbone Greenstone belt. 

The Back River Project is comprised of the George and Goose Lake gold deposits and contain measured & indicated gold resources of 9.9 million tonnes grading 8.33 g/t Au for 2.655 million ounces of gold and inferred resources of 5.6 million tonnes grading 8.65 g/t Au for 1.56 million ounces of gold.

Quality Assurance

Mr. Doug Cater, P. Geo, and Project Manager, Back River Project of Sabina Gold & Silver Corp is a Qualified Person under the terms of NI43-101 and has reviewed the technical content of this press release and approved its dissemination.

Mineral resources for Goose Lake and George Lake were generated by RSG Global Consulting Pty Ltd (Coffey Mining) in September 2007. Mineral resources for Llama and Umwelt deposits were generated by Roscoe Postle Associates (RPA) in March 2011 these are all posted on www.sedar.com.

Diamond drill core was sent to TSL Laboratories in Saskatoon, Sask. Quality control is monitored on a continual basis and utilizes a system of standards, blanks and duplicates to ensure analytical accuracy. The protocols and procedures used in 2011 are the same as those used in earlier campaigns by Sabina Gold & Silver Corp. and have been deemed appropriate in the above noted 43-101 compliant resource reports.

Forward Looking Statements

Statements relating to exploration, pre-feasibility work and future operations at the Back River Project and the expected results of this work are forward-looking statements within the meaning of securities legislation of certain Provinces in Canada. Forward looking statements are statements that are not historical facts and are generally, but not always, identified by the words "expects," "plans," "anticipates," "believes," "intends," "estimates," 'projects," "potential" and similar expressions, or that events or conditions "will," "would," "may," "could" or "should" occur. Information inferred from the interpretation of drilling results may also be deemed to be forward looking statements, as it constitutes a prediction of what might be found to be present when and if a project is actually developed. These forward-looking statements are subject to a variety of risks and uncertainties which could cause actual events or results to differ materially from those reflected in the forward-looking statements, including, without limitation: risks related to fluctuations in metal prices; uncertainties related to raising sufficient financing to fund the planned work in a timely manner and on acceptable terms; changes in planned work resulting from weather, logistical, technical or other factors; the possibility that results of work will not fulfill expectations and realize the perceived potential of the Company's properties; risk of accidents, equipment breakdowns and labour disputes or other unanticipated difficulties or interruptions; the possibility of cost overruns or unanticipated expenses in the work program; the risk of environmental contamination or damage resulting from Sabina's operations and other risks and uncertainties, including those described in Sabina's Annual Report for the year ended December 31, 2010.

Forward-looking statements are based on the beliefs, estimates and opinions of Sabina's management on the date the statements are made. Sabina undertakes no obligation to update these forward-looking statements should management's beliefs, estimates or opinions, or other factors, should change.

This news release has been authorized by the undersigned on behalf of Sabina Silver Corporation.

Table 3: 2011 Back River project – Goose Lake property Drill results as of April 27, 2011
Hole Id Area Section Easting Northing Depth From (m) To (m) Length (m) Au (g/t)   Comment/Mineral Zone
11GSE001 Umwelt 4600 430200 7270864 479 325.50 326.50 1.00 7.99   Main Zone East
            333.50 356.75 23.25 5.62   Main Zone East
Including           351.60 356.75 5.15 13.70   Main Zone East
            402.00 405.00 3.00 15.27   Main Zone West
11GSE002 Goose 5180 433831 7269560 287 156.25 170.50 14.25 2.60   Goose Main
Including           156.25 157.20 0.95 9.72   Goose Main
            184.70 185.70 1.00 1.30   Goose Main
            193.70 196.60 2.90 5.30   Goose Main
Including           195.60 196.60 1.00 13.68   Goose Main
            204.80 232.00 27.20 18.99   Goose Main
Including           215.80 219.90 4.10 63.51   Goose Main
And           225.00 226.00 1.00 75.87   Goose Main
And           229.00 230.10 1.10 102.00   Goose Main
11GSE003 Goose 4730 434394 7269504 169 NSV          
11GSE004B Goose 4730 434376 7269481 134 28.00 33.00 5.00 5.95   Greywacke
            35.80 38.80 3.00 1.39   Greywacke
            43.20 43.70 0.50 8.78   Greywacke
            48.30 54.50 6.20 3.38   Greywacke
Including           48.30 49.40 1.10 9.88   Greywacke
            63.20 66.20 3.00 9.57   Greywacke
11GSE006 Umwelt 4550 430252 7270843 545.6 355.00 367.50 12.50 6.72   Main Zone East
            355.00 386.33 31.33 3.40   Main Zone East
including           360.00 364.50 4.50 15.12   Main Zone East
            467.00 468.00 1.00 1.13   Main Zone West
            472.00 476.00 4.00 2.51   Main Zone West
            Additional assays pending          
11GSE009 Umwelt 4450 430186 7270658 431.7 339.00 314.00 25.00 10.14   Main Zone Centre
Including           314.00 320.00 6.00 11.81   Main Zone Centre
Including           317.00 320.00 3.00 22.67   Main Zone Centre
And           324.25 325.75 1.50 9.76   Main Zone Centre
And           329.00 339.00 10.00 16.62   Main Zone Centre
Including           330.00 332.70 2.70 35.08   Main Zone Centre
            Additional assays pending          
11GSE014 Umwelt 5000 429998 7271215 352.3 Assays Pending          
11GSE016 Umwelt 4350 430279 7270608 500 368.00 387.20 19.20 5.55   Main Zone Centre
Including           375.00 379.00 4.00 8.32   Main Zone Centre
And           385.00 387.20 2.20 25.39   Main Zone Centre
            Additional assays pending          

To view the maps associated with this press release, please click on the following link: http://media3.marketwire.com/docs/sbb426.pdf



Sabina Gold & Silver Corp.
Nicole Hoeller
Director, IR
1 888 648-4218
nhoeller@sabinagoldsilver.com
or
Sabina Gold & Silver Corp.
Tony Walsh
President & CEO
604 998-4175
604 998-1051 (FAX)
www.sabinagoldsilver.com
Données et statistiques pour les pays mentionnés : Canada | Tous
Cours de l'or et de l'argent pour les pays mentionnés : Canada | Tous

Sabina Gold & Silver Corp

EN DÉVELOPPEMENT
CODE : SBB.TO
ISIN : CA7852461093
CUSIP : 785271 10 7
Suivi et investissement
Add to watch list Add to your portfolio Add or edit a note
Ajouter une alerte Ajouter aux Watchlists Ajouter au portefeuille Ajouter une note
ProfilIndicateurs
de Marché
VALEUR :
Projets & res.
Communiqués
de Presse
Rapport
annuel
RISQUE :
Profile actifs
Contactez la cie

Sabina est une société développant des projet miniers d'or et d'argent basée au Canada.

Sabina est en développement de projets d'or, d'argent, de cuivre, de plomb et de zinc au Canada, et détient divers projets d'exploration au Canada.

Son principal projet en développement est HACKETT RIVER au Canada et ses principaux projets en exploration sont DEL NORTE, ROCKSTONE, GOLDEN SIDEWALK, SKINNER, BACK RIVER - GOOSE LAKE, BACK RIVER, BACK RIVER - GEORGE LAKE, NEWMAN-MADSEN et WISHBONE au Canada.

Sabina est cotée au Canada, aux Etats-Unis D'Amerique et en Allemagne. Sa capitalisation boursière aujourd'hui est 482,9 millions CA$ (386,1 millions US$, 352,0 millions €).

La valeur de son action a atteint son plus bas niveau récent le 12 juillet 2002 à 0,05 CA$, et son plus haut niveau récent le 21 avril 2011 à 7,63 CA$.

Sabina possède 223 580 000 actions en circulation.

Votre avis nous interesse, merci de laisser un commentaire ou de noter cet article.
Evaluer : Note moyenne :0 (0 vote) Voir les mieux notés
 
Dans les médias de Sabina Gold & Silver Corp
22/04/2010Sabina Silver Corp. Business Summary
21/04/2010Emerging Precious Metals Stock Analysis
Rapports annuels de Sabina Gold & Silver Corp
2007 Annual report
Financements de Sabina Gold & Silver Corp
01/03/2011Completes $97.5 Million Financing
Nominations de Sabina Gold & Silver Corp
24/10/2011Appoints Rob Pease as New President and CEO and Director of ...
06/04/2011Appoints John Wakeford to Board of Directors
Rapports Financiers de Sabina Gold & Silver Corp
20/03/2015Announces Financial Results for the Year Ended 2014
09/08/2013Reports Q2 Financial Results
09/08/2013Reports Q2 Financial Results
02/04/2013Announces 2012 Year End Financial Results
09/11/2012Announces Q3 2012 Financial Results
14/08/2012Announces Q2 2012 Financial Results
14/05/2012Announces Q1, 2012 Financial Results
30/03/2012Announces 2011 Year End Financial Results
20/11/2008ANNOUNCES Q3FINANCIAL RESULTS
03/09/2008Q2 Financial Results
Projets de Sabina Gold & Silver Corp
13/10/2015Sabina Gold & Silver announces assays from Back River confir...
04/11/2013(Back River)Announces Positive Results From Echo Zone at Back River Proj...
22/10/2013(Back River)Announces Continued Positive Results from the Umwelt Deposit...
09/10/2013(Back River)Announces Positive Preliminary Feasibility Study on Back Riv...
22/08/2013(Back River)Announces Positive Results From the George Project at Back R...
24/07/2013(Back River)drills 18.6m of 19.27 g/t Gold at Back River
24/07/2013(Back River)Announces Positive Results from Umwelt Deposit at Back River...
04/07/2013(Back River)Announces Positive Results from George Property at Back Rive...
23/05/2013(Back River)Announces More Significant Assays From Llama Deposit at Back...
09/05/2013(Hackett River)Reports Glencore Xstrata Discloses New Hackett River Resourc...
30/04/2013(Back River)Announces First Results From 2013 Back River Drilling
14/02/2013(Back River)Announces Significant 2013 Back River Work Program
18/10/2012(Back River)Drilling Continues to Demonstrate Confidence at Back River P...
05/03/2012(Back River)Starts Drilling at Back River Gold Project, Nunavut Canada
14/02/2012(Back River)Mobilizes Back River Camps, Drilling Campaign to Commence Ea...
13/02/2012(Back River)Mobilizes Back River Camps, Drilling Campaign to Commence Ea...
12/01/2012(Back River)Completes Technical Report of Resource Estimate for Back Riv...
13/09/2011(Back River)Reports Continued Expansion at Umwelt & Llama Deposits, Back...
31/08/2011(Back River)Reports More Positive Results at Umwelt on the Back River Go...
25/08/2011(Back River)Reports Continued Positive Results at Back River and Wishbon...
22/07/2011(Back River)Reports Continued Positive Results at Back River Gold Projec...
28/06/2011(Back River - Goose Lake)Reports Umwelt Mineralization Now Extended Over a Strike Len...
31/05/2011(Back River)Announces Buy Back of the R.A. Olson Consulting Ltd. Royalti...
22/05/2011(Hackett River)Reports Positive Results from Early 2011 Drilling at the Hac...
27/04/2011(Back River)Reports Positive Results From Early 2011 Drilling at the Bac...
13/03/2011(Back River)Announces Updated Resource Estimate for Back River Gold Proj...
15/02/2011(Back River)Sabina Gold & Silver Files Updated Technical Report on Back ...
03/02/2011(Back River - Goose Lake)amp; Silver Opens Nunavut Camp for Aggressive 2011 Explorati...
15/09/2008(Hackett River)Hackett River Permitting Process Moves Forward
14/07/2008(Hackett River)Announces Interim Update on Corporate Initiatives on Hackett...
08/01/2008(Hackett River)Sabina drills 3.7 m of 40.28% Zn at Hacket River
Communiqués de Presse de Sabina Gold & Silver Corp
16/06/2016Sabina Gold & Silver Statement On The Nunavut Impact Review ...
10/06/2016Sabina Gold & Silver Announces AGM Voting Results
09/06/2016Sabina Gold & Silver Discovers New Gold Zone and Advanced Hi...
25/05/2016Sabina Gold & Silver Reports Encouraging Metallurgical Optim...
20/05/2016Sabina Closes $32 Million Bought Deal Financing: Enables Con...
02/05/2016Sabina Gold & Silver Corp. Announces C$30 Million Bought Dea...
31/03/2016Sabina Gold & Silver Announces Anna Stylianides Appointed To...
24/03/2016Sabina Gold & Silver Announces Financial Results for the Yea...
20/01/2016Sabina Gold & Silver announces 2016 Budget and Work Plans
25/11/2015Sabina Gold & Silver Corp Completes $2.2 Million Financing
13/10/2015Sabina Gold & Silver Announces Assays from Back River Confir...
14/09/2015Sabina Gold & Silver Announces Positive Initial Project Feas...
13/08/2015Sabina Gold & Silver Announces Q2 Financial Results
29/07/2015Sabina Gold & Silver Commences Feasibility Study Assessing L...
14/07/2015Sabina Completes $1.3 Million Financing
23/06/2015Sabina Gold & Silver Files NI 43-101 Technical Report for Fe...
18/06/2015Sabina Gold & Silver Announces John Wakeford Joins As Adviso...
04/02/2015Sabina Gold & Silver Reports Change in Management
12/01/2015Sabina Gold & Silver Reports On Important Back River Permitt...
12/01/2015Sabina Gold & Silver Reports on Important Back River Permitt...
14/11/2014SABINA GOLD & SILVER ANNOUNCES Q3 2014 FINANCIAL RESULTS $38...
14/11/2014Sabina Gold & Silver Announces Q3 2014 Financial Results
07/10/2014Sabina Gold & Silver Reports on Back River Feasibility Study...
07/08/2014Sabina Gold & Silver Announces Q2 2014 Financial Results
31/07/2014Sabina Gold & Silver Reports Completion of Drilling at Echo ...
25/06/2014Sabina Gold & Silver Completes Sale of Newman-Madsen, Ontari...
14/05/2014Sabina Gold & Silver Announces Q1 2014 Financial Results
13/05/2014Sabina Gold & Silver Announces Sale of Newman-Madsen, Ontari...
28/04/2014Sabina Gold & Silver & Kitikmeot Inuit Association Announce ...
22/04/2014Sabina Gold & Silver Reports Significant Estimated Improveme...
07/04/2014Sabina Gold & Silver Announces 2014 Back River Work Program ...
27/03/2014Sabina Gold & Silver Announces 2013 Year End Financial Resul...
13/03/2014Sabina Gold & Silver Reports Completion Of Hackett River 201...
12/03/2014Sabina Gold & Silver Reports Completion of Hackett River 201...
11/06/2013Completes $20.6 Million Financing
02/10/2012(Back River)Reports Drilling Confirms Thickness and Grade at Back River ...
17/09/2012(Back River)Announces New Shallow High Grade Discovery at Back River Pro...
09/08/2012(Back River)Announces High Grade Drill Results from Umwelt Deposit at th...
19/07/2012(Back River)Announces Continued Positive Drill Results From 2012 Drillin...
09/07/2012(Back River)Initiates Permitting Process at Back River Project, Nunavut;...
26/06/2012Completes $34.5 Million Financing
04/06/2012(Back River)Announces More Positive Drill Results from 2012 Drilling at ...
29/05/2012(Back River)Announces Positive Preliminary Economic Assessment at Back R...
26/04/2012(Back River)Announces High Grade Drill Results from 2012 Drilling at Lla...
23/01/2012Announces Aggressive 2012 Nunavut Work Program
04/10/2011to Set Up Development Trust for the Kitikmeot Region of Nuna...
20/09/2011(Back River)Reports Updated Resource Estimate for the Goose Deposit, Bac...
24/03/2011Announces Memorandum of Understanding With the Nunavut Resou...
03/11/2008New Address
26/08/200825 August 2008
21/08/2008ADDS TO ?NORTHERN? MANAGEMENT TEAM
Publication de commentaires terminée
 
Dernier commentaire publié pour cet article
Soyez le premier à donner votre avis
Ajouter votre commentaire
TORONTO (SBB.TO)Other OTC (SBBFF)
2,16+0.93%0,760-2.56%
TORONTO
CA$ 2,16
21/04 17:00 0,020
0,93%
Cours préc. Ouverture
2,14 2,12
Bas haut
2,11 2,16
Année b/h Var. YTD
 -  -
52 sem. b/h var. 52 sem.
- -  2,16 -%
Volume var. 1 mois
1 177 929 -%
24hGold TrendPower© : 27
Produit
Développe Copper - Gold - Lead - Silver - Zinc
Recherche Gold - Silver - Zinc
 
 
 
Analyse
Interactive chart Add to compare
Graphique
interactif
Imprimer Comparer Exporter
Dernière mise à jour le : 23/01/2010
Vous devez être connecté pour accéder au portefeuille (gratuit)
Top Newsreleases
LES PLUS LUS
Variation annuelle
DateVariationMaxiMini
20240,00%
202362,41%2,261,31
2022-8,90%1,830,93
2021-55,62%3,541,23
202070,47%3,380,71
 
Graphique 5 ans
 
Graphique 3 mois
 
Graphique volume 3 mois
 
 
Nouvelles des Sociétés Minières
Plymouth Minerals LTDPLH.AX
Plymouth Minerals Intersects Further High Grade Potash in Drilling at Banio Potash Project - Plannin
0,12 AU$-8,00%Trend Power :
Santos(Ngas-Oil)STO.AX
announces expected non-cash impairment
7,75 AU$+0,52%Trend Power :
Oceana Gold(Au)OGC.AX
RELEASES NEW TECHNICAL REPORT FOR THE HAILE GOLD MINE
2,20 AU$+0,00%Trend Power :
Western Areas NL(Au-Ni-Pl)WSA.AX
Advance Notice - Full Year Results Conference Call
3,86 AU$+0,00%Trend Power :
Canadian Zinc(Ag-Au-Cu)CZN.TO
Reports Financial Results for Q2 and Provides Project Updates
0,12 CA$+4,55%Trend Power :
Stornoway Diamond(Gems-Au-Ur)SWY.TO
Second Quarter Results
0,02 CA$+100,00%Trend Power :
McEwen Mining(Cu-Le-Zn)MUX
TO ACQUIRE BLACK FOX FROM PRIMERO=C2=A0
11,75 US$+7,62%Trend Power :
Rentech(Coal-Ngas)RTK
Rentech Announces Results for Second Quarter 2017
0,20 US$-12,28%Trend Power :
KEFIKEFI.L
Reduced Funding Requirement
0,54 GBX-2,55%Trend Power :
Lupaka Gold Corp.LPK.V
Lupaka Gold Receives First Tranche Under Amended Invicta Financing Agreement
0,06 CA$+0,00%Trend Power :
Imperial(Ag-Au-Cu)III.TO
Closes Bridge Loan Financing
2,48 CA$+4,20%Trend Power :
Guyana Goldfields(Cu-Zn-Pa)GUY.TO
Reports Second Quarter 2017 Results and Maintains Production Guidance
1,84 CA$+0,00%Trend Power :
Lundin Mining(Ag-Au-Cu)LUN.TO
d Share Capital and Voting Rights for Lundin Mining
15,54 CA$+1,44%Trend Power :
Canarc Res.(Au)CCM.TO
Canarc Reports High Grade Gold in Surface Rock Samples at Fondaway Canyon, Nevada
0,24 CA$+0,00%Trend Power :
Havilah(Cu-Le-Zn)HAV.AX
Q A April 2017 Quarterly Report
0,19 AU$+0,00%Trend Power :
Uranium Res.(Ur)URRE
Commences Lithium Exploration Drilling at the Columbus Basin Project
6,80 US$-2,86%Trend Power :
Platinum Group Metals(Au-Cu-Gems)PTM.TO
Platinum Group Metals Ltd. Operational and Strategic Process ...
1,89 CA$+6,78%Trend Power :
Devon Energy(Ngas-Oil)DVN
Announces $340 Million of Non-Core Asset Sales
52,12 US$+0,03%Trend Power :
Precision Drilling(Oil)PD-UN.TO
Announces 2017Second Quarter Financial Results
8,66 CA$-0,35%Trend Power :
Terramin(Ag-Au-Cu)TZN.AX
2nd Quarter Report
0,04 AU$+0,00%Trend Power :