Midway Gold Announces Positive Prefeasibility Study for Pan Gold Project, Nevada

 

 

 

 

 

Midway Gold Corp. (TSX.V and NYSE Amex: MDW) (the "Company") announces the results of a positive Prefeasibility Study of its Pan gold project located in White Pine County, Nevada. The accompanying National Instrument (NI) 43-101 technical report will be filed on SEDAR within 45 days. This NI 43-101 report was independently prepared by Gustavson Associates, LLC ("Gustavson") of Lakewood, Colorado, and concludes that the Pan Project is economically viable and amenable to heap leach mining operations, as summarized below.

Highlights of the Prefeasibility Study (Base Case at $1,050/oz gold)

• Resource growth over the July 2010 Preliminary Economic Assessment
o 848,700 contained ounces in Measured and Indicated Resource categories at a grade of 0.016 oz gold per short ton at a 0.008 oz/ton cutoff grade
• Proven and Probable Reserves of 716,900 contained ounces grading 0.017 oz/ton gold
• Robust project economics
o Capital costs of US$79.25 million including 15% contingency
o Total cash operating costs (including taxes) projected to be $431 per oz
o Total cash costs (including royalties) projected to be $473 per oz
o Fully loaded production cost (cash costs and capital) is expected to be $666 per oz
o At $1,050 per oz gold, after-tax net present value (NPV) at 5% discount of US$91.1 million and internal rate of return (IRR) of 32.5% using a 0.008 oz/ton cutoff grade
o At $1,250 per oz gold, the NPV increases to approximately $142 million (55% higher)
o At $1,450 per oz gold, the NPV increases to approximately $192 million (111% higher)
• Project lifespan in excess of 9 years with heap leach stacking of 17,000 tons per day (tpd)
o Average of 77,000 ounces per year produced over 8.5 years of operation
• Average estimated recovery of 80% gold for the South Pit and 70% gold for the North Pit
• Life of mine (LOM) strip ratio of 1.40:1
• Expansion potential includes
o Inferred resources in the $1,050 pit
o Open mineralization at depth and along strike at North and South Pan

Pan Mineral Reserves and Resources

The open pit mineral reserves and resources were completed by Gustavson, with Ms. Terre A. Lane and Mr. Donald E. Hulse acting as the Qualified Persons (QP). The Prefeasibility Study demonstrates the project is economically viable therefore the Measured and Indicated Mineral Resources within the designed pits are considered Proven and Probable Reserves. Only the two main ore bodies (North Pan and South Pan) are included in the mine design. A 0.008 oz/ton cutoff grade resulted in the highest NPV for the project and is the selected Base Case. Mineral Reserves were based upon a design pit using Lerchs Grossmann generated pit surfaces that maximize revenue based on a $1,050 per ounce three-year trailing average price of gold.

The resource estimation includes all data collected through February 28, 2011, including 15 core holes drilled in 2010 by Midway as well as new lithology and alteration models for breccia controlled mineralization. Ordinary Kriging was used to estimate gold grades in a block model with blocks 20 feet wide, 20 feet long and 20 feet high. Measured and Indicated resource estimates are limited to drill intervals with fire assay results. Inferred resource estimates include all available assay data.

The mineral resources and reserves are summarized in Table 1 and Table 2 below.
Mineral resources are inclusive of mineral reserves.

Table 1: Gustavson Total Pan Mineral Resource, March 2011

Cutoff Grade
(gold oz/ton)

Short Tons
(x 1000)

Gold Grade
(gold oz/ton)

Ounces
(x 1000)

Measured

0.01

21,996

0.019

426.9

0.008

25,025

0.018

453.7

0.006

28,110

0.017

474.5

0.004

30,685

0.016

487.9

Indicated

0.01

21,273

0.016

346.2

0.008

26,814

0.015

394.8

0.006

32,162

0.013

432.2

0.004

36,629

0.013

456.1

Measured plus Indicated

0.01

43,269

0.018

770.7

0.008

51,839

0.016

848.7

0.006

60,272

0.015

909.8

0.004

67,314

0.014

946.2

Inferred

0.01

4,977

0.016

80.5

0.008

7,164

0.014

100.2

0.006

10,834

0.012

125.1

0.004

14,690

0.010

144.7

 

Table 2: Gustavson Total Pan Mineral Reserve, March 2011

Cutoff Grade
(gold oz/ton)

Short Tons
(x 1000)

Gold Grade
(gold oz/ton)

Ounces
(x 1000)

Proven

0.01

20,481

0.020

402.5

0.008

23,012

0.018

425.4

0.006

25,289

0.017

441.3

0.004

27,047

0.017

450.2

Probable

0.01

15,656

0.017

265.1

0.008

18,540

0.016

291.1

0.006

20,944

0.015

308.0

0.004

23,775

0.016

374.2

Proven plus Probable

0.01

36,137

0.018

667.6

0.008

41,553

0.017

716.5

0.006

46,233

0.016

749.3

0.004

50,822

0.016

824.4

Inferred within $1,050 Pit Design

0.01

530

0.015

8.1

0.008

774

0.013

10.3

0.006

1,110

0.011

12.6

0.004

1,542

0.010

14.8


Expansion Potential

Additional mineralization not included in the Prefeasibility Study includes Inferred resources in the $1,050 pit, open mineralization at depth and along strike at North and South Pan. Mineralization at North Pan has not been closed off at depth, particularly along the Pilot Shale-Devil's Gate Limestone contact, or to the north where it trends under Tertiary volcanic rocks. At the South Pan deposit, mineralization is open to the east and to the south where the deposit also trends under Tertiary volcanic rocks.

Mining and Production

Midway plans to use conventional open pit mining methods, using front end loaders and in-pit crush and convey with mobile jaw crushers and mobile conveyors conveying waste to the waste dump. The majority of the material from the mine will be drilled and blasted prior to loading. The initial mining fleet consists of two loaders, two jaw crushers, and two 100-ton trucks, with various support equipment. The mine plan produces 6.1 million tons of ore per year for delivery to the heap leach (17,000 tpd). Peak ore and waste production is estimated to be 52,000 tpd. The pit design is based on inter-ramp slope angles of 50 degrees for South Pan, 45 degrees for North Pan. The face slope angles are 70 degrees for South Pan and 63 degrees for North Pan.

Table 3: Operating Costs

Description

US$
Per ton of ore

US$
Per oz of gold

Mining

1.76

136.92

Processing

2.46

191.02

G&A

0.33

25.88

Production Taxes

0.50

38.44

Contingency -- 10%

0.51

39.23

Total Operating Cost

$5.56

$431.48

 

Table 4: Initial Capital Costs

Description

US$

Construction capital

58.11 million

Owner's capital

4.42 million

Contingency (15%)

9.45 million

Working capital and inventory

7.26 million

Total

$79.25 million


Metallurgy and Processing

Material from the North and South Pan pits will be processed using conventional heap leaching methods. Ore from both pits will be crushed by the primary in-pit mobile jaw crusher and secondary and tertiary cone crushers to a nominal 0.5 inches prior to leaching. The fines will be agglomerated. Crush size and leach kinetics are based on current metallurgical testing. Additional testing for optimization is underway.

Barren solution will be distributed on the leach pad with drip tube emitters. Pregnant solution and storm water storage ponds are integral to the leach pad system. Pregnant solutions will be treated in an adsorption/desorption refining (ADR) plant using conventional unit processes.

Opportunities and Recommendations

Gustavson has recommended the following work plans as part of Midway's ongoing project development effort to further refine costs, recoveries, engineering, and mine designs in order to produce a Feasibility Study:

• Proceed with the NEPA / EIS (environmental) permitting process.
• Expand the mineral resource and mineral reserve to determine the total mineral resource potential at depth and along strike at North and South Pan.
• Complete a statistical review of the RC/core twin holes completed on the property.
• Complete metallurgical testing of 29 composite diamond core samples.
• Selective core drilling to determine if historic RC assays are under-reporting gold grades. Limited data suggests that core assays average 30.5 percent higher grade than corresponding RC assays.
• Selectively re-drill areas with older mine lab solution assays, which average 14.7 percent lower gold grades than twin holes with fire assays.

This release has been reviewed and approved by Mr. Donald E. Hulse (P.E.), Principal Mining Engineer of Gustavson, and a "qualified person" as that term is defined in NI 43-101. This release has also been reviewed and approved for Midway by Mr. William S. Neal (M.Sc. and CPG), Vice President of Geological Services of Midway, and a "qualified person" as that term is defined in NI 43-101.

ON BEHALF OF THE BOARD
"Kenneth A. Brunk"
Kenneth A. Brunk, Director, President and COO

About Midway Gold Corp.

Midway Gold Corp. is a precious metals company with a vision to explore, design, build and operate mines in a manner accountable to all stakeholders while producing an acceptable return to its shareholders. For more information about Midway, please visit our website at www.midwaygold.com or contact R.J. Smith, Manager of Corporate Administration, at (877) 475-3642 (toll-free).

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.

This press release contains forward-looking statements about the Company and its business. Forward looking statements are statements that are not historical facts and include, but are not limited to, statements about the Company's intended work plans for the Pan project and resource and reserve estimates. The forward-looking statements in this press release are subject to various risks, uncertainties and other factors that could cause the Company's actual results or achievements to differ materially from those expressed in or implied by forward looking statements. These risks, uncertainties and other factors include, without limitation, risks related to the timing and completion of the Company's intended work plans for the Pan project, risks related to fluctuations in gold prices; uncertainties related to raising sufficient financing to fund the planned work in a timely manner and on acceptable terms; changes in planned work resulting from weather, logistical, technical or other factors; the possibility that results of work will not fulfill expectations and realize the perceived potential of the Company's properties; uncertainties involved in the interpretation of drilling results and other tests and the estimation of gold resources and reserves; the possibility that required permits may not be obtained on a timely manner or at all; the possibility that capital and operating costs may be higher than currently estimated and may preclude commercial development or render operations uneconomic; the possibility that the estimated recovery rates may not be achieved; risk of accidents, equipment breakdowns and labor disputes or other unanticipated difficulties or interruptions; the possibility of cost overruns or unanticipated expenses in the work program; and other factors identified in the Company's SEC filings and its filings with Canadian securities regulatory authorities. Forward-looking statements are based on the beliefs, opinions and expectations of the Company's management at the time they are made, and other than as required by applicable securities laws, the Company does not assume any obligation to update its forward-looking statements if those beliefs, opinions or expectations, or other circumstances, should change.

Cautionary note to U.S. investors concerning estimates of reserves and resources: This press release and the technical report referred to in this press release use the terms "resource", "reserve", "measured resources", "indicated resources" and "inferred resources", which are terms defined under Canadian National Instrument 43-101 and the Canadian Institute of Mining and Metallurgy Classification system. Estimates of mineral reserves in this press release and in the technical report referred to in this press release have been prepared in accordance with NI 43-101 and such definitions differ from the definitions in U.S. Securities and Exchange Commission ("SEC") Industry Guide 7. Under SEC Industry Guide 7 standards, a "final" or "bankable" feasibility study is required to report reserves, the three-year historical average price is used in any reserve or cash flow analysis to designate reserves and the primary environmental analysis or report must be filed with the appropriate governmental authority. Mineral resources are not mineral reserves and do not have demonstrated economic viability. We advise investors that while those terms are recognized and required by Canadian regulations, the SEC does not recognize them. U.S. investors are cautioned not to assume that any part or all of mineral deposits in these categories will ever be converted into reserves as defined in the SEC's Guide 7. In addition, "inferred resources" have a great amount of uncertainty as to their existence, and great uncertainty as to their economic and legal feasibility. It cannot be assumed that all or any part of an inferred mineral resource will ever be upgraded to a higher category. Under Canadian rules, estimates of inferred mineral resources may not form the basis of feasibility or pre-feasibility studies, except in rare cases. U.S. investors are cautioned not to assume that part or all of an inferred resource exists, or is economically or legally minable. The SEC normally only permits issuers to report mineralization that does not constitute SEC Industry Guide 7 compliant "reserves" as in-place tonnage and grade without reference to unit measures. It cannot be assumed that all or any part of mineral deposits in any of the above categories will ever be upgraded to Guide 7 compliant reserves. Accordingly, disclosure in this press release and in the technical reports referred to in this press release may not be comparable to information from U.S. companies subject to the reporting and disclosure requirements of the SEC.

 

 

 

 

 

 




http://app.streamsend.com/v/13690149/dV1e9Zx/g23Y

 

 

Midway Gold Corp.

EXPLORATION STAGE
CODE : MDW.TO
ISIN : CA5981531042
CUSIP : 598153104
Follow and Invest
Add to watch list Add to your portfolio Add or edit a note
Add Alert Add to Watchlists Add to Portfolio Add Note
ProfileMarket
Indicators
VALUE :
Projects & res.
Press
releases
Annual
report
RISK :
Asset profile
Contact Cpy

Midway Gold is a gold development stage company based in Canada.

Midway Gold holds various exploration projects in USA.

Its main exploration properties are BURNT CANYON, ROBERTS GOLD, GOLD ROCK, THUNDER MOUNTAIN, MIDWAY, PAN, SPRING VALLEY and GOLDEN EAGLE in USA.

Midway Gold is listed in Canada, in Germany and in United States of America. Its market capitalisation is CA$ 16.2 millions as of today (US$ 12.5 millions, € 11.3 millions).

Its stock quote reached its highest recent level on December 31, 2008 at CA$ 4.68, and its lowest recent point on July 28, 2015 at CA$ 0.01.

Midway Gold has 180 224 000 shares outstanding.

Your feedback is appreciated, please leave a comment or rate this article.
Rate : Average note :0 (0 vote) View Top rated
 
Annual reports of Midway Gold Corp.
2007 Annual Report
Financings of Midway Gold Corp.
2/11/2011Accelerates Expiry date of Warrants
10/14/2009Private Placement of Up To Cdn$10.0 MM
5/14/2009warrants exercised - debt retired
6/13/2008Barrick steps up as Midway Closes private placement
5/16/2008Private Placement
11/14/2007Over 900,000 Midway warrants exercised
8/30/20075.4m private placement finalized...read the PR
8/24/2007Closes $5.4 Million Financing With Resolute Performance Fund
5/17/2007Warrants Excercised-$4.7 million proceeds
Option Grants of Midway Gold Corp.
1/8/2009Options Granted
Nominations of Midway Gold Corp.
3/22/2011– CFO change
11/5/2007's New Executive Appointments
4/27/2007Appoints New Board Members
Project news of Midway Gold Corp.
6/4/2013(Pan)\222s Pan Project R...
3/27/2013(Pan)Pan Project Receives Key Permit
4/5/2011(Midway)Announces Initial Underground Resource for Midway Project, N...
4/4/2011(Pan)Announces Positive Prefeasibility Study for Pan Gold Project...
3/29/2011(Gold Rock)Provides Initial Evaluation of the Gold Rock Project, Nevada
2/24/2011(Spring Valley)Adds 1.8 km of Potential Strike Length at Spring Valley Proj...
2/17/2011(Midway)Signs Cooperative Agreement with Town of Tonopah
2/19/2011(Gold Rock)Responds to BCSC Comments on Technical Disclosure
2/19/2011(Midway)Responds to BCSC Comments on Technical Disclosure
2/19/2011(Pan)Responds to BCSC Comments on Technical Disclosure
2/5/2011(Pan)Begins Drill Program at Pan Gold Project, Nevada
7/20/2010(Pan)Preliminary Economic Assessment results
11/5/2009(Pan)s NI 43-101 Gold Resource at Pan Project, Nevada
8/5/2009(Golden Eagle) Files NI 43-101 Technical Report for Gold Resource at Golde...
6/26/2009(Golden Eagle)NI 43-101 Gold Resource at Golden Eagle Project
3/2/2009(Spring Valley)1.8 Million Ounce Gold Resource at Spring Valley Project, Ne...
3/2/2009(Spring Valley)Announces 1.8 Million Ounce Gold Resource at Spring Valley P...
1/26/2009(Midway)Announces Project Updates and Plans for 2009
1/21/2009(Midway)Kinross completes initial drilling at Midway's Thunder Mount...
1/19/2009(Spring Valley)Spring Valley Project, Nevada Deep Core Results and Update
7/9/2008(Pan)Finds Near Surface High Grade Gold at Pan Project
6/23/2008Intercepts High-Grade Intervals within 135 ft of 0.086 OPT G...
5/14/2008(Midway)Announces High Grade Gold at Midway Project, Nevada
5/1/2008(Thunder Mountain) announces High Grade Gold at Thunder Mountain Project
4/21/2008(Midway)Test Results at Midway Project, Nevada Indicates 94% Gold Re...
4/10/2008(Spring Valley)UPDATES ON DRILLING IN SPRING VALLEY GOLD PROJECT, NEVADA
3/11/2008Announces Land Expansion of Gold Rock Project in Nevada
2/21/2008(Afgan)Announces Drill Results from Afgan Project
1/21/2008Announces Initiation of Project Permitting
1/9/2008(Spring Valley)Encounters 10 Feet 1.15 Ounce Per Ton Gold at Spring Valley,...
10/18/2007(Thunder Mountain) Hi Grade Found at Thunder Mountain
7/23/2007(Spring Valley)Announces High Grade Gold Intercepts
2/28/2007(Midway)New Gold Intercepts at Midway Project
2/7/2007(Spring Valley)Reports Spring Valley Drill Results
Corporate news of Midway Gold Corp.
1/29/2016Midway Gold Welcomes Matt Goldfarb As New Director
6/22/2015IIROC Trading Halt - MDW
6/22/2015Midway Gold Corp. Announces Filing Of Voluntary Petition For...
6/19/2015Midway Announces Reduction In Workforce
5/14/201510-Q for Midway Gold Corp.
5/5/201510-K for Midway Gold Corp.
4/20/2015Midway Secures Financing For Pan Mine And Provides Update Of...
4/2/2015Midway Ramps Up Gold Production At Pan Mine And Provides Ope...
4/1/2015Gold Investment Letter New Blog Report: Midway Gold: There's...
3/30/2015Midway Announces Planned Close Of Public Comment For Draft E...
3/27/2015Midway Announces Planned Close of Public Comment for Draft E...
3/27/2015Midway Pours First Gold at Pan Mine
3/17/2015Midway Gold Corp. (TSX and NYSE-MKT: MDW) (the "Company" or ...
3/17/2015Midway Announces 2014 Fourth Quarter Financial Results
3/4/2015Construction At Pan Gold Project Nears Completion; Midway Ex...
3/3/2015Construction at Pan Gold Project Nears Completion Midway Exp...
2/25/2015Barrick Announces First Resource At Spring Valley Midway Pro...
2/25/2015Barrick Announces First Resource at Spring Valley
2/13/2015Midway Completes Draft Environmental Impact Statement for Go...
1/23/2015Midway Clarifies Growth in Resource Estimate at Spring Valle...
1/16/2015Midway Provides Construction Update for Pan Gold Project, Ne...
12/12/2014Midway Gold Welcomes William M. Zisch As CEO
12/9/2014Midway Reports Employment Inducement Award Pursuant to Secti...
5/2/2011(Spring Valley)Spring Valley, Nevada Gold Project Experiences Substantial R...
4/8/2011Builds Operations Team for Nevada Gold Projects
6/16/2010Closes C$6.6 Million Equity Placements
6/10/2010Increases Offering to C$6.6 Million
5/19/2010Hires Kenneth A. Brunk
4/28/2010Retains Windward Global
1/11/2010Join Midway Gold in Vancouver
12/23/2009Increases Board
8/24/2009Spring Valley Quarterly Update
3/11/2009Finalizes Joint Venture with Barrick at Spring Valley Projec...
11/24/2008Announces Director Changes
9/11/2008STRIKES PORPHYRY GOLD AT BIG LEAP ZONE SPRING VALLEY, NEVADA
8/6/2008featured in Hume Report
8/4/2008 Golden Eagle Property Acquired
7/30/2008Announces Director Retires
7/17/2008Golden Predator Mines Inc. and Midway Gold Corp. Announce Si...
7/16/2008Kinross Enters Option To Joint Venture Midway's Thunder Moun...
7/8/2008Drills to Connect Gold Discoveries at Spring Valley
5/30/2008agrees to acquire Gold Eagle Property from Kinross Gold
5/21/2008Additional Information on Junior Gold Market
4/4/2008Year end financial report
2/29/2008Announces 2008 Plans for Nevada
1/23/2008Increases Spring Valley Gold Resource
1/3/2008APPROVED FOR LISTING ON AMERICAN STOCK EXCHANGE
12/4/2007 GOLD INTERCEPTS EXPAND MIDWAY’S SPRING VALLEY DEPOSIT IN NE...
11/27/2007finds more gold at PAN Project
11/5/2007"We're doing everything right"/ Tonopah Times Newspaper Arti...
11/1/2007North Pan Deposit Extended 1000 Ft.!!
10/3/2007Broadcast to tens of millions around the world on CNBC
10/3/2007New drilling Encounters Higher Gold grades
9/24/2007Spring Valley Project Expanding
9/7/2007 New website
8/22/2007Sells Jessup Project
8/10/2007Extends Gold at South Pan Deposit
8/7/2007Extends Gold at Pan Project
7/10/2007Announces Drill Results at Spring Valley
6/6/2007Spring Valley Plan of Operation Approved
6/5/2007Announces New Gold Discovery at Pan Project
5/15/2007 with Six Drill Rigs on Nevada projects
4/19/2007Initiates Drilling on Pan Gold Project, Nevada
4/13/2007Completes Pan-Nevada Acquisition
2/20/2007Gold & Pan Nevada Sign Arrangement Agreement
Comments closed
 
Latest comment posted for this article
Be the first to comment
Add your comment
TORONTO (MDW.TO)AMEX (MDW)
0.090+0.00%0.695+0.00%
TORONTO
CA$ 0.090
07/28 15:58 -
0%
Prev close Open
0.090 0.090
Low High
0.090 0.110
Year l/h YTD var.
 -  -
52 week l/h 52 week var.
- -  0.090 800.00%
Volume 1 month var.
900,782 800.00%
Produces
Develops
Explores for Gold
 
 
 
Analyse
Interactive chart Add to compare
Interactive
chart
Print Compare Export
Last updated on : 10/14/2010
You must be logged in to use the porfolio and watchlists (free)
Top Newsreleases
MOST READ
Annual variation
 
5 years chart
 
3 months chart
 
3 months volume chart
 
 
Mining Company News
Plymouth Minerals LTDPLH.AX
Plymouth Minerals Intersects Further High Grade Potash in Drilling at Banio Potash Project - Plannin
AU$ 0.12-8.00%Trend Power :
Santos(Ngas-Oil)STO.AX
announces expected non-cash impairment
AU$ 7.49+0.13%Trend Power :
OceanaGold(Au)OGC.AX
RELEASES NEW TECHNICAL REPORT FOR THE HAILE GOLD MINE
AU$ 2.20+0.00%Trend Power :
Western Areas NL(Au-Ni-Pl)WSA.AX
Advance Notice - Full Year Results Conference Call
AU$ 3.86+0.00%Trend Power :
Canadian Zinc(Ag-Au-Cu)CZN.TO
Reports Financial Results for Q2 and Provides Project Updates
CA$ 0.12+4.55%Trend Power :
Stornoway Diamond(Gems-Au-Ur)SWY.TO
Second Quarter Results
CA$ 0.02+100.00%Trend Power :
McEwen Mining(Cu-Le-Zn)MUX
TO ACQUIRE BLACK FOX FROM PRIMERO=C2=A0
US$ 11.76+1.29%Trend Power :
Rentech(Coal-Ngas)RTK
Rentech Announces Results for Second Quarter 2017
US$ 0.20-12.28%Trend Power :
KEFIKEFI.L
Reduced Funding Requirement
GBX 0.54-0.92%Trend Power :
Lupaka Gold Corp.LPK.V
Lupaka Gold Receives First Tranche Under Amended Invicta Financing Agreement
CA$ 0.06+0.00%Trend Power :
Imperial(Ag-Au-Cu)III.TO
Closes Bridge Loan Financing
CA$ 2.59-0.38%Trend Power :
Guyana Goldfields(Cu-Zn-Pa)GUY.TO
Reports Second Quarter 2017 Results and Maintains Production Guidance
CA$ 1.84+0.00%Trend Power :
Lundin Mining(Ag-Au-Cu)LUN.TO
d Share Capital and Voting Rights for Lundin Mining
CA$ 15.15+0.80%Trend Power :
Canarc Res.(Au)CCM.TO
Canarc Reports High Grade Gold in Surface Rock Samples at Fondaway Canyon, Nevada
CA$ 0.24-7.84%Trend Power :
Havilah(Cu-Le-Zn)HAV.AX
Q A April 2017 Quarterly Report
AU$ 0.22+0.00%Trend Power :
Uranium Res.(Ur)URRE
Commences Lithium Exploration Drilling at the Columbus Basin Project
US$ 6.80-2.86%Trend Power :
Platinum Group Metals(Au-Cu-Gems)PTM.TO
Platinum Group Metals Ltd. Operational and Strategic Process ...
CA$ 1.79-2.72%Trend Power :
Devon Energy(Ngas-Oil)DVN
Announces $340 Million of Non-Core Asset Sales
US$ 50.54+0.40%Trend Power :
Precision Drilling(Oil)PD-UN.TO
Announces 2017Second Quarter Financial Results
CA$ 8.66-0.35%Trend Power :
Terramin(Ag-Au-Cu)TZN.AX
2nd Quarter Report
AU$ 0.04+0.00%Trend Power :