Hana Mining Ltd.

Published : May 14th, 2012

Announces Positive Preliminary Economic Assessment for the Ghanzi Copper-Silver Project

( 0 vote, 0/5 ) Print article
  Article Comments Comment this article Rating Follow Company  
0
Send
0
comment
Monday, May 14, 2012
NEWS RELEASE
 
Hana Announces Positive Preliminary Economic Assessment for the Ghanzi Copper-Silver Project

May 14, 2012 (Vancouver, British Columbia). Hana Mining Ltd. ("Hana" or the "Company") - (TSX-V: HMG) (Frankfurt: 4LH) is pleased to announce the positive results of its initial independent National Instrument 43-101 compliant Preliminary Economic Assessment ("PEA") for the Banana Zone and Zone 5 at its 70-percent owned Ghanzi Copper-Silver Project ("Project") in northwestern Botswana. The PEA was prepared by independent consultants and DRA Mineral Projects ("DRA") of Johannesburg, South Africa and will be filed on SEDAR within 45 days of this news release. The results of the PEA describe the technical and economic viability of establishing a new copper-silver mine and mill complex for the Project. The base-case scenario utilizes a long-term copper price of US$3.40/lb. This copper price represents the current three-year trailing average LME price for reference purposes. As a result of the positive outcome of the PEA, Hana will now commence with a feasibility study on the Project.

The PEA is based on the mineral resources at the Banana Zone and Zone 5 that are detailed later in this press release. Drilling is continuing through 2012 to explore the potential to extend and upgrade the current planned in-pit and global resources. The results from these holes will be included in the feasibility study.

Key highlights of the PEA study are as follows:

  • Initial development capital expenditure of US$285.5 million and a total capital expenditure of US$399.0 million
  • Pre-tax NPV(8%) of US$363.3 million and an IRR of 22.1% for the base case, using prices of US$3.40/lb for copper, US$30/oz for silver and a discount rate of 8%
  • After-tax NPV(8%) of US$262.5 million for the base case
  • After-tax IRR of 19.3% for the base case
  • Payback of capital in 5 years
  • Minimum 13-year mine life supporting a 10,000 tonne-per-day conventional grinding mill and flotation circuit to produce a clean high-grade (approximately 46% copper) copper-silver concentrate
  • Life-of-mine strip ratio of 6.8 to 1 to an average pit depth of 183m from four pits with no more than two pits operating at any given time. Mining operations will be carried out utilizing contract mining
  • Average production of 66.4 million pounds of copper and 878,000 ounces of silver for life of mine
  • Cash costs utilizing heavy fuel oil ("HFO") generator power of US$1.96/lb of payable copper (net of silver byproduct credits) for the first five years and US$1.75/lb (power supplied by Botswana Power Corporation ("BPC") from the national power grid for the remaining life of mine (C1 costs include on-site mining and processing costs, transport and TC/RC charges and is net of by-product credits)
  • Strongly leveraged for potential upside:
    • Adding an additional two years to the mine life increases the NPV(8%) by 19% to US$313.7 million
    • Increasing the life-of-mine copper grade by 0.10% increases the NPV(8%) by 44%
    • A 10% increase in copper prices or grades increases the NPV(8%) by 48%
  • Robust economic indicators justify immediate commencement of the feasibility study

A PEA should not be considered to be a pre-feasibility or feasibility study, as the economics and technical viability of the Project has not been demonstrated at this time. A PEA is preliminary in nature and includes Inferred Mineral Resources that are considered too geologically speculative at this time to have the economic considerations applied to them to be categorized as Mineral Reserves. Furthermore, there is no certainty that the details outlined in the PEA will be realized.

Hana Mining's CEO and Chairman, Marek Kreczmer, commented as follows:


"The PEA is the culmination of many months of hard work by our highly-experienced technical team. This document represents a current snap shot and firmly demonstrates that the Project has robust economics and will be a long-lived copper-silver operation. Therefore, we have commenced activities for a feasibility study,

The initial capital cost of US$285.5 million will support a 31,000 tonne per year copper-silver mining operation, meaning that this project will have one of the lowest capital intensities among global copper development projects. While the PEA assumes contract mining, where a third party contract-mining firm would carry out the in-pit mining operations, lower cost owner-operated mining needs to be considered, and this will be done in the feasibility study. In addition, none of the holes drilled in 2012, including those with high copper and silver values from the Northeast Fold area were included in the PEA. However, the results from these holes and holes from other parts of the Banana Zone and Zone 5 will be included in the feasibility study. With the additional drilling planned for the next few months we also expect to get a better handle on pit optimization in order to potentially reduce the payback period and increase the NPV of the project.

There are many aspects of the PEA which I believe can be optimized during the feasibility study such as:

  • Upside potential at Zone 5, Zone 6, and the Banana Zone, specifically in the Northeast Fold area where the high-grade copper-silver drilling results from 2012 were not included in the PEA,
  • There is excellent potential for identification of additional mineralization through infill and expansion drilling at the Project which could support estimation of additional mineral resources, and be incorporated into an updated mine plan,
  • A reduction in our projected mining and milling costs through further optimization of our processes and the possible utilization of alternative energy resources such as solar and wind power. Owner versus contract mining will also be investigated,
  • A reduction in the estimated capital costs of the project through further optimization in the costs of the plant and other equipment needed to operate the mine and mill,
  • The economics of the project may also be significantly optimized with more timely access to Botswana's national power grid,
  • Investigating the economics of establishing an underground mining operation.

Our primary corporate focus is to work with the Botswana government to accelerate the extension of their national grid to the project site. As well, we will also investigate the use of alternative energy sources such as coal, solar and wind power to offset the higher cost HFO generated power that was used in the study.

The Project is uniquely positioned to secure low-cost financing given that it has a low capital cost, will produce a high-quality highly sought after concentrate and is located in one of the most stable mining jurisdictions in the world.

Given the positive outcome of the PEA we will now move forward with a feasibility study. We remain well financed with Cdn$20 million in cash in the treasury."

Preliminary Economic Assessment -- Mining and Processing:

The PEA is based on a conventional truck and shovel, open-pit mine design at four pits with milling and sulphide concentration of both near-surface secondary/transition copper material and underlying primary sulphide mineralization.

Preliminary metallurgical work on the oxide/transitional material and sulphides show an average blended recovery of 87% for copper and 80% for silver. The two mineralization types will be processed simultaneously through conventional milling and flotation for a minimum mine life of 13 years. Total production is projected to be 10,000 tonnes per day.

Production will come from two pits, at any given time, at the Northeast Fold, New Discovery and South Limb areas of the Banana Zone and from Zone 5. Pit depths in the Banana Zone will have a maximum vertical extent up to 200 m, whereas the pit depth in Zone 5 is currently 150 m. Key parameters and assumptions used for the PEA study are discussed below and summarized in a series of tables on the following pages.

Type of Mining Total Years Avg t/yr
(000's)
Avg t/day Total
(000's)
Open pit mineralized material (Years 0 -- 13)
13
3,600
10,000
45,700
Open pit waste (Years 0 -- 13)
13
23,880
66,000
310,000
     
Total material mined
355,700
Average strip ratio for the life of mine
6.8:1

Table 1 - Mining rates and volumes of mined material

Metal Total Production Average Annual Production
Life of Mine
  lbs (000's) tonnes lbs (000's) Tonnes
Copper in concentrate
863,000
392,000
68,000
31,000
  ounces Ounces
Silver in concentrate
11,408,000
899,000

Table 2 - Projected metal production

Head Grades
Copper
%
1.02
Silver
g/t
12.13
Metal Recoveries
Copper -- sulphides
%
91
Copper -- oxides
%
50
Average copper recovery -- sulphides and oxides
%
87
Smelter losses
%
3
Total payable copper
%
84
Average silver recovery -- sulphides and oxides
%
80
Total payable silver
%
64
Copper concentrate grade
%
46
Silver concentrate grade
g/t
414
Metal Prices
Copper
US$/lb
3.40
Silver
US$/oz
30.00
Other Parameters
Life of mine
Years
13
Heavy fuel oil price
US$/l
1.06
Electrical power -- HFO
US$/kWhr
0.22
Electrical power -- national grid
US$/kWhr
0.12

Table 3 - The Base case head grades, recoveries, metal prices, and other data used.

Preliminary Economic Assessment - Project Economics:

The results of a discounted cash flow analysis for the Project are presented in Table 4 below. Net Present Value (NPV), Internal Rate of Return (IRR) and Payback values are presented for both pre-tax and after-tax scenarios. The base-case scenario utilizes a long-term copper price of US$3.40/lb and a discount rate of 8%. IRR and NPV values are calculated for a range of copper prices from US$3.00 to US$4.00. The copper price of US$3.40/lb represents the current three-year trailing average LME price for reference purposes. The discount rate of 8% is indicative for a stable country like Botswana. Table 5 summarizes the key financial results for the project.

A Botswana net smelter return royalty of 3% for base metals and 5% for precious metals, and a corporate tax rate of 22.5%, have been used in the cash flow analysis.

Please note that as Mineral Resources (of the Indicated and Inferred categories) do not have economic viability and are geologically considered to be too speculative to have economic considerations applied to them, this PEA is entirely preliminary in nature.

Pre-tax NPV
(US$ million)
Copper Price
(US$/lb)
3.00 3.25 Base Case
3.40
3.50 4.00
Discount Rates
5%
289
431
516
573
857
Base Case 8%
173
291
363
410
646
10%
113
218
281
324
535
   
IRR
%
15.0
19.5
22.0
23.7
31.8
Payback
Years
7
6
5
5
4


After-tax NPV
(US$ million)
Copper Price
(US$/lb)
3.00 3.25 Base Case
3.40
3.50 4.00
Discount Rates
5%
209
320
387
431
652
Base Case 8%
112
206
262
299
484
10%
61
145
196
229
394
 
IRR
%
13.0
17.0
19.3
20.7
27.9
Payback
Years
7
6
5
5
4

Table 4. Pre-tax and after-tax discounted cash flow results for varying copper prices

Cash costs
(US$ million)
Total
Life of Mine
Annual
Life of Mine
Annual
Years 1-5
Annual
Years 6-10
Royalties (Cu at 3%, Ag at 5%)
88
6.8
6.8
6.8
Net pre-tax income
932
71.7
68.9
79.8
 
Cash Costs
(US$/lb Cu produced)
Life of Mine Years 1-5 Years 6-13
Mine site (net of by-product credits)
1.48
1.62
1.40
C1 (delivered metal -- net of by-product credits)
1.82
1.96
1.75

Table 5. Summary of cash costs

Capital Costs

The PEA estimates the initial development capital expenditure at US$285.5 million during the proposed 1.5-year construction period and the first year of partial production. With sustaining (deferred and working) capital over the life of the mine, the expected investment is US$399.0 million. All estimates are based on the consultant's experience with similar projects and are not definitive estimates based on vendor quotations.

Capital Estimate
(US$ million)
 
Mining infrastructure
31.1
Concentrator plant
125.1
Surface general infrastructure
17.6
Power generation
19.3
Tailings dam and piping
9.9
Wellfield and piping
13.1
Accommodation
15.3
Indirect (managing contractor, owner's costs, spare, etc.)
54.0
Initial development capital
285.5
Pre-production costs
15.0
Sustaining capital
82.1
Deferred capital (tailing dam extensions)
16.4
Total capital expenditure for the life of mine
399.0

Table 6. Capital estimate summary

Infrastructure

Power will be supplied by 20MW onsite heavy fuel oil ("HFO") generators, at a capital cost of US$19.3 million, for the first five years of commercial production. In year six of operations, which is projected to be the year 2021, BPC is expected to have connected the Project to the national power grid. Onsite power costs using HFO are estimated to be US$0.22/kWh, assuming a HFO of US$1.06/l. Power from the grid is expected to cost US$0.08/kWh. Water will be supplied from an aquifer located approximately 50 kilometers from the concentrator facility. Water will be transported to the processing plant by pipeline.

Operating Costs

The project produces approximately 863 million pounds of copper at an average C1 cash operating cost of US$1.82/lb Cu over the 13-year mine life. For the first five full years of production, utilizing HFO generators, C1 cash costs are estimated to be US$1.96/lb Cu. For the remaining eight years, with power sourced from the national grid, C1 cash costs are expected to decrease to US$1.75/lb Cu. These cash costs are net of silver byproducts and include transport and refining charges. Cash operating costs are based on prevailing wage rates, commodity prices, and power rates in southern Africa. Maintenance parts and repairs are estimated based on industry standard factors for these costs. Details of the operating costs are presented in Table 7 below.

Operating Cost
(as indicated)
Mining
$/tonne processed
20.80
Processing -- HFO generated
$/tonne processed
13.92
Processing - Grid power
$/tonne processed
9.92
Overheads -- Administration
$/tonne processed
2.90
Overheads -- Marketing commission
% of revenue
1.50
Overheads -- Transportation concentrate
US$/tonne of concentrate
180.00
Overheads -- Toll treatment
% of revenue
3.00

Table 7. Operating costs, freight, treatment and refinement charges

Mineral Resource Estimate

The mineral resource estimate upon which the PEA was based was completed by or under the direction of Ms. Susan N. Meister, SME, and an independent Qualified Person as set forth by NI 43-101. Drill results used in the mineral resource estimates include core and RC drilling from the 2011 drilling program, 2006-2011 drilling by Hana and drilling completed by previous owners that could be verified in the field. The drilling cutoff date for Banana Zone and Zone 5 was December 13, 2011 with assay results available on February 15, 2012. The drilling cutoff date for one sub-zone, NLN, was 28 August 2011 with assays finalized on October 18, 2011. The overall effective date of this resource is February 15, 2012. The mineral resource for Banana Zone is supported by 559 core holes (approximately 75,800 m) and 431 RC holes (approximately 51,400m) drilled by Hana and 21 core holes (approximately 4,250m) and 31 RC holes (approximately (3,600m) drilled by predecessors on the property. Zone 5 is supported by 69 RC drill holes (approximately 7,400m) and 2 core holes (approximately 370m) drilled by Hana. The geological and assay database have been reviewed and audited by Grant Geological Services. Included in this review was the analysis of assaying QA/QC measures implemented by Hana, a study of core to RC drill results and a review of pre-Hana drilling.

Mineral Resources are reported from six block models covering the Banana Zone and a separate one covering Zone 5. Three dimensional solids models were created of continuous mineralized zones at 0.1% Cu and 0.5% Cu grade thresholds that are tied to lithology. The block size (5x1.5x4m, 5x3x4m, 10x3x4m and 40x6x4m) in combination with partial block coding maintained control on mineralized zone volumes and boundary limits. Cu and Ag assays were variably capped by sub-zone prior to compositing and block grade estimation. Nearest neighbor (NN) and inverse distance to a power of 3 (ID3) estimates were run, with ID3 used for resource reporting and NN used for checking. Cu and Ag grades were interpolated for the different grade zones then combined into an overall grade for the mineralized portion of the block. Search distances ranged from 450x350x250m to 150x105x20m, depending upon the estimation pass number and drill spacing within the subzone. In general, blocks were categorized as Indicated within areas of 100 x 50m drill spacing, and Inferred in areas with approximate 200m spacing along strike.

Differences between the previously reported mineral resource estimate (as reported in the Technical Report dated February 3, 2011) are primarily related to additional drilling (292 drill holes, approximately 39,700m in Banana Zone and 33 drill holes, 3800m in Zone 5), a different resource modeling approach and a reduction in the projection distance for categorizing Inferred Mineral Resources.

An updated resource model is planned for Zone 6 following completion of additional drilling, assaying and geological interpretations.

Additional information about the resource modeling methodology and differences between previously issued resource statements will be documented in the upcoming 43-101 technical report.

Banana Zone - Indicated Mineral Resource
New Discovery, North Limb North, Northeast Fold and South Limb Definition Subzones
Cutoff Cu
(%)
Tonnes
(M tonnes)
Cu Grade (%) Contained CU Metal Ag Grade (g/t) Contained Ag Metal
(K tonnes) (M lbs) (tonnes) (M oz Ag)
0.3
53.1
0.75
396
873
10.7
569
18.3
0.4
40.9
0.87
354
780
12.5
510
16.4
0.5
31.7
0.99
313
690
14.3
453
14.6
0.6
24.7
1.11
275
605
16.3
402
13.0
0.7
19.6
1.23
242
533
18.2
358
11.5
0.8
15.9
1.35
214
472
20.2
320
10.3
0.9
12.9
1.47
189
417
22.2
287
9.2
1.0
10.5
1.58
166
366
24.3
254
8.2


Banana Zone - Inferred Mineral Resource
(includes Chalcocite)
Cutoff Cu
(%)
Tonnes
(M tonnes)
Cu Grade (%) Contained CU Metal Ag Grade (g/t) Contained Ag Metal
(K tonnes) (M lbs) (tonnes) (M oz Ag)
0.3
299.5
0.51
1,575
3,472
6.0
1,771
57.0
0.4
191.6
0.60
1,207
2,662
7.1
1,392
44.7
0.5
120.3
0.70
892
1,966
8.4
1,060
34.1
0.6
76.0
0.80
652
1,438
9.8
797
25.6
0.7
49.1
0.90
480
1,057
11.1
602
19.4
0.8
31.8
1.00
351
775
12.5
453
14.6
0.9
21.6
1.10
266
586
13.7
348
11.2
1.0
14.3
1.22
197
435
14.9
263
8.5


Zone 5 - Inferred Mineral Resource
Cutoff Cu
(%)
Tonnes
(M tonnes)
Cu Grade (%) Contained CU Metal Ag Grade (g/t) Contained Ag Metal
(K tonnes) (M lbs)    
0.3
16.9
1.41
239
526
12.6
213
6.8
0.4
16.0
1.47
236
520
13.2
211
6.8
0.5
16.0
1.47
236
520
13.2
211
6.8
0.6
16.0
1.47
236
519
13.2
211
6.8
0.7
15.5
1.50
232
512
13.2
205
6.6
0.8
14.9
1.53
228
502
13.5
201
6.5
0.9
14.1
1.57
221
488
13.8
195
6.3
1.0
13.3
1.61
213
470
14.2
189
6.1
Notes:
  1. Mineral Resources are not Mineral Reserves and do not have demonstrated economic viability.
  2. Indicated Mineral Resources are supported by an approximate drill hole spacing of 100 x 50m.
  3. Inferred Mineral Resources are supported by an approximate drill hole spacing of 200m along strike.
  4. The Base Case Mineral Resources are reported above a 0.3% Cu cutoff, based on commodity pricing of US$3.40/lb Cu and US$30.00/oz Ag, additional cutoffs are shown as sensitivity cases.

Table 8 - Indicated and Inferred Resources at the Banana Zone and Zone 5

DRA carried out pit optimization using the Whittle Four-X software. The optimal shells for Indicated and Inferred Mineral Resources were selected through a combination of maximum NPV and optimum strip ratios.

  Copper Grade
(%)
Silver Grade
(g/t)
In-pit Material
(M tonnes)
Strip Ratio Waste
(M tonnes)
Indicated Inferred Indicated Inferred Indicated Inferred
New Discovery
0.88
0.87
14.26
13.30
10.131
0.025
5.74
53.340
North East Fold
0.84
1.16
11.16
12.18
12.168
1.624
7.15
98.586
South Limb Definition
0.79
0.98
10.95
15.14
3.262
1.066
10.07
43.562
South Limb South
-
0.90
-
10.94
-
2.981
8.14
24.270
Zone 5
-
1.33
-
11.75
-
14.437
5.93
85.624
Total
0.85
1.23
12.36
11.85
25.560
20.132
6.79*
310.382
*Average

  Contained Copper
(k tonnes)
Contained Copper
(M lbs)
Contained Silver
(M ounces)
Indicated Inferred Indicated Inferred Indicated Inferred
New Discovery
89.397
0.216
197.087
0.476
4.644
0.011
North East Fold
102.342
18.854
225.625
41.567
4.364
0.636
South Limb Definition
25.777
10.419
56.829
22.970
1.149
0.519
South Limb South
-
26.859
-
59.214
-
1.048
Zone 5
-
191.708
-
422.644
-
5.456
Total
217.516
248.056
479.541
546.871
10.157
7.670
Note: No reserves can be declared in the PEA
Table 9 - Results of the pit optimization

Project Sensitivities

Project cash flow is highly sensitive to changes in the price of copper as indicated in Table 10. The project is also sensitive to variations in capital and operating costs as indicated in Table 11 below. These tables show the effect of increasing or decreasing the capital expenditure and operating expenditure estimates for the project by +/-10% and +/- 20%

NPV
After-Tax
(US$ million)
Capex Estimate Variance Opex Estimate Variance
+10% Base Case -10% +10% Base Case -10%
Discount Rates
5%
361
388
414
282
388
494
Base Case 8%
236
263
289
174
263
351
10%
169
196
196
116
196
276
 
 
IRR%
17.5
19.3
19.3
10.0
19.3
22.8

Table 10. Project sensitivity to variations in capital and operating expenditure

After-tax NPV
(US$ Million)
Variance in Cu Head Grades
0.90% 0.95% 1.02%
(Base Case)
1.10% 1.20% 1.30% 1.40%
Discount Rates
5%
   
388
499
638
776
915
Base Case 8%
   
263
355
472
587
702
10%
   
196
$79
383
487
590
 
IRR
%
   
19.3
23.0
27.4
31.7
35.9

Table 11. Project sensitivity to variations in copper head grades


Project Information

All drilling for the Project, up to December 13, 2011 was incorporated into the PEA. In the preparation of the PEA, the Independent Consultants and DRA received written or verbal data from Hana's staff, metallurgical reports from G&T Metallurgical Services Ltd. of Kamloops, British Columbia and Mintek of Johannesburg, South Africa. The parties listed in Table 12 above independently confirmed the data utilized in the preparation of this PEA. The capital and operating data developed in the PEA came from review of the metallurgical test work, in-house DRA data and discussions with other consultants and copper mining operations in southern Africa and elsewhere. Hana provided the tax, royalty and legal information.

Qualified Persons and NI 43-101 Technical Report

The PEA summarized here for the Project was completed by the independent consultants and DRA (listed in Table 12); and will be incorporated in a NI 43-101 compliant, independent Technical Report which will be available on SEDAR and the Hana website within 45 days from the date of this news release.

Area of Responsibility Contributing Company Qualified Person Professional Qualification

Geology

Farscape Exploration

David Catterall

Pr.Sci.Nat

Database Validation

Grant Geology

Jerry Grant

P.Geo

Resource Estimate

Independent

Susan Meister

SME

Mining and Infrastructure

DRA

Thomas Obiri-Yeboah

Pr.Eng

Metallurgy and Infrastructure

DRA

Mark Cresswell

Pr.Eng


Table 12. PEA Contributors

All of Hana's exploration programs and pertinent disclosure of a technical or scientific nature are prepared by, or prepared under the direct supervision of Mr. Marek Kreczmer, Hana's CEO and Chairman, who serves as the Qualified Person (QP) under the definitions of National Instrument 43-101. Hana's security, chain of custody and quality control procedures are described on their website and are filed on the website and on SEDAR under the section on best practices -- sampling methodologies. Mr. Kreczmer has reviewed and approved the information contained in this release.

The PEA is preliminary in nature and includes the use of Inferred Resources, which are considered too speculative to apply economic considerations that would enable them to be categorized as Mineral Reserves. Mineral Resources do not have demonstrated economic viability and future in-fill drilling and scoping, pre-feasibility and feasibility studies will determine what percentage of the inferred resource can be placed into the mineable category. Thus, there is no certainty that the production profile concluded in the PEA will be realized. Actual results may vary, perhaps materially. The Company is not aware of any environmental, permitting, legal, title, taxation, socio-political, marketing or other issue which may materially affect this estimate of mineral resources. The projections, forecasts and estimates presented in the scoping study and PEA constitute forward-looking statements and readers are urged not to place undue reliance on such forward-looking statements. Additional cautionary and forward-looking statement information is detailed at the end of this press release.


For Further Information, contact:
Marek Kreczmer
CEO
Hana Mining Ltd.
Tel: (604) 676-0824
Email: info@hanamining.com
Website: www.hanamining.com

Patrick Donnelly
VP - Corporate Development
Hana Mining Ltd.
Tel: (604) 676-0824
Email: patrick@hanamining.com
Website: www.hanamining.com


The TSX Venture Exchange has not reviewed and does not accept responsibility for the adequacy or accuracy of this release. Statements in this press release, other than purely historical information, including statements relating to the Company's future plans and objectives or expected results, may include forward-looking statements. Forward-looking statements are based on numerous assumptions and are subject to all of the risks and uncertainties inherent in resource exploration and development. As a result, actual results may vary materially from those described in the forward-looking statements.

You can also view this News Release on our website at:
http://www.hanamining.com/s/NewsReleases.asp?ReportID=524747
 

Home    Corporate    Projects    Investors    News    Reports    Contact    Disclaimer    Subscribe    
Data and Statistics for these countries : Botswana | South Africa | All
Gold and Silver Prices for these countries : Botswana | South Africa | All

Hana Mining Ltd.

EXPLORATION STAGE
CODE : HMG.V
Follow and Invest
Add to watch list Add to your portfolio Add or edit a note
Add Alert Add to Watchlists Add to Portfolio Add Note
ProfileMarket
Indicators
VALUE :
Projects & res.
Press
releases
Annual
report
RISK :
Asset profile
Contact Cpy

Hana Mining is a copper and silver development stage company based in Canada.

Hana Mining holds various exploration projects in Botswana.

Its main exploration property is GHANZI in Botswana.

Hana Mining is listed in Canada and in Germany. Its market capitalisation is CA$ 80.6 millions as of today (US$ 78.4 millions, € 58.5 millions).

Its stock quote reached its lowest recent point on March 27, 2009 at CA$ 0.06, and its highest recent level on December 17, 2010 at CA$ 5.68.

Hana Mining has 99 494 000 shares outstanding.

Your feedback is appreciated, please leave a comment or rate this article.
Rate : Average note :0 (0 vote) View Top rated
 
Financings of Hana Mining Ltd.
2/7/2012Announces Completion of Non-Brokered Financing and Investmen...
1/30/2012Announces Final Allocation of Previously Announced Financing
1/27/2012Announces Non-Brokered Financing
5/20/2010Closing of Bought-Deal Private Placement
4/30/2010Arranges $21Million Bought-Deal Private Placement
5/27/2009has closed the first tranche of its brokered private placeme...
Nominations of Hana Mining Ltd.
11/7/2012New Hana Mining Builds the Corporate Structure with Appointm...
5/5/2011Appoints New Chief Financial Officer
4/5/2011shareholders overwhelmingly approve the appointment of three...
3/21/2011Announces the Nomination of Three Highly Experienced Candida...
7/19/2010Appointment of Pat Donnelly, former mining analyst, as VP Co...
Project news of Hana Mining Ltd.
2/8/2013Receives Approval from Botswana Minister of Minerals, Energy...
1/10/2013(Ghanzi)Receives Renewal of Ghanzi Project Prospecting Licenses
10/25/2012Agrees To C$0.82 Per Share All-Cash Acquisition By Cupric Ca...
8/20/2012Expands Zone 5 at Depth with Strong Drill Results
8/13/2012Continues to Hit High-Grade Copper-Silver Mineralization at ...
6/29/2012(Ghanzi)Files Ghanzi Preliminary Economic Assessment Technical Repor...
4/17/2012continues to hit high-grade copper-silver mineralization at ...
2/21/2012(Ghanzi)Infill drilling at the Northeast Fold confirms new geologica...
6/13/2011(Ghanzi)Comments on Share Price - Drilling Continues
5/26/2011(Ghanzi)Provides Update on Banana Zone
3/14/2011(Ghanzi)Provides Update on Banana Zone Preliminary Economic Assessme...
8/5/2010(Ghanzi)RC Drilling in Banana Zone Intersects 3.40% Cu and 48.0 g/t ...
7/14/2010(Ghanzi)Expands Banana Zone at Ghanzi Copper-Silver Project by 4.2 K...
6/18/2010(Ghanzi)Expands Banana Zone by 7 Kilometres
6/3/2010(Ghanzi)Expands Chalcocite Zone - New Drilling Increases Strike Leng
5/19/2010Files NI 43-101
3/30/2010(Ghanzi)RC drilling in Banana Zone intersects 1.63% Cu and 39.5 g/t ...
3/4/2010(Ghanzi)RC drilling in Banana Zone intersects 1.90% Cu and 17.4 g/t ...
1/5/2010(Ghanzi)New VP Engineering to Support Ghanzi Copper-Silver Project P...
12/8/2009drilling intersects 1.84% Cu and 23.6 g/t Ag over 7 metres i...
10/1/2009(Ghanzi)Announces New President and COO to Drive Ghanzi Copper-Silve...
9/28/2009(Ghanzi)RC drilling intersects 2.53% Cu and 32 g/t Ag over 17 metres...
9/15/2009(Ghanzi)Reports Positive Results From a Preliminary Groundwater Inve...
8/26/2009(Ghanzi)Letter from the CEO-Hana Mining Ltd.
7/15/2009(Ghanzi)Agrees to Purchase 100% of Ghanzi Copper-Silver Project in B...
6/25/2009(Ghanzi)43-101 Technical Report for Ghanzi Copper-Silver Deposit, Bo...
5/28/2009(Ghanzi)New results at Ghanzi Copper-Silver Project in Botswana
Corporate news of Hana Mining Ltd.
2/20/2013Completes Arrangement with Cupric Canyon Capital LP
2/14/2013Receives Approval From Botswana Competition Authority
2/5/2013Intersects 4.03% Cu and 50.7g/t Ag over 14 m Further Increas...
2/4/2013Provides Update on Arrangement with Cupric Canyon Capital
1/7/2013Receives Final Court Order for Arrangement with Cupric Canyo...
12/11/2012Advises Regarding Shareholder Meeting
11/1/2012Discovers New Mineralization Further Increasing the Size of ...
10/26/2012from DML's Neighbour, Hana Mining
10/23/2012Reports Consistent High Grades over Thick Intersections at Z...
10/22/2012New Hana Mining Builds Corporate Advisory Team
9/24/2012Finds Strong Copper-Silver Mineralization from New Drill Pro...
9/18/2012Welcomes Two New Board Members
8/27/2012Reports More Strong Results from Zone 5 including 4.54% CuEq...
8/1/2012Drilling continues to encounter down-dip mineralization and ...
7/24/2012Diamond Drilling Extends Down Dip Extension and Confirms Thi...
7/16/2012announces high-grade copper-silver mineralization from Zone ...
5/23/2012Shares Commence Trading on the Botswana Stock Exchange
5/14/2012(Ghanzi)Announces Positive Preliminary Economic Assessment for the G...
3/28/2012Diamond Drilling Extends the Strike and Down Dip Extension o...
3/27/2012to Cancel the Issuance of Stock Options
3/12/2012Diamond drilling encounters consistent high-grade copper-sil...
2/27/2012Infill drilling continues to encounter consistent high-grade...
1/24/2012Infill drilling encounters some of the best intercepts of co...
1/9/2012Infill drilling encounters consistent high-grade copper-silv...
11/28/2011Infill Drilling Again Encounters Consistent High-Grade Coppe...
10/24/2011(Ghanzi)announces the appointment of a highly experienced Technical ...
10/3/2011announces exceptional silver recoveries from oxide-transitio...
9/20/2011(Ghanzi)announces the appointment of highly experienced and successf...
9/13/2011Infill drilling again encounters consistent high-grade coppe...
8/29/2011Infill drilling continues to encounter consistent high-grade...
8/22/2011Infill drilling encounters high-grade copper-silver minerali...
8/15/2011(Ghanzi)announces the appointment of a highly experienced Project Di...
7/26/2011Infill Drilling Again Encounters Thick Intersections of Copp...
7/11/2011Infill drilling still continues to encounter thick intersect...
6/16/2011Infill drilling continues to encounter thick intersections o...
6/13/2011Comments on Share Price-Drilling Continues
4/19/2011Infill Drilling Extends Copper-Silver Mineralization by 300 ...
7/8/2010Comments on Share Price-Drilling Continues
5/25/2010Revisions to Arrangement for Spin-out of New Hana Copper Min...
4/29/2010Letter to Shareholders
3/19/2010New Advisory Board Member
3/5/2010New Chief Financial Officer
1/22/2010Spin-Out of Kuke Property to New Hana Copper Mining Ltd.
7/13/2009Botswana ranked as most favourable mineral investment climat...
6/1/2009completion of inferred resource estimate - Ghanzi Copper-Sil...
5/30/2009Completes $3.2 Million Placement
Comments closed
 
Latest comment posted for this article
Be the first to comment
Add your comment
TSX-V (HMG.V)FRANKFURT (4LH.F)
0.810+0.00%0.144+132.26%
TSX-V
CA$ 0.810
02/19 16:59 -
0%
Prev close Open
0.810 0.810
Low High
0.810 0.810
Year l/h YTD var.
 -  -
52 week l/h 52 week var.
- -  0.810 -%
Volume 1 month var.
61,000 -%
24hGold TrendPower© : 27
Produces
Develops
Explores for Copper - Silver
 
 
 
Analyse
Interactive chart Add to compare
Interactive
chart
Print Compare Export
Last updated on : 1/6/2010
You must be logged in to use the porfolio and watchlists (free)
Top Newsreleases
MOST READ
Annual variation
DateVariationHighLow
 
5 years chart
 
3 months chart
 
3 months volume chart
 
 
Mining Company News
Plymouth Minerals LTDPLH.AX
Plymouth Minerals Intersects Further High Grade Potash in Drilling at Banio Potash Project - Plannin
AU$ 0.12-8.00%Trend Power :
Santos(Ngas-Oil)STO.AX
announces expected non-cash impairment
AU$ 7.68-0.52%Trend Power :
Oceana Gold(Au)OGC.AX
RELEASES NEW TECHNICAL REPORT FOR THE HAILE GOLD MINE
AU$ 2.20+0.00%Trend Power :
Western Areas NL(Au-Ni-Pl)WSA.AX
Advance Notice - Full Year Results Conference Call
AU$ 3.86+0.00%Trend Power :
Canadian Zinc(Ag-Au-Cu)CZN.TO
Reports Financial Results for Q2 and Provides Project Updates
CA$ 0.12+4.55%Trend Power :
Stornoway Diamond(Gems-Au-Ur)SWY.TO
Second Quarter Results
CA$ 0.02+100.00%Trend Power :
McEwen Mining(Cu-Le-Zn)MUX
TO ACQUIRE BLACK FOX FROM PRIMERO=C2=A0
US$ 11.19+2.75%Trend Power :
Rentech(Coal-Ngas)RTK
Rentech Announces Results for Second Quarter 2017
US$ 0.20-12.28%Trend Power :
KEFIKEFI.L
Reduced Funding Requirement
GBX 0.54-2.53%Trend Power :
Lupaka Gold Corp.LPK.V
Lupaka Gold Receives First Tranche Under Amended Invicta Financing Agreement
CA$ 0.06+0.00%Trend Power :
Imperial(Ag-Au-Cu)III.TO
Closes Bridge Loan Financing
CA$ 2.50+5.93%Trend Power :
Guyana Goldfields(Cu-Zn-Pa)GUY.TO
Reports Second Quarter 2017 Results and Maintains Production Guidance
CA$ 1.84+0.00%Trend Power :
Lundin Mining(Ag-Au-Cu)LUN.TO
d Share Capital and Voting Rights for Lundin Mining
CA$ 16.00+2.27%Trend Power :
Canarc Res.(Au)CCM.TO
Canarc Reports High Grade Gold in Surface Rock Samples at Fondaway Canyon, Nevada
CA$ 0.24+4.26%Trend Power :
Havilah(Cu-Le-Zn)HAV.AX
Q A April 2017 Quarterly Report
AU$ 0.20+7.89%Trend Power :
Uranium Res.(Ur)URRE
Commences Lithium Exploration Drilling at the Columbus Basin Project
US$ 6.80-2.86%Trend Power :
Platinum Group Metals(Au-Cu-Gems)PTM.TO
Platinum Group Metals Ltd. Operational and Strategic Process ...
CA$ 1.90+1.60%Trend Power :
Devon Energy(Ngas-Oil)DVN
Announces $340 Million of Non-Core Asset Sales
US$ 51.42-0.49%Trend Power :
Precision Drilling(Oil)PD-UN.TO
Announces 2017Second Quarter Financial Results
CA$ 8.66-0.35%Trend Power :
Terramin(Ag-Au-Cu)TZN.AX
2nd Quarter Report
AU$ 0.03-2.94%Trend Power :