Chart usGOLD   Chart usSILVER  
 
Food for thought
To think is to speak low, to speak is to think loud
Max Mueller  
Search for :
LATEST NEWS  :
MINING STOCKS  :
Subscribe
Write Us
Add to Google
Search on Ebay :
PRECIOUS METALS (US $)
Gold 1394.5017.80
Silver 22.860.39
Platinum 1469.759.75
Palladium 747.703.50
WORLD MARKETS
DOWJONES 1538853
NASDAQ 35026
NIKKEI 15627246
ASX 5142-14
CAC 40 4026-10
DAX 8466-6
HUI 254-7
XAU 97-3
CURRENCIES (€)
AUS $ 1.3237
CAN $ 1.3334
US $ 1.2932
GBP (£) 0.8571
Sw Fr 1.2591
YEN 133.1800
CURRENCIES ($)
AUS $ 1.0241
CAN $ 1.0307
Euro 0.7734
GBP (£) 0.6629
Sw Fr 0.9736
YEN 102.9730
RATIOS & INDEXES
Gold / Silver61.00
Gold / Oil14.52
Dowjones / Gold11.03
COMMODITIES
Copper 3.400.06
WTI Oil 96.05-0.66
Nat. Gas 4.18-0.02
Market Indices
Metal Prices
RSS
Precious Metals
Graph Generator
Statistics by Country
Statistics by Metals
Advertise on 24hGold
Projects on Google Earth
( 0 vote, 0/5 ) Print article
     
Tweet

 

NPV of US$960.0M and IRR of 17.7%
(After tax, long term copper price of US$2.25 /lb, and 8% discount rate)

Copper Production to Average 262 million Pounds per Year
Over Mine Life of 22 Years



Vancouver, British Columbia, January 18, 2011. Candente Copper Corp. (TSX:DNT, BVL:DNT, US:CDOUF) ("Candente") is very pleased to announce receipt from AMEC Americas Limited ("AMEC") of a positive Pre-Feasibility Progress Report for its 100% owned Ca�ariaco Norte copper project in Northern Peru.

Based on projected annual production of 262 million lbs of copper, 39,000 ozs of gold and 911,000 ozs of silver over a mine life of 22 years, the Ca�ariaco Norte project has an after tax net present value ("NPV") of US$960.0M, and after tax Internal Rate of Return ("IRR") of 17.7% using a long term copper price reverting to US$2.25 /lb and a discount rate of 8%.

The key parameters of the Pre-Feasibility Progress Report are as follows:

  • After-tax NPV of US$960.0M for base case with US$2.25 /lb Cu, US$1,015 /oz gold, US$15.85 /oz silver, and 8% discount rate
  • After-tax IRR of 17.7% for base case with US$2.25 /lb Cu, US$1,015 /oz gold, and US$15.85 /oz silver
  • Highly leveraged to higher copper price
  • Payback of preproduction capital in 3.1 years
  • Cash operating cost of US$0.99 /lb of copper including all on-site and off-site costs, TCRC charges, net of by-product credits
  • Average metal production of 262 million pounds (119,000 tonnes) copper /yr, 39,000 ozs gold per year, and 911,000 ozs silver per year
  • Average production of 306 million pounds (139,000 tonnes) copper /yr for first 3 years of production
  • Preproduction capital cost of US$1.437 billion based on leased mining equipment and including contingency of 20%
  • All in capital cost of US$1.565 billion based on leased mining equipment and including working capital, life-of-mine sustaining capital, and closure cost
  • Processing rate of 95,000 t/day using conventional crush/grind and flotation technology
  • Waste to ore strip ratio of 0.98 to 1
  • Average life-of-mine metal recoveries of 89.7% for copper, 55% for gold and 50% for silver
  • Concentrate grades average approximately 30% copper, 3 g/t gold and 73 g/t silver
  • 22 year mine life, with potential for extension by mining additional resources identified below proposed pit
  • Ca�ariaco Norte is located at a moderate elevation with pit centroid and process plant at approximately 3,000 metres above sea level;
  • Connection to national power grid approximately 57 km
  • New access road to major paved highway approximately 42 km
  • Significant potential for discovery of additional resources at nearby Ca�ariaco Sur and Quebrada Verde targets


Management Discussion

"We are very pleased with the results of the Ca�ariaco Norte Pre-Feasibility Progress Report," stated Sean Waller, P.Eng., President of Candente. "The work completed by Candente and AMEC during 2010 certainly demonstrates the very attractive technical and financial parameters of the Ca�ariaco Norte project. With the significant increase in the size of the resource announced late last year, a solid scope of development and robust financials, Ca�ariaco Norte is rapidly evolving into one of the premier undeveloped large scale copper projects in the world - with the added benefit of being located in Peru."

The Ca�ariaco Norte project offers many advantages. It is reasonably close to key road and power infrastructure, has a low strip ratio, soft rock, low operating cost, offers excellent potential for discovery of additional resources, and is located in Peru, one of the most favourable countries in the world for mining project development.

Candente advises readers that additional geotechnical drilling and rock quality assessment is required to complete the open pit slope design to a level consistent with generally accepted prefeasibility requirements. Due to the preliminary level of pit wall design, this report does not meet the criteria of a Pre-Feasibility Study and therefore is classified as a Pre-Feasibility Progress Report.

The above ground structures in the tailings management facility ("TMF") have been designed to a pre-feasibility level, however geotechnical investigations in the TMF area have not been completed and as a result there is a risk that the TMF design may require revision. The remainder of the Pre-Feasibility Study Progress Report does however meet a pre-feasibility level of assessment, and Candente is satisfied that this report provides sufficient level of project development to justify advancement to a Feasibility Study.

Conference Call

Candente will host a telephone conference call for investors and analysts on Tuesday, January 18th, at 5:30 am Pacific (8:30 am Eastern, 1:30 pm GMT) to discuss the Pre-Feasibility Progress Report for the Ca�ariaco Norte Copper Project, Peru.

Sean Waller, President and Joanne Freeze, CEO will review the report and take questions.

The conference call may be accessed by calling:

Toll-free 1-877-240-9772 in Canada and the United States
1-800-2787-2090 internationally
1-416-340-8530 in the Toronto area
The conference call can also be heard in real time at www.candentecopper.com



The conference call will be archived for later playback and may be accessed by dialing 1-905-694-9451or 1-800-408-3053 and entering the pass code 7678614, or at www.candentecopper.com. The archived playback will be available until February 1, 2011.

Financial Analysis

The Net Present Values of the Ca�ariaco Norte project at various copper price points and discount rates are presented below. Candente has selected as the Base Case a long term copper price of US$2.25 /lb. The financial model applied by AMEC utilizes a reverting price curve whereby metal prices in the early years of operation are higher and gradually decrease to fixed long term prices after year 10. This approach recognizes the industry consensus view that future copper and precious metal prices will remain higher than historical price trends over the short to medium term, with reversion to lower long term prices.

For the Base Case with year 1 production anticipated in 2015, the initial copper price is US$2.92 /lb reverting to US$2.25 /lb after year 10; a gold price of US$1,159 /oz reverting to US$1,015 /oz; and a silver price of US$20.96 /oz reverting to US$15.85 /oz.

As of January 2011, AMEC is applying long term metal prices of US$2.40 /lb copper, US$1,015 /oz gold and US$15.85 /oz silver. The Ca�ariaco Norte project is highly leveraged to the price of copper. At long term copper prices of US$2.40 /lb and above, the after tax NPVs and IRRs increase significantly. Sensitivity to the copper price is presented below:

Table 1: Project Net Present Value & IRR (After Tax)

 

NPV (US$M)

 

Long Term Copper Price US$ /lb

 

 

Base Case

AMEC

 

 

 

$2.00

$2.25

$2.40

$2.75

$3.00

Undiscounted
Cumulative Net Cash Flow

$2,742

$3,575

$4,072

$5,224

$6,041

Discounted

 

 

 

 

 

6%

$938

$1,355

$1,604

$2,177

$2,583

8%

$617

$960

$1,164

$1,634

$1,967

10%

$373

$659

$829

$1,220

$1,497

IRR%

14.6%

17.7%

19.5%

23.3%

25.8%


Table 2: Project Net Present Value & IRR (Pre-Tax)

 

NPV (US$M)

 

Long Term Copper Price US$ /lb

 

 

Base Case

AMEC

 

 

 

$2.00

$2.25

$2.40

$2.75

$3.00

Undiscounted
Cumulative Net Cash Flow

$4,335

$5,649

$6,421

$8,209

$9,478

Discounted

 

 

 

 

 

6%

$1,766

$2,414

$2,800

$3,691

$4,320

8%

$1,303

$1,836

$2,152

$2,883

$3,399

10%

$950

$1,394

$1,658

$2,266

$2,695

IRR%

20.9%

25.2%

27.6%

32.7%

36.1%



The financial model is based on open pit mining by the owner with leased supply of mobile mining equipment including scheduled additions and replacements. All other project costs are the responsibility of the owner including process and infrastructure preproduction capital, life-of-mine sustaining capital, and closure costs. Peru corporate income tax of 30%, employee profit sharing tax of 8% and the Peru mineral production royalty is applied on a sliding scale of 1% to 3% according to revenue levels. Depreciation on capital equipment as permitted by Peru tax regulations has been applied. Finance charges for project construction capital have not been applied in the model.

The mine plan is based on Measured and Indicated mineral resources only, with Inferred mineral resources considered as waste. Mineral resources that are not mineral reserves do not have demonstrated economic viability.

Capital Costs

Preproduction direct capital costs for the 95,000 tonnes per day project are estimated to be US$904.6 million which includes US$171.9 million for mine preproduction development, US$381.3 million for process plant, US$101.5 million for tailings management facility, US$26.9 million for concentrate storage and handling facilities at the load-out port, and US$223.0 million for infrastructure including diversion channel, access road, and connection to the national power grid. Indirects, owner's cost, and contingency total US$532.5 million.

The capital cost estimate is predominantly based on 3rd quarter 2010 costs. In addition to the capital cost, the financial analysis includes owner's preproduction costs of US$52.9 million, working capital of US$65.7 million, sustaining capital and closure costs of US$128.1 million.

Table 3: Capital Cost Summary

Cost Area

Cost (US$ x 1,000)

Prestripping

$70,008

Mining Infrastructure & Equipment

$101,942

Processing Plant & Acid Plant

$381,277

Site Related Infrastructure (inc. Power)

$133,444

Tailings Management

$101,527

Project Access Road

$38,795

Diversion Channel and Reservoir

$50,753

Port Site

$26,887

Subtotal -- Directs

$904,633

Indirects

$243,076

Owner's Cost

$52,899

Contingency

$236,552

Subtotal - Indirects

$532,527

TOTAL PREPRODUCTION CAPITAL

$1,437,160

 

 

Sustaining Capital (Life-of-Mine)

$70,438

Closure Costs

$57,650

Subtotal Life-of-Mine

$128,088

TOTAL PROJECT CAPITAL COSTS

$1,565,248



Capital cost for the mobile mining equipment including drills, haul trucks and shovels (LOM total of US$291,773) is excluded and would be supplied under a lease agreement with the equipment supplier.

Operating Costs

Mine site cash operating costs are projected to be US$6.28 per tonne processed or US$0.82 per pound of payable copper produced. All-in C1 cash costs including concentrate transportation, off-site smelting and refining, applicable taxes, and by-product credits (gold, silver, and sulphuric acid) are projected to be US$0.995 per pound of payable copper.

Table 4: Operating Costs Summary

Area

Unit

US$

Unit

US$ /lb Cu

 

 

 

 

 

On-site Costs

 

 

 

 

Mining

$/t processed

$2.74

$/lb Cu

$0.360

Processing

$/t processed

$3.11

$/lb Cu

$0.408

General & Administration

$/t processed

$0.43

$/lb Cu

$0.056

Sub-total Site Costs

$/t processed

$6.28

$/lb Cu

$0.824

 

 

 

 

 

Off-site Costs

 

 

 

 

Concentrate Transport--Land

$/t concentrate

$21.00

$/lb Cu

$0.035

Concentrate Handling--Port

$/t concentrate

$12.06

$/lb Cu

$0.020

Concentrate Transport--Ocean

$/t concentrate

$52.30

$/lb Cu

$0.086

Smelting & Refining

$/t concentrate

$181.31

$/lb Cu

$0.280

Sub-total Off-site Costs

$/t concentrate

$266.67

$/lb Cu

$0.421

Total Cost On-Site & Off-Site

$/lb Cu

$1.245

Credits (Gold, Silver, Acid)

$/lb Cu

$0.250

Total Cost

$/lb Cu

$0.995



Ca�ariaco Norte Project Description

An outline of the Ca�ariaco Norte project including mineral resources, mining, processing, product handling, and financial analysis is provided below. The development scope for Ca�ariaco Norte is based on proven industry technology.

Mineral Resources

The mine plan and production parameters for the Pre-Feasibility Progress Report are based on the Mineral Resources below (previously reported in Candente Copper NR010, Nov. 1, 2010).

Table 5: Mineral Resource Estimate (0.30% Copper Cut-off Grade)

 

 

 

 

 

 

 

Contained Metal

Resource
Classification

tonnes
(M)

Cu Eq*

Cu Eq**

Cu

Au
(g/t)

Ag
(g/t)

Copper
(B lbs)

Gold
(M Ozs)

Silver
(M Ozs)

Measured

338.1

0.55%

0.52%

0.48%

0.08

2.0

3.587

0.870

21.635

Indicated

414.3

0.49%

0.46%

0.43%

0.06

1.8

3.945

0.799

23.602

Measured+
Indicated

752.4

0.52%

0.49%

0.45%

0.07

1.9

7.533

1.669

45.237

Inferred

157.7

0.47%

0.44%

0.41%

0.06

1.8

1.434

0.304

8.932


*Copper equivalent grade including gold and silver values and based on 100% metal recoveries. Copper grade equivalent calculation. Cu Eq% = (Cu % + ((Au grade x Au price) + (Ag grade x Ag price)) / (22.0462 x Cu price x 31.0135 g/t)

**Copper equivalent grade including gold and silver, metal recoveries (gold 55%; silver 50%) and smelter returns (copper 96.5%: gold 93%; silver 90%) applied. Copper grade equivalent calculation: Cu Eq% =(Cu % + ((Au grade x Au price x Au recovery x Au smelter return%)+(Ag grade x Ag price x Ag recovery x Ag smelter return%))/(22.0462 x Cu price x 31.0135 g/t x Cu recovery x Cu smelter return%)


This updated mineral resource estimate is based on 230 drill holes and includes the results of 16 drill holes completed after the previous estimate by SRK Consulting (Canada) Inc. in September 2008, as well as a review of the deposit lithology, alteration and specific gravities. Metal prices used by AMEC for the updated resource estimate are: copper US$2.50 /lb, gold US$1,035 /oz and silver US$17.25 /oz.

Mining

The Ca�ariaco Norte copper project will see development of a large scale open pit mine utilizing conventional truck and shovel mining. The mine plan calls for the extraction of 728.2 million tonnes of mineralized material and 713.5 million tonnes of waste over the projected 22 year mine life (strip ratio of 0.98 to 1). Average life-of-mine head grades to the process plant will be 0.40% copper, 0.067 g/t gold and 1.71 g/t silver. Importantly, the mine grades during the first three years of production will be higher, with average feed grades of 0.48% copper, 0.086 g/t gold and 2.14 g/t silver.

The open pit mine design relating to the angle of the pit wall slopes has been developed based on geotechnical logging of drill core plus rock quality evaluation and compressive strength testing of a limited number of core samples. The amount of geotechnical data available is not sufficient however to support development of a pre-feasibility level design for the pit wall slopes. As a result, the mine plan developed for this report must be considered to be at a preliminary level.

In the absence of sufficient geotechnical data AMEC has applied overall pit slopes of 35 degrees on the high west wall and south wall, and 44 degrees on the lower north and east walls. Additional geotechnical drilling in the pit area is required to permit a pre-feasibility and feasibility level pit wall design. Candente plans to complete the required geotechnical drilling and rock quality testing as part of a Feasibility Study program.

Metallurgy and Process

Grinding and flotation test work was performed by SGS Lakefield located in Santiago, Chile, under the direction of Transmin Metallurgical Consultants in Lima. Preliminary concentrate roasting test work for the removal of arsenic was conducted by Outotec Oyj in Sweden.

The metallurgical test work confirms that conventional crushing, grinding and flotation technologies are appropriate for the recovery of copper, gold and silver from the Ca�ariaco Norte deposit. The preliminary concentrate roasting test work supports the application of this technology for the reduction of arsenic in the Ca�ariaco Norte concentrate.

Processing will utilize primary crushing, semi-autogenous and ball mill grinding for size reduction followed by rougher and cleaner flotation for copper recovery and production of copper concentrate. The copper concentrate will then be subjected to a partial concentrate roast process at site to reduce arsenic levels and improve the marketability of the copper concentrate.

Final copper concentrate will be trucked to a load-out port facility near Eten in Northern Peru for ocean shipment to offshore smelters. Sulphuric acid produced as a by-product of the roasting process will be upgraded and sold to consumers in western South America. Process tailings will be contained at the project site in a facility design for long term tailings management.

Water Management

Candente management recognizes and fully respects the importance of water to both the daily lives of the surrounding communities and agricultural projects downstream. For Ca�ariaco Norte, a controlled water management system has been developed and preliminary engineering studies indicate that the Ca�ariaco Norte project will have minimal impact on the local water resources.

Local ground water and surface water courses within the proposed mine area are expected to be adequate to supply the majority of water required for the proposed mine operation. Discharge of water to the environment is anticipated only after project closure. The water management system will ensure that discharge streams meet the appropriate Peruvian regulations for water quality and be suitable for downstream agricultural usage. As part of the next phase of project engineering study Candente plans to work with the local community to assess opportunities for the provision and distribution of water for agricultural purposes.

Environment and Community

Development of the Ca�ariaco Norte project would result in a significant increase in local and regional employment opportunities and would generate significant ongoing expenditures to regional and national suppliers for goods and services required for mine operation. Furthermore, the Ca�ariaco Norte mine would provide a substantial long-term addition to the tax base for the Lambayeque region.

In keeping with world best practice, Candente intends to follow the Equator Principals and World Bank Standards for the proposed mining development at Ca�ariaco Norte.
These protocols outline best practices for developing projects with regard to protecting the environment, biodiversity and managing social impact.

Permitting Advances

Environmental and Social Impact Assessment ("ESIA") studies have been underway since 2007 with AMEC Peru S.A., an internationally recognized environmental consultant in Lima. The assessment is ongoing but at this point there are no findings that suggest the project would not meet environmental approval. Candente has received several permits for certain aspects of Ca�ariaco Norte development and previously received a Certificate from the Peruvian National Institute for Culture confirming that no archaeological remains exist in the area of the Ca�ariaco Norte pit.

Timeline

The proposed timeline for project development to production is scheduled to be approximately four years after commencement of a Feasibility Study.

Opportunities

Based on the work completed to date there are several significant opportunities that may offer the potential to further enhance the Ca�ariaco Norte project including:

The mine plan for the first 18 months of operations may be optimized to maximize the IRR and reduce project payback period.

The Ca�ariaco Norte deposit is open to depth and the potential exists for the mine life to be extended beyond the 22 years proposed in this report and/or the mining and processing rate to be increased. Both opportunities offer the potential to enhance the economics of the Ca�ariaco Norte project.

The potential exists to discover and delineate additional resources at the Ca�ariaco Sur and Quebrada Verde targets which are located approximately 1.5 kms and 3.5 kms south of the Ca�ariaco Norte deposit. These targets are located within Candente's Ca�ariaco property and, should an economic deposit be delineated at either site, it is possible that development would utilize the proposed Ca�ariaco Norte facilities.

Risks

As with most projects at this level of assessment, risks exist that may affect the development of the project. Factors that could pose a risk to the Ca�ariaco Norte project include changes in world commodity markets, equity markets, costs and supply of labour and materials relevant to the mining industry, extent of resources actually contained in mineral deposits, geotechnical conditions, actual recoveries achieved in processing ore, marketing of concentrate, technological change, water management, local community opposition, environmental permitting, change in government and changes to regulations affecting the mining industry.

Qualified Persons and NI 43-101 Technical Report

The Pre-Feasibility Progress Report summarized here for the Ca�ariaco Norte project was completed by AMEC Americas Limited, of Vancouver British Columbia, a preeminent international mining and metals engineering firm.

The findings of the Pre-Feasibility Progress Report will be disclosed in a NI 43-101 Technical Report which will be completed and available on SEDAR and Candente Copper's website within 45 days from the date of this news release.

The qualified persons for the Mineral resource Estimate and Pre-Feasibility Progress Report are identified below:

Mr. David Thomas, P.Geo. Principal Geologist with AMEC and an independent Qualified Person as set forth by NI 43-101. Responsible for the Ca�ariaco Norte Mineral Resource Estimate reported on November 1, 2010 and included in the Pre-Feasibility Progress Report.

Ms. Alexandra Kozak, P.Eng. Manager of Process with AMEC and an independent Qualified Person as set forth by NI 43-101. Ms Kozak served as AMEC's project manager for the Ca�ariaco Norte Pre-Feasibility Report. Ms. Kozak is responsible for project capital costs and financial analysis.

Mr. Tony Lipiec, P.Eng. Principal Metallurgist with AMEC and an independent Qualified Person as set forth by NI 43-101, responsible for metallurgy and process, process equipment capital costs, process operating costs, and general and administration operating costs.

Mr. Jay Melnyk, P.Eng. Principal Mining Engineer with AMEC and an independent Qualified Person as set forth by NI 43-101, responsible for mine design and mine capital and operating costs.

About Candente Copper

Candente Copper's flagship project is the 100% owned, 7.5 billion pound, pre-feasibility stage Ca�ariaco Norte Copper Project located in northern Peru's prolific mining district. The Ca�ariaco Norte deposit contains a Measured and Indicated resource of 752 million tonnes grading 0.45 % copper, 0.07 g/t gold and 1.90 g/t silver.
____

Sean Waller, P.Eng., President and Stacy Freudigmann, P.Eng., Candente Project Manager are the Qualified Persons as defined by National Instrument 43-101 for the projects discussed above. They have reviewed and approved the contents of this release. This news release may contain forward-looking statements including but not limited to comments regarding the timing and content of upcoming work programs, geological interpretations, receipt of property titles, potential mineral recovery processes, etc. Forward-looking statements address future events and conditions and therefore involve inherent risks and uncertainties. Actual results may differ materially from those currently anticipated in such statements. Candente relies upon litigation protection for forward-looking statements.

CAUTIONARY NOTE TO U.S. INVESTORS

We advise U.S. investors that this news release uses terms that are not recognized by the United States Securities and Exchange Commission ("SEC"), including "mineral resources", "measured resources", "indicated resources" and "inferred resources". The estimation of measured and indicated resources involves greater uncertainty as to their existence and economic feasibility than the estimation of proven and probable reserves. U.S. investors are cautioned not to assume that mineral resources in these categories will be converted to reserves. The estimation of inferred resources involves far greater uncertainty as to their existence and economic viability than the estimation of other categories of resources. U.S. investors are cautioned not to assume that estimates of inferred mineral resources exist, are economically mineable, or will be upgraded into measured or indicated mineral resources. U.S. investors are cautioned not to assume that mineral resources in any of these categories will be converted into reserves.


On behalf of the Board of Candente Copper Corp.
"Sean Waller" P.Eng.
President & Director
______________________________________

For further information please contact:

John Foulkes
VP Corporate Development
mobile: +1 (604) 614-2999
local: + 1 (604) 689-1957 ext 2
toll free: 1 (877) 689-1964 ext 2
info@candentecopper.com

or:

Walter Spagnuolo
Manager, Investor Relations
mobile: +1 (604) 306-8477
local: + 1 (604) 689-1957 ext 3

www.candente.com


Data and Statistics for these countries : Peru | All
Gold and Silver Prices for these countries : Peru | All
Tweet

Candente Copper Corp.

DEVELOPMENT STAGE
CODE : DNT.TO
ISIN : CA13739Y1060
Follow and Invest
Add to watch list Add to your portfolio Add or edit a note
Email Alert Add to Watchlist Add to Portfolio Add Note
ProfileMarket
Indicators
VALUE :
Projects & res.
Press
releases
Annual
report
RISK :
Asset profile
Contact Cpy
Your feedback is appreciated, please leave a comment or rate this article.
Rate : Average note :0 (0 vote) View Top rated
 
Annual reports of Candente Copper Corp.
2007 Annual report
2006 Annual report
Financings of Candente Copper Corp.
2/17/2011Announces Closing of $26.9 Million Bought Deal and $3.2 Mill...
3/4/2010Increases Size of Private Placement
2/17/2010Terms and Commitments of Private Placement
2/12/2010Private Placement
7/8/2009Terms of Private Placement of Candente Gold Corp
6/26/2008Private Placements Oversubscribed and Closed
6/16/2008 Private Placements Fully Committed
6/13/2008Private Placements Amended
6/9/2008 Announces Private Placements
6/8/2007Private Placement Closed and Amerigo Acquires Position in Ca...
5/30/2007Private Placement Increased
5/15/2007Announces Private Placement
Nominations of Candente Copper Corp.
8/16/2012Appoints CFO
1/25/2011Appoints John Black to Board of Directors
7/19/2010Appoints Michael Thicke as VP Exploration
12/5/2008 Appointment of CFO
8/7/2008Announces Management Appointments
Financials of Candente Copper Corp.
11/13/2009Financial Results for Quarter Ended Setember 30, 2009 & Cana...
8/12/2009Financial Results For Quarter Ended
5/15/2009Financial Results forthe quarter ended march 31, 2009
3/31/2009 Financial Results for the Year Ended December 31, 2008
Project news of Candente Copper Corp.
2/19/2013(Cañariaco)Intersects 113.5 metres of 0.42% Copper Equivalent(i) (CuEq)...
4/6/2011(Cañariaco)Commences Feasibility Study on the Canariaco Norte Copper Pr...
3/22/2011(Cañariaco)Plans Exploration Drilling for 2011-Drill Programs Planned f...
3/7/2011Files NI 43-101 Technical Report and Updates Key Financial R...
1/18/2011(Cañariaco)Announces Positive Pre-Feasibility Progress Report for the C...
12/17/2010(Cañariaco)Files 43-101 Technical Report for the Canariaco Norte Copper...
11/29/2010(Cañariaco)Canariaco Norte Pre-Feasibility Study Update
11/1/2010(Cañariaco)Canariaco Norte Copper Resource Increases Significantly
7/22/2010(Cañariaco)Provides an Update on the Norte Pre-Feasibility Study
6/28/2010Awards AMEC the Canariaco Norte Pre-Feasibility Study Contra...
6/22/2010(El Oro)Gold Begins Underground Drilling
3/25/2010(Cañariaco)Resumes Feasibility Studies & Exploration
6/26/2009(El Oro Mexico)Candente Gold Provides More Detail on Historic Resources on ...
2/27/2009(El Oro Mexico)Corporate Update
12/12/2008(Cañariaco)Preliminary Economic Assessment on Ca=F1ariaco Norte Copper ...
10/30/2008(Cañariaco)Resource Corp.: Canariaco Norte Technical Parameters for the...
10/2/2008(Cañariaco)Discovers a Second Copper-Gold Porphyry on the Canariaco pro...
9/18/2008(Cañariaco)Gold and Silver Added to Canariaco Norte Mineral Resource Es...
5/29/2008(Cañariaco)Updates Canariaco Norte Mineral Resource Estimate
1/15/2008(Cañariaco) Initial Flotation Results for the Canariaco Norte Copper De...
10/25/2007(Cañariaco)Third Drill Mobilized to Test Southern Extension to Canariac...
10/4/2007(El Oro Mexico) and Canaco Resources Inc.: Drilling Intersects Vertical Ext...
8/29/2007(Cañariaco)Intersects 702 Metres of 0.59% Cu at Canariaco Norte, Peru
7/25/2007(Cañariaco)Copper Mineralization Extended to Depth of 767 Metres at Can...
7/11/2007High Grade Silver in Veins and Gold in Vuggy Silica Found
4/20/2007(Cañariaco)Upgraded Starter Pit Shows Robust Economics at Canariaco No...
Corporate news of Candente Copper Corp.
5/17/2013Canariaco Norte Project Update
5/9/2013(Cañariaco)Drills 308m at 0.32% Copper Equivalent(i) at Cañariaco Sur
4/11/2013Drills 225m at 0.42% Copper Equivalent (CuEq)(i) at Canariac...
2/28/2013Extends Copper Gold Mineralization at Canariaco Sur
1/23/2013s Drilling at Canariaco
1/3/2013Commences Drilling at Canariaco
12/6/2012Temporary Road Blockage in Canaris
10/1/2012Provides Comment on Recent Community Activities in Peru
10/13/2011Shareholder Rights Plan Becomes Effective
5/17/2011to Form a New Copper and Base Metals Exploration Company
3/9/2010Completes $6.2 Million Financing
12/31/2009Closing Financing of $9 Million and Listing of Candente Gold...
12/17/2009Closing First Tranche of $6.8 Million and Listing of Candent...
9/10/2009Resource Corp. and Candente Gold Corp.-Update
7/30/2009Candente Gold Corp.-Toronto Stock Exchange Conditional Listi...
6/16/2009 Engagement of BMO Capital Markets for Financing and Schedul...
11/17/2008Results and Summary for the Nine Months Ended September 30, ...
8/15/2008Results and Summary for the Six Months Ended June 30, 2008
4/3/2008Results For The Fiscal Year Ended December 31, 2007
3/13/2008Corporate and Canariaco Project Update
3/12/2008Termination of U.S. Registration of Common Shares
8/29/2007Santa Luisa Returns Candente's El As de Zinc Property in Cen...
8/23/2007Has No Direct Exposure to Asset-Backed Commercial Paper
8/16/2007Personnel and Projects Are Safe and All Activities Operate a...
8/16/2007Results for the Period Ending June 30, 2007
5/11/2007Reverts to 100% Ownership at Pamel Property in Peru
4/2/2007Gets Attention in Chile
Comment this article
You must be logged in to comment an article8000 characters max.
 
Sign in
User : Password : Login
Sign In Forgot password?
 
Latest comment posted for this article
Be the first to comment
Add your comment
TORONTO (DNT.TO)
0.290-3.33%
TORONTO
CA$ 0.290
05/21 15:55 -0.010
-3.33%
Prev close Open
0.300 0.290
Low High
0.280 0.290
Year l/h YTD var.
0.270 -  0.610 -29.27%
52 week l/h 52 week var.
0.270 -  0.680 -50.85%
Volume 1 month var.
126,900 -%
24hGold TrendPower© : -22
Produces
Develops Copper - Gold - Silver
Explores for Copper - Gold - Iron - Molybdenum - Silver
 
 
 
Analyse
Interactive chart Add to compare
Interactive
chart
Print Compare Export
You must be logged in to use the porfolio and watchlists (free)
TOP NEWSRELEASES
Annual variation
DateVariationHighLow
2013-49.12%
2012-43.00%1.210.45
2011-42.53%2.630.82
2010286.67%1.850.29
2009200.00%0.680.15
 
5 years chart
 
3 months chart
 
3 months volume chart