Medusa Mining Limited: Co-O Operations Update
Published : July 08, 2013
( 0 vote, 0/5 ) Print article
  Article Comments Comment this article Rating Follow Company  
0
Send
0
comment
Keywords :   Australia | Diamond | Gold | Growth | Market | Report | United Kingdom |

COMO, WESTERN AUSTRALIA--(Marketwired - July 8, 2013) - Medusa Mining Limited (News - Market indicators)(LSE:MML) ("Medusa" or the "Company") wishes to provide an update for the Co- O Operations following the previous announcement of 21 June 2013 regarding the Co-O Mill construction managers.

OVERVIEW

  • CPC Engineering ("CPC") appointed as the new Co-O Mill expansion managers with immediate effect.

  • Commissioning of the new Co-O Mill is commencing with the mobilisation of CPC Engineering commissioning personnel to site.

  • Commissioning of the Co-O Mill delayed by approximately four to five weeks and likely to be completed in August 2013. Arccon administration has had no other effect on the Company's operations.

  • With the current subdued gold price and the delay to the commissioning of the new Co-O Mill Medusa has been reviewing the efficiency of its operations and its costs.

  • Overdraft facilities arranged with two Philippine banks totalling US$14 million.

  • Exploration drilling reduced to two surface and two underground drill rigs, reducing the exploration expenditure from approximately US$25 million in FY2013 to approximately US$12 million in FY2014.

  • L8 shaft (formerly the Saga shaft) production reduced during June quarter as a result of narrower veins than expected near the shaft.

  • Production and cash cost forecasts under review pending completion of commissioning and additional Level 8 development.

  • Bananghilig feasibility study status being reviewed in light of lower gold price and in recognition of the newly discovered high grade zone, B2.

Peter Hepburn-Brown, Managing Director of Medusa, commented:

"We are very pleased with the appointment of a replacement manager to complete the final stages of the plant construction and commence commissioning with minimum disruption and minor delays. We are all looking forward to operating a new plant which we anticipate will have a high availability.

Production has been hampered by the underperformance of Level 8 to date in the immediate vicinity of the shaft due to thinner veins which are more faulted than anticipated. We have prioritised development headings to reach more productive areas.

The discovery of the new high grade B2 zone adjacent to the Bananghilig 1 million ounce deposit provides various options for future development. We are continuing to drill at B2 so these options can be evaluated, including possibly treating high grade material at the Co-O Mill, and in this way, be able to increase production while postponing the need to build a new stand-alone milling facility."

1. Co-O Mill

Following the announcement of 21 June 2013 regarding the appointment of administrators to Allmine Group Limited, the parent company of Arccon (WA) Pty Ltd, who were the managers for the Co-O Mill expansion, the Company has appointed new managers CPC Engineering. CPC is an engineering design, construction and maintenance group of companies that has gained industry-wide recognition for providing professional services to the resources and infrastructure sectors over the past 30 years.

CPC are currently starting to mobilise commissioning personnel to site. It is estimated that the commissioning will be delayed by approximately 4 to 5 weeks with completion expected in August 2013.

Medusa can confirm that the situation with Arccon administration has had no other effect on the Co-O Mill as all of the equipment required is already on site and construction is being undertaken by a local Philippine company which is not affected by Arccon's situation.

2. Co-O Mine

(a) L8 Shaft

The L8 Shaft to Level 8 is operating normally and during July when the first ore pass becomes operational, will be hauling in excess of 1,000 tonnes per day. Its capacity is approximately 1,500 tonnes per day.

(b) Level 8

Approximately 350 metres of cross-cut development have been completed and 300 metres of on-vein development have been completed.

The first Alimak ore-pass from Level 6 to Level 8 is newly completed and in July will start supplying ore to the L8 Shaft.

The second Alimak ore pass from Level 6 to Level 8 is underway and will be completed at the end of August.

The ore pass developed by winzing from Level 6 to Level 8 has reached Level 8 and will be connected to the Level 8 development by around the end of July.

Diamond drilling commenced in May on Level 8 to provide additional definition of the veins ahead of development and mining. On-going model review has identified areas for priority development headings.

(c) Level 8 resource model and geological discussion

Recent recognition of different rock types (rheological effects) possibly influencing the intensity and width of the vein mineralisation are thought to be a factor in the poor model correlation in the immediate L8 Shaft area, in addition to a higher than normal amount of faulting. Many of the faults are parallel to the drill direction hence cannot be recognised from drilling alone. Work is underway to better understand these effects and to upgrade the modelling of the possibly more favourable rock units.

(d) Baguio Shaft

The timbering of the Baguio Shaft extension from Level 3 to Level 5 will be completed in August. In the meantime haulage from Level 3 is continuing. The updated resource model is expected to be finalised in August.

3. Production

Production for Level 8 has so far underperformed due to narrower vein width and grade than that predicted by the resource model.

As frequently highlighted by the Company, drilling of narrow epithermal veins generally provides an indication of the presence of the gold mineralised vein but may not always provide good quantitative data with respect to accurate grade and volume estimations. Veins commonly pinch and swell and may be brecciated or displaced by faults.

The Company regards the initial drilling as indicative only and operates the policy of using drilling to locate the position and extent of the mineralised veins. This is then followed by on-vein development to support the drilling results, and to provide a more accurate estimate of vein grades which results in the upgrading of the resource category from Inferred to Indicated. The development supports the estimation of resources and facilitates the conversion of resources to reserves.

The veins on the Level 8 in the vicinity of the shaft, 100 metres below the current mining levels, were expected to be 1.4 metres to 5.5 metres wide according to the resource model, but on three veins developed to date in the immediate vicinity of the shaft, the widths have been less than 1 metre in conjunction with extensive faulting, thus reducing the Level 8 budgeted production during this June quarter. Priority headings are focusing on reaching more productive zones as soon as possible.

The poor performance of Level 8 in the immediate shaft area compared to the resource model to date has affected the production for the June quarter. The anticipated production for the June quarter will be around 15,600 ounces of gold and for FY2013, 62,200 ounces of gold.

Due to this underperformance of Level 8 and the delay in the new mill commissioning, the revised production forecast for FY2014 September quarter is approximately 17,000 ounces and for FY2014 December quarter is approximately 35,000 ounces. Full FY2014 forecast production will be estimated once the mill is fully commissioned and further development has been completed on Level 8.

4. Funding

With the current subdued gold price and the delay to the commissioning of the new Co-O Mill caused by the situation with Arccon, Medusa has been reviewing the efficiency of its operations and also its costs. As a result of this review, the Company has deemed it prudent to arrange funding facilities with two Philippine banks. The overdraft facilities available to the Group total Php600 million (approximately US$14 million) and to date the Company has drawn down Php120 million (approximately US$3 million).

A new contract payment system that has been introduced for the underground operations is being evaluated with the aim of improving the efficiency and costs of underground development and stoping.

In addition, the exploration drilling that has been a major part of Medusa's resource growth has been reduced to two surface and two underground drill rigs, reducing the exploration expenditure from approximately US$25 million in FY2013 to approximately US$12 million in FY2014. The Company has also re-organised its on-site operations departments to improve operational efficiencies.

5. Bananghilig Project

The feasibility study initiated under Arccon's management is being reviewed, particularly as a consequence of the discovery of significant high grade mineralisation east of the current Bananghilig resource of 1,080,000 ounces of gold (see announcement of 29 January 2013).

Drilling has re-commenced in the high grade area (see announcement 2 April 2013), known as B2, approximately 160 meters further northwest of TDH 284 (31.60 metres at 7.33 g/t gold, 13.05 metres at 2.24 g/t gold, 43.70 metres at 2.48 g/t gold, 13.30 metres at 2.30 g/t gold), with hole TDH 303 intersecting additional high grade mineralisation as shown in Table 1 and on Figure 1. At this stage the high grade zone is interpreted to be approximately 300 metres wide.

The Company will evaluate the high grade area and the options it provides to the project economics and alternatives over the next several months as drilling to an Inferred Resource status is progressed by the two surface rigs. One possible option includes separate mining of B2 and treatment at the Co-O Mill at a much lower Capex than a new large stand-alone operation at Bananghilig. If this initiative is successful and gold prices remain subdued, it would mean a saving of approximately $220 million in Capex over the next 3 years for the planned new stand-alone mill.

Table 1. Bananghilig B2 drill results ≥ 1g/t gold.


Hole
Number
 
East
 
North
  Depth
(metres)
  Dip
(degrees)
  Azimuth
(degrees)
  From
(metres)
  Width
(metres)
  Gold
 Grade

(un-
cut)

(g/t
 Au)
TDH303   613,502   945,188   321.60   60   130   155.10   21.15   0.94
                        190.85   7.45   1.51
                        207.30   13.90   5.15
                        229.90   10.70   19.28
                        309.00   2.10   3.28

Notes:                        

  1.  Composited intercepts' 'weighted average grades' calculated by using the following parameters  
    (i)   no upper gold grade cut-off applied, and
    (ii)   lower cut-off grade of 0.5 g/t gold, and
    (iii)   ≥ 5 metres down hole intercept width at ≥ 0.5 g/t gold, or
    (iv)   ≤ 5 metres down hole intercept width at ≥ 5 gram per metres, and
    (v)   maximum of 3 metres of down hole internal dilution at ≤0.5 g/t gold.
  2. Intersection widths are downhole drill widths not true widths;  
  3. Assays are by Intertek McPhar Mineral Services Inc. in Manila;  
  4. Grid coordinates based on the Philippine Reference System 92.  

To view Figure 1. Bananghilig geology map showing the B2 drill hole locations, please visit the following link: http://media3.marketwire.com/docs/885142_Fig_1.pdf.

JORC COMPLIANCE - CONSENT OF COMPETENT PERSONS

Medusa Mining Limited

Information in this report relating to Exploration Results has been reviewed and is based on information compiled by Mr Geoff Davis, who is a member of The Australian Institute of Geoscientists. Mr Davis is the Non-Executive Chairman of Medusa Mining Limited and has sufficient experience which is relevant to the style of mineralisation and type of deposits under consideration and to the activity which he is undertaking to qualify as a "Competent Person" as defined in the 2004 Edition of the "Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves". Mr Davis consents to the inclusion in the report of the matters based on his information in the form and context in which it appears.

Cube Consulting Pty Ltd

Information in this report relating to Mineral Resources has been estimated and compiled by Mark Zammit of Cube Consulting Pty Ltd of Perth, Western Australia. Mr Zammit is a member of The Australasian Institute of Mining & Metallurgy and has sufficient experience that is relevant to the style of mineralisation and type of deposit under consideration and to the activity which he is undertaking to qualify as a Competent Person as defined in the 2004 Edition of the "Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves". Mr Zammit consents to the inclusion in the report of the matters based on his information in the form and context in which it appears.

DISCLAIMER

This announcement may contain certain forward-looking statements. The words 'anticipate', 'believe', 'expect', 'project', 'forecast', 'estimate', 'likely', 'intend', 'should', 'could', 'may', 'target', 'plan' and other similar expressions are intended to identify forward-looking statements. Indications of, and guidance on, future earnings and financial position and performance are also forward-looking statements.

Such forward-looking statements are not guarantees of future performance and involve known and unknown risks, uncertainties and other factors, many of which are beyond the control of Medusa, and its officers, employees, agents and associates, that may cause actual results to differ materially from those expressed or implied in such statements.

Actual results, performance or outcomes may differ materially from any projections and forward-looking statements and the assumptions on which those assumptions are based.

You should not place undue reliance on forward-looking statements and neither Medusa nor any of its directors, employees, servants or agents assume any obligation to update such information.

ABN: 60 099 377 849



Australia
Medusa Mining Limited
Peter Hepburn-Brown, Managing Director
+61 8 9367 0601
+61 8 9367 0602 (FAX)
admin@medusamining.com.au
www.medusamining.com.au
or
United Kingdom
SP Angel Corporate Finance LLP (Financial Adviser & Broker)
Ewan Leggat/Laura Littley
+44 (0)20 3463 2260
Data and Statistics for these countries : Australia | United Kingdom | All
Gold and Silver Prices for these countries : Australia | United Kingdom | All

Medusa Mining Ltd

EXPLORATION STAGE
CODE : MML.AX
ISIN : AU000000MML0
Follow and Invest
Add to watch list Add to your portfolio Add or edit a note
Add Alert Add to Watchlists Add to Portfolio Add Note
ProfileMarket
Indicators
VALUE :
Projects & res.
Press
releases
Annual
report
RISK :
Asset profile
Contact Cpy

Medusa Mining is a gold and copper producing company based in Australia.

Medusa Mining holds various exploration projects in Philippines.

Its main exploration properties are CO-O, CORPLEX, ABACUS, ANOLING and APICAL in Philippines.

Medusa Mining is listed in Australia, in Canada, in Germany and in United Kingdom. Its market capitalisation is AU$ 125.7 millions as of today (US$ 90.7 millions, € 89.2 millions).

Its stock quote reached its highest recent level on June 03, 2011 at AU$ 8.60, and its lowest recent point on June 27, 2017 at AU$ 0.27.

Medusa Mining has 207 790 000 shares outstanding.

Your feedback is appreciated, please leave a comment or rate this article.
Rate : Average note :0 (0 vote) View Top rated
 
Corporate Presentations of Medusa Mining Ltd
9/5/2016Investor Presentation September 2016
2/14/2011Investor Presentation February 2011
8/18/2008Aegis report
6/16/2008 BGF Equities Research Report
3/12/2008Fairfax ResearchContent-class: urn:content-classes:message
7/31/2007 Quarterly Activity Report
3/11/2007Investor Presentation
In the News and Medias of Medusa Mining Ltd
6/17/2008Building a low cost production base with blue sky potential
3/13/2007Broker Report
Annual reports of Medusa Mining Ltd
: 2013 Annual Report
: 2011 Annual Report
Annual Report and Notice of Meeting
2006 Annual Report
Nominations of Medusa Mining Ltd
5/31/2013: Retirement and Appointment of CFO
1/25/2013: New Board Appointments
6/9/2011Board Restructure Following TSX Delisting to Oversee the Nex...
7/9/2010Appointment of Non-Executive Chairman
2/15/2010Appointment of director
9/15/2009Appointment of Director
Financials of Medusa Mining Ltd
2/21/2012: Interim Financial Results
4/27/2011March 2011Quarterly Report
2/22/2011MEDUSA ACHIEVES RECORD HALF-YEAR PROFIT
9/7/2009Records strong 2009 financial results
Project news of Medusa Mining Ltd
4/8/2013(Co-o): Co-O Mill & Mine Expansion Update
2/21/2013(Co-o): Co-O Drilling Update
10/18/2012(Co-o): Co-O Mine Shafts Update
8/15/2012(Co-o): Co-O Mine Geology and Mineralisation Update
7/10/2012(Co-o): Co-O Drilling Update
7/10/2012(Co-o)Limited: Co-O Drilling Update
4/16/2012(Co-o): Co-O Drilling Update
3/21/2012(Co-o): Co-O Operations-Unscheduled Mill Maintenance
4/5/2011(Co-o)Co-O DRILLING CONTINUES HIGH GRADE RESULTS
12/1/2010(Saugon) - Saugon Drilling Expands High-Grade Gold-Silver Potential
6/30/2010(Co-o)Co-O Mine Update
3/29/2010(Co-o)Co-O Mine drilling update
3/16/2010(Co-o)Co-O expanded mill commissionning
7/17/2009(Co-o)Co-O mine reserve now 500 000 ounces
1/19/2009(Co-o) Co-O MINE RESOURCES INCREASED 40% TO 1.2 MILLION OUNCES
12/1/2008MAJOR NEW HIGH GRADE VEIN DISCOVERY
8/12/2008(Co-o)Co-O MINE RESOURCE EXPANSION
5/7/2008(Co-o)WIDE-HIGH GRADE INTERSECTION AT Co-O MINE
3/26/2008(Co-o)Co-O MPSA GRANTED
1/21/2008(Co-o)NEW CATTO VEIN EXTENSIONS DISCOVERED
10/1/2007(Co-o)Co-O Mine Expansion
9/4/2007713,000 resource ounces and growing
8/15/2007CO-O MINE RESOURCE DRILL HOLE RESULTS
7/9/2007New Discoveries
6/20/2007(Anoling)POSITIVE RESULTS FROM ANOLING GOLD PROJECT
5/16/2007(Co-o)Co-O Mine Update
3/19/2007(Anoling)Anoling Gold Project tenements granted
5/23/2006Tambis project exploration, Philippines
Corporate news of Medusa Mining Ltd
6/20/2016Relocation of Office Premises
5/9/2016Investor Presentation May 2016
5/6/2016Market Briefing May 2016 – Medusa Mining Ltd
5/2/2016Cancellation of Unquoted Securities (Options)
4/5/2016Terms of Appointment of CEO
3/21/2016CEO Appointment
1/22/2016CEO Appointment Update
1/20/2016Exploration Pipeline and Tenement Review
1/18/2016L8 Shaft Upgrade
1/18/2016Mineral Resources and Reserves Statement Addendum to 2014 An...
1/18/2016Cancellation of Unquoted Securities
10/9/2015Notice of Annual General Meeting and Proxy Form
10/5/2015Investor Presentation October 2015
9/25/2015Annual Mineral Resources & Ore Reserve Update Statement
9/4/2015Annual Mineral Resources Update Statement
9/3/2015Asset Impairment of US260M
8/27/2015ASX Appendix 4E and Financial Results for ended year June 30...
8/27/2015Full Year Results 2015
7/28/2015Investor Presentation July 2015
7/27/2015Quarterly Report June 2015
7/7/2015Co-O Mine Service Shaft Update
4/13/2015Investor Presentation April 2015 – Zurich and London
4/9/2015Co-O Mine Geology & Service Shaft Updates
1/21/2015Exploration Pipeline and Tenement Review
1/16/2015L8 Shaft Upgrade
1/12/2015Cancellation of Unquoted Securities
1/12/2015Mineral Resources and Reserves Statement Addendum to 2014 An...
12/9/2014Appendix 3Z – Directors Final Notice (Gary Raymond Powell)
11/21/2014Results of Annual General Meeting November 2014
11/20/2014Executive Appointments
2/13/2014Fatality Underground
2/13/2014Medusa Mining Limited: Fatality Underground
1/31/2014Medusa Mining Limited Quarterly Activities Report: Period En...
1/28/2014Operations Update
1/28/2014Medusa Mining Limited: Operations Update
1/21/2014Operations Update
10/29/2013: Quarterly Activities Report Period Ended 30 September 2013
10/23/2013: SAG Mill Update
9/4/2013: Operations Update-New Mill and Level 8
7/31/2013: Quarterly Activities Report Period Ended 30 June 2013
7/8/2013(Co-o): Co-O Operations Update
5/2/2013: Quarterly Activities Report Period Ended 31 March 2013
4/15/2013: Investor Presentation April 2013
10/30/2012: Quarterly Activities Report Period Ended 30 September 2012
8/29/2012: Full Year Results
8/6/2012(Co-o): Co-O Mine Mineral Resource Update
7/31/2012: Quarterly Activities Report Period Ended 30 June 2012
4/30/2012: Investor Presentation May 2012
4/24/2012: Quarterly Activities Report Period Ended 31 March 2012
2/10/2012: Investor Presentation February 2012
1/30/2012December 2011 Quarterly Report
1/17/2012: Bananghilig Deposit Drilling Update
12/16/2011: Appendix 3B
12/5/2011: Issue of Performance Rights
10/24/2011: Investor Presentation
8/29/2011Achieves Record Full Year Profit
8/24/2011ASX Announcement
8/22/2011(Co-o): Co-O Mine Mineral Reserve Estimate
7/28/2011ASX Announcement - Quarterly Report
1/25/2011- Medusa Quarterly Report
5/24/2010AIM cancellation & admission to the official list
5/7/2010Copper portfolio - Lingig update
3/8/2010Bonus issue of shares
1/25/2010Notice of no corporate associations
10/9/2009Lingig drilling extends mineralisation
8/12/2009ASX Announcement
7/3/2009MML - ASX Ann - S&P/ASX 200 Index
6/22/2009ASX Announcement
6/1/2009MML - ASX Announcement
2/26/2009UNDERWRITTEN A$24.5 MILLION PLACEMENT
1/28/2009Quarterly Report
11/5/2008ASX Announcement
9/23/2008ASX Announcement
9/19/2008Crosby Makes $182 Million Takeover Bid for Medusa Mining
8/20/2008ASX Announcement
7/25/2008ASX Announcement
6/10/2008ASX Announcement
4/11/2008Joint Venture With Bunawan Mining Corporation
3/14/2008Half Year Financial Report – 31 December 2007
2/25/2008IRON ORE TARGETS IDENTIFIED
11/13/2007LINGIG PORPHYRY COPPER DISCOVERY
10/31/2007 QUARTERLY ACTIVITIES REPORT PERIOD ENDING 30 SEPTEMBER 2007
8/16/2007Ambrian Morning Research
8/1/2007Heads of Agreement and Placement with Sierra Mining Ltd
7/16/2007Barobo Mineralised Corridor
6/13/2007 Acquisition of Co-O Mine Royalty
5/25/2007Equity Research
5/15/2007ASX Announcement
4/30/2007Quarterly Report March 2007
3/21/2007Releases
3/8/2007 Dismissal of motion for reconsideration on CO-o mise
6/13/2006appointement of nominated advisor & broker - AIM London
5/17/2006Acquisition of Apical gold project, Philippines
4/10/2006Alternative Investment Market (AIM) London
3/16/2006half year financial report 31 december 2005
1/30/2006Gold Production started, increasing quickly from here
1/21/2006ANALYSIS : MEDUSA MINING
Comments closed
 
Latest comment posted for this article
Be the first to comment
Add your comment
AUSTRALIA (MML.AX)TORONTO (MLL.TO)
0.605-15.38%7.43-0.80%
AUSTRALIA
AU$ 0.605
07/08 11:00 -0.110
-15.38%
Prev close Open
0.715 0.615
Low High
0.600 0.625
Year l/h YTD var.
 -  -
52 week l/h 52 week var.
- -  0.605 -%
Volume 1 month var.
123,619 -%
24hGold TrendPower© : -44
Produces
Develops
Explores for Gold
 
 
 
Analyse
Interactive chart Add to compare
Interactive
chart
Print Compare Export
Last updated on : 3/2/2010
You must be logged in to use the porfolio and watchlists (free)
Top Newsreleases
MOST READ
Annual variation
DateVariationHighLow
2022-14.79%0.950.60
2021-7.79%0.990.66
20200.00%1.070.40
 
5 years chart
 
3 months chart
 
3 months volume chart
 
 
Mining Company News
Plymouth Minerals LTDPLH.AX
Plymouth Minerals Intersects Further High Grade Potash in Drilling at Banio Potash Project - Plannin
AU$ 0.12-8.00%Trend Power :
Santos(Ngas-Oil)STO.AX
announces expected non-cash impairment
AU$ 7.75+0.52%Trend Power :
Oceana Gold(Au)OGC.AX
RELEASES NEW TECHNICAL REPORT FOR THE HAILE GOLD MINE
AU$ 2.20+0.00%Trend Power :
Western Areas NL(Au-Ni-Pl)WSA.AX
Advance Notice - Full Year Results Conference Call
AU$ 3.86+0.00%Trend Power :
Canadian Zinc(Ag-Au-Cu)CZN.TO
Reports Financial Results for Q2 and Provides Project Updates
CA$ 0.12+4.55%Trend Power :
Stornoway Diamond(Gems-Au-Ur)SWY.TO
Second Quarter Results
CA$ 0.02+100.00%Trend Power :
McEwen Mining(Cu-Le-Zn)MUX
TO ACQUIRE BLACK FOX FROM PRIMERO=C2=A0
US$ 10.92-1.71%Trend Power :
Rentech(Coal-Ngas)RTK
Rentech Announces Results for Second Quarter 2017
US$ 0.20-12.28%Trend Power :
KEFIKEFI.L
Reduced Funding Requirement
GBX 0.55+0.00%Trend Power :
Lupaka Gold Corp.LPK.V
Lupaka Gold Receives First Tranche Under Amended Invicta Financing Agreement
CA$ 0.06-8.33%Trend Power :
Imperial(Ag-Au-Cu)III.TO
Closes Bridge Loan Financing
CA$ 2.38-3.64%Trend Power :
Guyana Goldfields(Cu-Zn-Pa)GUY.TO
Reports Second Quarter 2017 Results and Maintains Production Guidance
CA$ 1.84+0.00%Trend Power :
Lundin Mining(Ag-Au-Cu)LUN.TO
d Share Capital and Voting Rights for Lundin Mining
CA$ 15.32+0.46%Trend Power :
Canarc Res.(Au)CCM.TO
Canarc Reports High Grade Gold in Surface Rock Samples at Fondaway Canyon, Nevada
CA$ 0.24-2.08%Trend Power :
Havilah(Cu-Le-Zn)HAV.AX
Q A April 2017 Quarterly Report
AU$ 0.19+0.00%Trend Power :
Uranium Res.(Ur)URRE
Commences Lithium Exploration Drilling at the Columbus Basin Project
US$ 6.80-2.86%Trend Power :
Platinum Group Metals(Au-Cu-Gems)PTM.TO
Platinum Group Metals Ltd. Operational and Strategic Process ...
CA$ 1.77-1.12%Trend Power :
Devon Energy(Ngas-Oil)DVN
Announces $340 Million of Non-Core Asset Sales
US$ 52.10-0.89%Trend Power :
Precision Drilling(Oil)PD-UN.TO
Announces 2017Second Quarter Financial Results
CA$ 8.66-0.35%Trend Power :
Terramin(Ag-Au-Cu)TZN.AX
2nd Quarter Report
AU$ 0.04+0.00%Trend Power :