Great Panther Silver Achieves Several Production Records in Third Quarter 2013
Published : October 10, 2013
( 0 vote, 0/5 ) Print article
  Article Comments Comment this article Rating Follow Company  
0
Send
0
comment

VANCOUVER, BRITISH COLUMBIA--(Marketwired - Oct. 10, 2013) - GREAT PANTHER SILVER LIMITED (News - Market indicators)(NYSE MKT:GPL) (the "Company") today reports third quarter ("Q3") production results at its two wholly-owned Mexican silver mining operations, Guanajuato and Topia.

Third Quarter 2013 Operations Highlights (Compared to Third Quarter 2012)

  • Ore processed was up 32% to 76,898 tonnes, the highest quarterly throughput the Company has achieved;
  • Metal production increased 33% to a record of 789,250 silver equivalent ounces ("Ag eq oz"), at a 60:1 silver:gold ratio;
  • Silver production rose 24% to a record 459,924 silver ounces ("Ag oz");
  • A new high for quarterly gold production was achieved, at 4,695 gold ounces ("Au oz"), a 56% increase; and,
  • Environmental Impact Assessment Permit received (subsequent to quarter end) for San Ignacio.

"We are pleased to report new records for total metal production and for each of our two mines for the third quarter of 2013, in addition to record production for silver and gold," stated Robert Archer, President and CEO. "With year-to-date production totaling 2,076,963 silver equivalent ounces, we expect to exceed our production guidance for the year. Our continued focus on grade control and operational efficiencies is having a meaningful, positive impact on production volumes while reducing unit costs. In light of lower metal prices, the Company has concentrated on reducing site costs and improving operating efficiencies, and has also focused capital expenditure and development programs on those with the greatest return on investment."

"The Rayas Shaft rehabilitation at the Guanajuato Mine Complex is almost complete and the shaft is expected to resume operations in October. This will reduce transportation times of personnel to their work places and further improve operational efficiencies. Subsequent to the end of the quarter we received the final permit required for the development of our San Ignacio mine. Production from San Ignacio will commence in early 2014 and is expected to have a significant and positive impact on the Guanajuato operations."

Consolidated Q3 Operations Summary Q3 2013 Q3 2012 Change   Q3 2013 Q2 2013 Change  
Ore processed (tonnes milled) 76,898 58,307 32 % 76,898 67,569 14 %
Silver equivalent ounce production 1 789,250 592,586 33 % 789,250 680,212 16 %
Silver ounce production 459,924 371,857 24 % 459,924 396,730 16 %
Gold ounce production 4,695 3,015 56 % 4,695 3,994 18 %
Lead production (tonnes) 300 226 33 % 300 243 24 %
Zinc production (tonnes) 411 369 11 % 411 411 0 %
Total underground development (m) 3,610 3,925 (8 )% 3,610 4,044 (11 )%
Underground Diamond drilling (m) 11,638 8,134 43 % 11,638 6,907 68 %
   
1 Silver equivalent ounces for 2013 were established in November 2012 using prices of US$28 per oz, US$1,680 per oz (60:1 ratio), US$0.85 per lb and US$0.85 per lb for silver, gold, lead & zinc, respectively, and applied to the recovered metal content of the concentrates that were produced by the two operations. For consistency, these prices will be used for the balance of 2013.

Guanajuato Mine Complex

For the third quarter, the Guanajuato operation processed 60,536 tonnes, up 38% compared to the same period in 2012, at ore grades of 166 grams/tonne ("g/t") Ag and 2.54g/t Au. Metal production included 289,671 Ag oz, and 4,531 Au oz, or 561,544 Ag eq oz, which represented an increase of 36% over the same period in 2012 and the highest quarterly production yet. Plant metallurgical performance remained strong, with metal recoveries of 89.4% for silver and 91.8% for gold.

Guanajuato Q3 Operations Summary Q3 2013   Q3 2012   Change   Q3 2013   Q2 2013   Change  
Ore processed (tonnes milled) 60,536   43,714   38 % 60,536   52,917   14 %
Silver equivalent ounce production 1 561,544   411,959   36 % 561,544   466,925   20 %
Silver ounce production 289,671   239,992   21 % 289,671   236,454   23 %
Gold ounce production 4,531   2,866   58 % 4,531   3,841   18 %
                         
Ag grade (g/t) 166   188   (11 )% 166   159   5 %
Au grade (g/t) 2.54   2.22   14 % 2.54   2.47   3 %
Ag recovery (%) 89.4 % 90.9 % (2 )% 89.4 % 87.2 % 3 %
Au recovery (%) 91.8 % 91.9 % 0 % 91.8 % 91.5 % 0 %
Total underground development (m) 1,811   1,466   23 % 1,811   1,790   1 %
Underground Diamond drilling (m) 11,020   7,485   47 % 11,020   6,426   71 %
   
1 Silver equivalent ounces for 2013 were established in November 2012 using prices of US$28 per oz, US$1,680 per oz (60:1 ratio), US$0.85 per lb and US$0.85 per lb for silver, gold, lead & zinc, respectively, and applied to the recovered metal content of the concentrates that were produced by the two operations. For consistency, these prices will be used for the balance of 2013.

Metal production at Guanajuato came primarily from the Cata and Santa Margarita mines and there was noticeable improvement in terms of production and grades from the Los Pozos and Guanajuatito mines. The slight improvement in grades over the previous quarter is due to mining in areas where mineralized structures merge into each other, reducing the dimension of production headings and stopes and leading to more selective mining, higher efficiencies and reduced dilution. Gold grades remain strong due to the steady production from the gold-rich Santa Margarita vein. 

Underground development at Guanajuato consisted of 1,811 metres, up 23% compared to the same period in 2012. The development program for the quarter concentrated on expanding core production levels and developing new stopes to increase production and improve ore grades. In addition, the ventilation system has been upgraded by driving new ventilation raises and improving the fresh air circulation in all working areas, resulting in better health and safety conditions and higher operational efficiencies.

For the quarter, Diamond drilling totaled 11,020 metres, up 47% compared to the same period in 2012. The increase in Diamond drilling is primarily due to an exploration program completed at the Guanajuatito mine, with the goal of upgrading the mineral resources between the 245 and 390 metre levels and targeting a development plan during the fourth quarter.

Exploration drilling at the Cata mine further defined silver-gold mineralization between the 465 and 545 metre levels. Significant intercepts were recorded on the Veta Madre, Contact vein and hanging wall (Alto) veins, in particular demonstrating the continuity of mineralization on the newly identified Alto 4 vein. In addition, the overall drilling program defined the south-east orientation of silver-gold mineralization to depth, becoming a potential area for exploration in the near future. Exploration drilling at Santa Margarita was focused on defining Veta Madre and Santa Margarita veins between the 300 and 454 metre levels, returning positive intersections.

A thorough assessment of the Cata shaft, the main production shaft, is being conducted in order to ensure a safe skipping operation. Any maintenance activities at Cata shaft will have a minor impact on productivity as they will be harmonized with ongoing operations.

The Cata processing plant was upgraded with the installation of a new filter press, new ball mill liners, and improvements to the thickener tank. As a result, concentrate quality has been improved and electricity consumption has been reduced. The construction of the 13th dyke lift at the Guanajuato tailings dam was completed and certified and survey reference points were installed over various dykes to monitor the stability of the tailings dam.

Topia Mine

For the third quarter, 16,362 tonnes were processed at Topia, up 12% compared to the same period in 2012, at grades of 358g/t Ag, 0.55g/t Au, 1.96% lead ("Pb") and 2.73% zinc ("Zn"). Metal production included 170,254 Ag oz, 164 Au oz, 300 Pb tonnes, and 411 Zn tonnes, to a record 227,706 Ag eq oz, which is 26% up over the same period in 2012. Plant metallurgical performance was steady with metal recoveries of 90.4% for silver, 56.4% for gold, 93.5% for lead, and 91.8% for zinc.

Topia Q3 Operations Summary Q3 2013   Q3 2012   Change   Q3 2013   Q2 2013   Change  
Ore processed (tonnes milled) 16,362   14,593   12 % 16,362   14,652   12 %
Silver equivalent ounce production 1 227,706   180,627   26 % 227,706   213,287   7 %
Silver ounce production 170,254   131,865   29 % 170,254   160,276   6 %
Gold ounce production 164   149   10 % 164   153   7 %
Lead production (tonnes) 300   226   33 % 300   243   24 %
Zinc production (tonnes) 411   369   11 % 411   411   0 %
                         
Ag grade (g/t) 358   316   13 % 358   376   (5 )%
Au grade (g/t) 0.55   0.55   1 % 0.55   0.57   (3 )%
Ag recovery (%) 90.4 % 89.0 % 2 % 90.4 % 90.6 % 0 %
Au recovery (%) 56.4 % 57.8 % (2 )% 56.4 % 57.0 % (1 )%
Total underground development (m) 1,799   2,459   (27 )% 1,799   2,254   (20 )%
Underground Diamond drilling (m) 619   649   (5 )% 619   481   29 %
   
1 Silver equivalent ounces for 2013 were established in November 2012 using prices of US$28 per oz, US$1,680 per oz (60:1 ratio), US$0.85 per lb and US$0.85 per lb for silver, gold, lead & zinc, respectively, and applied to the recovered metal content of the concentrates that were produced by the two operations. For consistency, these prices will be used for the balance of 2013.

Metal production for the quarter was principally derived from the Durangueno mine and increased production at the Argentina mine, followed by production from the El Rosario, 1522 and Hormiguera mines. Silver grades were up 13% compared to the same period in 2012, however, grades were lower than anticipated for the quarter due to the irregularity of ore vein formations, resulting in higher dilution. 

Underground development at Topia in the quarter was down 27%, to 1,799 metres, compared to the same period in 2012 due to a focus on production and grade control at the 1522, San Gregorio, La Prieta, Argentina and Durangueno mines. Exploration drilling at Topia totaled 619 metres, down 5% compared to the same period in 2012.

The processing plant is being upgraded by the installation of a new cone crusher and extensive metallurgical tests are being carried out to improve recoveries. In addition, the metallurgical investigation laboratory was reconditioned and upgraded equipment was installed.

San Ignacio Project

On October 8, subsequent to quarter end, the Company announced that it had received the Environmental Impact Assessment Permit for San Ignacio. The EIA permit allows for the initiation of site preparation and underground development. The construction of a two-kilometre road has commenced to provide access to the new portal for ramp and mine development. Production is anticipated to commence in early 2014. See "Great Panther Silver Receives Final Permit for San Ignacio" for further details.

El Horcon Project

An internal resource estimate and preliminary economic assessment were prepared in the third quarter based upon the 2,156 metre, 24 hole surface drill program completed during the second quarter. The drill program tested 650 metres of strike length on the Diamantillo vein and various splays and nearby parallel structures and veins. The Company is considering the results in light of current metal prices in order to decide whether to proceed with the project at this time.

Outlook

With Year-to-date production totaling 2,076,963 silver equivalent ounces, the Company expects to exceed its guidance of 2.4 to 2.5 million silver equivalent ounces for fiscal 2013.

Although precious metals prices recovered slightly in the third quarter from their lows at the end of June, the Company continues to focus on improving and strengthening the operational efficiency of its mines. As a result of these efforts, cash costs are expected to be significantly lower in the second half of the year, as compared to the first half.

Road construction and site preparation are underway at San Ignacio and will set the stage for ramp and mine development that will continue into the first quarter of 2014. Production from San Ignacio, commencing at about 100 tonnes per day and increasing to about 250 by the end of 2014, will be trucked to and processed at the Company's Cata plant at the main Guanajuato Mine Complex, 22 kilometres away. The ability to increase throughput at Guanajuato with no further capital expenditures at the plant, will have an immediate and positive impact on cash costs.

ABOUT GREAT PANTHER

Great Panther Silver Limited is a profitable, primary silver mining and exploration company listed on the Toronto Stock Exchange trading under the symbol GPR, and on the NYSE MKT trading under the symbol GPL. The Company's current activities are focused on the mining of precious metals from its two wholly-owned operating mines in Mexico, Topia and Guanajuato. Great Panther is also in the process of developing its San Ignacio Project and has two exploration projects, El Horcon and Santa Rosa.

For further information, please visit the Company's website at www.greatpanther.com.

This news release contains forward-looking statements within the meaning of the United States Private Securities Litigation Reform Act of 1995 and forward-looking information within the meaning of the Securities Act (Ontario) (together, "forward-looking statements"). Such forward-looking statements may include but are not limited to the Company's plans for production at its Guanajuato and Topia Mines in Mexico, exploring its other properties in Mexico, the overall economic potential of its properties, the availability of adequate financing and involve known and unknown risks, uncertainties and other factors which may cause the actual results, performance or achievements expressed or implied by such forward-looking statements to be materially different. Such factors include, among others, risks and uncertainties relating to potential political risks involving the Company's operations in a foreign jurisdiction, uncertainty of production and cost estimates and the potential for unexpected costs and expenses, physical risks inherent in mining operations, currency fluctuations, fluctuations in the price of silver, gold and base metals, completion of economic evaluations, changes in project parameters as plans continue to be refined, the inability or failure to obtain adequate financing on a timely basis, and other risks and uncertainties, including those described in the Company's Annual Information Form for the year ended December 31, 2012 and Material Change Reports filed with the Canadian Securities Administrators available at www.sedar.com, and reports on Form 40-F and Form 6-K filed with the Securities and Exchange Commission and available at www.sec.gov.



Great Panther Silver Limited
Robert Archer
President & Chief Executive Officer
1-888-355-1766
or
Great Panther Silver Limited
Rhonda Bennetto
Vice President Corporate Communications
1-888-355-1766
info@greatpanther.com
www.greatpanther.com
Data and Statistics for these countries : Argentina | Mexico | All
Gold and Silver Prices for these countries : Argentina | Mexico | All

Great Panther Silver Limited

PRODUCER
CODE : GPR.TO
Follow and Invest
Add to watch list Add to your portfolio Add or edit a note
Add Alert Add to Watchlists Add to Portfolio Add Note
ProfileMarket
Indicators
VALUE :
Projects & res.
Press
releases
Annual
report
RISK :
Asset profile
Contact Cpy

Great Panther Silver is a silver producing company based in Canada.

Great Panther Silver produces silver, gold, lead and zinc in Mexico, and holds various exploration projects in Mexico.

Its main assets in production are TOPIA MINE and GUANAJUATO MINES in Mexico and its main exploration properties are MAPIMI (KM 66), SAN ANTONIO (CHIHUAHUA), SAN IGNIACIO and LA SIERRA in Mexico.

Great Panther Silver is listed in Canada, in Germany and in United States of America. Its market capitalisation is CA$ 181.3 millions as of today (US$ 145.0 millions, € 127.0 millions).

Its stock quote reached its highest recent level on August 29, 1997 at CA$ 9.00, and its lowest recent point on September 05, 2003 at CA$ 0.10.

Great Panther Silver has 166 370 000 shares outstanding.

Your feedback is appreciated, please leave a comment or rate this article.
Rate : Average note :0 (0 vote) View Top rated
 
In the News and Medias of Great Panther Silver Limited
7/22/2009Mining in Mexico with Great Panther
7/16/2009Mining in Mexico with Great Panther
8/1/2007Jay Taylor Reaffirms his "A" Progress Rating Of Great Panthe...
6/20/2006Presentation by Sean Rahkimov
4/18/2006Corporate analysis
Annual reports of Great Panther Silver Limited
2008 Annual report
Financings of Great Panther Silver Limited
7/7/2016Great Panther Silver increases previously announced bought d...
7/6/2016arranges US$20 million bought deal financing
3/24/2011Announces $21 Million Bought Deal Financing
3/13/2011EXTINGUISHES LONG TERM DEBT
10/27/2009Announces $10 Million Equity Offering
1/24/2009GPR - GREAT PANTHER CLOSES PRIVATE PLACEMENT
4/10/2008Reprices Out-Of-The-Money Warrants And Options
1/4/2008Sees 100% Exercise Of "J" Warrants
11/30/2007100% Exercise of Great Panther "I" Warrants
Nominations of Great Panther Silver Limited
8/7/2013Appoints New Director
5/14/2013Appoints New Director and Strengthens Senior Management Team...
1/24/2013Announces Resignation of Director
4/5/2012Appoints Rhonda Bennetto as Vice President Corporate Communi...
2/6/2012Appoints Independent Chairman
10/14/2011(Guanajuato Mines)Reports Third Quarter Production and Appoints New Mine Manag...
10/14/2011(Guanajuato Mines)Reports Third Quarter Production and Appoints New Mine Manag...
5/3/2011Appoints Martin Carsky Executive Vice President & Chief Fina...
3/17/2011ADDS MINING/METALLURGICAL EXPERTISE TO BOARD
7/3/2008Appoints Former Mexican Senior Trade Commissioner As Vice Pr...
3/20/2008Appoints Financial & Metallurgical Professionals To Ad...
11/26/2007Appoints New Management at Guanajuato Mine
Financials of Great Panther Silver Limited
8/4/2016Reports Second Quarter 2016 Financial Results
7/25/2016to announce second quarter 2016 financial results on August ...
7/14/2016reports second quarter
5/5/2016First Quarter 2016 Financial Results Webcast and Conf
5/5/2016reports first quarter
11/5/2015Reports Third Quarter 2015 Financial Results
10/21/2015to Announce Third Quarter Consolidated Financial Results on ...
11/6/2013Reports Lower Costs and Improved Operating Margins for the T...
8/16/2013Second Quarter 2013 Financial Results Webcast Replay
8/7/2013Reports Second Quarter 2013 Financial Results
5/8/2013Reports First Quarter 2013 Financial Results
3/13/2013Reports Fiscal Year 2012 Financial Results
11/14/2012Postpones Release of Third Quarter 2012 Financial Results fo...
5/14/2012Reports First Quarter 2012 Financial Results
3/13/2012Reports 37% Increase in Revenues to $57.8 Million and $11.5 ...
10/14/2011Reports Third Quarter Production and Appoints New Mine Manag...
8/11/2011Reports Second Quarter Results
6/14/2011Reports Record Quarterly Net Income of $7 Million
4/18/2011REPORTS FIRST QUARTER PRODUCTION; SILVER INCREASES BY 15%, G...
4/7/2011FILES AMENDMENT TO ITS ANNUAL INFORMATION FORM WITH NO CHANG...
3/16/2011REPORTS ANNUAL NET PROFIT OF $5 MILLION
1/11/2010 Exceeds Production Target for 2009 With Record Fourth Quart...
10/22/2007Doubles Production in Third Quarter 2007
Project news of Great Panther Silver Limited
7/18/2016(Topia Mine)Resumes Full Operation
12/23/2015Great Panther Silver releases drill results for Guadalupe de...
7/9/2015Great Panther Silver updates mineral resources at Topia mine
1/14/2014Reports a 19% Increase in Metal Production in 2013
12/16/2013Announces Results of San Ignacio Surface Drilling
12/3/2013s Mineral Resource Estimates at the Guanajuato Mine Complex
10/21/2013Moves Ahead with El Horcon Project
10/8/2013Receives Final Permit for San Ignacio, Initiates Site Prepar...
1/14/2013(Topia Mine)s Mineral Resources at Topia Mine
5/9/2012s Mineral Resource Estimates at the Guanajuato Mine Complex ...
12/15/2011(Guanajuato Mines)Eliminates Backlog of Concentrate Inventory at Guanajuato an...
12/5/2011(San Igniacio)s Drilling Results for San Ignacio Property, Guanajuato; Gra...
11/30/2011(Guanajuato Mines)Confirms Continuity of Santa Margarita Gold-Silver Veins and...
10/13/2011(San Igniacio)Reports Initial Mineral Resource Estimate at San Ignacio Pro...
8/30/2011(Guanajuato Mines)Extends High Grade Silver-Gold Mineralization and Discovers ...
8/18/2011(Guanajuato Mines)Commences Shipment of Silver-Gold Concentrates From Guanajua...
7/21/2011(La Sierra)Purchases New Silver-Gold Project in Guanajuato
5/25/2011(San Igniacio)POSTPONES RESOURCE ESTIMATE FOR SAN IGNACIO MINE PROPERTY, G...
3/13/2011(Topia Mine)Increases Mineral Resources at the Topia Mine
1/27/2011(Guanajuato Mines)Extends Guanajuatito Silver-Gold Zones to Depth
7/22/2009(Topia Mine)Increases Resources At The Topia Mine
1/26/2009(Topia Mine)GPR - GREAT PANTHER REPORTS NEW HIGH GRADE SILVER ALONG THE ...
11/26/2008(Topia Mine)Samples 95 Metres Of 1,867G/T Silver, 1.00G/T Gold, 2.67% Le...
9/9/2008(Guanajuato Mines)ACQUIRES TWO NEW UNDERGROUND LOADERSTO BOOST PRODUCTION OF T...
7/14/2008(Guanajuato Mines)Produces Another Record of 436,072 Ag Eq Oz in Q2
6/3/2008(Topia Mine)Extends High Grade Argentina Veins At The Topia Mine
5/27/2008(Mapimi (km 66))Discovers Molybdenum-Rich Skarn and Carbonate Replacement St...
4/28/2008 PRODUCES FROM HIGH GRADE SILVER-GOLD ZONE AT GUANAJUATO; GR...
3/25/2008(Guanajuato Mines)Extends Strike Length Of Deep Mineralization At Guanajuato M...
2/26/2008(Topia Mine) Extends High Grade Silver-Gold To 600 Metre Depth At Guanaj...
2/20/2008(Topia Mine)Extends Silver-Gold-Lead-Zinc Veins At The Topia Mine
11/29/2007(Guanajuato Mines)Confirms Depth Continuity of High Grade Mineralization at Gu...
11/13/2007(San Antonio) Diamond Drilling Commences on the San Antonio Project, Chih...
10/30/2007(Guanajuato Mines) EXPANDS NEAR-SURFACE SILVER-GOLD ZONES AT GUANAJUATO
5/10/2007Releases Additional Drilling Results For Mapimi Silver-Lead-...
4/11/2007(Guanajuato Mines)Doubles Production At Guanajuato In First Quarter; Inc...
4/5/2007(Topia Mine)Extends Gold-rich Zones with Surface Drilling at Topia Mine
Corporate news of Great Panther Silver Limited
7/27/2016Coverage Initiated on Silver Stocks First Majestic Silver, S...
7/25/2016Great Panther Silver to announce second quarter 2016 financi...
7/15/2016Great Panther Silver Resumes Full Operation at Topia Mine
7/14/2016Great Panther Silver Reports Second Quarter 2016 Production ...
7/13/2016Great Panther Silver reports fatal accident at its Topia Min...
7/12/2016Great Panther Silver completes previously announced US$29.9 ...
7/6/2016Great Panther Silver arranges US$20 million bought deal fina...
6/23/2016Great Panther Silver reports fatality at Guanajuato
6/10/2016Great Panther Silver Reports Annual General and Special Meet...
5/5/2016Great Panther Silver reports first quarter 2016 financial re...
4/25/2016Great Panther Silver to Announce First Quarter 2016 Financia...
4/21/2016Great Panther Announces At-the-market Offering Of Up To Us$1...
4/21/2016Great Panther Silver Reports First Quarter 2016 Production R...
4/13/2016Great Panther Silver reports first quarter 2016 production r...
3/4/2016Great Panther reports 4Q loss
1/19/2016Great Panther Silver Reports 30% Increase In Metal Productio...
1/15/2016Great Panther resumes full operations at its Guanajuato Mine...
11/5/2015Great Panther Silver Reports Third Quarter 2015 Financial Re...
10/21/2015Great Panther Silver to Announce Third Quarter Consolidated ...
10/14/2015Great Panther Silver Reports Third Quarter 2015 Production R...
8/28/2015Great Panther Board Completes Review of Director Election St...
8/5/2015Great Panther Silver Reports Second Quarter 2015 Financial R...
7/30/2015Great Panther Silver to Release Second Quarter Financial Res...
7/14/2015Great Panther Silver Reports Second Quarter 2015 Production ...
7/9/2015(Topia Mine)s mineral resources at Topia mine
7/2/2015Great Panther Silver Provides Update on 2015 Drilling Progra...
4/15/2015Great Panther Silver Reports First Quarter 2015 Production R...
4/13/2015Cangold and Great Panther Silver Execute Definitive Arrangem...
4/13/2015Great Panther And Cangold Execute Definitive Arrangement Agr...
3/25/2015Why GoPro Will Trade Lower Until 'Capitulation'
3/15/2015Great Panther Silver to Acquire Cangold
3/5/2015Great Panther reports 4Q loss
3/4/2015Great Panther Silver reports fiscal year 2014 financial resu...
12/18/2013Season's Greetings from Great Panther Silver
10/10/2013Achieves Several Production Records in Third Quarter 2013
7/25/2013Announces 2013 Second Quarter Financial Results Release Date...
7/11/2013Reports Second Quarter 2013 Production
6/28/2013Reports Annual and Special Meeting Results
5/24/2013Adopts Advance Notice Policy
4/15/2013Reports First Quarter 2013 Production
3/14/2013Video Library Updates
2/5/2013Intersects High Grade Silver-Gold Mineralization and Discove...
1/16/2013Reports Improved Fourth Quarter and Fiscal 2012 Production R...
11/5/2012Announces 2012 Third Quarter Financial Results Release Date ...
10/10/2012Reports Third Quarter 2012 Production Results
9/18/2012Google Earth Virtual Tour
9/5/2012Purchases El Horcon Silver-Gold Project
8/21/2012Purchases Surface Rights for San Ignacio Project
8/2/2012Announces 2012 Second Quarter Financial Results Release Date...
7/12/2012Reports Second Quarter 2012 Production Results
6/28/2012Reports Annual and Special Meeting Results
5/8/2012Announces 2012 First Quarter Financial Results Release Date ...
4/16/2012Reports First Quarter 2012 Production
3/5/2012Announces 2011 Fourth Quarter And Year-End Financial Results...
1/17/2012Reports Improved Fourth Quarter Production
8/4/2011Announces Second Quarter 2011 Financial Results Release Date...
7/12/2011Reports Second Quarter Production
6/23/2011Set to Join the Russell Global Index
4/12/2011Closes $24 Million Bought Deal Financing
4/5/2011Receives Recognition for Corporate Social Responsibility
2/7/2011Secures US Listing on NYSE Amex
8/17/2010GPR - GREAT PANTHER SILVER REPORTS INCREASED REVENUE, EARNIN...
10/1/2009GPR - GREAT PANTHER DISCOVERS AND DEVELOPS 3 NEW ZONES AT GU...
8/14/2009Continues Production And Earnings Growth, Reduces Operating ...
7/7/2009continues record-setting growth with Q2 production
6/19/2009Signs New Sales Contracts For Topia Concentrates
2/18/2009Anticipates 20% Increase In Silver Production In 2009
12/10/2008 ANNOUNCES $2,700,000 FINANCING
11/15/2008LOWERS OPERATING COSTS TO KEEP MINES PROFITABLE
8/13/2008GPR - GREAT PANTHER ACHIEVES 488% INCREASE IN EARNING...
8/11/2008 INCREASES RESOURCES AT THE TOPIA MINE
6/23/2008Exposes Excellent Grades At Topia Ag-Pb-Zn Mine
6/3/2008Celebrates Renaissance Of 400+Year-Old Silver Mine
5/17/2008GRANTS STOCK OPTIONS
5/12/2008ANNOUNCES Q1 2008 RESULTS, ACHIEVES 55% INCREASE IN REVEN...
5/6/2008Drills 15.94 Metres @ 1,305G/T Silver And 4.60G/T Gold And D...
4/8/2008's Record Output Continues With 431,639 Ag Eq Oz In...
4/1/2008Announces Fy2007 Results, Achieves First Mining Profit...
3/19/2008Receives Upgraded Mineral Resource Estimate for La Gloria Zo...
3/8/2008ADOPTS SHAREHOLDER RIGHTS PLAN
1/28/2008SETS NEW PRODUCTION RECORDS TO END 2007
1/15/2008Provides Update On Resource Estimates
11/1/2007 COMMENCES PHASE II DRILLING PROGRAM ON MAPIMI SILVER-LEAD-Z...
9/19/2007Commences Deep Drilling Program at Guanajuato; Provides Prod...
9/14/2007OUTLINES EXPANSIVE GEOPHYSICAL ANOMALIES AND UPDATES PHASE 1...
9/12/2007Adds New COO To Management Team
8/28/2007'S FUNDS ARE SAFE
8/15/2007RELEASES Q2 RESULTS, REPORTS RECORD SALES MARGIN FROM MINING...
7/13/2007Closes $4.05 Million Convertible Loan Notes Placement
7/9/2007Discovers New Silver-Gold Zones At Guanajuato
7/4/2007To Raise $4.05 Million Through Convertible Loan Notes With T...
6/16/2007Dissident Members Abandon Lawsuit Against Cooperativa
5/28/2007Adds New Cfo To Management Team
4/30/2007Releases Results From First Year as Silver Producer
4/17/2007Confirms Grades, Completes Airborne Geophysical Survey On Ma...
4/4/2007Announces Delay in Filing Annual Financial Statements
3/1/2007UNDERGROUND DRILLING EXTENDS HIGH GRADE SILVER-GOLD-LEA...
4/4/2006Re-discovers spanish riches at Guanajuato
Comments closed
 
Latest comment posted for this article
Be the first to comment
Add your comment
TORONTO (GPR.TO)FRANKFURT (G3U.F)
1.09+0.00%0.102+0.00%
TORONTO
CA$ 1.09
10/14 10:30 -
0%
Prev close Open
1.09 1.09
Low High
1.09 1.09
Year l/h YTD var.
 -  -
52 week l/h 52 week var.
- -  1.09 -%
Volume 1 month var.
0 -%
24hGold TrendPower© : 9
Produces Gold - Lead - Silver - Zinc
Develops
Explores for Gold - Molybdenum - Silver
 
 
 
Analyse
Interactive chart Add to compare
Interactive
chart
Print Compare Export
Last updated on : 12/27/2010
You must be logged in to use the porfolio and watchlists (free)
Top Newsreleases
MOST READ
Annual variation
DateVariationHighLow
2022240.63%1.520.12
2021-70.64%1.470.30
202065.15%1.420.32
 
5 years chart
 
3 months chart
 
3 months volume chart
 
 
Mining Company News
Plymouth Minerals LTDPLH.AX
Plymouth Minerals Intersects Further High Grade Potash in Drilling at Banio Potash Project - Plannin
AU$ 0.12-8.00%Trend Power :
Santos(Ngas-Oil)STO.AX
announces expected non-cash impairment
AU$ 7.75+0.52%Trend Power :
Oceana Gold(Au)OGC.AX
RELEASES NEW TECHNICAL REPORT FOR THE HAILE GOLD MINE
AU$ 2.20+0.00%Trend Power :
Western Areas NL(Au-Ni-Pl)WSA.AX
Advance Notice - Full Year Results Conference Call
AU$ 3.86+0.00%Trend Power :
Canadian Zinc(Ag-Au-Cu)CZN.TO
Reports Financial Results for Q2 and Provides Project Updates
CA$ 0.12+4.55%Trend Power :
Stornoway Diamond(Gems-Au-Ur)SWY.TO
Second Quarter Results
CA$ 0.02+100.00%Trend Power :
McEwen Mining(Cu-Le-Zn)MUX
TO ACQUIRE BLACK FOX FROM PRIMERO=C2=A0
US$ 11.11+2.21%Trend Power :
Rentech(Coal-Ngas)RTK
Rentech Announces Results for Second Quarter 2017
US$ 0.20-12.28%Trend Power :
KEFIKEFI.L
Reduced Funding Requirement
GBX 0.55-0.90%Trend Power :
Lupaka Gold Corp.LPK.V
Lupaka Gold Receives First Tranche Under Amended Invicta Financing Agreement
CA$ 0.06-8.33%Trend Power :
Imperial(Ag-Au-Cu)III.TO
Closes Bridge Loan Financing
CA$ 2.47+3.78%Trend Power :
Guyana Goldfields(Cu-Zn-Pa)GUY.TO
Reports Second Quarter 2017 Results and Maintains Production Guidance
CA$ 1.84+0.00%Trend Power :
Lundin Mining(Ag-Au-Cu)LUN.TO
d Share Capital and Voting Rights for Lundin Mining
CA$ 15.25-3.42%Trend Power :
Canarc Res.(Au)CCM.TO
Canarc Reports High Grade Gold in Surface Rock Samples at Fondaway Canyon, Nevada
CA$ 0.24+0.00%Trend Power :
Havilah(Cu-Le-Zn)HAV.AX
Q A April 2017 Quarterly Report
AU$ 0.19+0.00%Trend Power :
Uranium Res.(Ur)URRE
Commences Lithium Exploration Drilling at the Columbus Basin Project
US$ 6.80-2.86%Trend Power :
Platinum Group Metals(Au-Cu-Gems)PTM.TO
Platinum Group Metals Ltd. Operational and Strategic Process ...
CA$ 1.79-3.76%Trend Power :
Devon Energy(Ngas-Oil)DVN
Announces $340 Million of Non-Core Asset Sales
US$ 52.57+0.84%Trend Power :
Precision Drilling(Oil)PD-UN.TO
Announces 2017Second Quarter Financial Results
CA$ 8.66-0.35%Trend Power :
Terramin(Ag-Au-Cu)TZN.AX
2nd Quarter Report
AU$ 0.04+0.00%Trend Power :