Selwyn Resources News Releases - August 29, 2011 - Selwyn�s ScoZinc (Restart) Project Delivers Robust Economic Results
Can't read this email?
August 29, 2011

News Release

Selwyn�s ScoZinc (Restart) Project Delivers Robust Economic Results

Vancouver, BC, August 29, 2011 � Selwyn Resources Ltd. (SWN.TSX-V) is pleased to announce results of the ScoZinc Preliminary Economic Assessment (�PEA�) Report for the restart of the ScoZinc zinc-lead project in Nova Scotia, Canada. The PEA indicates excellent potential for a seven-plus years mine life with pre-stripping beginning in the fourth quarter of 2011 and full operation in the second quarter (Q2) of 2012, provided the debt offering announced August 22, 2011 is timely completed. The full text of the report, which meets National Instrument 43-101 standards, will shortly be filed for review on www.sedar.com.
Dr. Harlan Meade, President and CEO of Selwyn Resources Ltd (�Selwyn�) states: �Much progress has been made since announcing the acquisition of ScoZinc Ltd. on February 8th, 2011. The completion of new mineral resource estimates (announced April 6th, 2011) and the Preliminary Economic Assessment provide a strong basis for the implementation of the restart plan to return the ScoZinc mine (formerly the Scotia Mine) to production in Q2 2012. ScoZinc operations could provide near term cashflow to help the company advance its Selwyn Project in the Yukon. Ongoing and planned drilling activities, along with the continued evaluation of opportunities to reduce operating costs, are expected to provide additional operating improvements and to increase profitability of the ScoZinc mine. Selwyn is very pleased with this acquisition and looks forward to growing its mineral assets at ScoZinc.�

Highlights

The PEA reports:
� 2,500 tonnes per day mill processing plan;
� Unit operating costs of $51.77 per tonne milled for the first three years ($49.16 per tonne milled for the life-of-mine);
� Mine and mill restart capital expenditures (CAPEX) of CAD $30 Million (including 15% contingency and two months of working capital);
� Base Case zinc and lead prices of US$1.10 and US$1.20/lb respectively;
� Exchange rate of 1 Canadian dollar to 1 US dollar;
� Project pre-tax NPV 8% of CAD $54.1 million (NPV 5% - CAD $63.9 million);
� Project pre-tax Internal Rate of Return (IRR) of 63.9%;
� Zinc C1 or Direct cash cost of production (after deducting credits for lead) for the first three years is CAD $0.56/lb to be optimized through ongoing studies;
� Earnings before interest, taxes, depreciation and amortization (EBITDA) for the first three years of operations averages CAD $26.2 million per annum.

The PEA was led by independent firm Allnorth Consultants Ltd., a nationwide mineral industry consulting firm familiar with ScoZinc and having offices local to the project (qualified person and project manager, Colin Fisher, P.Eng.). The PEA considers the sequential development of three open pit operations in close proximity to the existing mill. The zinc-lead mill feed will be processed by standard flotation methods to produce clean, high-grade zinc and lead concentrates. The ScoZinc mill is currently being refurbished and modernized by Selwyn to increase the throughput to 2,500 tonnes per day. The economic evaluation is based on a mineral resource inventory from the mineral resource technical report dated July 6, 2011 (see SEDAR filing dated July 8, 2011) and production records generated as recently as 2009. It is expected that continued optimization studies will further reduce cash operating and equipment costs, while additional drilling is expected to expand potentially mineable resources and defer lower grade mineralization to later in the project�s life.
The PEA provides a positive project value and an estimate of the capital and operating cost parameters for the ScoZinc operations. The capital and operating costs included in the PEA were derived by estimating detailed costs for the mill refurbishment and updating the known historical operating costs from the open pit operations conducted by the previous operators (2007 to 2009). The use of historical operating data as a basis for the PEA is considered a more accurate approach than the methods used in a typical scoping study based on a greenfield project. The PEA provides Selwyn with guidance for on-going detailed engineering work to achieve the ScoZinc mine and mill commissioning in early 2012.

Metallurgy
Selwyn proposes plant modifications including redesign and replacement of the crushing circuit and concentrate filters. These modifications, together with improved plant availability, will allow average mill feed rates of 875,000 dry metric tonnes (dmt) per annum or 2,500 dmt per day. The projected feed grades for the first three years average 3.81% zinc and 1.69% lead (projected life-of-mine mill feed grades are 2.95% zinc and 1.64% lead). The projected metallurgical performance, based on historical data, provides for a zinc concentrate grading 57% zinc at 86% recovery and a lead concentrate grading 70% lead at 88% recovery.

The production schedule contains allowances to reflect the operating inefficiencies commonly experienced during plant tune-up and crew training during the first six months of operation. No deleterious minor elements are contained in the concentrates. The products are expected to be readily marketable, given their clean, high-grade nature.

Mining
Three conventional open pits are to be mined sequentially; Main, Northeast, and Getty, each of which were optimized using Whittle software. Production scheduling is based on an average production rate of 875,000 tonnes per year (or 2,500 tonnes per day) into the mill over an average of 350 operating days per year. The average strip ratio for the life-of-mine is 20.6 to 1 (excluding pre-stripping which is included in the capital costs). Approximately 58% of the waste is readily removed without blasting, including soils that will be used for reclamation, and 11% of the waste is gypsum, which may be marketable. Mine dilution and mining losses are assumed to be 10% and 5%, respectively.
The open pits contain the life-of-mine potentially mineable resources listed in the table below with classifications following CIM guidelines.

Concentrate Marketing and Metal Prices
Based on historical concentrate data, Selwyn expects to produce readily marketable concentrates grading 57% and 70% for zinc and lead respectively, with no penalties. Previous concentrate shipments from the ScoZinc mine were shipped to Europe and Asia.. Selwyn expects to confirm its marketing contracts approximately three months prior to production.
Selwyn believes the outlook for zinc and lead prices will remain positive given expected forthcoming industry macro-level supply challenges, justifying the use of $1.10/lb zinc and $1.20/lb lead as the Base Case for the PEA.
Current infrastructure provides a number of options for the shipment of ScoZinc�s concentrate. The final concentrate shipment plan will be determined at a time closer to the commencement of production at the ScoZinc mine.

Infrastructure
Excellent infrastructure is in place at the ScoZinc mine. The mine has access to low-cost power and ample water supply. Paved roads lead to the mine property with nearby rail access. ScoZinc has its own storage and concentrate loading facility at Sheet Harbour with a capacity of 8,500 tonnes, or 1.5 times the expected shipment size.

Environment, Community Relations, and Permitting
Selwyn has consulted with the Nova Scotia government and local community and has received strong support for the restart of the ScoZinc mine. Permitting for the southwest extension of the Main deposit open pit is well underway and all necessary permits to re-start operations are expected in the fourth quarter of 2011. Staffing of restart operations is in progress, led by the recently hired General Manager and Manager of Mining (see August 16, 2011 news release). The mine is expected to employ approximately 120 persons upon commencement of full operations in Q2 2012.

Selwyn Resources Ltd.

Selwyn�s primary focus is the exploration and development of its properties that make up the Selwyn Project in the Yukon, which is being advanced by Selwyn Chihong Mining Ltd, a company jointly owned by Selwyn and its joint venture partner Yunnan Chihong Canada Ltd. The known deposits at Selwyn Project have the potential for large-scale production, and to provide a secure supply of zinc and lead to meet the future needs of these markets in Asia and beyond. The acquisition of the assets of ScoZinc Limited provides Selwyn with a second opportunity for growth and the potential for production revenues in 2012.
This news release has been reviewed and approved by Colin Fisher, P.Eng., project manager with Allnorth Consultants Ltd., an independent Qualified Person under NI 43-101, and Joseph Ringwald, P.Eng., Vice President Mining with Selwyn Resources Ltd., a Qualified Person under NI 43-101.

Cautionary Note

The PEA is preliminary in nature and includes inferred mineral resources that are considered too geologically speculative to be subject to economic considerations that would enable them to be categorized as mineral reserves. There is no certainty that the forecast results stated in the PEA will be realized. For a full description of known risks that could materially affect potential development of the ScoZinc zinc-lead project, see Selwyn�s July 8, 2011 Final Short Form Prospectus under the heading �Risk Factors� which are incorporated by reference herein and are available on www.sedar.com under the Selwyn Resources profile. In addition, Selwyn needs to raise approximately $30 million to fund the restart of the ScoZinc Mine.

Cautionary and Forward-Looking Information Comments
This news release contains �forward-looking information� within the meaning of applicable Canadian securities legislation, which is also referred to as �forward-looking statements.� Wherever possible, words such as �plans,� �expects,� or �does not expect,� �budget,� �scheduled,� �estimates,� �forecasts,� �anticipate� or �does not anticipate,� �believe,� �intend,� and similar expressions or statements that certain actions, events or results �may,� �could,� �would,� �might� or �will� be taken, occur or be achieved, have been used to identify forward-looking information. In particular, this news release describes future events and conditions related to Selwyn�s plans for restarting the ScoZinc Mine and further exploration and studies at the ScoZinc lead-zinc project. Forward-looking information is based on management�s reasonable assumptions, estimates, expectations, analyses and opinions on the date of this news release. These are based on management�s experience and perception of trends, current conditions and expected developments, and other factors that management believes are relevant and reasonable in the circumstances, but which may prove to be incorrect.
Assumptions have been made regarding, among other things, Selwyn�s ability to carry on exploration and development activities, the timely receipt of required approvals, operating costs for the [ScoZinc Mine], the price of zinc and lead, Selwyn�s ability to operate in a safe, efficient and effective manner and Selwyn�s ability to obtain financing as and when required and on reasonable terms. Readers are cautioned that the foregoing list is not exhaustive of all factors and assumptions which may have been used. Selwyn�s actual results, programs and financial position could differ materially from those anticipated in such forward-looking statements as a result of numerous factors, many of which are beyond Selwyn�s control. These factors include, but are not necessarily limited to, results of the restart program at the ScoZinc Mine, exploration and development activities, the interpretation of drilling results and other geological data, the uncertainties of resource and reserve estimations, receipt of permits to conduct mining activities, project cost overruns or unanticipated costs and expenses, the availability of funds, fluctuations in metal prices, currency fluctuations, and general market and industry conditions. There is no assurance that forward-looking information will prove to be accurate, as actual results and future events could differ materially from those anticipated in such information. Accordingly, readers should not place undue reliance on this information. Selwyn does not undertake to update any forward-looking information, except as, and to the extent required by, applicable securities laws. For more information about the risks and challenges of Selwyn�s business, investors should review Selwyn�s Final Short Form Prospectus dated July 8, 2011 available at www.sedar.com.

Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.

For more information contact:
Dr. Harlan Meade, President and CEO
Catalin Chiloflischi, Manager of Investor Communications
Telephone: (604) 801-7242), Toll-free: 1-888-989-9188, International Toll-free: 800-7581-2133,
Facsimile: (604) 689-8355, and info@selwynresources.com

 

Copyright � 2009 Selwyn Resources Ltd.

 

.
Data and Statistics for these countries : Canada | All
Gold and Silver Prices for these countries : Canada | All

Selwyn Resources Ltd.

PRODUCER
CODE : SWN.V
ISIN : CA81662B1040
Follow and Invest
Add to watch list Add to your portfolio Add or edit a note
Add Alert Add to Watchlists Add to Portfolio Add Note
ProfileMarket
Indicators
VALUE :
Projects & res.
Press
releases
Annual
report
RISK :
Asset profile
Contact Cpy

Selwyn Res. is a zinc and lead development stage company based in Canada.

Selwyn Res. holds various exploration projects in Canada and in Mexico.

Its main asset in production is SCOTIA MINE - in Canada, its main assets in development are SELWYN / HOWARD PASS and HOWARD'S PASS in Canada and its main exploration properties are GETTY DEPOSIT in Canada and VINATA in Mexico.

Selwyn Res. is listed in Canada, in Germany and in United States of America. Its market capitalisation is CA$ 4.7 millions as of today (US$ 3.5 millions, € 3.2 millions).

Its stock quote reached its lowest recent point on November 21, 2008 at CA$ 0.04, and its highest recent level on March 11, 2011 at CA$ 4.88.

Selwyn Res. has 3 940 000 shares outstanding.

Your feedback is appreciated, please leave a comment or rate this article.
Rate : Average note :0 (0 vote) View Top rated
 
In the News and Medias of Selwyn Resources Ltd.
2/25/2008Zinc Markets, the perfect storm ?
Financings of Selwyn Resources Ltd.
1/13/2012Announces $4 Million Flow-Through Share Financing
8/24/2011Announces US$30 Million Bond Financing for ScoZinc Mine Rest...
6/9/2011Completes $12,784,500 Special Warrant Offering
6/1/2011Announces Closing of the Second Tranche of its Special Warra...
5/27/2011Announces Closing of the First Tranche of Its Special Warran...
6/17/2010Announces up to $3 Million Non-brokered Flow-through and Uni...
12/24/2009 Announces Up to $1,000,000 Non-brokered Flow-through Financ...
9/16/2009Increase Up to $7,092,000 Non-brokered Share Financing
9/8/2009Up to $6 Million Non-brokered Share Financing
5/14/2009Closing of $250,000 Non-brokered Flow-through Financing
10/23/2007Announces Closing of $3,150,000 Non-brokered Flow-Through Fi...
Option Grants of Selwyn Resources Ltd.
8/15/2009Grants Stock Options
Nominations of Selwyn Resources Ltd.
4/22/2013Announces Resignation of A. Jay Collins as a Director
3/12/2013Announces Appointment of New Manager of Investor Communicati...
9/24/2012Appoints Directors to Its Board
2/24/2011Expands Management Team
7/7/2009Appointment of Korea Zinc Representative to Board
Project news of Selwyn Resources Ltd.
6/14/2013New Mine Plan for ScoZinc Project Filed on SEDAR
6/11/2013Announces Updated ScoZinc Mine Plan
6/4/2013Announces Completion of Sale of Selwyn Project
4/20/2013to Hold Vote on Sale of Selwyn Project Only on April 22, 201...
8/22/2012s Revised Mine Development Plan for the Selwyn Project
5/23/2012Receives Approval for ScoZinc Mine Expansion
5/11/2012=E2??s Assays Confirm High-Grade Mineralization at Don Conne...
4/30/2012Chihong Receives Howard=E2??s Pass Mine Access Road Licence
4/16/2012Drilling in Don Connector Confirms Thick Zinc-Lead Mineraliz...
2/17/2012Acquires Surface Rights for Expansion at ScoZinc Mine
10/11/2011Receives Environmental Approval for ScoZinc Mine
9/19/2011New High-Grade Discovery Mineralization Extends XY West to t...
9/6/2011Significantly Expands XY West Deposit
8/16/2011Deep Drilling at Don Deposit Defines New Mineral Potential i...
8/11/2011Mobilizes Drills to ScoZinc Mine
7/6/2011Supreme Court of Yukon Dismisses Liard First Nation Applicat...
6/7/2011Don Deposit - Significant Potential at Depth Confirmed
6/1/2011Announces Completion of Acquisition of ScoZinc Limited
4/25/2011Chihong Receives B Water License: Project Update
4/4/2011Successfully Completes Winter Mobilization of Mining Equipme...
4/1/2011(Scotia Mine -)Announces Equity Financing of Up to $15 Million for Scotia M...
3/16/2011Commences Winter Mobilization of Mining Equipment
2/22/2011(Scotia Mine -)Signs Binding Agreement to Acquire ScoZinc Limited
2/15/2011(Selwyn / Howard Pass)Intercepts Thick High-Grade Mineralization in XY Central Dep...
10/7/2009(Vinata)Announces the Commencement of Drilling on Vinata Property
9/24/2009(Howard's Pass)Expands XY High-Grade Mineral Potential
8/13/2009(Vinata)Receives Regulatory Approval of Vinata Property Acquisition
1/29/2008Announces 2008 Mineral Resources and Expanded High-Grade Und...
1/15/2008Don East Deposit Continues to Expand Mineral Potential
1/10/2008Infill Drilling Confirms Higher-Grade XY Open Pit
9/4/2007 Announces Significant Step-out on High-grade in Don Valley
Corporate news of Selwyn Resources Ltd.
8/25/2015Selwyn Announces Board Changes and Grant of Stock Options
2/19/2015Selwyn Announces Grant of Incentive Stock Options
1/17/2015Selwyn Announces Failure of Scotian to Close ScoZinc Sale Tr...
12/30/2014IIROC Trading Resumption - SWN
12/30/2014Selwyn Announces Further Extension to Closing of Sale of Sco...
12/22/2014IIROC Trading Halt - SWN
11/24/2014IIROC Trading Resumption - SWN
11/21/2014Selwyn Announces Extension to Closing of Sale of ScoZinc
11/18/2014IIROC Trading Halt - NSP; SWN
10/29/2014Selwyn Announces Annual General and Special Meeting Results
9/10/2014Selwyn Res Ltd. IIROC Trading Resumption - SWN
9/10/2014Selwyn Announces Definitive Agreement for the Sale of ScoZin...
9/10/2014IIROC Trading Halt - SWN
6/2/2014Selwyn Appoints Victor Lazarovici Chairman of the Board
6/18/2013Announces Annual General and Special Meeting Results
6/12/2013Announces Repayment of Waterton Loan Facility
6/7/2013Addresses Statements Made in Dissident Circular
5/23/2013Important Notice
5/21/2013Announces Closing Date for the Sale of Selwyn Project and Pr...
5/13/2013Announces Satisfaction of Additional Closing Conditions for ...
4/29/2013Announces Date of Annual and Special Meeting
4/23/2013Responds to Press Release from Samara Capital Regarding Purp...
4/16/2013Announces Change of Venue for Annual General and Special Mee...
4/9/2013Announces Receipt of Second $5 Million Purchase Price from C...
2/18/2013Announces New Vice President of Exploration
10/24/2012Grants Stock Options
10/12/2012Announces Changes to its Management
10/10/2012Updated Gays River Deposit Mineral Resource Technical Report...
9/27/2012d Selwyn Project Mineral Resource Technical Report Filed on ...
9/10/2012Announces Changes to its Board
9/6/2012Suspends Strategic Review Process
8/13/2012Announces Updated Mineral Resource For Selwyn Project
7/19/2012Announces Selwyn Chihong Agreement with Kaska Communities
5/28/2012Joint Venture To Evaluate A Smaller Tonnage High-Grade Mine ...
5/15/2012Announces Updated Mineral Resource For XY West Deposit
5/14/2012Announces Special and Annual General Meeting Results
5/3/2012Announces Management Reorganization
4/18/2012Chihong Agreement with Naha Deh=C3=A9 Dene
4/17/2012Progress Update
4/17/2012Announces Closing of Debt Facility
4/10/2012Announces $10 Million Debt Facility
3/28/2012Metallurgical Drilling Further Defines Thick High-Grade Mine...
3/26/2012RETAINS CUTFIELD FREEMAN
3/12/2012Expands Airborne Geophysical Survey for Nova Scotia Properti...
2/2/2012Commissions Airborne Geophysical Survey for Nova Scotia Prop...
9/13/2011ANNOUNCES UPDATED MINERAL RESOURCES FOR SELWYN PROJECT
8/30/2011=?UTF-8?Q?Selwyn=E2=80=99s_ScoZinc_(Restart)_Projec?=t Deliv...
8/22/2011Announces Termination of the Proposed 24 Million Share Offer...
8/16/2011Expands Management Team
7/19/2011Continues To Confirm Don Deposit Mineralization
7/11/2011Announces Acceptance of Prospectus by Regulatory Authorities
7/7/2011Announces Korea Zinc Warrants Exercise
7/5/2011-Drilling on Don Deposit Continues to Confirm Continuity
6/7/2011Don Deposit-Significant Potential at Depth Confirmed
6/2/2011Announces Transamine Shareholding
5/17/2011Announces Pricing and Change to Equity Financing of up to $1...
5/9/2011Closing of the Acquisition of the Assets of ScoZinc Extended...
4/19/2011Expands Management Team
4/6/2011Announces Scotia Mine Mineral Resources
4/6/2011High Grade Drill Results Continue from Don Deposit
4/1/2011Intercepts High-Grade Mineralization in Don Deposit
3/30/2011(Getty Deposit)Announces Getty Deposit Mineral Resources
2/17/2011Exercises Savant Common Share Purchase Warrants
1/27/2011Announces Intention to make a Normal Course Issuer Bid
7/28/2010$650,000 Closing of Second Tranche of Financing
7/8/2010Announces Chihong Approvals for Selwyn Project
6/16/2010 Closes $562,500 Unit Financing
5/6/2010 Enters into Cooperation Agreement with Tulita District Land...
3/2/2010Updates progress on joint venture transaction with Yunnan Ch...
12/15/2009 C$100 Million Joint Venture Transaction With Yunnan Chihong...
12/15/2009Corporate Update Teleconference
10/29/2009Announces Receipt of Class A Land Use Permit from the Sahtu ...
10/23/2009$960,000 Closing of Second Tranche of Financing
9/30/2009$6.132 Million Closing of First Tranche of Financing
7/21/2009Advances the Selwyn Project
6/3/2009$2.25 Million Closing of First Tranche of Unit Financing
Comments closed
 
Latest comment posted for this article
Be the first to comment
Add your comment
TSX-V (SWN.V)FRANKFURT (P3Z.F)
1.20+0.00%0.049+0.00%
TSX-V
CA$ 1.20
09/30 15:52 -
0%
Prev close Open
1.20 1.20
Low High
1.20 1.20
Year l/h YTD var.
 -  -
52 week l/h 52 week var.
- -  1.20 -%
Volume 1 month var.
400 -%
24hGold TrendPower© : -27
Produces Lead - Zinc
Develops Lead - Zinc
Explores for Lead - Zinc
 
 
 
Analyse
Interactive chart Add to compare
Interactive
chart
Print Compare Export
Last updated on : 1/23/2010
You must be logged in to use the porfolio and watchlists (free)
Top Newsreleases
MOST READ
Annual variation
DateVariationHighLow
 
5 years chart
 
3 months chart
 
3 months volume chart
 
 
Mining Company News
Plymouth Minerals LTDPLH.AX
Plymouth Minerals Intersects Further High Grade Potash in Drilling at Banio Potash Project - Plannin
AU$ 0.12-8.00%Trend Power :
Santos(Ngas-Oil)STO.AX
announces expected non-cash impairment
AU$ 7.75+0.52%Trend Power :
Oceana Gold(Au)OGC.AX
RELEASES NEW TECHNICAL REPORT FOR THE HAILE GOLD MINE
AU$ 2.20+0.00%Trend Power :
Western Areas NL(Au-Ni-Pl)WSA.AX
Advance Notice - Full Year Results Conference Call
AU$ 3.86+0.00%Trend Power :
Canadian Zinc(Ag-Au-Cu)CZN.TO
Reports Financial Results for Q2 and Provides Project Updates
CA$ 0.12+4.55%Trend Power :
Stornoway Diamond(Gems-Au-Ur)SWY.TO
Second Quarter Results
CA$ 0.02+100.00%Trend Power :
McEwen Mining(Cu-Le-Zn)MUX
TO ACQUIRE BLACK FOX FROM PRIMERO=C2=A0
US$ 11.11+2.21%Trend Power :
Rentech(Coal-Ngas)RTK
Rentech Announces Results for Second Quarter 2017
US$ 0.20-12.28%Trend Power :
KEFIKEFI.L
Reduced Funding Requirement
GBX 0.55-0.90%Trend Power :
Lupaka Gold Corp.LPK.V
Lupaka Gold Receives First Tranche Under Amended Invicta Financing Agreement
CA$ 0.06-8.33%Trend Power :
Imperial(Ag-Au-Cu)III.TO
Closes Bridge Loan Financing
CA$ 2.47+3.78%Trend Power :
Guyana Goldfields(Cu-Zn-Pa)GUY.TO
Reports Second Quarter 2017 Results and Maintains Production Guidance
CA$ 1.84+0.00%Trend Power :
Lundin Mining(Ag-Au-Cu)LUN.TO
d Share Capital and Voting Rights for Lundin Mining
CA$ 15.25-3.42%Trend Power :
Canarc Res.(Au)CCM.TO
Canarc Reports High Grade Gold in Surface Rock Samples at Fondaway Canyon, Nevada
CA$ 0.24+0.00%Trend Power :
Havilah(Cu-Le-Zn)HAV.AX
Q A April 2017 Quarterly Report
AU$ 0.19+0.00%Trend Power :
Uranium Res.(Ur)URRE
Commences Lithium Exploration Drilling at the Columbus Basin Project
US$ 6.80-2.86%Trend Power :
Platinum Group Metals(Au-Cu-Gems)PTM.TO
Platinum Group Metals Ltd. Operational and Strategic Process ...
CA$ 1.79-3.76%Trend Power :
Devon Energy(Ngas-Oil)DVN
Announces $340 Million of Non-Core Asset Sales
US$ 52.57+0.84%Trend Power :
Precision Drilling(Oil)PD-UN.TO
Announces 2017Second Quarter Financial Results
CA$ 8.66-0.35%Trend Power :
Terramin(Ag-Au-Cu)TZN.AX
2nd Quarter Report
AU$ 0.04+0.00%Trend Power :