Nevada Copper Announces Positive Feasibility Study Results
Published : January 23, 2012
( 0 vote, 0/5 ) Print article
  Article Comments Comment this article Rating Follow Company  
0
Send
0
comment
Keywords :   Barclays | Copper | Gold | Housing | Iron | Lead | Lme | London | Market | Recovery | Silver | Storage | Water |

VANCOUVER, BRITISH COLUMBIA--(Marketwire - Jan. 23, 2012) - Nevada Copper Corp. (News - Market indicators) ("Nevada Copper") is pleased to announce the results of its definitive Feasibility Study for its 100% owned Pumpkin Hollow Copper Project located in Yerington, Nevada. The Feasibility Study was prepared under the direction of Tetra Tech, Inc. ("Tetra Tech"), an industry leading international engineering firm, with substantial input from Merit Consultants International Inc. ("Merit"), which compiled and reviewed the initial capital cost estimate. The Feasibility Study, with capital costs defined to within plus/minus 15%, builds upon two previous Preliminary Economic Assessments prepared by Tetra Tech, and significant metallurgical and geotechnical work completed in 2010 and 2011. The Feasibility Study confirms the technical and financial viability of constructing and operating a 67,500 ton-per-day copper mining and processing operation at Pumpkin Hollow. 

Highlights of the Feasibility Study (all amounts are stated in United States dollars):

  • The project development consists of a 60,000 ton-per-day open pit operation; and a 7,500 ton-per-day underground operation, feeding a single 67,500 ton-per-day concentrator;
  • First production targeted for mid-2015, with a current mine life of 18 years;
  • Proven and Probable Mineral Reserves of 4.29 billion pounds of copper; 952,000 ounces of gold and 27.3 million ounces of silver on the basis of drill data up to October 2010;
  • Life-of-Mine ("LOM") metal production contained in concentrates totals 3.83 billion pounds of copper, 641,917 ounces of gold and 15.37 million ounces of silver;
  • Average annual copper production in concentrates:

            Years 1 to 5: 274 million pounds per year 
            Years 1 to 10: 254 million pounds per year
            LOM: 226 million pounds per year

  • Initial capital costs are estimated to be $1.04 billion including contingencies, excluding working capital of $48.9 million;
  • LOM site operating cash costs are $12.33 per ton of ore-milled; copper production costs net of gold and silver credits are:

            Years 1 to 5: $1.28 per pound of payable copper
            Years 1 to 10: $1.37 per pound of payable copper
            LOM: $1.43 per pound of payable copper

  • Summary of Economic Results:
  1. Base Case: Three year trailing average price of $3.24/lb. copper, $1,252/oz. gold and $23.19/oz. silver:

            Net Present Value at 5% is $1.91 billion, pre-tax. 
            Net Present Value at 8% is $1.26 billion, pre-tax. 
            Internal Rate of Return is 23.1% and payback is 3.6 years.

  1. Alternate Case (1): Quoted forward prices to 2021 declining to long term of $2.50/lb. copper; gold and silver same as Base Case:

            Net Present Value at 5% is $1.49 billion, pre-tax. 
            Net Present Value at 8% is $1.02 billion, pre-tax.
            Internal Rate of Return is 23.5% and payback is 3.3 years.

  1. Alternate Case (2): $3.75/lb. copper; gold and silver same as Base Case:

            Net Present Value at 5% is $2.93 billion, pre-tax. 
            Net Present Value at 8% is $2.05 billion, pre-tax.
            Internal Rate of Return is 30.8% and payback is 3.0 years.

  1. Average annual operating cash-flow (Years 1 to 5):

            Base Case: $450 million
            Alternate Case (1): $494 million
            Alternate Case (2): $570 million

"The completion of the definitive Feasibility Study is a significant milestone in Nevada Copper's development," commented Giulio Bonifacio, President & CEO. "We are extremely pleased with the results as it further validates our expectations for the project while providing independent confirmation that the Pumpkin Hollow project will support a low-risk, and economically robust, copper mine with an initial mine life of 18 years. The Board of Directors has approved a positive production decision, subject to completion of project financing arrangements and receipt of required permits. With the Feasibility Study results in hand, we will now move to secure a strategic partner in 2012. A number of companies have expressed interest in the project and have been conducting due diligence while awaiting the Feasibility Study.

"Additionally, the Feasibility Study will be updated by mid-2012 to incorporate the benefits of magnetite recovery and sales from the iron magnetite resource. If the iron values are incorporated into the future mining plans, the size and tonnage of the North and South open pit deposits are expected to increase significantly while lowering the waste tonnage and strip ratio. Also, since late 2010 drilling has demonstrated extensions to the mineralized zones in the North and South deposits and these extensions will be incorporated into an updated mineral resource, mineral reserve and related mining plans. The dual benefits of the iron resource and results from the current 50,000 meter drilling program are expected to have a further positive impact on already robust economics."

Permits and Land Transfer

The Pumpkin Hollow project is located on private land and unpatented mining claims located on Bureau of Land Management ("BLM") administered federal lands ("Federal Lands"). The City of Yerington (the "City") has proposed to acquire the Federal Lands ("Land Transfer") and transfer the Federal Lands to the City. Nevada Copper has agreed to collaborate with the City to support the Land Transfer. If successful, the Land Transfer would convey all Federal Lands associated with the project from BLM jurisdiction to the City. This would allow the City to receive a portion of both property tax and Nevada net proceeds tax. It would also provide additional lands around the project for sustainable development, including current and long-term, post-mining commercial and industrial development, recreational opportunities, and expansion of community and cultural events. Subject to successful completion of the Land Transfer, all permitting would come under the jurisdiction of the State of Nevada and the City, with receipt of permits targeted for early 2013.

The Nevada Congressional delegation is planning to introduce legislation in Congress as soon as Congress returns to a full schedule on January 24, 2012. The City is requesting that hearings be scheduled as soon as possible to assure timely hearing and passage of this legislation that is critically important to the City. In the event the Land Transfer is not completed as planned, the project activities would require a Plan of Operations with the BLM and compliance with the National Environmental Policy Act of 1969 ("NEPA"). NEPA compliance would entail preparation of an Environmental Impact Statement ("EIS") pursuant to BLM guidelines.

Regardless of the land status and permit process, the environmental, engineering and baseline technical studies associated with the entire project are in progress and will be completed in conformance with all Federal, State and local standards. That assures that the project is designed, constructed and operated to meet those standards and that either permitting process, including preparation of an EIS, would not be delayed. If BLM approval is required, BLM process and State permits for the project would be expected to be complete in early 2015.

Development Schedule

An underground contractor was selected in December 2011 for purposes of sinking of a 2,200 foot, 24 foot diameter production-sized shaft to access the East underground deposit. The contractor is in the process of mobilizing to site. All permits to allow for shaft sinking and construction are in hand. Engineering work will start shortly on the design and installation of hoist and head frame facilities at the shaft location. A production hoist has been secured and will be refurbished prior to shipment to site.

Detailed engineering and ordering of key long-lead-time mining and process equipment will start by mid-2012. Pre-stripping the North deposit and construction of the mill and related facilities will occur in 2013-14 once permits are obtained. Production is anticipated to commence in the second quarter of 2015.

Project Opportunities

Project opportunities in the near term to further enhance the economic value of the Pumpkin Hollow project will be included in an updated feasibility study which is targeted for completion in mid-2012 and would reflect the following:

Iron

Work has been initiated to further assess the metallurgy and marketability of the Pumpkin Hollow iron magnetite resources, to incorporate the iron values into the project block models, to revise the current mining plans to generate an iron production schedule and to include the additional revenues from this source in the revised project cash flows. The inclusion of iron values in the block model is expected to greatly improve strip ratios since much of what is now considered open pit waste material would have sufficient value to be processed through the mill facility.

Resource expansion

Drilling since late 2010 demonstrated material extensions to the known mineral inventories at Pumpkin Hollow, particularly the North open pit deposit. Updating the mineral resource inventory to reflect this drilling, along with updated mining plans, is expected to expand the mineral resources and reserves at the project.

Pit expansion

Whittle pit analysis using the recent drilling and marketable iron product is expected to produce a mine design where the North and South pits will intersect. A merged pit configuration is expected to have a positive effect on the strip ratio, as well as improvements in pit scheduling and equipment utilization.

Mineral Resources

The project mineral resource was prepared by the mineral resource and mining division of Tetra Tech, incorporating the results of drilling to the end of October 2010, as previously disclosed in a news release on March 31, 2011. This resource was an update of a previous mineral resource estimate disclosed in July 2009 and filed on SEDAR on August 24, 2009.

Measured and Indicated Resources - Western Open-Pit Deposits

Category
Copper Cut-off
Tons
Copper
Grade

 Copper
Gold Grade
Gold
Silver Grade
Silver
  %
(000's)

%

lbs. (000's)

Oz./ton
Ozs. (000's)
Oz./ton
Ozs. (000's)
Measured 0.20 138,393 0.51 1,391,417 0.003 344 0.062 8,458
Measured 0.15 175,553 0.43 1,507,947 0.002 410 0.058 10,012
Indicated 0.20 276,073 0.44 2,432,205 0.002 551 0.056 15,305
Indicated 0.15 385,046 0.37 2,803,327 0.002 652 0.051 19,677
 
M & I Total 0.20 414,465 0.46 3,823,622 0.002 892 0.058 23,763
M & I Total 0.15 560,599 0.39 4,311,274 0.002 1,061 0.053 29,689
 
Measured and Indicated Resources - Eastern Underground Deposits
Category Copper Cut-off
Tons
Copper
Grade

 Copper
Gold Grade
Gold
Silver Grade Silver
 
%

(000's)

%

lbs. (000's)

Oz./ton
Ozs. (000's)
Oz./ton
Ozs. (000's)
Measured 1.00 9,206 1.81 333,324 0.011 104 0.24 2,205
Measured 0.75 12,497 1.56 390,372 0.01 128 0.216 2,699
Indicated 1.00 24,338 1.72 835,589 0.01 247 0.245 5,971
Indicated 0.75 38,092 1.40 1,069,452 0.008 321 0.213 8,118
 
M & I Total 1.00 33,544 1.74 1,168,913 0.01 351 0.244 8,176
M & I Total 0.75 50,589 1.45 1,459,824 0.009 449 0.213 10,817

The mineral resource estimate was performed by or under the direction of John Rozelle, PG, Tetra Tech's Mineral Resource Division Principal Geologist at the time of this estimate, an independent Qualified Person as set forth by Canadian National Instrument 43-101 ("NI 43-101").

The following Inferred Resources are in addition to the Measured and Indicated Resources:

Inferred Resources - Western Open-Pit Deposits

Category
Copper Cut-off
Tons
Copper
Grade

Copper
Gold Grade
Gold
Silver Grade
Silver
 
%

(000's)

%

lbs (000's)

Oz./ton
Ozs. (000's)
Oz./ton
Ozs. (000's)
Inferred 0.20 243,670 0.38 1,815,712 0.001 242 0.038 9,255
Inferred 0.15 387,757 0.30 2,288,414 0.001 385 0.039 14,960
Inferred Resources - Eastern Underground Deposits
Category Copper Cut-off
Tons
Copper
Grade

Copper
Gold Grade
Gold
Silver Grade Silver
 
%

(000s)

%

lbs (000s)

Oz./ton
Ozs. (000's)
Oz./ton
Ozs. (000's)
Inferred 1.00 4,926 1.45 143,313 0.002 10 0.101 498
Inferred 0.75 12,098 1.11 267,533 0.002 24 0.065 792

Mineral resources that are not categorized as mineral reserves have not demonstrated economic viability.

Mineral Reserve

Proven and Probable mineral reserves are the economically-mineable portions of the Measured and Indicated mineral resources above, respectively, as demonstrated by the Feasibility Study. The proven and probable reserves at Pumpkin Hollow are summarized below:

Mineral Reserves East & E2 - Underground Deposits
Classification
Ore

Copper

Gold

Silver
Contained Copper Contained Gold Contained Silver Copper Equiv.
000's tons
%

Oz./ton

Oz./ton

Billion lbs.

Ozs.

Ozs.

%
Proven 12,366 1.58 0.011 0.217 0.39 133,005 2,687,889 1.79
Probable 23,411 1.50 0.006 0.151 0.70 138,681 3,535,363 1.62
Proven & Probable 35,777 1.53 0.008 0.174 1.09 271,686 6,223,252 1.68
Mineral Reserves North & South - Open Pit Deposits
Classification
Ore

Copper

Gold

Silver
Contained
Copper
Contained
Gold
Contained
Silver
Copper Equiv.
000's tons
%

Oz./ton

Oz./ton

Billion lbs.

Ozs.

Ozs.

%
Proven 136,411 0.47 0.0022 0.061 1.28 299,383 8,286,908 0.52
Probable 233,276 0.41 0.0016 0.055 1.92 380,829 12,773,036 0.45
Proven & Probable 369,687 0.43 0.0018 0.057 3.20 680,212 21,059,944 0.47
Total Mineral Reserve - All Deposits
Classification
Ore

Copper

Gold

Silver
Contained
Copper
Contained
Gold
Contained
Silver
Copper Equiv.
000's tons
%

Oz./ton

Oz./ton

Billion lbs.

Ozs.

Ozs.

%
Proven 148,777 0.56 0.0029 0.0738 1.67 432,388 10,974,797 0.62
Probable 256,687 0.51 0.0020 0.0635 2.62 519,510 16,308,399 0.55
Proven & Probable 405,464 0.53 0.0024 0.0673 4.29 951,898 27,283,196 0.58

The mineral reserves and mine plans for each of the underground and open pit deposits were determined using cutoff grades developed by Tetra Tech as appropriate for the mining method and costs associated with the deposits. For the open pit western deposits the cutoff grade used was 0.18% copper and 0.8% copper for the eastern underground deposits. A copper price of $3.00 per pound was assumed. Tetra Tech is the independent Qualified Person who is responsible for the mineral reserve estimate. The copper equivalency was determined using Base Case metals prices and metallurgical recoveries of 89.3%, 67.3% and 56.3% for copper, gold and silver respectively.

Drilling has been continuous since November 2010 with 3 drill rigs that, to date, have completed 28,000 meters of the expanded 50,000 meter drilled program. These drill results have not yet been incorporated into the above mineral resource or reserve numbers. Nevada Copper intends to update its mineral resource and reserve in 2012.

Iron Mineral Resource

Though not considered in the Feasibility Study, the Pumpkin Hollow project also has considerable resources of iron in the form of magnetite. The following tables include only those iron resources amenable to open-pit mining methods in the Western deposits. Possible mining, recovery and sale of a magnetite concentrate will be considered in an updated feasibility study. The updated definitive feasibility study will build off the current Feasibility Study and is targeted for completion by mid-2012.

Iron Resources
Category Iron Cut-off Tons Iron Grade Tons Iron
% (000's) % (000's)
Measured 20 205,836 34.57 71,162
Measured 30 123,627 41.14 50,857
Measured 40 62,218 47.42 29,505
 
Indicated 20 135,062 29.56 39,926
Indicated 30 53,740 37.88 20,356
Indicated 40 15,932 45.79 7,295
 
Inferred 20 29,769 25.6 7,613
Inferred 30 3,429 36.1 1,239
Inferred 40 542 46.4 252

Mineral resources that are not categorized as mineral reserves have not demonstrated economic viability.

This iron mineral resource estimate was disclosed in Nevada Copper's March 31, 2011 News Release and was updated from a previous iron resource estimate disclosed in a Technical Report dated August 20, 2009 and filed in accordance with NI 43-101 on SEDAR. 

If an updated feasibility study demonstrates the iron resource to be economically viable, inclusion of iron in the open pit block model values is expected to significantly expand the size and tonnage of the North and South open pits, and lower waste tonnages and strip ratio.

Mining

Both underground and open pit mining methods were selected in order to maximize the overall recovery of copper from the Pumpkin Hollow deposits. The East underground deposit will be developed first via a 24 foot diameter production-sized shaft. All underground production (7,500 ton-per-day) will come initially from the East deposit only. Development of the E2 deposit will occur after development of the East deposit is completed. E2 development will occur from underground via a 4,800-foot conveyor-equipped decline from the East zone. Vent and secondary egress shafts will be constructed for both East and E2 zones as required. 

The open pit deposits will be developed sequentially starting with pre-stripping the North deposit. Open pit mill feed will come exclusively from the North deposit until year 8 when ore from the South deposit is added and is expected to eventually replace all North ore by year 13.

Total ore mined and processed from open pit and underground sources, LOM, is 405.4 million tons grading 0.53% copper, 0.002 oz./ton (0.081 g/tonne) gold and 0.067 oz./ton (2.31 g/tonne) silver.

Process Plant

Ore will be transported from the open pit and underground mines to a nominal 67,500 ton-per-day concentrator located west of the open pits. For open pit ores, a large semi-mobile in-pit crusher reduces ore size before conveyance to the process facility. Underground ore is crushed underground, hoisted to surface via a 24-foot diameter production shaft and transported overland approximately 2 miles by truck to the process facility. 

The concentration circuit is conventional with a single, large semi-autogenous grinding mill and secondary ball mill grinding and flotation, followed by thickening and pressure filtration to produce a final concentrate grading 25.5% copper and containing payable gold and silver. Primary grind size is 150 microns with an overall copper recovery of 89.3%. Gold and silver recoveries to the copper concentrates are 67.3% and 56.3% respectively.

Metals Production

Projected metals production to the copper concentrate is summarized below. LOM copper production in concentrates is estimated to be 3.83 billion pounds (1.9 million tons).



Description


Units
Years 1-5
Annual Average
Years 1-10
Annual Average
LOM
Annual Average

LOM Total
Copper Concentrate Tons/year (000's) 538 499 442 7,517
Copper in Concentrate Million lbs./year 274 254 226 3,834
Copper in Concentrate Tons/year; tons 137,128 127,155 112,762 1,916,953
Gold in Cu Concentrate Ozs./year; ozs. 53,241 43,422 37,760 641,917
Silver in Cu Concentrate Ozs./year; ozs. 1,138,151 1,020,799 904,292 15,372,968

Tailings Storage

To minimize water usage, tailings will be de-watered, filtered and conveyed to a "dry-stack" on-site storage facility. This water is then recycled to the process plant. This method is considered "best practice" for long term tailings storage in dry environments with finite water resources. It also lowers long term environmental monitoring costs.

Infrastructure

The project area is well supplied with nearby local infrastructure. Project-related infrastructure expenditures include a new 6 mile (10km) 120kV power line and related substation. An energy cost of $0.065/kwh was used for Feasibility Study purposes, based on NV Energy expected rates. A 5-mile (8 km) mine access road connects the site to state Highway 95 to the North, and a rail load-out facility located on Union Pacific tracks. The rail tracks run approximately 13 miles (21 km) north of the project and connect with Union Pacific mainline tracks for connection to west coast ports. Process make-up water will be piped 6 miles (10 km) from the City of Yerington, county seat for Lyon County, where housing and regional services are available and most employees are expected to reside. The communities of Silver Springs, Smith Valley, Fernley, Dayton, Fallon, Carson City and Hawthorne are also all within commuting distance, and have a labor pool and existing housing, particularly for a construction workforce.

Capital Costs

The project initial capital costs are estimated at $1.04 billion with an accuracy of plus/minus 15% as of January 2012, including a contingency of $64.1 million. The contingency allowance is calculated based on assessed factors for each of the major Direct and Indirect cost categories. The major direct cost items include development of the East underground mine, the North deposit pre-stripping, process plant, tailing storage facility, site infrastructure and offsite rail load-out facility. Indirect costs include such major areas as engineering and procurement, construction management, freight and commissioning, spares inventory, first fills, and Owners Costs.


Initial Capital Costs
  US$ Millions
Direct Costs  
Underground Mine Development $145.9
Surface Mine Development 245.3
Process and concentrates handling 224.7
Tailings Dewater & Dry Stack Facility 131.2
Other capitalized pre-production costs 1.1
Offsite Infrastructure 7.2
Power and Electrical 36.4
Site Utilities and Services 21.3
Site Preparation and Roads 8.7
Water Systems and Ancillary Facilities 25.1
Total Direct Costs $846.9
   
Indirect Costs  
Engineering & Procurement 34.4
Construction Management 14.5
Freight and Logistics 20.9
Construction Temp. Facilities, Services & Equipment 12.1
Environmental and reclamation Costs 10.9
Owner's Costs 10.9
Spares First Fills And Inventory 18.6
Commissioning and Start-Up 2.6
Total Indirect Costs 124.9
Total Direct and Indirect Costs $971.8
Contingency 64.1
Total Initial Capital $1,035.9

Working capital required for initial operations is estimated to be $48.9 million. 

LOM sustaining capital totals $1.0 billion and includes development of the E2 underground deposit and related equipment; South open pit deposit development costs; replacement of, and additions to, surface mobile equipment; lease costs for the initial mining fleet; reclamation costs; and expenditures on the tailings storage facility.

LOM Sustaining Capital
Area $Millions
Underground Mine  
  E2 equipment $58.6
  E2 development 81.0
  East equipment 75.3
  East development 83.8
Surface Mine  
  Mine equipment 404.8
  In-pit Crushing & Conveying 71.4
  General surface mobile equipment 36.2
  Access, site preparation and facilities 6.8
Process 59.1
Tailings 45.2
Reclamation 74.0
Hydrology / Dewatering 7.0
Total Sustaining Capital $1,003.2

Operating Costs

LOM site unit operating cash costs, net of capitalized pre-stripping and other predevelopment costs, are $12.33 per ton-milled, as summarized in the table below:

LOM Unit Operating Cost Summary
Area LOM
$/ton-milled
Mining (open pit & underground average) $6.83
Processing 4.70
Dry-stack Tailings Facility 0.21
Reclamation, Infrastructure, Hydrology 0.11
General & Administrative 0.48
Total $12.33

Open pit mining cash costs average $4.79 per ton of ore mined, including waste and ore mining costs. Average strip ratios for the North & South deposits respectively are 3.5 and 3.0 to 1, including the North deposit pre-strip. Underground mining costs average $27.98 per ton of ore mined. 

LOM Unit Mining Costs by Mining Method
Underground $/ton-ore mined Open Pit
$/ton-ore mined
$27.98 $4.79

Copper production cash costs per payable pound including site operating costs and copper conversion costs such as smelter charges and concentrate transport, net of gold and silver credits, are estimated to average $1.28/lb. for Years 1 to 5 and $1.37/lb. for Years 1 to 10.

Economic Analysis Summary

The project economics were evaluated using a cash flow analysis, whereby revenues and costs are projected into the future on an annual basis. Annual net cash flows are then discounted at a rate of interest to reflect the time value of money to yield a Net Present Value ("NPV"). The analysis includes all site operating costs, smelter charges and transport costs, royalties, estimated local property taxes, and Nevada Net Proceeds of Mining tax, but excludes corporate income taxes. 

The most significant input which affects project economics are projected future metals prices. The following three metal price scenarios were used:

  1. Base Case: Three year trailing average London Metal Exchange ("LME") prices were used as at December 22, 2011 and are as follows: 
  1. Copper: $3.24 per pound.
  2. Gold: $1,252 per ounce.
  3. Silver: $23.19 per ounce.
  1. Alternate Case (1):
  1. Copper: Long term forward prices as at December 8, 2011, supplied by Barclays Capital, were used.

These forward prices are available to 2021, and thereafter copper prices were reduced to a long term price of $2.50 per pound - See table below.

Year 2015 2016 2017 2018 2019 2020 2021 2022+
Copper Price $3.48 $3.46 $3.43 $3.40 $3.36 $3.32 $3.29 $2.50
  1. Gold: Same as Base Case.
  2. Silver: Same as Base Case.
  1. Alternate Case (2):
  1. Copper: $3.75 per pound
  2. Gold: Same as Base Case
  3. Silver: Same as Base Case

The cash LME copper price on January 19, 2012 was $3.78/lb.

Summary of Economic Results

Key economic indicators extracted from the Feasibility Study are summarized below:

  Base Case Alternate Case (1) Alternate Case (2)
  US$ Millions US$ Millions US$ Millions
Cumulative pre-tax cash-flow $3,771 $2,785 $5,459
NPV@ 5%, pre-tax $1,905 $1,488 $2,930
NPV@ 8%, pre-tax $1,261 $1,016 $2,048
Average annual operating cash-flow (Years 1 to 5) $450 $494 $570
Internal rate of return, pre-tax 23.1% 23.5% 30.8%
Payback (years from first production) 3.6 3.3 3.0

Royalties and Nevada Mining Taxes - The economic results include the costs of all third party royalties, and an estimate of local property taxes and Nevada Net Proceeds Tax payable on income from operations.

Corporate Income Tax - Corporate income taxes were excluded for the purposes of the economic analysis. Income tax calculations related to mining income can be complex in the United States with nominal tax rates on mining income in the United States being lowered by the net effects of percentage depletion and other adjustments.

Conference Call Details

A conference call to discuss the results of the Pumpkin Hollow Project Feasibility Study has been scheduled for Thursday, January 26, 2012 at 11:00am ET (8:00am PT). Dial-in numbers for North America are: toll free 866-696-5910 or 416-340-2217; for International 800-8989-6336 - Participant Pass Code No. 4343242. An instant replay will be available for two weeks following the conference call as follows: toll free 800-408-3053 or 905-694-9451; for International 800-3366-3052 - Participant Pass Code No. 8818300.

Qualified Persons

In November 2011 Nevada Copper commissioned Tetra Tech to complete the Pumpkin Hollow Project Feasibility Study in accordance with NI 43-101. The initial capital costs estimates for the Pumpkin Hollow Project in the Feasibility Study were compiled and reviewed by Merit under the direction of Jay Collins, P. Eng. The scientific and technical information in this release has been reviewed and approved by Erik Spiller, Q.P., Vice President, of Tetra Tech, and overall manager for the Feasibility Study, and by Mr. Collins both of whom are Independent Qualified Persons within the meaning of NI 43-101. 

This release was also reviewed by Gregory French, P.G., Vice-President & Project Manager of Nevada Copper and Robert McKnight, P. Eng., Executive Vice-President of Nevada Copper, both of whom are Non-independent Qualified Persons within the meaning of NI 43-101.

Readers should refer to the Feasibility Study Technical Report for further details of the project development. The Feasibility Study Technical Report will be filed in accordance with NI 43-101 on SEDAR (www.sedar.com) within the required 45 day statutory period and will be made available on Nevada Copper's website (www.nevadacopper.com). An updated PowerPoint presentation will be available on the Nevada Copper website.

NEVADA COPPER CORP.

Giulio T. Bonifacio, President & CEO

We seek safe harbour.



Nevada Copper Corp.
Eugene Toffolo
Corporate Communications
604-683-8266 or Toll Free: 1-877-648-8266
etoffolo@nevadacopper.com
or
Nevada Copper Corp.
Robert McKnight, P.Eng.
Executive Vice President
604-683-1309
bmcknight@nevadacopper.com
www.nevadacopper.com

Nevada Copper

DEVELOPMENT STAGE
CODE : NCU.TO
ISIN : CA64128F1099
CUSIP : 64128F
Follow and Invest
Add to watch list Add to your portfolio Add or edit a note
Add Alert Add to Watchlists Add to Portfolio Add Note
ProfileMarket
Indicators
VALUE :
Projects & res.
Press
releases
Annual
report
RISK :
Asset profile
Contact Cpy

Nevada Copper is a copper exploration company based in Canada.

Nevada Copper develops copper, gold, iron and silver in USA.

Its main asset in development is PUMPKIN HOLLOW in USA.

Nevada Copper is listed in Canada and in Germany. Its market capitalisation is CA$ 8.8 millions as of today (US$ 6.5 millions, € 6.1 millions).

Its stock quote reached its highest recent level on April 08, 2011 at CA$ 6.42, and its lowest recent point on November 06, 2020 at CA$ 0.06.

Nevada Copper has 88 170 000 shares outstanding.

Your feedback is appreciated, please leave a comment or rate this article.
Rate : Average note :0 (0 vote) View Top rated
 
In the News and Medias of Nevada Copper
5/9/2019Nevada Copper inks $115m deal to construct Pumpkin Hollow
8/31/2018Nevada Copper shares jump on construction decision
5/16/2018Nevada copper provides positive update on drill program: int...
Financings of Nevada Copper
4/19/2016Amends Red Kite and Pala Loan Terms
4/27/2010Closes $23,7 Million Bough-Deal Private Placement Financing
4/9/2010$20.6 Million Bought-Deal Private Placement Financement
10/27/2009$11,250,000 Private Placement with Capstone Mining Corp.
Nominations of Nevada Copper
8/8/2013Appoints Director
2/28/2012Appoints New Director and Launches Project Website
Project news of Nevada Copper
9/9/2013Receives All Permits For Stage 1 Underground Mine
7/28/2011(Pumpkin Hollow)Obtains 100% of Water Needs for the Pumpkin Hollow Project
4/28/2011(Pumpkin Hollow)Provides Update on Feasibility Study & Engages Merit for Pre...
4/12/2011INTERSECTS 415 FEET OF 1.84% COPPER
3/31/2011(Pumpkin Hollow)s Mineral Resource Estimate and Clarifies Technical Disclosu...
2/8/2011S FEASIBILITY STUDY PROGRESS
8/4/2010(Pumpkin Hollow)Intersects 230 Feet of 1.46% Copper in The Open Pittable Nor...
7/8/2010(Pumpkin Hollow)E2 Deposit Drilling Intersects 145 Feet of 2.37% Copper and ...
6/16/2010(Pumpkin Hollow)Mineralization Remains Open at North Deposit: Intersecting 9...
5/27/2010(Pumpkin Hollow)Increases Drilling Program
5/18/2010(Pumpkin Hollow)Discovers Two New Zones Intersecting 275 Feet of 0.98% Coppe...
5/6/2010(Pumpkin Hollow)Step Out Drilling Expands the Open Pittable North Deposit: I...
4/23/2010(Pumpkin Hollow)Drills Over 650 Feet Of Greater Than 0.70% Copper In Three S...
2/16/2010(Pumpkin Hollow)Continues to Intersect High Grade Copper
1/21/2010(Pumpkin Hollow)Intersects 31.1 Meters of 2.45% Copper
1/14/2010Files NI 43-101 Preliminary Economic Assessment
12/8/2009(Pumpkin Hollow)Commences Pre-Feasibility & 25,000 Meter Drilling Program
8/25/2009(Pumpkin Hollow)Files resource update NI 43-101 on Sedar
7/15/2009(Pumpkin Hollow)Reports Significant Resource Increase to 9.3 Billion Pounds ...
Corporate news of Nevada Copper
6/9/2016Nevada Copper Closes Cdn$4.6 Million Equity Offering
6/3/2016Nevada Copper Closes Cdn$ 10.5 Million Financing With Red Ki...
6/1/2016Nevada Copper Solar Zoning Approved
5/27/2016Nevada Copper Annual Meeting Results
5/27/2016Nevada Copper Announces Red Kite Funding Commitment And Equi...
5/3/2016Nevada Copper and City of Yerington Advance Solar Zoning
4/22/2016Nevada Copper Announces Filing Of Amended Prospectus And Exe...
4/5/2016Nevada Copper Amends Red Kite and Pala Loan Terms
1/28/2016Nevada Copper Appoints Directors
11/3/2015Nevada Copper Intersects 105 Feet of 2.55% Copper in the Eas...
10/13/2015Nevada Copper Acquires Private Land & Completes Federal Land...
9/30/2015Nevada Copper Provides Corporate and Project Update
9/10/2015Nevada Copper Intersects 462 Feet of 0.64% Copper
8/21/2015IIROC Trade Resumption - NCU
8/21/2015Federal Land Conveyance Complete at Nevada Copper's Pumpkin ...
8/20/2015IIROC Trading Halt - NCU
8/17/2015Nevada Copper Fully Permitted
7/31/2015Nevada Copper Extends and Increases Bridge Loan Facility
7/31/2015Nevada Copper Receives Air Pollution Control Permit
7/17/2015Nevada Copper Receives Decision Record on Yerington Land Con...
7/15/2015Nevada Copper Intersects 448 Feet Grading 1.0% Copper
7/9/2015Nevada Copper Files Integrated Feasability Study on SEDAR
6/29/2015Nevada Copper Election of New Director and Annual Meeting Re...
6/24/2015Nevada Copper Continues to Expand Open Pit Mineralization In...
4/23/2015Nevada Copper Pumpkin Hollow Project Update
2/10/2015Nevada Copper Pumpkin Hollow Project Update
12/30/2014Nevada Copper Closes US$200 Million Loan Facility
12/22/2014President Signs National Defense Authorization Act That Incl...
12/3/2014Nevada Copper Project Update
11/4/2014Nevada Copper Project Update
7/30/2014Nevada Copper Advances Lyon County Bill
7/16/2014Nevada Copper Provides 2014 Update
7/2/2014Nevada Copper Provides Update & AGM Results
5/12/2014Nevada Copper Update on Lyon County Land Bill
1/23/2014NCU - Nevada Copper featured on KTVN - Channel 2 News
10/28/2013Announces Management Additions
10/9/2013Receives Additional US$15 Million Under Its US$200 Million S...
10/1/2013Announces $24 Million Equipment Financing
8/26/2013Receives Water Pollution Control Permit
7/16/2013Remaining Stage One Permits Issued for Public Comment
6/25/2013Receives Special Use Permit and Provides Update on Land Bill
6/17/2013North Deposit Drilling Intersects Multiple Zones of Minerali...
6/10/2013Receives Reclamation Permit
5/28/2013Provides Update on State Permits
5/7/2013s Lyon County Bill Status
4/23/2013(Pumpkin Hollow)to Proceed With Two-Stage Approach to Building Pumpkin Hollo...
4/17/2013s Permitting and Yerington Land Bill Status
4/17/2013s Permitting and Yerington Land Bill Status
3/28/2013Closes US$200 Million Loan Facility and Concentrate Off-Take...
3/11/2013North Deposit Mineralization Continues to Expand Intersectin...
2/15/2013-Permitting and Feasibility Study Update
1/3/2013Status of Congressional Action-Lyon County Land Bill
10/30/2012North Deposit Mineralization Remains Open Intersecting 119 F...
10/19/2012Files Resource Update NI 43-101 Technical Report on SEDAR
10/5/2012to Purchase 17.8% of Mercator Minerals
9/5/2012Governor Sandoval's Trade Mission to China and South Korea
8/9/2012Drilling Continues to Expand Shallow Mineralization in the S...
7/10/2012Submits Mine Development Permit Applications and Announces D...
6/20/2012-Project Update/Land Bill Passed by the House
6/5/2012s Permitting and Yerington Land Conveyance
5/29/2012Intersects 470 Feet at 0.73% Copper in the North Deposit
4/19/2012Provides an Update on House Subcommitee Hearing on Yerington...
4/10/2012Mineralization Continues to Expand in the North Deposit; Lan...
3/26/2012Announces Introduction of Land Conveyance Bill in the United...
3/13/2012Intersects 9.08% Copper in Open Pittable North Deposit
2/27/2012Appoints New Director & Launches Project Website
2/22/2012Breaks Ground on Underground Shaft
2/16/2012Announces Introduction Of Yerington Land Conveyance Bill
2/7/2012Files Feasibility Study on SEDAR
1/23/2012Announces Positive Feasibility Study Results
1/17/2012(Pumpkin Hollow)Hosts Conference Call to Discuss Pumpkin Hollow Definitive F...
1/9/2012North Deposit Continues to Expand-NC1127 Intersects Minerali...
12/16/2011Announces Selection of Underground Contractor
11/29/2011Coppper-Update on Underground Contractor Selection & Feasibi...
9/29/2011Annnounces Management Addition and Shaft Contract Update
9/19/2011-Feasibility Study Update and Land Transfer
9/7/2011Mineralization Continues to Expand, Intersecting Over 600 Fe...
8/16/2011North Deposit Continues to Expand, Drilling Multiple Interva...
6/14/2011Expands North Deposit Intersecting 785 Feet of 0.73% Copper ...
5/25/2011Steps Out and Drills 126 Feet of 1.26% Copper/Definitive Fea...
5/3/2011(Pumpkin Hollow)Intersects 1,164 Feet of 0.49% Copper in the Pumpkin Hollow ...
12/1/2009Robust Economic Results
12/1/2009Reports robust economic results
11/3/2009Capstone Mining Makes Strategic Investment in Nevada Copper
6/29/2009US$2,000,000 Convertible Debenture
5/2/2007Press Release: Augusta Files Q1 Financials - Negotiates Sale...
Comments closed
 
Latest comment posted for this article
Be the first to comment
Add your comment
TORONTO (NCU.TO)FRANKFURT (ZYT.F)
0.100+5.26%0.045-4.26%
TORONTO
CA$ 0.100
04/23 16:03 0.010
5.26%
Prev close Open
0.095 0.095
Low High
0.095 0.105
Year l/h YTD var.
0.060 -  0.140 -28.57%
52 week l/h 52 week var.
0.060 -  0.355 -72.97%
Volume 1 month var.
133,519 -9.09%
24hGold TrendPower© : 20
Produces
Develops Copper - Gold - Silver
Explores for
 
 
 
Analyse
Interactive chart Add to compare
Interactive
chart
Print Compare Export
Last updated on : 3/23/2010
You must be logged in to use the porfolio and watchlists (free)
Top Newsreleases
MOST READ
Annual variation
DateVariationHighLow
2024-33.33%
2023-48.28%0.420.14
2022-53.23%0.790.20
2021327.59%1.220.07
2020-60.27%0.380.06
 
5 years chart
 
3 months chart
 
3 months volume chart
 
 
Mining Company News
Plymouth Minerals LTDPLH.AX
Plymouth Minerals Intersects Further High Grade Potash in Drilling at Banio Potash Project - Plannin
AU$ 0.12-8.00%Trend Power :
Santos(Ngas-Oil)STO.AX
announces expected non-cash impairment
AU$ 7.75+0.52%Trend Power :
Oceana Gold(Au)OGC.AX
RELEASES NEW TECHNICAL REPORT FOR THE HAILE GOLD MINE
AU$ 2.20+0.00%Trend Power :
Western Areas NL(Au-Ni-Pl)WSA.AX
Advance Notice - Full Year Results Conference Call
AU$ 3.86+0.00%Trend Power :
Canadian Zinc(Ag-Au-Cu)CZN.TO
Reports Financial Results for Q2 and Provides Project Updates
CA$ 0.12+4.55%Trend Power :
Stornoway Diamond(Gems-Au-Ur)SWY.TO
Second Quarter Results
CA$ 0.02+100.00%Trend Power :
McEwen Mining(Cu-Le-Zn)MUX
TO ACQUIRE BLACK FOX FROM PRIMERO=C2=A0
US$ 11.11+2.21%Trend Power :
Rentech(Coal-Ngas)RTK
Rentech Announces Results for Second Quarter 2017
US$ 0.20-12.28%Trend Power :
KEFIKEFI.L
Reduced Funding Requirement
GBX 0.55+0.18%Trend Power :
Lupaka Gold Corp.LPK.V
Lupaka Gold Receives First Tranche Under Amended Invicta Financing Agreement
CA$ 0.06-8.33%Trend Power :
Imperial(Ag-Au-Cu)III.TO
Closes Bridge Loan Financing
CA$ 2.47+3.78%Trend Power :
Guyana Goldfields(Cu-Zn-Pa)GUY.TO
Reports Second Quarter 2017 Results and Maintains Production Guidance
CA$ 1.84+0.00%Trend Power :
Lundin Mining(Ag-Au-Cu)LUN.TO
d Share Capital and Voting Rights for Lundin Mining
CA$ 15.25-3.42%Trend Power :
Canarc Res.(Au)CCM.TO
Canarc Reports High Grade Gold in Surface Rock Samples at Fondaway Canyon, Nevada
CA$ 0.24+0.00%Trend Power :
Havilah(Cu-Le-Zn)HAV.AX
Q A April 2017 Quarterly Report
AU$ 0.19+0.00%Trend Power :
Uranium Res.(Ur)URRE
Commences Lithium Exploration Drilling at the Columbus Basin Project
US$ 6.80-2.86%Trend Power :
Platinum Group Metals(Au-Cu-Gems)PTM.TO
Platinum Group Metals Ltd. Operational and Strategic Process ...
CA$ 1.79-3.76%Trend Power :
Devon Energy(Ngas-Oil)DVN
Announces $340 Million of Non-Core Asset Sales
US$ 52.57+0.84%Trend Power :
Precision Drilling(Oil)PD-UN.TO
Announces 2017Second Quarter Financial Results
CA$ 8.66-0.35%Trend Power :
Terramin(Ag-Au-Cu)TZN.AX
2nd Quarter Report
AU$ 0.04+0.00%Trend Power :