Golden Predator Announces Positive Preliminary Economic Assessment (PEA) Results for the Brewery Creek Project, Yukon

( 0 vote, 0/5 ) Print article
  Article Comments Comment this article Rating Follow Company  
0
Send
0
comment
Keywords :   Gold | Idaho | Recovery | Troy Ounce | Water |

Golden Predator Announces Positive Preliminary Economic Assessment (PEA) Results for the Brewery Creek Project, Yukon

HAYDEN, Idaho--(BUSINESS WIRE)--

Golden Predator Mining Corp. (GPY.V) (the “Company” or “Golden Predator”) is pleased to announce the results of a Preliminary Economic Assessment (PEA) for the company’s year-round road accessible Brewery Creek Gold Project. The NPV of the project ranges from $18.1 million at $1,150 gold to $114.5 million at $1,500 gold with IRRs ranging from 12% to 45% with corresponding gold prices; these scenarios are pre-tax and assume a 5% discount rate. Total Life of Mine Capital is estimated to be $89.4 million which includes initial capital, sustaining capital, indirect costs and owner costs.

“We are happy to have our belief regarding the potential economics of re-opening the Brewery Creek mine confirmed by this study. Having a project with truly modest CAPEX and a break-even point around $1,100 gold provides us with a quality asset with only a minimal revival in the price of gold,” said Janet Lee-Sheriff, Chief Executive Officer, “The compelling low start-up cost along with the untapped exploration potential of the project should make this an attractive opportunity for a prospective joint venture candidate.”

The PEA evaluated the economics of resuming mining at Brewery Creek through a combination of open pit mining and reprocessing former heap leach material for gold recovery to doré. The study was prepared by Tetra Tech EBA Inc. in cooperation with Tetra Tech Inc. of Tucson, AZ; SGS-E&S Engineering Solutions Inc. of Tucson, AZ; Resource Modeling Inc. of Stites, ID; Gustavson and Associates of Lakewood, CO and Access Consulting Group of Whitehorse, YT.

   

PEA Summary Mine Plan and Operating Assumptions

 
Total Oxide mined from Open Pits (tonnes)     10,264,000
Total Waste mined from Open Pits (tonnes)     43,520,000
Strip Ratio open pits     4.2:1
Total Gold Ounces Contained     445,000
Average Diluted Grade g/t Gold Open Pits     1.351
       
Total Material Re-processed from Old Heap Leach (tonnes)     4,195,000
Total Waste Moved on Old Heap (tonnes)     3,366,000
Total Gold Ounces Contained Old Heap Material     104,000
Average Diluted Grade g/t Gold Old Heap Material     0.772
       
Total Gold Ounces Recovered     372,000
Life of Mine     9 years
1   Based on a cut-off grade of 0.50 g/t gold
2 Based on a cut-off grade of 0.30 g/t gold
 

PEA Summary Capital and Operating Costs

 

Capital Costs (including contingency)

   
Total Direct Capital   $ 59,480,000  
Capitalized Mining Costs (pre-stripping)   $ 11,365,000  
Indirect Costs   $ 8,406,000  
Owner Costs (G&A year -2 & -1)   $ 5,998,000  
Sustaining Capital   $ 4,161,000  
Total Life Mine Capital   $ 89,410,000  
     
Unit Operating Costs (per tonne leached)    
Mining leach feed from pits1   $

3.522

Mining waste from pits   $

2.612

Mining leach feed from old heap   $ 1.17  
Processing (includes placement on heap leach pad)   $ 8.41  
General & Administrative   $ 3.11  
 
1 Mining cost of leach feed from pits is higher than waste mining due to longer haul distance to deliver feed to crushers than to deliver waste rock to repositories.
2 Includes $0.59 per tonne for equipment leasing
   

PEA Summary Economics at $1250/oz. Gold

 
Pre-tax and Royalty NPV at 5%     $ 45,658,000  
Pre-tax and Royalty IRR      

22%

Pre Tax payback       2.7  
Post Tax and Royalty NPV at 5%     $ 23,315,000  
Post Tax and Royalty IRR      

15%

Post Tax payback       3.2  
Total LOM Revenue     $ 463,089,000
Total LOM Operating Costs     $ 288,232,000
Total LOM Capital including sustaining and contingency     $ 89,410,000
Reclamation Costs     $ 8,000,000
Total LOM Royalties     $ 16,342,000
Total LOM Taxes     $ 14,864,000
Total cash Flow after taxes and royalties     $ 46,578,000
Cash Cost ($/oz gold)     $ 788

The base case summarized above assumes the owner will lease all mining equipment, instead of owner purchasing all mining equipment, to result in a lower initial capital cost. The base case assumes mining and crushing for 230 days per year at an average rate of 7,500 tonnes per day. All heap leach feed material would be crushed to 80% passing 9.5 mm. Some material on the old heap leach pad would be re-processed by crushing and re-leaching on an as needed basis to meet demand when open pit mining is not at full capacity. The existing leach pad would have the last three original designed cells built. Recent geotechnical studies indicate the pad can safely accommodate an increase in stacking height from 30 meters to 40 meters providing more capacity on the pad. Solutions would be circulated and gold recovered year round through a carbon Adsorption Desorption Recovery (ADR) plant to produce doré on site.

The existing road to Brewery Creek will continue to provide access. Power generation for the PEA was modeled as diesel powered providing a total of 5.0 megawatts with normal power draws of 3.93 MW. Waste rock generated from some of the new open pits has been designed to be used to backfill existing and new pits as scheduling allows.

                     

Sensitivities

 
Gold Price US$/oz     $ 1150       $ 1250       $ 1375       $ 1500  
Pre-Tax NPV 5% $000     $ 18,112       $ 45,658       $ 80,091       $ 114,524  
Post-Tax NPV 5% $000     $ 4,001       $ 23,315       $ 46,858       $ 69,360  
Pre-Tax IRR      

12%

     

22%

     

34%

     

45%

Post-Tax IRR      

7%

     

15%

     

24%

     

32%

Opportunities to Enhance Value

Trade off studies were evaluated against the base case and these included the owner purchasing all mining equipment. The owner purchase scenario, while increasing initial capital costs, project NPV remained relatively consistent, with less $1 million decrease in NPV. This scenario will be evaluated further in the future engineering studies. The current model includes commencing drilling and blasting activities at the surface of the deposits but in the previous operation it was found that level of oxidation was such that the surface material and some initial mining benches did not require drilling and blasting which would provide a positive effect on the economics. Additional economic enhancements could be found by reducing the base case throughput rate of 7,500 tonnes per day which would result in lower capital costs and extend mine life. The opportunity to mine and crush more than 230 days per year would also provide enhanced economics to the project. The property has high potential for resource expansion and discovery of new deposits. The known resources at the Classic and Lone Star deposits were not considered in this PEA and both deposits remain open to expansion. The Lone Star deposit has encountered higher grade skarn mineralization which has not been found before on the property and could develop in to a higher grade resource.

Mineral Resources

The mineral resources used in this PEA include Indicated and Inferred mineral resources estimated by three independent Qualified Persons (QP), Don Hulse, P.E., of Gustavson, Michael J. Lechner, P. Geo. of RMI, and James Barr, P. Geo., of Tetra Tech EBA. The resources are found in fifteen different deposits currently identified on the Brewery Creek property and the run of mine material (not crushed) on the old heap leach pad. The in-situ estimates used sample data from 2,608 drill holes and over 198,829 meters of drilling and the remaining resources in the existing heap were estimated using 18 sonic drills with a total of 266 meters of drilling.

The PEA utilized Indicated and Inferred resources from eight of the fifteen deposits and the old heap leach pad to develop the plans included in this PEA. The PEA mines a total of 10.2 million tonnes of oxide material at 1.35 g/t gold from the eight open pits and reprocesses 3.1 million tonnes from the old heap at 0.77 g/t gold. The total oxide resources for the Brewery Creek are estimated at 14.1 million tonnes at 1.27 g/t gold classified as Indicated and 9.3 million tonnes at 0.93 g/t gold classified as Inferred. For further details on the mineral resources the reader is referred to the complete PEA document.

 

Capital and Operating Costs

 
Capital Costs in US$000
Capital cost item    

Estimated
initial
capital

    Contingency %     Total Initial    

Sustaining
including
contingency

    Total capital
 
Direct
General site     $ 64     5 %     $ 67           $ 67
Site infrastructure     $ 2,857     15 %     $ 3,286           $ 3,286
Preproduction and haul roads     $ 812     10 %     $ 890           $ 890
Mining equipment     $ 65     25 %     $ 81           $ 81
Mining infrastructure     $ 615     15 %     $ 708           $ 708
Total mining and site infrastructure     $ 4,413     14 %     $ 5,031           $ 5,031
 
Processing excluding heap leach construction
Crushing     $ 10,902     20 %     $ 13,082           $ 13,082
Agglomeration     $ 3,349     20 %     $ 4,019           $ 4,019
Ore stacking     $ 728     20 %     $ 874           $ 874
ADR facility and heap leach equipment     $ 9,918     20 %     $ 11,901     $ 4,128     $ 16,029
Process infrastructure     $ 8,159     20 %     $ 9,790           $ 9,790
Total processing     $ 33,055     20 %     $ 39,666     $ 4,128     $ 43,795
 
Heap leach and water management
Heap leach facility including ponds     $ 12,764     15 %     $ 14,679           $ 14,679
Water management     $ 83     25 %     $ 103           $ 103
Total HLF and water management     $ 12,847     15 %     $ 14,782           $ 14,782
                               
Total direct     $ 50,316     18 %     $ 59,480     $ 4,128     $ 63,608
 
Indirect
Capitalized mining     $ 11,365           $ 11,365           $ 11,365
Process indirects     $ 5,550     20 %     $ 6,661     $ 33     $ 6,694
Mining and other indirects     $ 1,517     15 %     $ 1,745           $ 1,745
Owners costs (Overheads year -2 and -1)     $ 5,998     0 %     $ 5,998           $ 5,998
Total indirect     $ 24,431     5 %     $ 25,769     $ 33     $ 25,802
 
Total capital in US$000     $ 74,746     14 %     $ 85,249     $ 4,161     $ 89,410
 
Operating Costs per tonne processed
Average for mining leach feed from pits   $

3.521

Mining waste in pits   $

2.611

Re-handling old leach feed   $ 1.17  
     
Processing (includes crushing)   $ 8.37  
G&A   $ 3.11  
Life of Mine Operating Costs   $ 19.95  
1   Includes $0.59 per tonnes for equipment leasing

Mining

The Brewery Creek project was evaluated for mining in the PEA as open pit truck and shovel operation. Mining was considered on the oxide portions of eight deposits aligned in a more or less east-west trend along 8 kilometers in what is known locally as the “reserve trend”. The deposits are West Big Rock, East Big Rock, Lower Fosters, Kokanee, Golden, Lucky, Bohemian and Schooner. The mine schedule shows calls for mining and processing over 10.0 million tonnes of heap leach feed and 43.5 million tonnes of waste for a strip ratio of 4.2:1. The current life of mine is nine years. The mine plan also includes reprocessing 4.1 million tonnes of material from the old heap leach pad. An additional 3.3 million tonnes of old heap material will be moved but not processed. Recent studies have shown that since the original material was not crushed an additional 45% of the remaining contained gold can be recovered after crushing. The old pad material will be mined and processed when the mining in the open pits is not at full capacity.

Pit Area  

Process Feed Over Life
of Mine (kt)

  Gold Grade (gpt)
Schooner   1,044   2.07
Fosters   1,275   1.62
Bohemian   1,577   1.22
Golden   878   1.34
Kokanee   1,243   1.06
West Big Rock   809   1.17
East Big Rock   465   1.07
Lucky   2,973   1.27
Total from Pits   10,264   1.351
Total from old Heap   4,180   0.772

1Based on a cut-off grade of 0.50 g/t gold

2Based on a cut-off grade of 0.30 g/t gold

The mine plan was developed by importing the resource block models for the deposits into a pit optimization software package called GeoviaTM. Criteria were applied to the mining and processing of the mineralized and waste blocks that would be mined to create pit shells. The criteria included pit slopes generally ranging from 45o to 55o with small portions of individual pits allowing for slightly steeper or shallower pit slopes based on geotechnical assessment by Tetra Tech EBA. Gold recoveries for the pits ranged from 70.0% to 82.9% based on metallurgical testing including column leach tests.

The mining equipment was matched to achieve the planned daily mining rate of 7,500 tonnes on seasonal basis. The mining season is an anticipated 230 days of active mining and based on what the former Viceroy operation at Brewery Creek was able to achieve during its mine life. The PEA considered leasing of mining equipment to keep the initial capital costs low but does result in increasing the operating costs.

Operating costs average US$19.95/tonnes processed over the life of mine, including equipment leasing, which equates to US$778 per troy ounce sold. The estimation of operating costs is based on consumables, labor, maintenance and other requirements. Since the deposits considered in the PEA lie along an 8 kilometer trend and a crushing and heap leach pad which are located near the western end of the deposit trend different haulage costs of ore were estimated for each deposit. The cost of waste transport is generally less than the transport of the heap leach feed because the waste material is generally schedule to be deposited in engineered facilities near the respective open pits.

Operating Cost Estimates
Item  

Cost in
US$/tonne

    Source
LOM average unit cost of mining process feed from pits   $

3.521

    Runge XerasTM software
LOM unit cost of mining waste rock in pits   $

2.611

    Runge XerasTM software
LOM cost of mining (re-handling) process feed from old heap   $ 1.17       Runge XerasTM software
General and Administrative costs per tonne process feed   $ 3.11       Modeled by Year
1   Includes $0.59 per tonnes for equipment leasing

Processing

The process plant flow sheet was developed by SGS and is designed to crush and stack heap leach feed approximately 230 days per year and to recover gold from the heap leach solutions 365 days per year. The flow sheet used a daily feed rate of 7,500 tonnes per day or an annual feed rate of 1.7 million tonnes.

Material will be delivered to the crushing area and reduced to a nominal 80% passing 9.5 mm after tertiary crushing with modular crushing units. Feed material from the Fosters deposit and re-processed material from the old heap are planned to be agglomerated. The crushed material will be stacked on the leach pad by truck. Gold recovery for the leach solutions is done by through an ADR plant.

Estimates for gold recovery and consumption rates of regent is based on recent metallurgical testing conducted by McClelland Laboratories for five of the deposits and the old heap leach material. Recoveries and consumption rates for three of the deposits which were previously mined by Viceroy are based on historical data.

Heap Leach Feed Source  

Au Extraction
(%)

 

NaCN
(kg/t)

 

Lime
(kg/t)

 

Cement
(kg/t)

Schooner   73.9   0.26   2.53   0
Fosters   72.5   0.23   1.73   2.00
Bohemian   77.0   0.31   3.00   0
Golden   70.0   0.37   2.89   0.40
Kokanee   70.0   0.37   2.89   0.40
West Big Rock   82.9   0.30   3.87   0
East Big Rock   77.0   0.73   3.30   0
Lucky   70.0   0.37   2.89   0.40
Old Heap   45.0   0.27   0   5.75

Operating costs for the processing at Brewery Creek are estimated to be slightly variable depending on the material being processed and the table below shows the overall average processing plant operating costs. The costs include crushing, reagents, fuel, power, assay laboratory, labor and maintenance.

Item   Total US$(000)   US$/tonne feed
Reagents   39,892   2.96
Fuel   2,955   0.22
Power   40,768   3.03
Labor   23,962   1.78
Other   5,075   0.38
Total   112,655   8.37

First Nations, Community Engagement and Environment

Community and First Nation engagement has been a strong component of the Brewery Creek Project dating to the initial mine operator, Viceroy Resources. In 2011 Golden Predator updated and modernized the Socio Economic Agreement with the Tr’ondek Hwech’in (TH), which addresses environmental responsibilities, permitting, education and employment as well as preferential contracting opportunities and wealth sharing. The Brewery Creek Project lies with the traditional territory of both the Tr’ondek Hwech’in and the First Nation of Na Cho Nyak Dun (NND). Regardless of the pre-existing relationship and agreement with TH and the proximity to Dawson City, Yukon the Company has and will continue to consult with both First Nations on all permitting and regulatory matters.

The previous operator and the company have conducted extensive environmental studies and monitoring programs that document the property since the early 1990’s. Studies include water quality, fisheries, wildlife, heritage and vegetation. The company continues to conduct regular environmental sampling and monitoring on the property.

Disclosure

The PEA is only summarized in this press release as an initial high-level review of the project the complete detailed report will filed on SEDAR within 20 days of this press release. The PEA is preliminary in nature and it includes inferred mineral resources that are considered too speculative to be used in an economic analysis except as allowed for by Canadian Securities Administrator’s National Instrument 43-101 in PEA studies. There is no guarantee that the inferred mineral resources can be converted to Indicated or Measured mineral resources, and as such, there is no guarantee the project economics described in this report will be achieved.

Qualified Persons

The independent qualified persons responsible for preparing the Brewery Creek Preliminary Economic Assessment are James Barr, P. Geo., of Tetra Tech EBA Inc. Mark Horan, P. Eng., of Tetra Tech EBA Inc., Marvin Silva, Ph.D., P. Eng., of Tetra Tech EBA Inc., Joseph Keane, P. E., of SGS-E&S Engineering Solutions Inc., Mike Lechner, P. Geo., of Resource Modeling Inc., Donald E. Hulse, P.E., of Gustavson and Associates and Claiborne Newton, III, Ph.D., SME(RM), of Gustavson and Associates.

Michael Maslowski, CPG, a consultant to the company is the Company’s designated QP for this news release within the meaning of NI 43-101 and has reviewed and validated that the information contained in the release is consistent with that provided by the QP’s responsible for the PEA.

Golden Predator Mining Corp.

Golden Predator’s corporate mandate is to advance the Brewery Creek project towards production through a joint venture arrangement. The Brewery Creek mine operated from 1996 to 2002, before closing due to low gold prices. Mining licenses and permits are in place for continued exploration along with a Socio Economic Accord with the Tr'ondek Hwech'in. The Company holds additional projects with current resources and/or new discovery potential, including the high-grade 3 Aces and Grew Creek gold projects and the Marg and Clear Lake polymetallic massive sulfide deposits.

For additional information:

Janet Lee-Sheriff, Chief Executive Officer

(208) 635 5415

info@goldenpredator.com

www.goldenpredator.com

Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.

No stock exchange, securities commission or other regulatory authority has approved or disapproved the information contained herein. This press release contains projections and forward-looking information that involve various risks and uncertainties regarding future events. Such forward-looking information can include without limitation statements based on current expectations involving a number of risks and uncertainties and are not guarantees of future performance. There are numerous risks and uncertainties that could cause actual results and the Company’s plans and objectives to differ materially from those expressed in the forward-looking information. Actual results and future events could differ materially from those anticipated in such information. These and all subsequent written and oral forward-looking information are based on estimates and opinions of management on the dates they are made and are expressly qualified in their entirety by this notice. Except as required by law, the Company assumes no obligation to update forward-looking information should circumstances or management's estimates or opinions change.

NR 14-08

Read the rest of the article at finance.yahoo.com

Golden Predator.

PRODUCER
CODE : GPY.V
ISIN : CA38116P1053
Follow and Invest
Add to watch list Add to your portfolio Add or edit a note
Add Alert Add to Watchlists Add to Portfolio Add Note
ProfileMarket
Indicators
VALUE :
Projects & res.
Press
releases
Annual
report
RISK :
Asset profile
Contact Cpy

Golden Predator. is a gold development stage company based in Canada.

Golden Predator. develops gold and silver in USA, and holds various exploration projects in Canada.

Its main asset in production is BALD MOUNTAIN in USA, its main asset in development is TAYLOR MINE in USA and its main exploration properties are BREWERY CREEK, CLEAR CREEK, LANTERN DEPOSIT, ST. ELMO, BUENA VISTA/FRENCH BOY, CEDAR (NEVADA), BOND, OGOPOGO, DEL, AGATE, MEL, DAD, LED, CHOPIN, MCCONNEL, DOME HILL, GOLD (SCHEELITE) DOME, HARLAN, PHOENIX JV, ANTIMONY MOUNTAIN, WINDFALL LAKE, ALBERTA SUN, TUSCARORA, AFGAN, GREW CREEK, ADELAIDE, WILLOUGHBY, ALKALIC, ANGEL'S CAMP, GOLDEN RIDGE ( NEVADA), PAN, TONKIN PROJECT, SONORA GULCH, MARG, BRUIN CREEK and BROWNS CREEK in Canada and GUIJOSO and MAGISTRAL I in Mexico.

Golden Predator. is listed in Canada. Its market capitalisation is CA$ 14.7 millions as of today (US$ 11.6 millions, € 9.8 millions).

Its stock quote reached its highest recent level on November 19, 2010 at CA$ 9.80, and its lowest recent point on April 25, 2014 at CA$ 0.03.

Golden Predator. has 91 570 000 shares outstanding.

Your feedback is appreciated, please leave a comment or rate this article.
Rate : Average note :0 (0 vote) View Top rated
 
Corporate Presentations of Golden Predator.
9/16/2011Corporate Presentation - Precious Metal Summit (September 15...
8/20/2009Corporate presentation August 2009
In the News and Medias of Golden Predator.
1/22/2019Golden Predator extends 3 Aces mineralization
Annual reports of Golden Predator.
receives 2,533,333 Shares of Silver Predator Corp.; Provides...
2008 Annual Report
Financings of Golden Predator.
9/23/2011Extends 950,000 Warrants
6/22/2011Golden Predator and Seabridge Gold Agree to Contribute Selec...
Nominations of Golden Predator.
2/13/2013Appoints Financial Advisor
Project news of Golden Predator.
8/18/2016(3ace Property)Predator Pours First Gold from Bulk Sample
8/15/2016(3ace Property)Predator Discovers Coarse Visible Gold in New Vein at 3 Aces...
9/27/2012(Brewery Creek)arranges USD $35,000,000 Loan Facility with RK Mine Finance;...
7/16/2012(Brewery Creek)and Tr'ondek Hwech'in First Nation Update Brewery Creek Proj...
7/10/2012(Brewery Creek)Drilling extends Brewery Creek\222s Bohemian Zone...
3/5/2012(Brewery Creek)Drills Third Major Brewery Creek Discovery; Classic Zone Hos...
1/5/2012(Pan)continues to expand North Slope Zone at its Brewery Creek Pr...
12/5/2011(Pan)Calculates NPV of Royalty Interest in Pan Project at USD $32...
9/1/2011Acquires Livingstone District; Now Controls Largest Land Pos...
8/11/2011(Brewery Creek)Continues Easterly Extension of Bohemian-Schooner Zone at Br...
8/11/2011(Brewery Creek)Continues Easterly Extension of Bohemian-Schooner Zone at ...
7/26/2011(Harlan)Commences Drill Program on its Enticing Harlan Project in ...
7/18/2011(Brewery Creek)Investigates Gold Recovery from Existing Heap Leach Pad at ...
7/5/2011(Grew Creek)drills 92.0 m of 2.02 g/t Gold; Commences Resource Calcu...
6/1/2011(Brewery Creek)Triples 2011 Budget, Adds Second Drill, and Plans for Third ...
5/26/2011(Grew Creek)Intersects 98.3 m of 1.83 g/t Gold at Carlos Zone, Grew Cree...
4/26/2011(Brewery Creek)Intersects 74 m of 7.08 g/t Gold 250m East of Bohemian Zone,...
4/21/2011(Harlan)Increases Land Position in the Yukon's Selwyn Basin to 7,800...
4/14/2011(Swede Dome)Stakes 4 Project Areas in Historic Yukon Placer Headwaters
4/8/2011(Brewery Creek)Intercepts 28 m of 5.06 g/t Gold at Brewery Creek's Bohemian...
3/24/2011(Brewery Creek)expands Bohemian Discovery with 32.9 m of 3.01 g/t Gold at ...
2/22/2011(Brewery Creek)COMMENCES 2011 YUKON DRILL PROGRAM
1/24/2011(Harlan)Acquires Harlan Property, Yukon
1/6/2011(Mcconnel)Acquires McConnell Property, Yukon
11/30/2010(Gold (scheelite) Dome)Intercepts 21.95 m of 1.00 g/t Gold from Hawthorne Ridge Zon...
12/10/2009(Brewery Creek)Intersects 20.17 gpt Gold over 1.90 m and 4.72 gpt Gold over...
11/16/2009(Gold (scheelite) Dome)Intersects 11.12 gpt Gold over 25.40 m including 52.35 gpt G...
11/5/2009(Antimony Mountain)Intersects 12.45 gpt Gold over 4.88 m including 28.81 gpt Go...
8/10/2009(Adelaide)completes Technical Report on the Adelaide Project, Nevada
6/8/2009(Brewery Creek)GOLDEN PREDATOR ACQUIRES BREWERY CREEK PROJECT, YT
2/11/2009(High Grade Gp) Reports on Initial Exploration at High Grade Project
Corporate news of Golden Predator.
8/2/2016Golden Predator Increases Previously Announced Offering to C...
7/26/2016Golden Predator Closes C$16.36 Million Financing; Includes C...
7/13/2016Golden Predator Commences Geotechnical and Metallurgical Dri...
7/6/2016Golden Predator Increases Previously Announced Offering to C...
6/27/2016Golden Predator and Tr’ondëk Hwëch’in Amend Brewery Creek Pr...
6/27/2016Golden Predator Announces $7,300,000 Investment By Eric Spro...
6/20/2016Golden Predator Intersects 11.43m of 31.82 g/t Gold at 3 Ace...
6/16/2016Golden Predator Retires 10,312,154 Common Shares
6/13/2016Tony Lesiak Appointed to Golden Predator’s Board of Director...
6/10/2016Golden Predator Exercises Option to Acquire Shares
6/8/2016Till Capital Receives $1,546,823 CDN From Sale of Golden Pre...
6/7/2016McEwen Mining’s Stefan Spears Appointed to Golden Predator’s...
6/6/2016Golden Predator Reports Initial Gold Gravity Recoveries of 8...
1/25/2016Golden Predator Recovers 79.9 to 90.8% Gold from 3 Aces Prel...
1/4/2016Golden Predator Announces TSXV Approval of Castle West Prope...
10/6/2015Golden Predator Chairman Increases Holdings
10/2/2015Golden Predator Announces Stock Option Grant
9/30/2015Golden Predator Arranges CDN $300,000 Line of Credit
9/30/2015Golden Predator Arranges CDN$300,000 Line of Credit
9/14/2015Golden Predator Confirms Continuity of High Grade Gold from ...
9/14/2015IIROC Trading Resumption - GPY
9/14/2015IIROC Trading Halt - GPY
9/11/2015Golden Predator announces re-election of board at Annual Gen...
9/3/2015Golden Predator Announces Board and Management Appointments;...
9/3/2015IIROC Trading Resumption - GPY
9/2/2015Golden Predator Announces Board and Management Appointments;...
9/2/2015Till Capital Announces Board and Executive Changes
8/24/2015Till Capital Reports on Golden Predator Annual General Meeti...
8/21/2015IIROC Trading Halt - GPY
7/30/2015Golden Predator Adopts Advance Notice Policy
7/16/2015Golden Predator Announces Convertible Debenture Financing
6/22/2015Golden Predator Receives 3 Aces Permit
4/21/2015Golden Predator Completes First Note Payable Payment
3/30/2015Golden Predator Announces Joint Venture and Option Agreement...
3/16/2015Golden Predator Announces Joint Venture and Option Agreement...
12/2/2014Metallurgical Tests Indicate 93.5% to 98.3% Overall Gold Rec...
11/20/2014Golden Predator Files Preliminary Economic Assessment Result...
11/12/2014Golden Predator Announces Positive Preliminary Economic Asse...
10/22/2014Golden Predator Appoints Janet Lee-Sheriff as Chief Executiv...
9/4/2014Gravity Tests Indicate 87% to 96% Gold Recovery at Golden Pr...
8/25/2014Golden Predator Leases the Castle West Property, Nevada
8/5/2014Preliminary Economic Assessment on Brewery Creek Project, Yu...
7/15/2014Golden Predator Commences Preliminary Metallurgical Characte...
7/10/2014Golden Predator Announces Former Yukon Premier Dennis Fentie...
2/21/2013to start trading as Americas Bullion Royalty Corp. (TSX:AMB)...
2/19/2013and Tr\222ondek Hwech\222in ...
2/19/2013and Tr'ondek Hwech'in Disagree with YESAB
2/7/2013Approves Creation of Shareholder Rights Plan, Finalizes Name...
1/30/2013Silver Predator and Redtail Metals Sign Exploration Agreemen...
1/24/2013(Rogue)Discovers High-grade Gold Mineralization on Rogue B Property...
1/18/2013Announces Name Change to Gold Bullion Royalty Corp.
1/8/2013Tr'ondek Hwech'in and Golden Predator Continue to Work Toget...
1/8/2013Tr'ondëk Hwëch'in and Golden Predator Continue to Work Toget...
11/5/2012(Brewery Creek)- Classic Zone Drilling Intersects 41.2 m of 1.04 g/t Go...
10/12/2012William Sheriff, Chairman & CEO, Interviewed on BNN's Commod...
10/11/2012(Alkalic)Announces New Brewery Creek Discovery; Open-Ended Lone Star ...
10/11/2012(Alkalic)Announces New Brewery Creek Discovery: Open-Ended Lone Star ...
10/4/2012(Brewery Creek)Lower Fosters Zone Drilling Intersects 29.0 m of 1.86 g/t Go...
7/19/2012New Mineralization Encountered at Moosehead Pit, Brewery Cre...
7/16/2012and Tr\222ond\353k Hw\353ch\222in ...
6/28/2012JOINT NEWS RELEASE: Golden Predator Corp. and Seabridge Gold...
6/7/2012Joint News Release: Golden Predator Corp. and Seabridge Gold...
5/1/2012Announces Resource Estimate at Brewery Creek Project of 580,...
3/22/2012(Brewery Creek)Sleeman Zone Drilling Intersects 40.9 m of 1.81 g/t Gold and...
3/15/2012(Brewery Creek)Bohemian-Schooner Zone Drilling Intersects 24.0 m of 1.47 g/...
2/23/2012(Grew Creek)Intersects 68 m of 5.96 g/t Gold at Carlos Zone, Grew Creek ...
2/22/2012(Brewery Creek)East Big Rock Zone Drilling Intersects 15.2 m of 1.93 g/t Go...
1/20/2012Upcoming Events
1/12/2012(Brewery Creek)intersects 30.5 m of 1.97 g/t Gold at its Brewery Creek Proj...
1/10/2012(Harlan)announces New Gold Discovery at Cache Creek (Harlan) Project...
1/9/2012(Brewery Creek)Encounters 35.1 m of 1.63 g/t Gold and 136.72 g/t Silver at ...
9/12/2011100%\240OF\240EXPIRING\240WAR...
8/29/2011(Pan)Brewery Creek\222s Expanding Sle...
8/5/2011and Ross River Dena Council Sign Traditional Knowledge P...
6/30/2011(Pan)Continues to Expand Brewery Creek's Bohemian-Schooner Zone
6/21/2011(Grew Creek)Intersects 46.7m of 3.78 g/t Gold at Carlos Zone, Grew Creek...
3/17/2011RECEIVES 5,000,000 SHARES OF SILVER PREDATOR CORP.
9/29/2009Provides Update on Yukon Projects
7/28/2009Drilling Commences at Gold Dome Project, Yukon Territory
3/7/2009Completes Spin-Out
3/5/2009Announces Voting Results of Special Meeting
3/3/2009Timing of Shareholders Meeting To be Held On March 4, 2009
2/26/2009to Retire Convertible Debentures of Subsidiary
2/13/2009Confirms Date of Shareholder Meeting
Comments closed
 
Latest comment posted for this article
Be the first to comment
Add your comment
TSX-V (GPY.V)
0.160+0.00%
TSX-V
CA$ 0.160
09/01 16:52 -
0%
Prev close Open
0.160 0.160
Low High
0.155 0.160
Year l/h YTD var.
 -  -
52 week l/h 52 week var.
- -  0.160 -%
Volume 1 month var.
201,699 -%
24hGold TrendPower© : 50
Produces Gold
Develops Silver
Explores for Antimony - Copper - Gold - Silver - Tungsten - Uranium
 
 
 
Analyse
Interactive chart Add to compare
Interactive
chart
Print Compare Export
Last updated on : 11/2/2010
You must be logged in to use the porfolio and watchlists (free)
Top Newsreleases
Annual variation
DateVariationHighLow
2021-33.33%0.300.12
2020-31.43%0.480.15
 
5 years chart
 
3 months chart
 
3 months volume chart
 
 
Mining Company News
Plymouth Minerals LTDPLH.AX
Plymouth Minerals Intersects Further High Grade Potash in Drilling at Banio Potash Project - Plannin
AU$ 0.12-8.00%Trend Power :
Santos(Ngas-Oil)STO.AX
announces expected non-cash impairment
AU$ 7.63+1.06%Trend Power :
OceanaGold(Au)OGC.AX
RELEASES NEW TECHNICAL REPORT FOR THE HAILE GOLD MINE
AU$ 2.20+0.00%Trend Power :
Western Areas NL(Au-Ni-Pl)WSA.AX
Advance Notice - Full Year Results Conference Call
AU$ 3.86+0.00%Trend Power :
Canadian Zinc(Ag-Au-Cu)CZN.TO
Reports Financial Results for Q2 and Provides Project Updates
CA$ 0.12+4.55%Trend Power :
Stornoway Diamond(Gems-Au-Ur)SWY.TO
Second Quarter Results
CA$ 0.02+100.00%Trend Power :
McEwen Mining(Cu-Le-Zn)MUX
TO ACQUIRE BLACK FOX FROM PRIMERO=C2=A0
US$ 12.17+0.66%Trend Power :
Rentech(Coal-Ngas)RTK
Rentech Announces Results for Second Quarter 2017
US$ 0.20-12.28%Trend Power :
KEFIKEFI.L
Reduced Funding Requirement
GBX 0.62+5.07%Trend Power :
Lupaka Gold Corp.LPK.V
Lupaka Gold Receives First Tranche Under Amended Invicta Financing Agreement
CA$ 0.06+0.00%Trend Power :
Imperial(Ag-Au-Cu)III.TO
Closes Bridge Loan Financing
CA$ 2.64+1.15%Trend Power :
Guyana Goldfields(Cu-Zn-Pa)GUY.TO
Reports Second Quarter 2017 Results and Maintains Production Guidance
CA$ 1.84+0.00%Trend Power :
Lundin Mining(Ag-Au-Cu)LUN.TO
d Share Capital and Voting Rights for Lundin Mining
CA$ 15.85-2.10%Trend Power :
Canarc Res.(Au)CCM.TO
Canarc Reports High Grade Gold in Surface Rock Samples at Fondaway Canyon, Nevada
CA$ 0.24+0.00%Trend Power :
Havilah(Cu-Le-Zn)HAV.AX
Q A April 2017 Quarterly Report
AU$ 0.20+2.50%Trend Power :
Uranium Res.(Ur)URRE
Commences Lithium Exploration Drilling at the Columbus Basin Project
US$ 6.80-2.86%Trend Power :
Platinum Group Metals(Au-Cu-Gems)PTM.TO
Platinum Group Metals Ltd. Operational and Strategic Process ...
CA$ 1.84+0.00%Trend Power :
Devon Energy(Ngas-Oil)DVN
Announces $340 Million of Non-Core Asset Sales
US$ 50.55-0.84%Trend Power :
Precision Drilling(Oil)PD-UN.TO
Announces 2017Second Quarter Financial Results
CA$ 8.66-0.35%Trend Power :
Terramin(Ag-Au-Cu)TZN.AX
2nd Quarter Report
AU$ 0.04+0.00%Trend Power :