RNS Number : 9398G
Ormonde Mining PLC
02 June 2017
 

 

This announcement contains inside information

 

Ormonde Mining plc

("Ormonde" or "the Company")

 

Barruecopardo Tungsten Project

Construction Update

 

 

The Board of Ormonde is pleased to provide an update of construction activities for the Barruecopardo Project in Salamanca, Spain ("Barruecopardo" or the "Project").

 

Following a period of review of the construction schedule, the Board of the Project company, Saloro SLU ("Saloro"), has authorised the issuance of outstanding approvals on various equipment and plant construction contracts, thus advancing the Project into an accelerated construction and implementation phase, with an updated schedule allowing for mine commissioning in the third quarter of 2018. These approvals come against a backdrop of rising tungsten APT prices, and increasing demand for tungsten concentrates, which will serve to de-risk the Project during the commissioning stage.

 

As the Project now moves into its most critical stage, in order to focus attention on implementation on time and within budget, Steve Nicol, Ormonde's current Managing Director, will relinquish his role at Ormonde in order to focus full time on his responsibilities as Managing Director of Saloro and Project Manager for Barruecopardo.  Therefore immediately following the upcoming Ormonde AGM, Steve will step down from his position as Ormonde Managing Director. Mike Donoghue, current Chairman, will act as interim Managing Director from that point.  

 

Michael Donoghue, Ormonde's Chairman, commented:

 

"The Company, together with its Project partner, have always recognised the importance to the Company's shareholders, and to Project stakeholders, of ensuring that the Barruecopardo Project comes online into a strengthening tungsten price environment, thus not exposing the Project or its shareholders to undue risk during the critical commissioning and start-up phases.  Against a backdrop of rising tungsten prices, and increasing demand for tungsten concentrates, the partners believe the time is now right to ensure that the construction of the Project progresses at full speed towards commissioning of a new mine at Barruecopardo, now targeted for the third quarter of 2018.

 

Steve Nicol, who has diligently guided the Barruecopardo Project over the past nine years through all the preparations leading up to this stage, will step down from the Board of Ormonde, at our next AGM, in order to focus on the implementation of this flagship project.  The Project partners consider this step to be of fundamental importance in reducing implementation risk and successfully bringing Barruecopardo into first production on time and on budget.

 

On behalf of the board, I wish to thank Steve for the major contribution that he has made to Ormonde, and particularly his efforts in taking the Barruecopardo Project from brownfield site into its current development stage.  Ormonde looks forward to continuing to work with Steve and the Saloro team as we advance the Project to production.

 

 

 

 

 

Detail

 

Construction Schedule

The Project partners have recognised the importance to the Company's shareholders, and to Project stakeholders, of reducing Project risk and optimising the likelihood of Project success through adopting a policy of continual assessment of the date for commissioning of the mine against the prevailing economic conditions, and adjusting the project's construction schedule accordingly. This has led to the construction schedule being extended on two occasions during 2016.

 

Following recent assessments, and against a backdrop of an improving tungsten market and general economic forecasts, the partners believe it is timely and advantageous to commit to the final stages of the equipment supply and construction contracts. Consequently, the company has authorised the necessary approvals to allow for construction and implementation of the Project, which will see the Barruecopardo entering commissioning in the third quarter of 2018.

 

Saloro has also agreed to certain amendments to be reflected in the debt facility agreement (as yet undrawn) for the Project, to align with the approved construction schedule. Ormonde has agreed that, subject to the latest development schedule being implemented as planned, the remaining component of the equity investment, of circa ?16 million, will be drawn on a pro rata basis with the debt during the development period, with any residual equity amounts being drawn on commissioning.

 

 

Metal Prices

APT prices have gradually been moving in an upwards direction since touching a low of $162 per metric tonne unit ("mtu") in January 2016, following a period which saw significant commodity price reductions associated with a general weakening of the commodity markets. In the case of tungsten this trend was magnified as a result of a significant drop-off in usage of tungsten in the energy sector, particularly relating to a significant reduction in US oil related drilling activity.  However, more recently there has been a reversal of this trend, with many indicators pointing towards a sustained increase in the tungsten price into the future.

 

These indicators include a more than doubling of the US oil rig count, improvements in economic outlooks in Europe and the US and supply shortages of tungsten concentrates outside of China caused, in part, by underperformance from some western world tungsten producers.

 

Currently the APT price is $220-225/mtu which represents a circa 37% increase since the January 2016 low, with the period since July 2016 seeing a modest but consistent uptrend in price. The medium to longer term outlook now looks increasingly positive.

 

Enquiries to:

 

Ormonde Mining plc

Steve Nicol, Managing Director Tel: +353 (0)1 8253570

 

Capital M Consultants

Simon Rothschild Mob: +44 (0)7703 167065

 

Murray Consultants

Mark Brennock  Tel: +353 (0)1 4980300 Mob: +353 (0)87 2335923

 

Davy (Nomad, ESM Adviser and Joint Broker)

John Frain Tel: +353 (0)1 679 6363

 

SP Angel Corporate Finance LLP (Joint Broker)

Ewan Leggat Tel: +44 (0)20 3 470 0470

 

For more information please visit www.ormondemining.com.

 


This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCDDGDLRSGBGRB

==

Ormonde Mining Email Alerts
Brought to you by Brighter IR

To stop receiving these alerts or change your preferences, click here to log in

.
Data and Statistics for these countries : China | Spain | All
Gold and Silver Prices for these countries : China | Spain | All

Ormonde Mining PLC

DEVELOPMENT STAGE
CODE : ORM.L
ISIN : IE0006627891
Follow and Invest
Add to watch list Add to your portfolio Add or edit a note
Add Alert Add to Watchlists Add to Portfolio Add Note
ProfileMarket
Indicators
VALUE :
Projects & res.
Press
releases
Annual
report
RISK :
Asset profile
Contact Cpy

Ormonde Mining is a zinc and lead exploration company based in Ireland.

Ormonde Mining develops zinc, lead, copper, gold, silver and tungsten in Spain, and holds various exploration projects in Spain.

Its main assets in development are LA ZARZA and BARRUECOPARDO in Spain and its main exploration property is SALAMANCA & ZAMORA in Spain.

Ormonde Mining is listed in United Kingdom. Its market capitalisation is GBX 3.3 millions as of today (US$ 4.0 millions, € 3.5 millions).

Its stock quote reached its highest recent level on September 10, 2004 at GBX 9.97, and its lowest recent point on May 26, 2023 at GBX 0.01.

Ormonde Mining has 472 507 482 shares outstanding.

Your feedback is appreciated, please leave a comment or rate this article.
Rate : Average note :0 (0 vote) View Top rated
 
Project news of Ormonde Mining PLC
3/16/2011(Salamanca & Zamora)Salamanca-Zamora Gold Exploration Update
3/2/2011(Barruecopardo)Barruecopardo Drilling Progress
5/27/2010(Barruecopardo)Doubling and major upgrade of tungsten Mineral Resource
10/27/2009(La Zarza)JV with Antofagasta on La Zarza
2/19/2010(La Zarza)Update on activities in Joint Venture with Antofagasta on La...
7/13/2009(La Zarza)Exploration deal with Major on La Zarza
7/15/2008(Barruecopardo)Issue of equity to fund Barruecopardo Tungsten Project
6/17/2008(Barruecopardo)New resource estimate trebles the size of the Barruecopardo ...
4/1/2008(Barruecopardo) Best drilling intersection to-date from the Barruecopardo T...
2/26/2008(Barruecopardo)Further drilling success at Salamanca Tungsten ProjectConten...
1/24/2008(Barruecopardo) Tungsten Resource & Preliminary Economic Evaluation
12/6/2007 Tungsten Drilling ResultsContent-class: urn:content-classes...
11/8/2007(La Zarza) Reports Thick zinc intersections from La Zarza drilling
9/27/2007Tungsten Drilling Results
8/7/2007Reports high grade gold drilling intercepts at its Salamanca...
5/10/2007reports high-grade tungsten in Salamanca drilling
5/2/2006(Salamanca & Zamora)extends new Salamanca gold zone to 2,5 km
Corporate news of Ormonde Mining PLC
9/16/2016Notification of Interest
6/28/2016Declaration of Urgent Occupation - Approved
6/28/2016Publication of Annual Report
6/17/2016Aurum Mining PLC - Convertible Loan and Trading Update
6/16/2016Final Results 2015
6/15/2016Barruecopardo Update
6/7/2016Barruecopardo Drilling Results
5/25/2016Drilling Update
4/15/2015Placing
3/24/2015Directorate Change
11/23/2014Barruecopardo - Granting of Mining Concession
4/10/2013Hemscott News Alert - Ormonde Mining PLC
2/22/2013Hemscott News Alert - Ormonde Mining PLC
2/4/2013Hemscott News Alert - Ormonde Mining PLC
1/23/2013Hemscott News Alert - Ormonde Mining PLC
11/9/2012Hemscott News Alert - Ormonde Mining PLC
10/15/2012Hemscott News Alert - Ormonde Mining PLC
9/17/2012Hemscott News Alert - Ormonde Mining PLC
7/4/2012Hemscott News Alert - Ormonde Mining PLC
6/6/2012Hemscott News Alert - Ormonde Mining PLC
3/28/2012Hemscott News Alert - Ormonde Mining PLC
3/12/2012Hemscott News Alert - Ormonde Mining PLC
2/28/2012Hemscott News Alert - Ormonde Mining PLC
2/13/2012Hemscott News Alert - Ormonde Mining PLC
12/6/2011Hemscott News Alert - Ormonde Mining PLC
9/29/2011Hemscott News Alert - Ormonde Mining PLC
5/16/2011Hemscott News Alert - Ormonde Mining PLC
4/14/2011Hemscott News Alert - Ormonde Mining PLC
6/30/2010Issue of Equity
4/12/2010Signs Option Agreement over Tharsis Project, Spain
9/28/2009Interim Results
7/20/2009Issue of Equity
5/26/2009Preliminary Results 2008
9/22/2008Interim Results
6/12/2008AGM operational update
5/13/2008Final results for the year ending 31 December 2007
5/12/2008 Related tungsten news
5/9/2008Ormonde Mining Announcement
4/16/2008 Steve Nicol joins Ormonde BoardContent-class: urn:content-c...
11/13/2007Multi-vein nature of Spanish tungsten project
11/1/2007 Wide gold intersection in Salamanca
7/12/2007Consolidates 100% interest in La Zarza Copper-Gold Project
7/4/2007Upgrades Barruecopardo Tungsten Prospec
5/16/2007Final Results for the year ended 31 December 2006
Comments closed
 
Latest comment posted for this article
Be the first to comment
Add your comment
LSE (ORM.L)
0.007-98.83%
LSE
GBX 0.007
05/26 09:00 -0.590
-98.83%
Prev close Open
0.600 0.007
Low High
0.007 0.007
Year l/h YTD var.
 -  -
52 week l/h 52 week var.
0.007 -  0.007 -98.83%
Volume 1 month var.
0 -%
24hGold TrendPower© : -15
Produces
Develops Copper - Gold - Lead - Silver - Tungsten - Zinc
Explores for Gold
 
 
 
Analyse
Interactive chart Add to compare
Interactive
chart
Print Compare Export
Last updated on : 6/7/2010
You must be logged in to use the porfolio and watchlists (free)
Top Newsreleases
MOST READ
Annual variation
DateVariationHighLow
20240.00%
2023-99.00%0.840.01
2022-22.22%1.100.41
2021-48.57%3.400.73
2020-32.69%2.740.42
 
5 years chart
 
3 months chart
 
3 months volume chart
 
 
Mining Company News
Plymouth Minerals LTDPLH.AX
Plymouth Minerals Intersects Further High Grade Potash in Drilling at Banio Potash Project - Plannin
AU$ 0.12-8.00%Trend Power :
Santos(Ngas-Oil)STO.AX
announces expected non-cash impairment
AU$ 7.76-1.52%Trend Power :
Oceana Gold(Au)OGC.AX
RELEASES NEW TECHNICAL REPORT FOR THE HAILE GOLD MINE
AU$ 2.20+0.00%Trend Power :
Western Areas NL(Au-Ni-Pl)WSA.AX
Advance Notice - Full Year Results Conference Call
AU$ 3.86+0.00%Trend Power :
Canadian Zinc(Ag-Au-Cu)CZN.TO
Reports Financial Results for Q2 and Provides Project Updates
CA$ 0.12+4.55%Trend Power :
Stornoway Diamond(Gems-Au-Ur)SWY.TO
Second Quarter Results
CA$ 0.02+100.00%Trend Power :
McEwen Mining(Cu-Le-Zn)MUX
TO ACQUIRE BLACK FOX FROM PRIMERO=C2=A0
US$ 11.04-1.95%Trend Power :
Rentech(Coal-Ngas)RTK
Rentech Announces Results for Second Quarter 2017
US$ 0.20-12.28%Trend Power :
KEFIKEFI.L
Reduced Funding Requirement
GBX 0.56-3.12%Trend Power :
Lupaka Gold Corp.LPK.V
Lupaka Gold Receives First Tranche Under Amended Invicta Financing Agreement
CA$ 0.06+0.00%Trend Power :
Imperial(Ag-Au-Cu)III.TO
Closes Bridge Loan Financing
CA$ 2.44-2.01%Trend Power :
Guyana Goldfields(Cu-Zn-Pa)GUY.TO
Reports Second Quarter 2017 Results and Maintains Production Guidance
CA$ 1.84+0.00%Trend Power :
Lundin Mining(Ag-Au-Cu)LUN.TO
d Share Capital and Voting Rights for Lundin Mining
CA$ 15.23-1.17%Trend Power :
Canarc Res.(Au)CCM.TO
Canarc Reports High Grade Gold in Surface Rock Samples at Fondaway Canyon, Nevada
CA$ 0.23-4.17%Trend Power :
Havilah(Cu-Le-Zn)HAV.AX
Q A April 2017 Quarterly Report
AU$ 0.20-7.14%Trend Power :
Uranium Res.(Ur)URRE
Commences Lithium Exploration Drilling at the Columbus Basin Project
US$ 6.80-2.86%Trend Power :
Platinum Group Metals(Au-Cu-Gems)PTM.TO
Platinum Group Metals Ltd. Operational and Strategic Process ...
CA$ 1.76+2.03%Trend Power :
Devon Energy(Ngas-Oil)DVN
Announces $340 Million of Non-Core Asset Sales
US$ 52.18-0.95%Trend Power :
Precision Drilling(Oil)PD-UN.TO
Announces 2017Second Quarter Financial Results
CA$ 8.66-0.35%Trend Power :
Terramin(Ag-Au-Cu)TZN.AX
2nd Quarter Report
AU$ 0.03+0.00%Trend Power :