Medusa Mining Limited: Quarterly Activities Report Period Ended 30 June 2012
Published : July 31, 2012
( 0 vote, 0/5 ) Print article
  Article Comments Comment this article Rating Follow Company  
0
Send
0
comment

TORONTO, ONTARIO--(Marketwire - July 31, 2012) - Medusa Mining Limited (News - Market indicators)(LSE:MML) -

Snapshot of Medusa:

  • Un-hedged, low cost, dividend paying gold producer focused on organic growth in the Philippines

  • Growth path to annualised production of 400,000 ozs per year by end 2015

  • Growth underpinned by strong cashflow from Co-O Mine (narrow vein underground)

    • FY 2012/13: production guidance of 100-120,000 ozs at cash costs circa US$210/oz

  • Current Mineral Resources comprise

    • Co-O Mine: Indicated 616k ozs at 12.0 g/t gold; Inferred  1,344k ozs at 8.8 g/t gold

    • Bananghilig: Inferred 650k ozs at 1.3 g/t gold

  • Current Probable Reserves : Co-O Mine 502k ozs @ 10.1 g/t gold

  • Co-O Mine Resources and Reserves to be maintained at current levels

  • Conceptual exploration target size ** of Co-O Mine of 3 to 7 million ozs

  • Excellent exploration upside: high grade vein and disseminated bulk gold targets, plus eight copper targets

  • 820 km2 of tenements and exploration revised budget for FY 2013/14 of US$30M

Board of Directors:

Geoffrey Davis (Non-executive Chairman)
Peter Hepburn-Brown (Managing Director)
Ciceron Angeles (Non-executive Director)
Robert Weinberg (Non-executive Director)
Andrew Teo (Non-executive Director)

Capital Structure:

Ordinary shares: 188,903,911  
Unlisted options: 1,715,000
Performance rights: 250,000
 
Listings: 
ASX and LSE (Code: MML)
 
Address and Contact Details:
PO Box 860
Canning Bridge  WA  6153   
Telephone: +618 9367 0601
Facsimile: +618 9367 0602
 
Email: admin@medusamining.com.au
Website: www.medusamining.com.au

OVERVIEW:

EXECUTIVE ORDER ON MINING IN THE PHILIPPINES

  • Positive Executive Order No.79 on mining in the Philippines was released on 9 July 2012.

Co-O MINE PRODUCTION & DEVELOPMENT

  • New Mill: Construction on schedule. Tilted tanks back in operation. New leach tank will be completed by mid-August. Foundations for detoxification unit completed and for crusher and SAG mill advancing. SAG mill 50% delivered. ECC approval is progressing.

  • Production: 15,557 ounces at a recovered grade of 8.1 g/t gold and cash costs of US$283 per ounce. Production for the FY to 30 June 2012 totalled 60,595 ounces at a recovered grade of 8.1 g/t gold and cash costs of US$261 per ounce. Mill availability was influenced by on-going leach tank repairs.

  • Saga Shaft: currently at 306 metres. Completion of sink to Level 8 (350 metres) by end of August. Winder in transit to site. Skips and loading pockets manufactured. Completion estimated Q4 in CY12.

Co-O MINE RESOURCES & EXPLORATION

  • The resource for Co-O is currently being compiled.

  • Drilling is continuing with six surface and five underground rigs.

  • Results include: 2.15 metres at 52.06 g/t gold, 1.20 metres at 21.40 g/t gold, 1.35 metres at 185.21 g/t gold, 2.90 metres at 78.94 g/t gold, 1.55 metres at 31.33 g/t gold, 1.20 metres at 45.03 g/t gold.

TAMBIS AREA - BANANGHILIG DEPOSIT

  • Infill resource drilling in progress with seven rigs with the aim of upgrading majority of resources to Indicated category. Infill drilling should be completed about the end of August 2012

  • An updated Inferred resource is planned during the September quarter followed by an Indicated resource and reserve when the infill drilling and assaying is completed.

LINGIG PROJECT

  • Lingig Induced Polarisation and Resistivity survey in progress.

ANOLING

  • Drilling with four rigs is continuing.

CORPORATE & FINANCIALS (unaudited)

  • Total cash, cash equivalent in gold on metal account and bullion at site at end of quarter of approximately US$53.5 million.
** The potential target size and grade is conceptual in nature, and there has been insufficient exploration to define a mineral resource, and it is uncertain if further exploration will result in the target being defined as a mineral resource. Refer to Stock Exchange announcement dated 24 August 2011.

PROJECT OVERVIEW

The locations of the Company's projects are shown on Figures 1 and 2.

To view Figure 1. Location diagram showing the Company's tenement areas and prominent East-West structures, please visit the following link: http://media3.marketwire.com/docs/808008A.jpg

To view Figure 2. Regional tenement map showing mines and prospects, please visit the following link: http://file.marketwire.com/release/808008B.jpg

EXECUTIVE ORDER ON MINING IN THE PHILIPPINES

The President of the Philippines on 9 July 2012 released Executive Order No.79 ("EO") designed to improve the alignment of the Philippines' national and regional interests with those of the mining industry through the updating of key policies, including but not limited to:

  • Improving transparency of the mining industry;

  • Improving the fiscal return to the government from all future projects, primarily through increased royalty payments. The fiscal settings of current operations will be honoured.

  • Improving the return and timing of financial benefits to local governments;

  • Tightening controls on illegal mining such as banning the use of mercury and restricting legitimate small scale mining activities to gold, silver and chromite;

  • Ensuring that mining is not allowed on designated key tourist areas and prime agriculture lands; and

  • Enforcement of strict environmental controls.

The EO requires the issuing of new implementing rules and regulations within 60 days of the EO publication after which the granting of exploration tenements will re-commence. The granting of construction permits for new projects will commence only after the new fiscal regime has been legislated. The fiscal settings of all existing contracts will be honoured.

Implications of the EO

Co-O

The EO will have no effect on the Co-O operations and the status quo will be maintained for this existing operation as it is linked to an existing mining agreement.

There will be no change in the existing tax structure until such time as Congress amends and approves new mining taxes and royalties within the existing Mining Act.

Bananghilig

The EO will have no immediate impact on the project as the Company can continue to explore, conduct feasibility studies and planning.

However, should the feasibility study be positive and the Company commits to constructing the project, timely issuance of the relevant permits to commence construction will be subject to legislation of the new law on mining taxes and royalties being passed by Congress.

Updates will be provided as information becomes available.

Anoling

The EO will not have any immediate effect on the Anoling project which requires the granting of its MPSA followed by completion of a feasibility study before an application can be submitted for construction permits.

The timing of the granting of the MPSA is still unclear and updates will be provided as information becomes available following the issue of new implementing rules within 60 days of the EO with respect to granting of new tenements.

In the meantime, drilling can continue to advance the project, however the Company is considering its drilling priorities. 

Co-O MINE

Gold Production

The production statistics for the March 2012 quarter with comparatives for the previous three quarters as well as the year-to-date production statistics are summarised in Table I below.

Table I. Gold production statistics
  Unit Qtr ended
30 Jun 12
Qtr ended
31 Mar 12
Qtr ended
31 Dec 11
Qtr ended
30 Sep 11
YTD
30 Jun 12
Tonnes mined WMT 74,969 85,748 71,872 41,596 274,185
Ore milled DMT 66,976 76,002 68,008 42,152 253,138
Recovered grade gpt 8.10 8.10 8.00 8.33 8.10
Recovery % 92% 92% 93% 93% 92%
Gold produced ozs 15,557 18,258 16,270 10,510 60,595
Cash costs (1) US$/oz $283 $239 $242 $291 $261
Gold sold ozs 20,000 10,000 10,000 15,446 55,446
Average gold price received US$ $1,624 $1,738 $1,761 $1,587 $1,658
 
Note:  
 
(1) Net of development costs and includes royalties and local business taxes

Gold production for the quarter was 15,557 ounces, at an average recovered grade of 8.10 g/t gold and cash costs of US$283 per ounce, inclusive of royalties and local business taxes.

As previously advised to the market, the mine continues to operate pre-dominantly in development mode to prepare for the future production increase and as a direct consequence of limited shaft haulage capacity, all development ore mined to date has been treated through the mill. The increased amount of development ore treated is the primary reason for the lower production levels for the year, compared to quarters from the previous years. The completion of the Saga Shaft (in the December 2012 quarter) with haulage capacity of 1,500 tpd is expected to solve the current shaft haulage issues.

Production for the June quarter was also disrupted due to reduced availability of the milling circuit, as repairs were carried out on four tilting leach tanks as reported on 20 March 2012. 

Cash costs per ounce for the quarter increased to US$283 per ounce (YTD: US$261 per ounce).

Medusa, an un-hedged gold producer, sold 20,000 ounces of gold at an average price of US$1,624 per ounce during the quarter (YTD: 55,446 ounces at average price of US$1,658 per ounce).

Preliminary Development Timetable

Graph 1 is the Preliminary Development Timetable and Production Guidance for the new Co-O Phase 3 Mill Expansion and Bananghilig Project.

The total estimated Capex (inclusive of mine development and shaft sinking) for the Phase 3 expansion of Co-O is US$70 million which will be funded entirely from the Company's cash flow.

New Co-O Mill

In November 2010, the Board approved the construction of a new mill with capacity to produce 200,000 ounces of gold per year based on processing up to 750,000 tonnes per year at the current reserve grade of the Co-O Mine.

The approval of the application to upgrade the Environmental Clearance Certificate for the current Co-O Mill to 2,500 tonnes per day is progressing.

Operations

Mine Development

Major renovations are continuing at the Co-O Mine to modernise the mine for its expanded production.

Acceleration of the lateral development is on-going to ensure the underground infrastructure and on-vein development will be in place for the Saga Shaft. This accelerated development was maintained at similar levels to the previous quarter and consequently maintained the high proportion of development ore supplied to the mill.

Sinking of the Saga Shaft progressed smoothly, and is currently at 306 metres depth and is expected at Level 8 (350 metres) by end of August. The winder is in transit to site, and the skips and loading pockets have been manufactured. Manufacture of the permanent headframe is commencing.

It is anticipated that the Saga Shaft with a haulage capacity of 1,500 tonnes per day will be completed during the December quarter 2012 and hauling from Level 8 will begin once on-vein development and rises on-vein are commenced from Level 8 through to Level 6.

Whilst the milling requirements have been reduced due to the tilting leach tank repairs, the opportunity has been used to upgrade the Baguio Shaft by doubling the skip size and improving the winder capability.

The average development metres has increased by 10% and at the end of June 2012 there were 57 development headings of which 50 headings were following veins. Haulage through the current shafts increased by 10% during the quarter.

Mine Production

Ore trucked to the mill during the quarter was primarily development ore and some stope ore.

Mill Expansion

The current status of activities is:

  • Priority was given to the returning the tilting leach tanks back into service which has been achieved;

  • Construction of the new large leach tank should be completed by mid-August;

  • Foundations for the new crushing and grinding sections are advancing on schedule;

  • The de-toxification unit foundations are completed and form work is on schedule;

  • Approximately 50% of the SAG mill components have been delivered;

  • The electrical supply systems to the mine and mill are advanced and the last stage will be completed when the mine is re-wired through the Saga Shaft.

Exploration

Drilling with six surface rigs and five underground drilling rigs is continuing.

Preparations are underway for an extensive regional Induced Polarisation/Resistivity ("IP/Res") and ground magnetics programme around the Co-O Mine.

Drilling results

Detailed information is contained in the announcement dated 9 July 2012 which lists intersections down to 0.2 metres downhole width since 16 April 2012.

Figure 3 shows the locations of the recently completed or in progress surface drill holes EXP146 to EXP175. Completed holes (excluding EXP169, 170, and 172-175) comprise 25 holes for a total of approximately 16,316 metres. Table II lists the EXP surface Diamond drill hole results ≥ 3 g/t gold over ≥ 0.5 metres downhole. Assay results are awaited for holes EXP154, EXP161, EXP163 and EXP165 to EXP175.

Figure 4 (attached) shows the locations of the recently completed underground drill holes totalling 7,932 metres in 46 holes. Table III lists underground drill hole results ≥ 3 g/t gold over ≥ 0.2 metres received since 31 March 2012 as well as some previously completed holes whose locations were shown on Figure 2 in the announcement dated 16 April 2012. Assays are awaited for holes L2-2E-001, L5-35W-109, L5-43E-012, L5-20W-008 and L6-23E-034.

Table II. Surface drill hole results ≥ 3 g/t gold and ≥ 0.5 metres downhole for previously completed holes EXP138 to EXP145 and new holes EXP146 to EXP164. 

Hole
number
East North Dip
(Degrees)
Azimuth
(Degrees)
From
(metres)
Width
(metres)
Grade
(uncut)
(g/t gold)
EXP 140 614659 913216 -54 180 309.20 1.00 3.07*
          484.35 1.20 15.73*
          488.05 1.00 6.08*
          499.90 1.45 6.91*
          604.60 0.50 27.93*
          609.45 1.45 7.76*
          640.15 1.35 5.94*
EXP 141 614550 912992 -69 180 344.20 1.00 4.30*
          568.85 0.55 4.77*
          746.00 1.00 3.75*
EXP 142 614604 913032 -55 180 593.75 1.00 4.22*
          637.65 3.00 3.79*
EXP 144 614519 913082 -51 180 219.00 1.00 3.87*
          459.00 1.00 8.93*
          496.85 1.00 21.70*
          532.70 0.90 7.19*
          634.45 1.00 8.47*
EXP 145 614442 912987 -69 180 397.30 2.15 52.06*
          620.00 2.25 3.25*
EXP 146 614550 913122 -66 180 370.80 1.60 3.27*
          432.90 1.20 21.40*
          527.50 0.75 60.46*
          620.50 1.00 3.53*
          735.05 1.35 16.66*
EXP 147 614394 913026 -67 180 520.60 1.00 9.70*
EXP 149 61439 913101 -64 180 141.20 1.40 3.41*
          362.55 1.45 6.12*
          528.25 0.50 8.43*
          682.05 2.00 3.15*
          742.25 2.10 3.32*
EXP 150 614129 913260 -51 180 154.45 0.55 3.28*
          517.10* 1.00 4.73*
EXP 151 614442 912987 -57 180 349.60 2.70 5.67*
          384.40 1.20 3.82*
          535.30 1.85 5.20*
          602.90 2.75 6.60*
          644.15 0.90 52.33*
EXP 156 614199 913138 -55 180 187.05 0.75 15.33*
          193.10 0.55 7.07*
          303.00 1.00 3.86*
          377.60 1.45 3.33*
          423.85 1.00 3.32*
          483.45 0.90 31.84*
          536.05 1.35 185.21*
EXP 157 614510 913158 -49 180 310.30 1.00 4.19*
          441.45 2.90 78.94*
          543.90 3.00 10.20*
EXP 160 614354 912823 -52 180 226.60 1.50 8.17*
               
Notes:  
 
1. Intersection widths are downhole drill widths not true widths;
2. Assays denoted by * are by Philsaga Mining Corporation's laboratory, all other assays are by Intertek McPhar Mineral Services Inc. in Manila;
3. Intersection widths are downhole drill widths not true widths;
4. Grid coordinates based on the Philippine Reference System 92.

Table III. Underground drill hole results ≥ 3 g/t gold and ≥ 0.5 metres downhole for new holes and previously completed holes designated (t).

Hole
number
East North Dip
(Degrees)
Azimuth
(Degrees)
From
(metres)
Width
(metres)
Grade
(uncut)
(g/t gold)
LEVEL 2 L2-057(t)

 613275


 912928


 0


 61


 20.90


 1.00


 4.41*
LEVEL 3 L3-028(t)
 613733

 912898

 3

 143

 83.45

 0.55
3.13*
LEVEL 5              
L5-087(t)         25.50 0.70 4.80*
          82.75 0.90 16.50*
          85.80 0.50 17.41*
          127.55 0.70 3.32*
L5-091(t) 613615 912851 0 63 47.95 1.05 17.57*
          288.80 0.90 3.47*
L5-092(t) 613951 912921 -60 226 14.20 2.05 18.76*
          97.65 1.05 3.42*
          102.90 1.00 8.73*
          121.30 1.35 4.34*
          240.45 1.70 4.50*
          243.60 0.70 3.59*
L5-096(t) 613613 912853 0 27 0.00 0.80 3.84*
          67.15 0.95 9.37*
L5-105(t) 614196 912960 0 202 2.15 0.65 15.17*
          67.15 0.95 9.37*
L5-20W-003 613760 912853 0 177 5.30 0.55 26.40*
L5-20W-004 613759 912853 0 204 6.45 1.15 24.75*
L5-20W-007 613764 912855 -18 133 5.00 2.30 10.01*
L5-35W-108 613606 912814 0 171 1.10 0.90 5.34*
L5-35W-109 613605 912814 0 189 6.50 0.50 3.62*
L5-35W-110 613604 912814 0 215 61.00 0.60 29.33*
L5-35W-111 613602 912814 0 230 34.50 0.80 10.18*
          60.80 0.60 8.50*
L5-42E-013 614377 912690 -22 305 27.35 0.95 45.18*
          70.05 0.75 13.25*
          74.00 2.10 12.59*
          246.80 1.60 26.85*
          397.20 2.00 6.02*
L5-42E-014 614378 912690 -22 314 137.60 1.60 10.92*
          159.50 2.30 17.44*
          184.70 1.00 4.61*
L5-42E-015 614379 912691 0 321 22.50 0.50 7.50*
          130.85 0.75 3.57*
          156.30 1.60 10.71*
               
LEVEL 6              
L6-027 614213 912727 3 71 77.80 0.50 13.40*
L6-028 614213 912727 3 68 79.40 1.10 25.60*
L6-029 614213 912726 3 139 29.90 1.35 3.81*
L6-23E-030 614212 912724 0 167 5.30 1.20 23.37*
L6-23E-031 614208 912725 0 206 5.65 1.55 31.33*
L6-23E-033 614207 614207 0 225 8.40 1.20 45.03*
          10.70 2.50 23.47*
Notes:  
 
1. Intersection widths are downhole drill widths not true widths;
2. Assays denoted by * are by Philsaga Mining Corporation's laboratory, all other assays are by Intertek McPhar Mineral Services Inc. in Manila;
3. Intersection widths are downhole drill widths not true widths;
4. Grid co-ordinates based on the Philippine Reference System 92.

To view Figure 3. Map of the Co-O Mine Level 6 plan showing the locations of new drill holes EXP146 to EXP175, please visit the following link: http://file.marketwire.com/release/808008C.jpg

To view Figure 4. Map of the Co-O Mine Level 6 plan showing the locations of the new underground drill holes, please visit the following link: http://file.marketwire.com/release/808008D.jpg

Co-O Drill Hole Sampling and Assaying Procedures

Samples are taken from mainly HQ sized (hole outside diameter 96 mm, hole inside diameter 63.5mm) and some NQ sized (hole outside diameter 75.8 mm, hole inside diameter 47.6 mm) drill core. The selected sample intervals are halved by Diamond saw and half the core is bagged, numbered and sent to the Company laboratory. In a small number of cases to confirm the geological logging, the selected interval was re-split and 1/4 core re-submitted for assay.

Initial sample preparation and assaying is undertaken at the Company's on-site laboratory. Samples are dried at 105ºC for 6 to 16 hours, crushed to less than 1.25 cm by jaw crusher, re-crushed to less than 50 mm using a secondary crusher followed by ring grinding of 1kilogram of sample to nominal particle size of less than 200 mesh. Barren rock wash is used after every five samples in the preparation equipment. The samples are assayed by fire assay with Atomic Absorption Spectrometer (AAS) finish on a 30 gram sample. All assays over 5 g/t gold are re-assayed using gravimetric fire assay techniques on a 30 gram sample. Duplicate samples are inserted every 10 samples and standard samples are included in every sample batch.

Check assaying of samples used in the yearly resource estimates is undertaken by Intertek McPhar Mineral Services ("Intertek"), a NATA and ISO 9001/2000 accredited laboratory in Manila. The pulps are airfreighted to Intertek who fire assay 30 grams of samples using AAS finish and a selected number of samples are checked using gravimetric fire assay techniques. Duplicate samples and standards are included in each batch of check samples. When reporting results, where available, the assays of Intertek as an independent laboratory have been given priority over the Company laboratory's results.

Health and Safety

Lost time accident frequency rate (LTAFR) for the year is 1.04 including exploration. By comparison, the latest West Australian gold mining industry figure available to 30 September 2011 was 3.10, excluding exploration statistics of 6.70.

There were no breaches of any of the project's operating regulations during the quarter.

To view Graph 1. Preliminary Development Timetable, please visit the following link: http://media3.marketwire.com/docs/808008E.jpg

Production profile (ounces)      
       
Calendar years      
CY (Jan - Dec) CY 2011
(Actual)
CY 2012
(part actual)
CY 2013 CY 2014 CY 2015 CY 2016
Co-O Mill 77,127 73-78,000 160-175,000 200,000 200,000 200,000
Bananghilig Mill - - - - 100,000 200,000
Total 77,127 73-78,000 160-175,000 200,000 300,000 400,000
         
Financial years        
FY (Jul - Jun) FY 2012
(Actual)
FY 2013 FY 2014 FY 2015 FY 2016 FY 2017
Co-O Mill 60,595 100-120,000 200,000 200,000 200,000 200,000
Bananghilig Mill - - - - 200,000 200,000
Total 60,595 100-120,000 200,000 200,000 400,000 400,000

TAMBIS REGION

The Tambis project comprising the Bananghilig Gold Deposit (Fig. 2) is operated under a Mining Agreement with Philex Gold Philippines Inc. over Mineral Production Sharing Agreement ("MPSA") 344-2010-XIII which covers 6,262 hectares.

The Executive Order on Mining dated 6 July 2012, issued by the President of Philippines will have no immediate impact on the Bananghilig Project as the Company can continue to explore, conduct feasibility studies and planning.

However, should the feasibility study be positive and the Company commits to constructing the project, timely issuance of the relevant permits to commence construction will be subject to legislation of the new law on mining taxes and royalties being passed by Congress.

Updates will be provided as information becomes available.

BANANGHILIG PROJECT

In July 2010, new regional and detailed mapping and drilling programmes were commenced with the aim of validating the current resource of 650,000 ounces of gold and extending it to provide a reserve of approximately 1,000,000 ounces. This reserve would form the basis for a feasibility study which would target production of 200,000 ounces of gold per year from a new milling facility.

The announcement of 12 September 2011 summarises the Tambis regional geological setting, local geological setting, deposit description and mineralisation, shows a typical cross-section through the deposit and the drill hole intersections obtained for the period 24 July 2010 to 31 August 2011. Additional information is contained in the September 2011 quarterly report dated 24 October 2011 and in a drilling update on 17 January 2012.

Current drilling is focused on infill to upgrade the resources to the Indicated category. The infill programme totals approximately 18,200 metres and is on track to be completed around the end of August 2012.

A further update of drilling results and a new Inferred resource estimate are planned for the September quarter 2012.

USA PORPHYRY COPPER-GOLD PROSPECT

A Memorandum of Agreement with Corplex Resources Inc. covers the Usa prospect which is located within MPSA application XIII-00077. Processing of the tenement application is progressing.

LINGIG

The Lingig prospect is located in Mineral Production Sharing Agreement 343-2010-XIII with an area of 3,824 hectares over which the Company has an operating agreement.

The IP/Res and ground magnetics survey is underway.

ANOLING

The Mines Operating Agreement with Alcorn Gold Resources Inc. covers MPSA application 039-XIII situated approximately 8 kilometres by road to the north of the millsite as shown on Figure 2.

The Executive Order on Mining dated 6 July 2012, issued by the President of Philippines will not have any immediate effect on the Anoling Project which requires the granting of its MPSA followed by completion of a feasibility study before an application can be submitted for construction permits.

The timing of the granting of the MPSA is still unclear and updates will be provided as information becomes available following the issue of new implementing rules within 60 days of the EO with respect to granting of new tenements.

Four drill rigs are currently operating with on-going mapping, trenching and sampling, however the Company is assessing its drilling priorities.

SAUGON PROJECT

First Hit Vein 

Background

Figure 2 shows the Saugon Project located approximately 28 kilometres by road from the Co-O Mill. Work in 2004 involved drilling at the First Hit Vein (holes SDDH-001 to SDDH-035) in conjunction with underground development via a 30 metre deep inclined winze down the vein-breccia to assist in understanding the mineralisation.

Further details are contained in the announcements dated 20 April 2010 which summarised the historical results and 1 December 2010 which contained drilling results for holes SDDH-36 to SDDH-64A and the March 2012 quarterly report contained results for holes SDDH 65-104.

Exploration

Regional mapping, trenching and sampling are continuing.

FINANCIALS (unaudited)

As at 30 June 2012, the Company which is debt free, had total cash, cash equivalent in gold on metal account and bullion at site of approximately US$53.5 million (31 Mar 2012: US$71.3 million).

During the June 2012 quarter,

  • the Company sold 20,000 ounces of gold at an average price of US$1,624 per ounce (Mar 2012 qtr: sold 10,000 ounces at an average price of US$1,738 per ounce). Year to date gold sales totalled US$91.98 million from the sale of 55,446 ounces at an average price of US$1,659 per ounce;

  • incurred exploration expenditure of US$11.6 million (Mar 2012 qtr: US$8.2 million, YTD: US$35.1 million);

  • spent US$10.4 million on capital works, associated sustaining capital at the mine and mill and also costs for the new mill construction and infrastructure (Mar 2012 qtr: US$7.6 million, YTD: US$27.0 million); and

  • spent US$7.4 million on general and accelerated mine development, inclusive of shaft sinking costs (Mar 2012 qtr: US$9.0, YTD: US$31.0 million).

Peter Hepburn-Brown, Managing Director of Medusa, commented:

"We have made pleasing progress with the mill construction during the quarter particularly with returning the tilting leach tanks back into service, approaching completion for the new leach tank, and establishing the foundation work for the crusher, SAG mill and detoxification unit. It is also comforting that the SAG mill components have started to arrive at site on schedule.

At the mine, the pace of ancilliary activities is picking up in preparation for the Saga Shaft reaching target depth at the end of August. This includes the imminent arrival of the winder, completed manufacturing of the new skips and loading pockets, commencement of manufacturing of the permanent headframe, and finishing the installation of the surface electricals to accommodate the new winder and then complete the re-wiring of the Co-O Mine.

The commencement of haulage from the Saga Shaft in the December quarter will mark a major achievement in the Co-O expansion programme. This means that this FY's production guidance of 100-120,000 ounces will be weighted into the second half of the year."

Information in this report relating to Exploration Results has been reviewed and is based on information compiled by Mr Geoff Davis, who is a member of The Australian Institute of Geoscientists. Mr Davis is the Chairman of Medusa Mining Limited and has sufficient experience which is relevant to the style of mineralisation and type of deposits under consideration and to the activity which he is undertaking to qualify as a "Competent Person" as defined in the 2004 Edition of the "Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves" and is a "Qualified Person" as defined in "National Instrument 43-101" of the Canadian Securities Administrators. Mr Davis consents to the inclusion in the report of the matters based on his information in the form and context in which it appears.

Information in this report relating to Mineral Resources has been estimated and compiled by Mark Zammit of Cube Consulting Pty Ltd of Perth, Western Australia. Mr Zammit is a member of The Australasian Institute of Mining & Metallurgy and has sufficient experience that is relevant to the style of mineralisation and type of deposit under consideration and to the activity which he is undertaking to qualify as a Competent Person as defined in the 2004 Edition of the "Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves" and is a "Qualified Person" as defined in "National Instrument 43-101" of the Canadian Securities Administrators. Mr Zammit consents to the inclusion in the report of the matters based on his information in the form and context in which it appears.

Information in this report relating to Ore Reserves is based on information compiled by Dr Spero Carras of Carras Mining Pty Ltd. Dr Carras is a Fellow of the Australasian Institute of Mining & Metallurgy and has 30 years of experience which is relevant to the style of mineralisation and type of deposit under consideration and to the activity which he is undertaking to qualify as Competent Person as defined in the 2004 Edition of the "Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves" and is a "Qualified Person" as defined in "National Instrument 43-101" of the Canadian Securities Administrators. Dr Carras consents to the inclusion in the report of the matters based on his information in the form and context in which it appears. 

DISCLAIMER

This announcement may contain certain forward-looking statements. The words 'anticipate', 'believe', 'expect', 'project', 'forecast', 'estimate', 'likely', 'intend', 'should', 'could', 'may', 'target', 'plan' and other similar expressions are intended to identify forward-looking statements. Indications of, and guidance on, future earnings and financial position and performance are also forward-looking statements.

Such forward-looking statements are not guarantees of future performance and involve known and unknown risks, uncertainties and other factors, many of which are beyond the control of Medusa, and its officers, employees, agents and associates, that may cause actual results to differ materially from those expressed or implied in such statements.

Actual results, performance or outcomes may differ materially from any projections and forward-looking statements and the assumptions on which those assumptions are based.

You should not place undue reliance on forward-looking statements and neither Medusa nor any of its directors, employees, servants or agents assume any obligation to update such information.



Australia
Medusa Mining Limited
Geoffrey Davis
Chairman
+61 8 9367 0601
or
Medusa Mining Limited
Peter Hepburn-Brown
Managing Director
+61 8 9367 0601
or
United Kingdom
Fairfax I.S. PLC
Ewan Leggat/Laura Littley
Financial Adviser and Broker
+44 (0)20 7598 5368
Data and Statistics for these countries : Australia | Philippines | United Kingdom | All
Gold and Silver Prices for these countries : Australia | Philippines | United Kingdom | All

Medusa Mining Ltd

EXPLORATION STAGE
CODE : MML.AX
ISIN : AU000000MML0
Follow and Invest
Add to watch list Add to your portfolio Add or edit a note
Add Alert Add to Watchlists Add to Portfolio Add Note
ProfileMarket
Indicators
VALUE :
Projects & res.
Press
releases
Annual
report
RISK :
Asset profile
Contact Cpy

Medusa Mining is a gold and copper producing company based in Australia.

Medusa Mining holds various exploration projects in Philippines.

Its main exploration properties are CO-O, CORPLEX, ABACUS, ANOLING and APICAL in Philippines.

Medusa Mining is listed in Australia, in Canada, in Germany and in United Kingdom. Its market capitalisation is AU$ 125.7 millions as of today (US$ 90.7 millions, € 89.2 millions).

Its stock quote reached its highest recent level on June 03, 2011 at AU$ 8.60, and its lowest recent point on June 27, 2017 at AU$ 0.27.

Medusa Mining has 207 790 000 shares outstanding.

Your feedback is appreciated, please leave a comment or rate this article.
Rate : Average note :0 (0 vote) View Top rated
 
Corporate Presentations of Medusa Mining Ltd
9/5/2016Investor Presentation September 2016
2/14/2011Investor Presentation February 2011
8/18/2008Aegis report
6/16/2008 BGF Equities Research Report
3/12/2008Fairfax ResearchContent-class: urn:content-classes:message
7/31/2007 Quarterly Activity Report
3/11/2007Investor Presentation
In the News and Medias of Medusa Mining Ltd
6/17/2008Building a low cost production base with blue sky potential
3/13/2007Broker Report
Annual reports of Medusa Mining Ltd
: 2013 Annual Report
: 2011 Annual Report
Annual Report and Notice of Meeting
2006 Annual Report
Nominations of Medusa Mining Ltd
5/31/2013: Retirement and Appointment of CFO
1/25/2013: New Board Appointments
6/9/2011Board Restructure Following TSX Delisting to Oversee the Nex...
7/9/2010Appointment of Non-Executive Chairman
2/15/2010Appointment of director
9/15/2009Appointment of Director
Financials of Medusa Mining Ltd
2/21/2012: Interim Financial Results
4/27/2011March 2011Quarterly Report
2/22/2011MEDUSA ACHIEVES RECORD HALF-YEAR PROFIT
9/7/2009Records strong 2009 financial results
Project news of Medusa Mining Ltd
4/8/2013(Co-o): Co-O Mill & Mine Expansion Update
2/21/2013(Co-o): Co-O Drilling Update
10/18/2012(Co-o): Co-O Mine Shafts Update
8/15/2012(Co-o): Co-O Mine Geology and Mineralisation Update
7/10/2012(Co-o): Co-O Drilling Update
7/10/2012(Co-o)Limited: Co-O Drilling Update
4/16/2012(Co-o): Co-O Drilling Update
3/21/2012(Co-o): Co-O Operations-Unscheduled Mill Maintenance
4/5/2011(Co-o)Co-O DRILLING CONTINUES HIGH GRADE RESULTS
12/1/2010(Saugon) - Saugon Drilling Expands High-Grade Gold-Silver Potential
6/30/2010(Co-o)Co-O Mine Update
3/29/2010(Co-o)Co-O Mine drilling update
3/16/2010(Co-o)Co-O expanded mill commissionning
7/17/2009(Co-o)Co-O mine reserve now 500 000 ounces
1/19/2009(Co-o) Co-O MINE RESOURCES INCREASED 40% TO 1.2 MILLION OUNCES
12/1/2008MAJOR NEW HIGH GRADE VEIN DISCOVERY
8/12/2008(Co-o)Co-O MINE RESOURCE EXPANSION
5/7/2008(Co-o)WIDE-HIGH GRADE INTERSECTION AT Co-O MINE
3/26/2008(Co-o)Co-O MPSA GRANTED
1/21/2008(Co-o)NEW CATTO VEIN EXTENSIONS DISCOVERED
10/1/2007(Co-o)Co-O Mine Expansion
9/4/2007713,000 resource ounces and growing
8/15/2007CO-O MINE RESOURCE DRILL HOLE RESULTS
7/9/2007New Discoveries
6/20/2007(Anoling)POSITIVE RESULTS FROM ANOLING GOLD PROJECT
5/16/2007(Co-o)Co-O Mine Update
3/19/2007(Anoling)Anoling Gold Project tenements granted
5/23/2006Tambis project exploration, Philippines
Corporate news of Medusa Mining Ltd
6/20/2016Relocation of Office Premises
5/9/2016Investor Presentation May 2016
5/6/2016Market Briefing May 2016 – Medusa Mining Ltd
5/2/2016Cancellation of Unquoted Securities (Options)
4/5/2016Terms of Appointment of CEO
3/21/2016CEO Appointment
1/22/2016CEO Appointment Update
1/20/2016Exploration Pipeline and Tenement Review
1/18/2016L8 Shaft Upgrade
1/18/2016Mineral Resources and Reserves Statement Addendum to 2014 An...
1/18/2016Cancellation of Unquoted Securities
10/9/2015Notice of Annual General Meeting and Proxy Form
10/5/2015Investor Presentation October 2015
9/25/2015Annual Mineral Resources & Ore Reserve Update Statement
9/4/2015Annual Mineral Resources Update Statement
9/3/2015Asset Impairment of US260M
8/27/2015ASX Appendix 4E and Financial Results for ended year June 30...
8/27/2015Full Year Results 2015
7/28/2015Investor Presentation July 2015
7/27/2015Quarterly Report June 2015
7/7/2015Co-O Mine Service Shaft Update
4/13/2015Investor Presentation April 2015 – Zurich and London
4/9/2015Co-O Mine Geology & Service Shaft Updates
1/21/2015Exploration Pipeline and Tenement Review
1/16/2015L8 Shaft Upgrade
1/12/2015Cancellation of Unquoted Securities
1/12/2015Mineral Resources and Reserves Statement Addendum to 2014 An...
12/9/2014Appendix 3Z – Directors Final Notice (Gary Raymond Powell)
11/21/2014Results of Annual General Meeting November 2014
11/20/2014Executive Appointments
2/13/2014Fatality Underground
2/13/2014Medusa Mining Limited: Fatality Underground
1/31/2014Medusa Mining Limited Quarterly Activities Report: Period En...
1/28/2014Operations Update
1/28/2014Medusa Mining Limited: Operations Update
1/21/2014Operations Update
10/29/2013: Quarterly Activities Report Period Ended 30 September 2013
10/23/2013: SAG Mill Update
9/4/2013: Operations Update-New Mill and Level 8
7/31/2013: Quarterly Activities Report Period Ended 30 June 2013
7/8/2013(Co-o): Co-O Operations Update
5/2/2013: Quarterly Activities Report Period Ended 31 March 2013
4/15/2013: Investor Presentation April 2013
10/30/2012: Quarterly Activities Report Period Ended 30 September 2012
8/29/2012: Full Year Results
8/6/2012(Co-o): Co-O Mine Mineral Resource Update
7/31/2012: Quarterly Activities Report Period Ended 30 June 2012
4/30/2012: Investor Presentation May 2012
4/24/2012: Quarterly Activities Report Period Ended 31 March 2012
2/10/2012: Investor Presentation February 2012
1/30/2012December 2011 Quarterly Report
1/17/2012: Bananghilig Deposit Drilling Update
12/16/2011: Appendix 3B
12/5/2011: Issue of Performance Rights
10/24/2011: Investor Presentation
8/29/2011Achieves Record Full Year Profit
8/24/2011ASX Announcement
8/22/2011(Co-o): Co-O Mine Mineral Reserve Estimate
7/28/2011ASX Announcement - Quarterly Report
1/25/2011- Medusa Quarterly Report
5/24/2010AIM cancellation & admission to the official list
5/7/2010Copper portfolio - Lingig update
3/8/2010Bonus issue of shares
1/25/2010Notice of no corporate associations
10/9/2009Lingig drilling extends mineralisation
8/12/2009ASX Announcement
7/3/2009MML - ASX Ann - S&P/ASX 200 Index
6/22/2009ASX Announcement
6/1/2009MML - ASX Announcement
2/26/2009UNDERWRITTEN A$24.5 MILLION PLACEMENT
1/28/2009Quarterly Report
11/5/2008ASX Announcement
9/23/2008ASX Announcement
9/19/2008Crosby Makes $182 Million Takeover Bid for Medusa Mining
8/20/2008ASX Announcement
7/25/2008ASX Announcement
6/10/2008ASX Announcement
4/11/2008Joint Venture With Bunawan Mining Corporation
3/14/2008Half Year Financial Report – 31 December 2007
2/25/2008IRON ORE TARGETS IDENTIFIED
11/13/2007LINGIG PORPHYRY COPPER DISCOVERY
10/31/2007 QUARTERLY ACTIVITIES REPORT PERIOD ENDING 30 SEPTEMBER 2007
8/16/2007Ambrian Morning Research
8/1/2007Heads of Agreement and Placement with Sierra Mining Ltd
7/16/2007Barobo Mineralised Corridor
6/13/2007 Acquisition of Co-O Mine Royalty
5/25/2007Equity Research
5/15/2007ASX Announcement
4/30/2007Quarterly Report March 2007
3/21/2007Releases
3/8/2007 Dismissal of motion for reconsideration on CO-o mise
6/13/2006appointement of nominated advisor & broker - AIM London
5/17/2006Acquisition of Apical gold project, Philippines
4/10/2006Alternative Investment Market (AIM) London
3/16/2006half year financial report 31 december 2005
1/30/2006Gold Production started, increasing quickly from here
1/21/2006ANALYSIS : MEDUSA MINING
Comments closed
 
Latest comment posted for this article
Be the first to comment
Add your comment
AUSTRALIA (MML.AX)TORONTO (MLL.TO)
0.605-15.38%7.43-0.80%
AUSTRALIA
AU$ 0.605
07/08 11:00 -0.110
-15.38%
Prev close Open
0.715 0.615
Low High
0.600 0.625
Year l/h YTD var.
 -  -
52 week l/h 52 week var.
- -  0.605 -%
Volume 1 month var.
123,619 -%
24hGold TrendPower© : -44
Produces
Develops
Explores for Gold
 
 
 
Analyse
Interactive chart Add to compare
Interactive
chart
Print Compare Export
Last updated on : 3/2/2010
You must be logged in to use the porfolio and watchlists (free)
Top Newsreleases
MOST READ
Annual variation
DateVariationHighLow
2022-14.79%0.950.60
2021-7.79%0.990.66
20200.00%1.070.40
 
5 years chart
 
3 months chart
 
3 months volume chart
 
 
Mining Company News
Plymouth Minerals LTDPLH.AX
Plymouth Minerals Intersects Further High Grade Potash in Drilling at Banio Potash Project - Plannin
AU$ 0.12-8.00%Trend Power :
Santos(Ngas-Oil)STO.AX
announces expected non-cash impairment
AU$ 7.70-0.65%Trend Power :
Oceana Gold(Au)OGC.AX
RELEASES NEW TECHNICAL REPORT FOR THE HAILE GOLD MINE
AU$ 2.20+0.00%Trend Power :
Western Areas NL(Au-Ni-Pl)WSA.AX
Advance Notice - Full Year Results Conference Call
AU$ 3.86+0.00%Trend Power :
Canadian Zinc(Ag-Au-Cu)CZN.TO
Reports Financial Results for Q2 and Provides Project Updates
CA$ 0.12+4.55%Trend Power :
Stornoway Diamond(Gems-Au-Ur)SWY.TO
Second Quarter Results
CA$ 0.02+100.00%Trend Power :
McEwen Mining(Cu-Le-Zn)MUX
TO ACQUIRE BLACK FOX FROM PRIMERO=C2=A0
US$ 11.94+9.34%Trend Power :
Rentech(Coal-Ngas)RTK
Rentech Announces Results for Second Quarter 2017
US$ 0.20-12.28%Trend Power :
KEFIKEFI.L
Reduced Funding Requirement
GBX 0.54-2.55%Trend Power :
Lupaka Gold Corp.LPK.V
Lupaka Gold Receives First Tranche Under Amended Invicta Financing Agreement
CA$ 0.06+0.00%Trend Power :
Imperial(Ag-Au-Cu)III.TO
Closes Bridge Loan Financing
CA$ 2.69+13.03%Trend Power :
Guyana Goldfields(Cu-Zn-Pa)GUY.TO
Reports Second Quarter 2017 Results and Maintains Production Guidance
CA$ 1.84+0.00%Trend Power :
Lundin Mining(Ag-Au-Cu)LUN.TO
d Share Capital and Voting Rights for Lundin Mining
CA$ 15.60+1.83%Trend Power :
Canarc Res.(Au)CCM.TO
Canarc Reports High Grade Gold in Surface Rock Samples at Fondaway Canyon, Nevada
CA$ 0.24+0.00%Trend Power :
Havilah(Cu-Le-Zn)HAV.AX
Q A April 2017 Quarterly Report
AU$ 0.20+2.63%Trend Power :
Uranium Res.(Ur)URRE
Commences Lithium Exploration Drilling at the Columbus Basin Project
US$ 6.80-2.86%Trend Power :
Platinum Group Metals(Au-Cu-Gems)PTM.TO
Platinum Group Metals Ltd. Operational and Strategic Process ...
CA$ 1.87+5.65%Trend Power :
Devon Energy(Ngas-Oil)DVN
Announces $340 Million of Non-Core Asset Sales
US$ 52.61+0.98%Trend Power :
Precision Drilling(Oil)PD-UN.TO
Announces 2017Second Quarter Financial Results
CA$ 8.66-0.35%Trend Power :
Terramin(Ag-Au-Cu)TZN.AX
2nd Quarter Report
AU$ 0.04+5.56%Trend Power :