Copper Fox Metals Inc.

Published : September 15th, 2008

Announces Positive Results of Preliminary Feasibility Study on Schaft Creek Copper-Gold-Molybdenum-S

( 0 vote, 0/5 ) Print article
  Article Comments Comment this article Rating Follow Company  
0
Send
0
comment

Monday, September 15, 2008
Copper Fox Metals Announces Positive Results of Preliminary Feasibility Study on Schaft Creek Copper-Gold-Molybdenum-Silver Deposit


PRELIMINARY FEASIBILITY STUDY PROJECTS PRE-TAX 18.6% IRR, US$11.7 BILLION UNDISCOUNTED PRE-TAX CASH FLOW AND 4.7 YEAR PAYBACK.

(CALGARY, SEPTEMBER 15, 2008) Copper Fox Metals Inc. (CUU-TSX-V, CPFXF-S/P) announced today that the National Instrument 43-101 ("NI43-101") compliant Preliminary Feasibility Study ("PFS") on its 70% owned Schaft Creek deposit in northwestern British Columbia indicates the deposit can be developed economically as an open pit mine and recommends going to a full feasibility study.

The study projects (see Appendix A for: "Key Project Parameters and Results"):

  • A Measured and Indicated Resource of 1.393 billion tonnes with 0.25% Cu, 0.18g/t Au, 0.019% Mo, 1.55g/t Ag at a Copper Equivalent of 0.20% cutoff;
  • A Mineable Reserve mill feed of 812.2 million tonnes of 0.301% Cu, 0.212g/t Au, 0.020% Mo and 1.76g/t Ag;
  • 18.6% before tax internal rate of return;
  • $11.734 billion Pre-Tax Cash Flow (undiscounted);
  • $2.764 billion NPV before taxes, discounted at 8%;
  • The revenue generated by all the by-products covers all operating costs and adds a credit of (US) $0.32 /lb of copper produced to the revenue stream. Thus, a negative operating cost for copper is estimated;
  • 4.7 years before tax payback, and 4.9 years after tax payback.
"We are extremely pleased with the results of this study," said Guillermo Salazar, President and CEO of Copper Fox Metals Inc. "This study represents a major milestone in the progress to develop Schaft Creek and positions us to move forward in fall 2008 with the full Feasibility Study. We have already started this work expected to be completed in the first half of 2009".

For the base case, recoverable rock value per tonne is US $31.47 and cash operating costs are US $12.49 per tonne. The PFS confirms the viability of Schaft Creek and highlights the advantages of the project including: location, comparatively low capital expenditure requirements and operating costs and high metal recoveries."

The full report is expected to be available on the www.copperfoxmetals.com and www.sedar.com websites in compliance with Regulatory deadlines.

About the Preliminary Feasibility Study (PFS)

The NI 43-101 compliant PFS was undertaken by a team led by Matt R. Bender, P.E., Director of Process, Mining & Metals of Samuel Engineering, Inc of Denver, Colorado and independent Qualified Person who is the signatory of the PFS report. The PFS was initiated in 2007 following completion of the Schaft Creek Preliminary Economic Assessment (PEA). The effective date of the PFS is August 2008. Contributors to the report include, in addition to Samuel Engineering, Inc., include Knight Piesold, Moose Mountain Technical Services, Associated Geosciences Ltd., Hyyppa Engineering, LLC, G&T Metallurgical, Rescan Environmental Services Ltd., DST Consulting Engineers Inc., BGC Engineering, McElhanney Consulting Services Ltd., HM Hamilton & Associates Inc., PR Associates, Walter Hanych (BsC, Geol), Vandan Suhbatar (Ph.D, Met) and Copper Fox Metals Inc. This Press Release has been reviewed and approved by Matt Bender, P.E.

SUMMARY

For a mill capacity at Schaft Creek of 100,000 tonnes per day, the estimated Initial Capital Expenditure is (US)$2.95 billion. This sum includes a contingency allowance of $536.5 million (US) dollars (22%). The Exchange Rate used throughout the report and this News Release is one Canadian dollar = one US dollar.

  Before Taxes Diesel @ $1.0/lt After Taxes
IRR 18.6% 15.3%
Cash Flow, Undiscounted US$11,734,537,000 US$7,692,885,000
NPV@8% US$2,764,475,000 US$1,597,500,000
NPV@12% US$1,208,843,000 US$522,898,000
Payback Period 4.7 years 4.9 years
Recoverable Rock Value (US)$31.47  
Life of Mine Recoverable Rev. US$25,559,408,000  
Mine Life 22.6 years  
Production Target 4th Quarter 2013  

A number of factors affected cost included in the CAPEX and OPEX estimates from the PEA to the PFS, such as increased planned mill capacity (from 65,000 to 100,000 tpd), market, metal price, volatilities of construction material costs and comparable studies about rising OPEX and CAPEX costs from other parties working in the area. These, in turn, led to a review of forecasts and estimates for labour, construction material, sustaining capital and working capital. This resulted in a delay in the release of this study and an increase in the CAPEX and OPEX from those reported in last December's PEA. The Feasibility Study, is expected to be completed in first half of 2009.

Option Agreement with Teck Cominco Limited

At present Copper Fox has earned a 70% direct participating interest in the project from Teck Cominco Ltd, through an option agreement dated January 1, 2002. The agreement stipulates that:

  • Copper Fox can earn a further 23.4% indirect carried interest in the project upon completion of a positive Feasibility Study.
  • Teck Cominco has a right to buy back a 20%, 40% or 75% interest in Copper Fox's interest in the project by matching one, three or four times Copper Fox's expenditures. This right expires 120 days after Copper Fox has presented a positive Feasibility Study, as defined in the Option Agreement, to Teck Cominco.
  • In the case of a 75% buy back, Teck Cominco is also responsible for arranging all production financing.
Capital Costs

Total initial investment in the project is estimated to be US$2,950,406,000 which represents the total direct and indirect costs for the complete development of the project. Of this figure, US$1,315,484,000 represent direct mine development costs, US$610,108,000 indirect mine development costs, US$459,757,000 are owner's costs US$536,000,000 contingency, and US$28,566,000 are provincial taxes on identified capital expenditures.

The life-of-mine sustaining capital is as follows:

Mine US$232,893,000
Mill US$220,000,000
Tailings US$257,486,000
Reclamation and Closure US$87,000,000
Total Sustaining Capex US$797,379,000

Life of Mine Total direct Taxes are estimated at US$4,041,652,000.

Cash Operating Costs

Cash Operating Costs are estimated at US$12.49 per tonne of ore for the life of the mine. Average costs are US$4.14/t for mining, US$3.94/t for milling, US$0.93/t for general and administration, and US$3.49/t concentrate handling and treatment.

The revenue generated by the production of molybdenum, gold and silver (US$14.36/t) leaves a positive balance of US1.87 $/t. This translates into an additional credit to the copper production of US$0.32 /lb of copper produced.

FINANCIAL FORECAST

The independent PFS reports that development of the Schaft Creek deposit is expected to produce a pre-tax Internal Rate of Return (IRR) of 18.6% and an 8% discounted Net Present Value of (US)$2,764,475,000 dollars. The base case financial evaluation uses historical three year trailing averages for metal prices as of August 29, 2008. This approach is consistent with the guidance of the United States Securities and Exchange Commission, is accepted by the Ontario Securities Commission and is industry standard.

Commodity Prices

  Base Case Prices Based on 3 YR historical trailing averages of the LME as of August 29, 2008
Copper (US$/lb) 3.12
Molybdenum (US$/lb Cochilco) 33.00
Gold (US$/troy ounce) 692.85
Silver (US$/troy ounce) 13.09

Development Plan

The PFS recommends development of the Schaft Creek deposit as a conventional open pit, electrified, diesel truck and shovel operation. The sulphide deposit is expected to be processed using a conventional concentrator to produce separate copper-gold-silver and molybdenum concentrates.

The mill is designed to have a nominal capacity of 100,000 tonnes of sulphide ore per day. Including low grade and stockpile ore, the annual stripping ratio is estimated at 1.88 to 1.

Over a projected mine life of 22.6 years, the mill is expected to produce 4.76 billion pounds of copper, 255.2 million pounds of molybdenum, 4.5 million troy ounces of gold and 32.5 million troy ounces of silver. Rhenium is recovered in the molybdenum concentrate in significant quantities. At a present price of $350 per gram of pure rhenium this may represent a significant additional contribution to income. Copper Fox will report further results with respect to rhenium during the feasibility phase of the project.

Should Teck Cominco decide to exercise their back-in right to acquire 75% of the ultimate 93.4% Copper Fox interest in the Schaft Creek Project, it is expected to be responsible for securing financing for Copper Fox's portion as well as theirs. Copper Fox shall pay back its portion of the project debt out of project revenues. By this time Copper Fox is expected to own 23.35 % of the revenues generated by the project and is expected to pay its portion of the debt financing from revenue generated by production income from its 23.35 % equity of Schaft Creek.

Under such a scenario Copper Fox's share of production is projected to be 1.11 billion pounds of copper (22,400 tonnes per year), 1.05 million ounces of gold (46,500 ounces per year), 59.6 million pounds of molybdenum (2.64 million pounds per year), and 7.6 million ounces of silver (336,000 ounces per year) over the 22.6 year mine life. The Preliminary Feasibility Study reports start of production to be late 2013.

Environment & Permitting

Rescan-RTEC, a well regarded environmental consulting firm, has been engaged to assist Copper Fox in the permitting of Schaft Creek. Initial permits to support commencement of production are expected to be obtained in the fourth quarter of 2013 in time for sales of concentrates starting in 2014. Copper Fox is working with all levels of government and the Tahltan Nation to complete a streamlined assessment and permitting process.

FIRST FIVE YEARS PRODUCTION SCHEDULE

At a mill capacity of 100,000 tonnes per day, the mill feed for the first five years is expected to be a minimum of 180.0 million tonnes with a grade of 0.32% copper, 0.017% molybdenum, 0.237 g/t gold and 1.587 g/t silver. These higher grades are expected to be a contributing factor to the rapid repayment of CAPEX.

MILL RECOVERIES

Mill recoveries are projected to be: copper to the copper concentrate: 88.4%, molybdenum to the molybdenum concentrate: 71.3%, gold to the copper concentrate: 81.3%, silver to the copper concentrate: 70.7%.

  • The grades of the copper concentrate are expected to be: copper, 33.85%, gold, 21.9 g/t, silver, 158.3 g/t.
  • The grade of the molybdenum concentrate is 50.0%, and assays 368 ppm rhenium.
The copper grade in the copper concentrate is higher grade than industry standard chalcopyrite concentrate because of the bornite content and should command a premium from smelters and refiners seeking this product. The rhenium content of the molybdenum concentrate is expected to possibly command a premium.

RESOURCE ESTIMATES

The resource estimates prepared in 2006-2007 by Associated Geoscientists Ltd. were reviewed and a new pit optimization plan was designed by Moose Mountain Technical Services Ltd. of Calgary. The 100,000 tonnes per day pit and mill feed optimization plan presented in the NI 43-101 compliant PFS is expected to extract 812.2 million tonnes of minable reserve with a head grade of 0.301% copper, 0.020% molybdenum, 0.212 g/t gold and 1.761 g/t silver. A total of 1.54 billion tonnes of waste rock (LOM waste to ore ratio of 1.88) is expected to be removed concurrently with mining and milling.

COPPER FOX ACHIEVEMENTS

Since the formation of Copper Fox, the company has spent in excess of 32 million CDN dollars in developing the Schaft Creek mineral deposit. Copper Fox is positioned to complete the full Feasibility Study of the deposit and readying Schaft Creek for production at a minimum of 100,000 tpd.

Key development achievements include:

  • Improving historical core recoveries by drilling wider diameter holes and using state of the art drilling technology that has resulted in higher gold assays, but confirmed the historical copper, molybdenum and silver assay database.
  • Confirming the capability of separating copper, gold and silver from molybdenum and the gangue materials and
  • Demonstrating the capability of running a conventional 100,000 tpd mine and mill complex that would produce high quality copper-gold-silver and molybdenum-rhenium concentrates.
  • Metal Recoveries have improved substantially.
Flotation Recovery Improvements

Recoveries by Flotation Historical Results (*) Copper Fox -- Pre-Feasibility
Copper 50-75% 88.4%
Molybdenum 30-50% 71.3%
Gold 30-50% 81.3%
Silver 30-50% 70.7%
(*) Hecla Mining Co. (1969-1978) & Teck Cominco Ltd (1978-2002)

Social License

Since 2005, Copper Fox has worked with the Tahltan Nation to develop a relationship based on open, honest and transparent communication. The company has done this by entering into agreements with the Tahltan Central Council (TCC) and the Tahltan Nation's government, with the aim of building a solid working relationship. These agreements include: the Communications Agreement, which provides funding to build communications capacity within the TCC; the Tahltan Heritage Resources Environmental Assessment Team (THREAT) agreement, which outlines how the company works with THREAT through the environmental assessment process; the Heritage Agreement, which outlines how the company is expected to protect the heritage and cultural resources of the Tahltan Nation within the Schaft Creek Project area; and a Memorandum of Understanding (MOU) between the company and the Tahltan Nation Development Corporation (TNDC) which ensures that Copper Fox will hire Tahltan workers and use Tahltan suppliers when price and quality are comparable.

In addition to these agreements, Copper Fox has provided support to initiatives and projects that support the advancement of Tahltan youth and culture. These include: support for the Tahltan Language Camp, Youth Science Camp, bursaries to support continuing education and support for the Resource Forum.

As part of its commitment to open communication, Copper Fox has hosted open houses in the Tahltan communities of Dease Lake, Iskut and Telegraph Creek as well as the northern communities of Smithers, Terrace, Stewart and Kitimat. As the Schaft Creek Project advances towards feasibility these community meetings will continue and the company will seek further feedback on the project.

Enhancement Opportunities:

Samuel Engineering notes that the economics in the PFS do not take into account opportunities for improvement of the project economics based on:

  • Further improvements to the process design based on additional metallurgical test work, for example:
    • optimizing primary and secondary grind size -- thus reducing grinding circuit size and power;
    • optimizing rougher and cleaner flotation circuits -- thus reducing both size and number of flotation cells;
    • optimizing concentrate grades;
    • optimizing solid/liquid separation -- thus reducing size of thickeners and filters.
  • Optimize tailings deposition method;
  • Optimization of mill location;
  • Inclusion of revenue from rhenium;
  • Increasing the overall resources of the deposit;
  • Conversion of Inferred Resources into Measured and Indicated Resources; and
  • Sharing of infrastructure development costs and power with neighbouring potential producers and other stakeholders.
On behalf of the Board of Directors

Guillermo Salazar, President and CEO

For additional information contact: Investor inquiries: Jason Shepherd, Phoenix
Communications Group Tel: 1-866-913-1910, E-mail: investor@copperfoxmetals.com.

The TSX Venture Exchange has not reviewed the contents of this news release and accepts no responsibility for the adequacy or the accuracy thereof.

Cautionary Note Regarding Forward-Looking Information

This news release includes "forward-looking information" within the meaning of the Canadian securities laws. All statements, other than statements of historical fact, included herein and including, without limitation; anticipated dates for receipt, commencement or completion of permits, approvals, construction, production and other milestones; anticipated results of drilling programs, scoping, prefeasibility and feasibility studies and other analyses; anticipated availability and terms of future financings; estimated timing and amounts of future expenditures; Copper Fox's future production, operating and capital costs; operating or financial performance; geological interpretations and potential mineral recovery processes, are forward-looking statements. Information concerning mineral reserve and resource estimates also may be deemed to be forward-looking information in that it reflects a prediction of the mineralization that would be encountered if a mineral deposit were developed and mined. Forward-looking information is necessarily based upon a number of estimates and assumptions that, while considered reasonable by management, are inherently subject to significant business, economic and competitive uncertainties, risks and contingencies. For any forward looking information given, management has assumed that the geological, metallurgical, engineering, financial and economic advice it has received is reliable, and is based upon practices and methodologies which are consistent with industry standards. There can be no assurance that such information will prove to be accurate, and actual results and future events could differ materially from those anticipated in such information. Important factors that could cause actual results to differ materially from Copper Fox's expectations include: fluctuations in copper and other commodity prices and currency exchange rates; uncertainties relating to interpretation of drill results and the geology, continuity and grade of mineral deposits; uncertainty of estimates of capital and operating costs, recovery rates, production estimates and estimated economic return; the need for cooperation of government agencies and native groups in the exploration and development of properties and the issuance of required permits; the need to obtain additional financing to develop properties and uncertainty as to the availability and terms of future financing; the possibility of delay in exploration or development programs or in construction projects and uncertainty of meeting anticipated program milestones; uncertainty as to timely availability of permits and other governmental approvals; and other risks and uncertainties disclosed in Copper Fox's continuous disclosure filings with Canadian securities regulatory authorities at www.sedar.com. The forward-looking information in this news release is based on Copper Fox's current expectations and Copper Fox assumes no obligations to update such information to reflect later events or developments, except as required by law. This news release by Copper Fox uses the terms "resources", "measured resources" and "indicated resources" as well as the terms "Reserves" and "Mill Feed". United States investors are advised that, such terms are recognized and required by Canadian securities laws, the United States Securities and Exchange Commission (the "SEC") does not recognize them. Under United States standards, mineralization may not be classified as a "reserve" unless the determination has been made that the mineralization could be economically and legally produced or extracted at the time a reserve determination is made. Mineral resources that are not mineral reserves do not have demonstrated economic viability. The terms "Reserve" and "Mill Feed" have been used to define resources which extraction has been optimized and metallurgical recoveries defined to the satisfaction of independent professional engineers. NI 43-101 is a rule developed by the Canadian Securities Administrators, which established standards for all public disclosure an issuer makes of scientific and technical information concerning mineral projects. The requirements of NI 43-101 are not the same as those of the SEC.

Appendix 'A'
Schaft Creek Prefeasibility Study
Key Project Parameters and Results
September 9, 2008
       
Total Resource (M&I) tonnes 1,393,282,171  
Total Reserve tonnes 816,706,750  
LOM Mill Feed tonnes 812,230,421  
LOM Waste tonnes 1,543,190,551  
LOM Strip Ratio   1.88  
Daily Feed Rate tpd 100,000  
Mine Life yrs 22.6  
Connected Load MW 146.8  
Avg Power Demand MW 121.4  
Power Cost $/kWh 0.0469  
Foreign Exchange Rate   US$1 = C$1  
Total Initial Capex (000's) 2,950,406  
Directs (000's) 1,315,484  
Indirects (000's) 610,108  
Owner (000's) 459,757  
Taxes (000's) 28,566  
Contingency (000's) 536,490  
Working Capex (000's) 146,420  
Total Sustaining Capex (000's) 797,379  
Mine (000's) 232,893  
Mill (000's) 220,000  
Tailings (000's) 257,486  
Reclamation & Closure (000's) 87,000  
Total LOM Opex (000's) 10,138,610  
Total LOM Opex $/t ore 12.49  
Mining $/t ore 4.14  
Processing $/t ore 3.94  
G&A $/t ore 0.93  
Conc Handling & Treatment $/t ore 3.49  
Contingency (0%) $/t ore 0.00  
Total LOM Taxes (000's) 4,041,652  
Metrics %
Head Grades Concentrate Grades Recoveries
0.301% 33.85% 88.4%
0.020% 50.0% 71.3%
0.212 21.90 81.3%
1.761 158.30 70.%
Cu %
Mo g/t
Au g/t
Ag  
Base Case Pricing (Trailing 3 Year Avg - August 29, 2008)
Cu $/lb 3.12  
Mo $/lb 33.00  
Au $/oz 692.85  
Ag $/oz 13.09  
Cash Flow Results  
Before Tax After Tax Direct Tax Effects
18.6% 15.3% -3.21%
$11,734,537 $7,692,885 ($4,041,652)
$4,787,931 $2,983,847 ($1,804,084)
$2,764,475 $1,597,500 ($1,166,974)
$1,868,441 $979,686 ($888,755)
$1,208,843 $522,898 ($685,945)
4.7 4.9  
IRR %
NPV @ 0% (000's)
NPV @ 5% (000's)
NPV @ 8% (000's)
NPV @ 10% (000's)
NPV @ 12% (000's)
Payback Period yrs
Rock Value * $/t ore $31.47  
LOM Recoverable Revenue $(000's) 25,559,408  
Cu % 54.4%  
Mo % 32.2%  
Au % 12.0%  
Ag % 1.4%  
Total Metal Production  
LOM Annual Annual Tonnes
4,762,524,025 211,104,788 95,757
255,194,418 11,311,809 5,131
4,493,445 199,178  
32,480,015 1,439,717  
Cu lbs
Mo lbs
Au ozs
Ag ozs
CFM Portion of Metal Production  
LOM Annual Tonnes
1,112,049,360 49,292,968 22,359
59,587,897 2,641,307 1,198
1,049,219 46,508  
7,584,084 336,174  
Cu lbs
Mo lbs
Au ozs
Ag ozs
Facilities Startup   4 QTR 2013  
* Rock Value = LOM Recoverable Revenue / LOM Mill Feed

You can also view this News Release on our website at:
http://www.copperfoxmetals.com/s/NewsReleases.asp?ReportID=319027



  Copper Fox Home PageCorporateProjectsNewsInvestorsContactContactInvestorsNewsProjectsCorporateCopper Fox Home Page

Copper Fox Metals Inc.

DEVELOPMENT STAGE
CODE : CUU.V
ISIN : CA21749Q1046
Follow and Invest
Add to watch list Add to your portfolio Add or edit a note
Add Alert Add to Watchlists Add to Portfolio Add Note
ProfileMarket
Indicators
VALUE :
Projects & res.
Press
releases
Annual
report
RISK :
Asset profile
Contact Cpy

Copper Fox is a copper development stage company based in Canada.

Copper Fox develops copper, gold, molybdenum and silver in Canada.

Its main asset in development is SCHAFT CREEK in Canada.

Copper Fox is listed in Canada. Its market capitalisation is CA$ 96.3 millions as of today (US$ 70.4 millions, € 65.8 millions).

Its stock quote reached its highest recent level on April 21, 2011 at CA$ 2.63, and its lowest recent point on March 13, 2020 at CA$ 0.01.

Copper Fox has 427 809 984 shares outstanding.

Your feedback is appreciated, please leave a comment or rate this article.
Rate : Average note :0 (0 vote) View Top rated
 
Annual reports of Copper Fox Metals Inc.
2007 Annual report
2006 Annual report
Financings of Copper Fox Metals Inc.
7/1/2016Announces Closing of the Second placement
4/8/2013Announces Closing of a $2,653,000 Financing
2/22/2013announces a $2,500,000 Private Placement Unit Offering, insi...
1/22/2013ANNOUNCES the Closing of a $1,500,000 Financing by an Inside...
1/16/2013Announces a $1,500,000 Private Placement Unit Offering, Insi...
1/16/2013Announces a $1,500,000 Private Placement Unit Offering, Insi...
10/24/2012ANNOUNCES the Closing of a $2,500,000 Financing by an Inside...
9/14/2012Announces the Closing of a $4,025,000 Financing by an Inside...
7/23/2012ANNOUNCES a $4,025,000 Private Placement Unit Offering, Insi...
6/18/2012Announces A $4,480,000 Private Placement Unit Offering Insid...
1/30/2012Announces The Closing Of $2,200,000 Financing By An Insider
1/19/2012Announces a $2,200,000 Private Placement Unit Offering Insid...
12/14/2011Announces the Closing of $4,000,000 Financing by an Insider
12/7/2011Announces Increase of $2,000,000 to previously announced Pri...
10/5/2011Announces the Closing of $5,000,000 Financing by an Insider
9/13/2011Announces an Additional $2,000,000 Private Placement Unit Of...
9/8/2011announces a $3,000,000 Private Placement Unit Offering. Ins...
3/31/2011ANNOUNCES THE ACCELERATION TERM TO BE APPLIED TO THE EXPIRY ...
3/17/2011CLOSING OF A $3,750,000 NON BROKERED PRIVATE PLACEMENT FLOW-...
2/17/2011Announces a $3,750,000 Non Brokered Private Placement Flow-T...
10/22/2009closing of a $2,000,000 Private Placement Unit Offering
9/28/2009$2,000,000 Private Placement
6/23/2009Provides Update on its $6,000,000 Private Placement
6/19/2009 Updates on its $6,000,000 private placement
6/2/2009announces a $6,000,000 non-brokered Private Placement of whi...
12/16/2008Announces the Withdrawal of a Private Placement Financing
11/7/2008ANNOUNCES PRIVATE PLACEMENT FINANCING
11/7/2008Announces Private Placement Financing
5/15/2008closes Non Brokered Private Placement Financing of $12,398,2...
7/17/2007to raise $10,000,000 in flow-through and non-flow-through fu...
7/17/2007Intends to offer a brokered private placement
Option Grants of Copper Fox Metals Inc.
4/30/2012Announces Incentive Stock Option Grants
3/14/2011Grant of 1,700,000 shares at $ 1,69 par share
6/26/2008grant of incentive stock options to Employees, Officers, Con...
Nominations of Copper Fox Metals Inc.
5/3/2011ANNOUNCES RESIGNATION OF CFO, APPOINTMENT OF AN INTERIM CFO
7/16/2009Announces Executive Changes and the Appointment of a Directo...
9/17/2007Announces the appointment of Shane Uren as Vice President
Financials of Copper Fox Metals Inc.
9/22/2016Announces 2016 Third Quarter Financial Results
3/31/2016Announces 2016 First Quarter Financial Results
9/29/2015Announces Third Quarter Results
9/28/2013Announces Third Quarter Results
6/24/2013Announces Second Quarter Results
9/27/2012Announces Third Quarter Results
6/18/2012Announces Second Quarter Results
4/25/2012Announces First Quarter Results
2/29/2012Reports 2011 Annual Financial Results and a Corporate Update
9/29/2011Reports 2011 Third Quarter Financial Results and a Corporate...
6/30/2011Advances Feasibility Study and Reports 2011 Second Quarter F...
3/31/2011Announces First Quarter 2011 Highlights and Financial Result...
2/16/2011Announces Fourth Quarter Highlights and 2010 Year-End Financ...
2/25/2010Announces 2009 Year-End Financial Results
3/6/20092008 Year-end Financial Results
6/4/2008Second Quarter Results Three and Six Months Ended April 30, ...
6/3/2008Second Quarter Results
3/31/2008First Quarter Financials
3/27/2008First Quarter Results Three Months Ended January 31, 2008
2/11/20082007 Year-End Financial Results
9/24/2007Announces third quarter results
3/28/2007announces its first quarter results for the three months en...
Project news of Copper Fox Metals Inc.
1/9/2014Outlines 2014 Diamond Drilling Plans for Van Dyke Copper Pro...
11/19/2013Sampling Locates Two Large Areas Of Porphyry Style Copper-M...
4/12/2013Acquires Van Dyke Copper Deposit in Arizona
3/25/2013(Schaft Creek)Enters Into Facilities Study Agreement with BC Hydro for Sch...
2/4/2013(Schaft Creek)Files Positive Feasibility Study on Schaft Creek Project
9/10/2012Completes Acquisition Of Sombrero Butte Copper Project And V...
7/9/2012To Acquire From Bell Copper The Van Dyke Copper Deposit And ...
5/31/2012(Schaft Creek)Schaft Creek Resource Estimate Update
5/24/2012(Schaft Creek)Provides Update on Schaft Creek Project
5/10/2012(Schaft Creek)Announces 2012 Exploration Program And Acquires Additional M...
3/27/2012(Schaft Creek)Completes Land Acquisitions Covering Positive Magnetic Linea...
3/19/2012(Schaft Creek)s Activities on the Schaft Creek-Copper-Gold-Molybdenum-Silv...
2/3/2012(Schaft Creek)Announces Drilling Intersect of 0.96% CuEq Over 110m and Rep...
12/12/2011Drilling Expands Paramount Zone with Intersection of 1.10% C...
10/13/2011(Schaft Creek)Secures Shipping Facilities for Concentrate at Port of Stewa...
9/23/2011(Schaft Creek)Extends Mineralized Zone to the East And Completes Strategic...
9/6/2011Welcomes the Awarding of the Construction Contract for the N...
7/26/2011(Schaft Creek)Drilling Intersects 1.18% Copper Equivalent Over 161M at Sch...
5/31/2011(Schaft Creek)Commences 2011 Drilling Program, Updates Other Activities ...
5/10/2011(Schaft Creek)Welcomes the Federal Government of Canada's Approval of the ...
5/6/2011(Schaft Creek)Provides Update on 2011 Plans for Schaft Creek, Diamond Dril...
5/5/2011(Schaft Creek)FOX PROVIDES UPDATE ON 2011 PLANS FOR SCHAFT CREEK, DIAMOND ...
3/24/2011(Schaft Creek)Announces Strategic Acquisitions to Enlarge Schaft Creek Pro...
2/28/2011(Schaft Creek)Copper Fox Metals Applauds the Announcement of the Province ...
2/23/2011(Schaft Creek)DDH CF405 Tests Chargeability Anomaly And Expands Zone Of De...
2/14/2011(Schaft Creek)News Release
2/3/2011(Schaft Creek)Latest Assay Results Expands Zone of Deep, Higher Grade Mine...
6/18/2010files an amended Preliminary Feasibility Study on SEDAR
4/1/2010s Status of Feasibility Study and Reports 2010 First Quarter...
1/21/2010(Schaft Creek)Awards Feasibility Study On Schaft Creek Project
11/18/2009(Schaft Creek)Geophysical Survey Outlines "8" IP Anomalies at Schaft Creek...
9/15/2008Positive Results of Preliminary Feasibility Study on Schaft ...
9/15/2008Announces Positive Results of Preliminary Feasibility Study ...
7/14/2008(Schaft Creek)Strategic Drilling Program and Greenfield Camp Expansion Hig...
6/26/2008(Schaft Creek)2007 Drilling And Geophysical Results All Show Increased Pot...
3/20/2008(Schaft Creek)Announces Schaft Creek progress
1/14/2008(Schaft Creek)Releases Positive Preliminary Economic Assessment on its Sch...
11/27/2007(Schaft Creek)continues development of its Schaft Creek British Columbia m...
10/22/2007(Schaft Creek)'Pit Optimization Study Demonstrates 65,000-tonne per-day Op...
7/10/2007(Schaft Creek)Updates 2007 Schaft Creek Work Program
7/4/2007(Schaft Creek)Significantly Increases Resources at Schaft Creek
Corporate news of Copper Fox Metals Inc.
6/29/2016Copper Fox Announces 2016 Second Quarter Financial Results
6/10/2016Copper Fox Announces a $1,000,000 Non-Brokered Private Place...
3/31/2016Copper Fox Announces 2016 First Quarter Financial Results
3/30/2016Copper Fox Annnounces 2016 Schaft Creek Program
1/25/2016Copper Fox Announces Mineral Mountain Copper Project in Ariz...
12/24/2015Copper Fox Files Van Dyke Technical Report on SEDAR
12/22/2015Copper Fox Announces $1,650,000 Non-Brokered Private Placeme...
11/6/2015Copper Fox Provides Update of Activities
9/29/2015Copper Fox Announces Third Quarter Results
9/25/2015Copper Fox Extends Size of Exploration Target on Sombrero Bu...
9/8/2015Copper Fox Reports Large Chargeablity Signature on Sombrero ...
7/28/2015Copper Fox Provides Update of Activities
7/13/2015Copper Fox Commences Titan-24 DCIP Survey at Sombrero Butte ...
4/15/2015Copper Fox Announces Preliminary Results of Metallurgical Te...
4/8/2015Copper Fox Announces Commencement of Preliminary Economic As...
3/31/2015Copper Fox Annnounces First Quarter Results
3/17/2015Copper Fox Annnounces 2015 Schaft Creek Program
3/13/2015Copper Fox Receives $3.63 Million Cash Refund
3/12/2015Copper Fox Extends Warrant Expiry Dates and Announces AGM Da...
2/27/2015Copper Fox Announces Annual Results
2/9/2015Copper Fox Updates Schaft Creek Project Activities
2/3/2015Copper Fox Files Van Dyke Technical Report on SEDAR
1/15/2015Copper Fox Completes Top-Up Investmentin Carmax Mining Corp.
12/24/2014Copper Fox Provides Corporate Update on Project Activities
12/19/2014Copper Fox Completes Inferred Mineral Resource Estimate for ...
12/3/2014Copper Fox Announces Preliminary In-Situ Leach Test Results ...
10/28/2014Copper Fox Announces Commencement of Resource Estimate at Va...
10/23/2014Copper Fox Announces Update on Schaft Creek Project
9/25/2014Copper Fox Completes Top-Up Investment in Carmax Mining Corp...
9/23/2014Copper Fox Announces Third Quarter Results
9/10/2014Copper Fox Announces Van Dyke Drill Results and Provides Oth...
8/7/2014Copper Fox Announces Van Dyke Drill Results and Provides Cor...
7/21/2014Copper Fox Completes Van Dyke Drilling Program and Provides ...
6/18/2014Copper Fox Announces Second Quarter Results
5/29/2014Copper Fox Closes Carmax Investment
5/23/2014Copper Fox Announces Carmax Shareholders Approve Private Pla...
5/15/2014Copper Fox Adds Second Drill to Van Dyke Project and Provide...
12/3/2013s Activities on Van Dyke Copper Deposit in Arizona
11/19/2013Sampling locates two large areas of porphyry style copper-mo...
8/30/2013announces a corporate reorganization
8/12/2013provides update on corporate activities
7/16/2013(Schaft Creek)And Teck Resources Form Schaft Creek Joint Venture
6/5/2013(Schaft Creek)provides update on discussions regarding Schaft Creek
2/7/2013(Schaft Creek)Completes Land Acquisitions at Schaft Creek & Sombrero Butte...
1/17/2013Announces Extension Of Expiry Date Of Certain Stock Options
10/17/2012(Schaft Creek)Reports Diamond Drill Results From the 2012 Drilling Program...
9/25/2012(Schaft Creek)Reports the Status of the Schaft Creek Feasibility Study and...
9/25/2012(Schaft Creek)Reports the Status of the Schaft Creek Feasibility Study and...
9/4/2012Drilling Indicates Widespread Mineralization in the Discover...
8/2/2012(Schaft Creek)Drilling Extends Mineralization In Discovery Zone And Acquir...
2/16/2012(Schaft Creek)Locates a New Zone of Copper Mineralization 1,200M North of ...
1/23/2012Announces The Issuance Of 1,272,727 Shares For Outstanding ...
1/13/2012Announces Shares For Debt Agreement
9/6/2011(Schaft Creek)Drilling Intersects 0.81% Copper Equivalent Over 154m at Sch...
7/11/2011(Schaft Creek)Measured and Indicated Resource Estimate Exceeds 1 Billion T...
6/21/2011(Schaft Creek)High Resolution Magnetic Survey at Schaft Creek Confirms Sim...
4/13/2011Announces Completion of 3D Model and Award of High-Resolutio...
4/13/2011ANNOUNCES COMPLETION OF 3D MODEL AND AWARD OF HIGH-RESOLUTIO...
6/17/2010June 17 2010 news release
6/1/2010June 1 2010 News release
2/2/2010Feb 2 2010 news release
1/21/2010Jan 21, 2010
10/23/2009New release attached
10/22/2009announces the closing of a $2,000,000 Private Placement Unit...
9/17/2009Applauds Federal Government’s Support for British Columbia N...
9/17/2009Applauds Federal Government's Support for British Columbia N...
7/13/2009Special Shareholders Meeting Approves a New control Person -...
7/13/2009July 13, 2009 News release
6/30/2009Three and Six Months Ended April 30, 2009
6/26/2009June 25, 2009 news release
3/3/2009Annual Financial
2/27/2009Feb 26, 2009 News release
2/27/2009Lions Gate Metals Inc. and Copper Fox Metals Inc. Announce B...
2/12/2009Correct News release
2/12/2009Feb 11 09 News release
2/12/2009provides an update of Corporate Activities
2/3/2009Highway 37 Power Line Coalition Applauds Premier for Express...
1/22/2009Cambridge House Invitation - Vancouver
12/18/2008December 17 2008 News release
12/18/2008Announces Resignation Of A Director
9/30/2008Sept 30/08
9/29/2008Applauds Advancement of Northwest Power Line
9/29/2008Applauds Advancement of Northwest Power Line
9/26/2008Northwest Power Line Could Create Thousands of Jobs, Attract...
9/17/2008Schaft not Galore says Copper Fox president
9/2/2008LV Hard Assets Conference Personalized Html
7/17/2008from the Ministry of Energy, Mines and Petroleum Resources r...
6/26/2008June 26 2008 Options
6/26/2008June 26, 2008
5/26/2008Register Today for a Discounted Rate to the New Orleans 2008...
4/4/2008Applauds Advancement of Northwest Power Line Study
3/31/2008$16mm offering
11/15/2007announces the renewal of the engagement of Jason Shepherd fo...
10/12/2007Announces is has earned a 70% Direct Interest in the World C...
10/2/2007$400 million to empower B.C.'s far northwest
8/8/2007Drilling to Commence at Copper Flats
7/12/2007Press Release: Augusta Files Plan of Operations for Rosemont...
7/3/2007 2nd Quarter Financials
6/11/2007announces its request for a trading halt
5/4/2007and the Tahltan Nation Development Corporation complete a "M...
4/22/2007Adopts a Shareholder Rights Plan.
2/27/2007Welcomes New Executive to the Team
Comments closed
 
Latest comment posted for this article
Be the first to comment
Add your comment
TSX-V (CUU.V)
0.225-8.16%
TSX-V
CA$ 0.225
04/26 13:30 -0.020
-8.16%
Prev close Open
0.245 0.240
Low High
0.220 0.240
Year l/h YTD var.
0.160 -  0.250 -2.17%
52 week l/h 52 week var.
0.150 -  0.300 -18.18%
Volume 1 month var.
73,181 32.35%
24hGold TrendPower© : 40
Produces
Develops Copper - Gold - Molybdenum - Silver
Explores for
 
 
 
Analyse
Interactive chart Add to compare
Interactive
chart
Print Compare Export
Last updated on : 7/8/2010
You must be logged in to use the porfolio and watchlists (free)
Top Newsreleases
MOST READ
Annual variation
DateVariationHighLow
202415.38%
202321.88%0.310.15
2022-36.00%0.320.13
2021-25.37%0.660.20
2020346.67%0.470.01
 
5 years chart
 
3 months chart
 
3 months volume chart
 
 
Mining Company News
Plymouth Minerals LTDPLH.AX
Plymouth Minerals Intersects Further High Grade Potash in Drilling at Banio Potash Project - Plannin
AU$ 0.12-8.00%Trend Power :
Santos(Ngas-Oil)STO.AX
announces expected non-cash impairment
AU$ 7.70-0.65%Trend Power :
Oceana Gold(Au)OGC.AX
RELEASES NEW TECHNICAL REPORT FOR THE HAILE GOLD MINE
AU$ 2.20+0.00%Trend Power :
Western Areas NL(Au-Ni-Pl)WSA.AX
Advance Notice - Full Year Results Conference Call
AU$ 3.86+0.00%Trend Power :
Canadian Zinc(Ag-Au-Cu)CZN.TO
Reports Financial Results for Q2 and Provides Project Updates
CA$ 0.12+4.55%Trend Power :
Stornoway Diamond(Gems-Au-Ur)SWY.TO
Second Quarter Results
CA$ 0.02+100.00%Trend Power :
McEwen Mining(Cu-Le-Zn)MUX
TO ACQUIRE BLACK FOX FROM PRIMERO=C2=A0
US$ 12.40+3.85%Trend Power :
Rentech(Coal-Ngas)RTK
Rentech Announces Results for Second Quarter 2017
US$ 0.20-12.28%Trend Power :
KEFIKEFI.L
Reduced Funding Requirement
GBX 0.53-1.87%Trend Power :
Lupaka Gold Corp.LPK.V
Lupaka Gold Receives First Tranche Under Amended Invicta Financing Agreement
CA$ 0.06+0.00%Trend Power :
Imperial(Ag-Au-Cu)III.TO
Closes Bridge Loan Financing
CA$ 2.65-1.49%Trend Power :
Guyana Goldfields(Cu-Zn-Pa)GUY.TO
Reports Second Quarter 2017 Results and Maintains Production Guidance
CA$ 1.84+0.00%Trend Power :
Lundin Mining(Ag-Au-Cu)LUN.TO
d Share Capital and Voting Rights for Lundin Mining
CA$ 16.10+3.21%Trend Power :
Canarc Res.(Au)CCM.TO
Canarc Reports High Grade Gold in Surface Rock Samples at Fondaway Canyon, Nevada
CA$ 0.24+4.26%Trend Power :
Havilah(Cu-Le-Zn)HAV.AX
Q A April 2017 Quarterly Report
AU$ 0.20+2.63%Trend Power :
Uranium Res.(Ur)URRE
Commences Lithium Exploration Drilling at the Columbus Basin Project
US$ 6.80-2.86%Trend Power :
Platinum Group Metals(Au-Cu-Gems)PTM.TO
Platinum Group Metals Ltd. Operational and Strategic Process ...
CA$ 1.88+0.53%Trend Power :
Devon Energy(Ngas-Oil)DVN
Announces $340 Million of Non-Core Asset Sales
US$ 52.57-0.07%Trend Power :
Precision Drilling(Oil)PD-UN.TO
Announces 2017Second Quarter Financial Results
CA$ 8.66-0.35%Trend Power :
Terramin(Ag-Au-Cu)TZN.AX
2nd Quarter Report
AU$ 0.04+5.56%Trend Power :