CANADA LITHIUM ANNOUNCES POSITIVE FEASIBILITY FOR
QUEBEC LITHIUM PROJECT; CONSTRUCTION TO COMMENCE MID-2011; FULL PRODUCTION IN
2013
TORONTO, Dec. 17 /CNW/ -
Canada Lithium Corp. (TSX: CLQ; U.S. OTC: CLQMF) announced today the results of
its National Instrument 43-101-compliant Feasibility Study (FS) for the
development of a mine and lithium carbonate processing facility at its Quebec Lithium
Project near Val d'Or, Quebec. Initial construction is planned to commence in
mid-2011, commissioning is currently scheduled to be under way by the end of
2012, with full production expected in 2013, subject to financing and final
permitting.
Feasibility Study
Highlights:
Stage
1 Open Pit Mine
|
2,950
tonnes per day (1 million tonnes
per year)
|
Average Annual Stage 1 Production
|
>20,000
tonnes per year (44 million pounds) Li2CO3
|
Quality of Li2CO3
|
>99.5% battery-grade
|
Average Annual Stage 1 Revenue
|
US$120 million per year
|
Stage
1 Pre-tax NPV @ 8%
|
US$270 million
|
Pre-tax Internal Rate of Return
(IRR)
|
24%
|
Average Cash Costs ($/t Li2CO3)
|
US$2,600*
|
Total Initial Plant Capital Costs
|
US$202
million (includes contingency and owner's costs)
|
(* During the first two
years of operations, the kiln will operate on propane gas and operating costs
will be marginally higher.)
The Quebec Lithium
operation, which will consist of an open-pit mine and processing plant, is
expected to produce over 20,000 tonnes (44 million
pounds) per year of battery-grade lithium carbonate (Li2CO3)
at the new plant site near Val d'Or, Quebec. The component sections of the FS
(accuracy of +/-15%) have been prepared by a number of leading Canadian-based
consultants, including SGS Lakefield (SGS), Genivar
Inc., Technology Management Group Inc., BBA Inc. and Golder
Associates.
"This Feasibility
Study indicates the Quebec Lithium hard-rock operation can compete financially
with the South American lithium brine operations," said Peter Secker,
Canada Lithium President and CEO. "Our competitive advantages are that we
have good infrastructure, access to relatively cheap power and a clean ore.
Canada Lithium will be producing a very pure, 99.5% - 99.9% battery-grade
lithium carbonate and we can develop this project on a faster timeline than
most proposed brine or hard-rock projects."
Other highlights:
- Measured
and Indicated Mineral Resources of approximately 46.7Mt at 1.19% Li2O
and an additional Inferred Mineral Resource of approximately 57.6Mt at
1.18% Li2O, as previously disclosed in October 2010
- Initial
development covers a production period of 14.8 years, mining and
processing approximately one million tonnes per
year
- The
plant would produce high-quality, battery-grade product of 99.5% - 99.9%
Li2CO3
- The
project has excellent existing road, rail and power infrastructure and
lies within a 5-hour drive to the Port of Montreal, that can access
European and Asian markets and a 14-hour drive to Detroit, the emerging
North American centre for electric vehicle and battery manufacturers
Following the positive
outcome of the FS announced today, Canada Lithium will commence detailed design
engineering with a development schedule based on commencement of construction
activities on site in May 2011 and planned plant commissioning before the end
of 2012.
Economic modelling at a
preliminary Scoping Study level (+/-35%) indicates that the project has the
potential to produce an additional 40,000/50,000 tonnes per year of a 6.5%
spodumene product that could be saleable to the North American and European
glass, foundry and ceramics markets. When the potential revenue from this
material is used as a co-product credit, unit operating costs are expected to
be lowered to US$0.97/lb (US$2,140/t), demonstrating what is believed to be a
comparable operating cost structure to the South American carbonate brine
producers. Additional financial and resource modelling is being undertaken to
further develop this strategy.
Project Introduction
The Quebec Lithium Project,
owned 100% by Canada Lithium Corp., is located in the north-east quadrant of
Lacorne Township, approximately 60 km north of Val d'Or, Quebec. Access to the
site is by paved road from Val d'Or, a mining-friendly community that has over
75 years of mining history and a population of some 35,000 people. The city
hosts an airport and significant support infrastructure. Quebec is one of the
top-rated mining jurisdictions in the world and electricity costs, a key input
in mining operations, are among the lowest in North America.
Canada Lithium's Quebec
property hosts one of the larger known lithium deposits in North America. The
property consists of 19 contiguous claims covering 643 hectares. The spodumene
mineralisation is hosted within a number of steeply dipping pegmatite dykes
ranging between 10 and 50 metres in width over a strike length of up to 1,500
metres.
In April 2010, the Company
released a 43-101 Pre-Feasibility Study (PFS) for development of the Quebec
Lithium mine and processing plant producing 19,300 tonnes per year of lithium
carbonate at an operating cost of US$2,850/t, estimated capital cost of C$166.0
million and a mine life of 14.8 years. Since completing the PFS, the C$/US$
exchange rate has moved unfavourably; in addition, there have been some changes
to the grinding and hydrometallurgical flow sheets based on the results from
the metallurgical pilot plant testwork. The overall capital costs have,
therefore, been slightly impacted.
An updated mineral resource
estimate was prepared by Michelle Stone, P.Geo., a
geologist with Canada Lithium Corp. and released Oct. 28, 2010. The
technical report detailing the estimate has been posted on SEDAR. The following
tables present the summary of lithium resources reported at a 0.8% Li2O
cut-off and rounded to the nearest 100,000 tonnes.
Table 1: Measured and
Indicated Mineral Resources
Category
|
Million
Tonnes
|
*Li2O
%
|
Measured
|
5.7
|
1.15
|
Indicated
|
41.0
|
1.20
|
Total
M+I
|
46.7
|
1.19
|
Table 2: Inferred Mineral
Resources
Category
|
Million
Tonnes
|
*Li2O
%
|
Inferred
|
57.6
|
1.18
|
Mining Operations
The mine is planned as an
open-pit operation using conventional drill/blast, truck/shovel mining methods.
Mining operations will be carried out with a fleet of hydraulic
excavators/front-end loaders and mine-haul trucks and an ancillary
fleet of dozers, graders and water trucks. The stripping ratio is approximately
3.6:1. The Stage 1 mining plan indicates a total of 15.4Mt of ore to be treated
over an initial 14.8-year mine operating life. The proven and probable mineral
reserves are based on a 92% ore recovery and a dilution of 11% at 0% Li2O.
Table 3: Proven and
Probable Mineral Reserves (1.1% Li2O cut-off)
Category
|
Million
Tonnes
|
*Li2O
%
|
Proven
|
3.9
|
1.12
|
Probable
|
11.5
|
1.19
|
Total
Reserves
|
15.4
|
1.17
|
An additional 3.24Mt of
Inferred material, at a grade of 1.28% Li2O would be mined within
the pit shell. This material would be stockpiled during the mining operation
and its economic viability reviewed. This material has not been included in the
economic model.
Notes
*Percent Li2O is
reported to two decimal places.
The Measured, Indicated and
Inferred Mineral Resource and Proven and Probable Mineral Reserve estimates in
this press release were prepared in accordance with the CIM "Definition
Standards on Mineral Resources and Mineral Reserves" adopted by the CIM
Council on Dec. 11, 2005, and the CIM "Estimation of Mineral Resources and
Mineral Reserves Best Practice Guidelines," adopted by CIM Council on Nov.
23, 2003, in compliance with NI 43-101 guidelines, using inverse distance
squared.
Metallurgical Processing
Metallurgical pilot plant
testwork for the FS was performed at SGS on samples from the Quebec Lithium
deposit. This work resulted in the production of marketing samples for delivery
to North American, European and Asian end users at a purity of >99.9% Li2CO3.
Based on this testwork, the process flow sheets and engineering design concepts
were developed by BBA from the SGS data. The proposed processing design
comprises conventional crushing, grinding and flotation to produce a 6.5% Li2O
spodumene concentrate. The flotation circuit is followed by a
hydrometallurgical treatment process comprising a rotary conversion kiln,
leaching circuit, a series of precipitation tanks, ion exchange (IX) washing/filtration
circuits and a packaging system to produce a >99.5% battery-grade Li2CO3
product. Overall process plant lithium recovery of >67% is anticipated to be
achieved. In addition, a sodium sulphate circuit has been integrated into the
current process flow sheet.
Open-pit Mining Capital
Costs
Mining capital equipment
costs are based on BBA's recent work on a number of open-pit mining projects in
northern Quebec and budgetary quotations from equipment suppliers. The
open-pit mining capital costs are based on a fleet of one 10m3 hydraulic
excavator, one front end loader, up to four 90-ton haul trucks at full
production, plus an ancillary mobile fleet. Pre-stripping has been capitalised
until the first ore production. The capital cost of the open-pit mine is
estimated to be US$12.2 million (with an accuracy of +/- 15%).
Table 4: Initial Mining Capital Costs
Category
|
Total
(US$000)
|
Mining equipment
|
6,599
|
Ancillary equipment
|
2,804
|
Other/Pre-strip
|
2,783
|
Total
|
12,186
|
Process Plant Capital Costs
The capital cost estimate
prepared for the metallurgical processing facility is based on an on-site
processing plant comprising all new equipment, producing battery-grade lithium
carbonate. The plant would be capable of processing 2,950 tonnes per day of ore
(dry basis). The total cost to design, procure and construct the plant
facilities and associated infrastructure is US$151.1 million (with an accuracy
of +/-15%). The following table summarizes the initial process plant capital
costs by area.
Table 5: Plant Construction Capital Costs
Category
|
Total
(US$000)
|
Crushing/Flotation
plant
|
55,010
|
Hydrometallurgical plant
|
76,868
|
Freight/other
|
6,250
|
Contingency
|
13,000
|
Total
|
151,128
|
These processing plant
capital cost estimates were determined using BBA's in-house database and
budget/tender price proposals for the larger components of new equipment.
Infrastructure, Owner's
Costs and Sustaining Capital
The capital cost estimates
for infrastructure; Tailings Management Facility (TMF) construction;
Engineering, Procurement, Construction and Management (EPCM) fees; Canada
Lithium owner's costs and general administration costs were determined by
independent consultants and Canada Lithium personnel and are shown in Table 6.
Table 6: General Capital Costs
Category
|
Total
(US$000)
|
TMF
and infrastructure
|
13,403
|
EPCM/Owner cost
|
24,959
|
Total
|
38,362
|
In addition, there are
working capital requirements of US$12.0 million.
Operating Cost Estimate
The operating costs (+/-15%
accuracy) are for a plant processing approximately 1.0Mt per year (2,950 tonnes
per day) of ore, with an average annual production of >20,000 tonnes of
battery-grade 99.5% - 99.9% Li2CO3. The estimated
operating cost for the mine, primary and secondary processing facilities are
presented below.
Table 7: Overall Project Operating Costs
Category
|
US$/t (mined)
|
US$/t (Li2CO3)
|
US$/lb (Li2CO3)
|
Mining
|
11.55
|
587
|
0.27
|
Crush/Grind/Float
|
9.97
|
507
|
0.23
|
Hydrometallurgical
|
26.06
|
1,326
|
0.60
|
Administration
|
3.00
|
153
|
0.07
|
Total
|
50.58
|
2,573
|
1.17
|
The average operating cost
estimates of approximately US$51/t mined (approximately US$2,600/t Li2CO3)
are based on the use of natural gas for the fuel source in the spodumene
conversion kiln. During the first two years of operations the kiln will operate
on propane gas and operating costs will be marginally higher. Negotiations with
a supplier are under way regarding the natural gas supplies, and sufficient
capital funds have been included in the sustaining capital cost estimates for
the capital cost of the gas line.
Cash Flow Analysis
For the Stage 1
development, cash flows are based on a 100% equity basis and the base-case
economic analysis indicates a pre-tax Net Present Value (NPV), discounted at
8%, of US$270.0 million, at a US$2.67/lb (US$5,875/t) price for lithium
carbonate (99.5%), as reported by Roskill Information Services in a study on
lithium carbonate pricing done for the Quebec Lithium Project. The projected
pre-tax Internal Rate of Return (IRR) is 24% (a C$/US$ exchange rate of 1:1 has
been used for the 2011 and 2012 construction phase of the project and 1.1:1
over the remaining life of the mine).
Table 8: Sensitivity Analysis
Discount
Rate
|
NPV(US$ millions)
|
3%
|
518
|
5%
|
400
|
8%
|
270
|
Life-of-Mine revenue for
Stage 1 is estimated at US$1.78 billion, with earnings before interest, taxes,
depreciation and amortization (EBITDA) of approximately US$1.0 billion. Initial
capital costs are estimated to be US$202.0 million. In addition, there is
estimated to be sustaining capital costs of US$47.0 million. The project is
projected to have a simple payback period of four years.
Project Timetable
Canada Lithium believes
commissioning could begin by Q4, 2012, based on the following milestones and subject
to final economic analysis, engineering reviews, government approvals, board
approvals and general market conditions:
- Q1,
2011: Financing, Initiation of Engineering
and Design
- Q2, 2011: Obtain government approvals
- Q2, 2011: Construction
Start-up
- Q4, 2012: Process Plant Commissioning
- Q4, 2013: Achieve design production
Community and Environment
In August 2009, the Company
appointed Genivar Inc. of Amos, Quebec, to undertake an Environmental Study for
the proposed mine development. In September 2010, the Mining License
application for the mine was submitted to the relevant government authorities.
At the same time, submission of detailed environmental documentation also
commenced.
As part of the
environmental program, the local communities are being involved in the project
development process. The first public meetings were held in January 2010. A
second round of 32 meetings was held in October/November 2010, inclusive of two
meetings with the local Anishnabe First Nations. A number of additional
meetings will be held over the coming months as the project development stages
commence. As part of the Environmental Management Plan, the Company may be
required to lodge an Environmental Bond of up to C$4.0 million with the relevant
Quebec government departments, during the construction phase of the project.
These costs are included in the project capital costs.
Report Filing
A 43-101-compliant
technical report on the Feasibility Study will be filed on SEDAR at www.sedar.com and at www.canadalithium.com within 45 days of the date of this news release.
Qualified Persons
The Feasibility Study
Report was integrated and prepared by Technology Management Group Inc. under
the supervision of Peter Woodhouse, P.Eng., a
registered professional engineer in the Province of Ontario, and independent
Qualified Person under the standards set forth by National Instrument 43-101.
Mr. Woodhouse has read and approved the contents of this news release.
Mitch Lavery, P.Geo., is the Qualified Person for the Quebec Lithium
Project in accordance with NI 43-101. Mr. Lavery has read and approved
the contents of this news release.
About
Canada Lithium Corp.
Canada Lithium Corp. is
a Canadian-based "clean tech" mine developer trading under the symbol
CLQ on the TSX and on the U.S. OTCQX market under the symbol CLQMF. It has an
agreement with Japanese metals trading firm, Mitsui and Co. Ltd., to market a portion
of Canada Lithium Corp.'s product in China, Korea and Japan. Metallurgical
tests from deposit samples have produced 99.9% battery-grade lithium carbonate.
Conference Call
Canada Lithium Corp. will
host a conference call at 10:30 a.m. EST on Friday, Dec. 17, 2010 to discuss
details of this release and answer any questions from analysts, investment
advisers and shareholders. Company President and CEO Peter Secker and
Chairman Kerry Knoll will be available for the call.
To participate, please dial
in North America 1 (888) 231-8191; Local or International (647) 427-7450 about
five minutes prior to the start time. The conference call will be archived for
replay until Dec. 24, 2010. To access the archived conference call, please dial
1 (800) 642-1687 and enter pass code 32843037.
An audio replay of the
conference call will be available at www.newswire.ca and www.canadalithium.com.
Neither the TSX Venture
Exchange nor its Regulation Services Provider (as that term is defined in the
policies of the TSX Venture Exchange) accepts responsibility for the adequacy
or accuracy of this release.
Forward-looking
Information
The statements made in this
news release may contain certain forward-looking statements concerning
potential developments affecting the business, prospects, financial condition
and other aspects of Canada Lithium Corp. The actual results of the
specific items described in this release, and the company's operations generally,
may differ materially from what is projected in such forward-looking
statements. Although such statements are based upon the best judgments of
Canada Lithium Corp. management as of the date of this release, significant
deviations in magnitude, timing and other factors may result from business
risks and uncertainties including, without limitation, the Company's dependence
on third parties, general market and economic conditions, technical and design
factors, costs and budget estimates, the availability of outside capital,
receipt of revenues and other factors, many of which are beyond the control of
the Company. Canada Lithium Corp. disclaims any obligation to update
information contained in any forward-looking statement.