Pele Mountain Resources Inc

Published : July 05th, 2011

Announces Preliminary Economic Assessment for Eco Ridge Mine Rare Earths and Uranium Project with $1

( 0 vote, 0/5 ) Print article
  Article Comments Comment this article Rating Follow Company  
0
Send
0
comment
Keywords :   Canada | China | Dysprosium | Gem | Gold | Market | Rare Earth | Recovery | Uranium |

Pele Mountain Announces Preliminary Economic Assessment for Eco Ridge Mine Rare Earths and Uranium Project with $1.31-Billion Pre-Tax Cash Flow, $662-Million NPV (at 7.5% Discount Rate), 47% IRR

TORONTO, July 5, 2011 /CNW/ - Pele Mountain Resources Inc. (TSXV: GEM) (OTCQX: GOLDF) ("Pele" or the "Company") today announced results of a NI 43-101 Preliminary Economic Assessment (the "PEA") on its Eco Ridge Mine Rare Earths and Uranium Project ("Eco Ridge" or the "Project"). The PEA was prepared by Roscoe Postle Associates ("RPA") and demonstrates that Eco Ridge has potential to become a profitable producer of rare earth oxides ("REO") and uranium oxide ("U3O8").

The Project is located in Elliot Lake, Ontario, the only Canadian mining camp to ever achieve commercial REO production and an historically important source of "Heavy" REO in North America.  Recent extraordinary REO market developments, sparked by China's reduction of export quotas, have resulted in sharply higher prices, inciting a rush to find and bring to production new sources outside of China. With well-understood geology, excellent regional infrastructure, and strong local support, Eco Ridge is an ideal location for a safe, secure, and reliable long-term supply of REO and U3O8. Pele is focused on transitioning Eco Ridge into the feasibility and licensing stages as it advances the Project toward development and production.

Highlights of the PEA include (all financial terms in US$):

  • 9,400-tonne per day operation with life-of-mine production of 10.7-million pounds of Total REO and 24.9-million pounds of U3O8 over a 14-year mine life.
  • Cumulative operating cash flow of US$1.72-billion; Cumulative pre-tax cash flow of US$1.31-billion.
  • Positive NPV of $662-million (at a 7.5% discount rate); IRR of 47-percent.
  • Operating cash cost of $16 per pound U3O8, net of REO credits.
  • Start-up capital cost of $212-million; Sustaining capital cost of $195-million.
  • Life-of-mine production includes 430,000 pounds of dysprosium oxide (Dy2O3), 1.28-million pounds of neodymium oxide (Nd2O3), 2.08-million pounds of yttrium oxide (Y2O3), and 67,000 pounds of scandium oxide (Sc2O3).
  • Two-thirds of REO revenue is from Heavy REO (including yttrium and scandium oxides) many of which are forecast to be in particularly short supply in the years ahead while demand continues to rise sharply.
  • Opportunities for improvement of project economics include improved REO and U3O8 recoveries, and increased resources and production rate.

Pele President and CEO Al Shefsky, stated:  "We are extremely pleased with this PEA of our Eco Ridge Mine Project.  The PEA confirms our long-standing belief that Eco Ridge can be an important future source of rare earths and uranium, perhaps most critically as a secure and reliable long-term source of Heavy REO outside of China.  Our project economics are robust and compelling and we are already planning next steps to rapidly advance towards development and production. The Eco Ridge PEA forecasts pre-tax cash-flow exceeding $7.00 per fully diluted Pele share.  We do not believe that our stock price currently reflects the value of this important asset."

The 14-year production plan calls for a 9,400-tonne per day operation with average annual production of 708,000 pounds of Total REO and 2.07-million pounds of U3O8.   Underground development has been designed to be developed within the mineralized beds. This development muck, plus approximately 40-percent of the material broken in stopes will be brought to surface and processed on the Heap Leach Facility ("HLF").  The remaining material will be bioleached underground with leach solutions circulated in closed systems within each stope. Leach solutions from both surface and underground will go through a solvent extraction plant designed to recover U3O8. The effluent from the U3O8 recovery plant will go through a secondary solvent extraction plant to recover the REO.  The PEA is based on mining and processing plans designed by engineers who have direct experience with commercial production in the Elliot Lake camp.  The mining and processing methods utilized in the PEA have been successfully used in past commercial production at other mines in the area.

Key operational and economic data are summarized in Tables 1 & 2 below.

Table 1: Key Operational Data

Forecast Mine Life:   14 years
Total Tonnage Mined1:   37.0 million tonnes
U3O8 Produced2:   24.9 million pounds
Total REO Produced2:   10.7 million pounds

Notes:

  1. The PEA is based on a Mineral Resource estimate that was publicly disclosed in Pele's press release dated February 24, 2011.  See Table 4 below.
  2. See Tables 3A & 3B for more details, including forecast production of each individual oxide.

Table 2: Base Case Economic Data (all financial terms in US$000)

Gross Revenue from U3O81 $   2,119,000  
Gross Revenue from REO1 $    1,470,000  
Total Gross Revenue:  $    3,589,000  
       
Total Realized Revenue2 $    3,428,000  
Realized Revenue per Tonne:  93  
       
Total Operating Costs3 $    1,707,000  
Operating Cost per Tonne:  46  
       
Operating Cash Flow:  1,721,000  
       
Start-Up Capital Cost4 212,000  
Sustaining Capital Cost:  195,000  
Total Capital Cost:  407,000  
       
Pre-Tax Cash Flow:  1,314,000  
Pre-Tax IRR:     46.8%  
       
Net Present Value:  826,000  (5.0% discount rate)
  662,000  (7.5% discount rate)
  533,000  (10.0% discount rate)

Notes:

  1. See Tables 3A & 3B for more details.
  2. Deductions from Gross Revenue were applied to account for royalty payments as well as for an assessment of $30 per kg of oxide in concentrate to account for offsite separation and upgrading costs to produce high purity saleable REOs.
  3. Operating costs include mining, processing and G&A costs.
  4. Pre-production capital cost estimates includes a 25-percent contingency.
  5. The PEA assumes a C$:US$ exchange rate of 1.00:1.00.

Note: The PEA is preliminary in nature. It includes inferred mineral resources which are considered too speculative geologically to have the economic considerations applied to them that would enable them to be categorized as mineral reserves and there is no certainty that the preliminary economic assessment will be realized.

Mr. Shefsky continued, "Light REO at Eco Ridge occur primarily in the mineral monazite and would likely require a different processing circuit to achieve significantly better recoveries than the range reported today. Economic trade off studies will be undertaken to determine if this approach is advisable. However, several of the Heavy REO at Eco Ridge occur within uranium minerals together with U3O8.  Based on metallurgical and mineralogical studies to date, we believe there are excellent prospects for improving Heavy REO recoveries from the 34-percent average we are reporting today.  Increased recoveries of Heavy REO (and U3O8) present an important opportunity to enhance the economics at Eco Ridge."

Estimated mineral recoveries used in the PEA are based on historic operations in Elliot Lake for underground recovery of U3O8 and on extrapolations of time recovery curves from preliminary metallurgical testing at SGS Canada Ltd. for REO.  Assumed recoveries of individual oxides, along with forecast production and revenue contributions from each individual oxide are listed in Tables 3A & 3B below.

Table 3A: Uranium Recovery & Revenue

Uranium Oxide Average Grade Estimated
Recovery
Recovered
Oxide (000 lb)
Base Case
Price
(US$/lb)
Revenue
(US$000)
U3O8 0.044 % 70 % 24,931 85 2,119,147

Table 3B: Rare Earths Recovery & Revenue

Individual REO Average
Grade (g/t)
Estimated
Recovery
Recovered
Oxides (000 kg)
Base Case
Price
(US$/kg)
Revenue
(US$000)
CeO2 643.3 7 % 1,547 43 66,954
La2O3 338.1 7 % 813 45 36,566
Nd2O3 196.6 8 % 582 571 332,135
Pr6O11 60.1 8 % 178 142 25,167
Sm2O3 33.2 14 % 166 211 35,002
Eu2O3 1.9 15 % 10 2,445 25,163
Gd2O3 23.2 19 % 158 292 46,294
Sc2O3 5.1 16 % 30 5,308 160,942
Y2O3 64.4 40 % 942 209 196,777
Yb2O3 4.5 41 % 67 126 8,441
Dy2O3 14.1 38 % 195 1,744 340,111
Er2O3 5.9 41 % 88 492 43,479
Ho2O3 2.6 38 % 36 381 13,797
Lu2O3 0.7 39 % 10 1,151 11,184
Tb4O7 3.1 28 % 32 2,651 85,478
Tm2O3 0.9 41 % 13 3,182 42,842
           
Total Light REO1 1,271.3 7 % 3,286   495,824
Total Heavy REO2 126.4 34 % 1,583   974,508
           
Total REO 1,397.7   4,869   1,470,332

Notes:

  1. Light REO includes La2O3, CeO2, Pr6O11, Nd2O3, and Sm2O3.
  2. Heavy REO includes Eu2O3, Gd2O3, Tb4O7, Dy2O3, Ho2O3, Er2O3, Tm2O3, Yb2O3, and Lu2O3. Y2O3 and Sc2O3 are also included in Heavy REO.

The "Base Case" U3O8 price of $85 per pound is based on forecast price expectations by a group of independent analysts.  This compares to a current long-term contract price of $68 per pound.

Base Case REO price calculations began with a 6-month trailing average of daily prices from January 1, 2011 to June 30, 2011 as published by Asian Metal, a market service whose price assessments serve as the benchmark for contracts signed by major industry participants worldwide. The trailing average was based on daily FOB China prices as available. Otherwise, domestic China prices were used with an escalation factor of 25-percent to account for duties and taxes (scandium is the only significant contributor to which this escalation applies).

The 6-month trailing average price of each individual REO (except thulium oxide) was then adjusted by RPA according to a factor (the "Adjustment Factor") provided in a June 7, 2011 report by Asian Metal (the "REO Price Forecast") prepared for Pele to be used in the PEA. The Adjustment Factor is based on the percentage change between the REO prices prevailing on June 7, 2011 and Asian Metal's forecasted REO prices for 2015 and was used by RPA to decrease or increase the 6-month trailing average prices to determine Base Case prices for REO in the PEA. RPA chose to reduce the 6-month trailing average price for thulium oxide from $22,000 per kilogram to $2,000 per kilogram, because it is traded in a very low volume market, before applying the Adjustment Factor to arrive at the Base Case price of $3,182 per kilogram.

If the Asian Metal REO Price Forecast figures are applied to the PEA model, it results in considerably stronger financial projections for the Project, including a NPV (at a 7.5-percent discount rate) of $1.48-billion and an IRR of 92-percent.

The Project has no known environmental liabilities and enjoys strong local support.  The Province of Ontario has recently granted two renewable 21-year mining leases at Eco Ridge (the "Mining Leases"), giving Pele the exclusive right to mine in the leased areas. The Mining Leases also include surface rights except for an area covered by surface patents owned by the City of Elliot Lake (the "City"). The City has also granted Pele a renewable 21-year lease with a conditional option to purchase the City's surface patents (the "City Lease"). Both the Mining Leases and the City Lease allow for siting of project infrastructure like mine portals and processing facilities.

Pele places great value on community relations and has maintained friendly and productive dialogue with local First Nations and the City of Elliot Lake since the inception of the Eco Ridge Mine project. The Company's approach to sustainable development and operations at Eco Ridge is set out in a Project Description, which was filed with the Canadian Federal Government's Office of Major Projects Management and the Canadian Nuclear Safety Commission in September 2008.  Pele is committed to sustainable development and seeks to provide long-term benefits to local communities.

Pele intends to pursue the following potential opportunities to improve project economics at Eco Ridge:

  • Increased recovery of REO and U3O8 brought to surface.  Process efficiencies may be improved by crushing ore delivered to the HLF.
  • Increased recovery of REO and U3O8 from underground by optimizing leaching conditions and the time recovery curve. Metallurgical test work is underway at SGS Canada.
  • Adding to the mine life and/or production rate by drilling off additional resources. A drill program is currently underway with objectives to improve the classification and expand the mineral resource as described below.
  • Participation in higher margin downstream REO value chain through strategic alliances and/or vertical integration.

NI 43-101 Compliant Resource

Classification Tonnes of Resource Total REO U3O8
Pounds (%) Pounds (%)
Indicated 14,312,000 51,859,000 0.164 15,182,000 0.048
Inferred 33,121,000 96,352,000 0.132 31,444,000 0.043

Notes:

  1. CIM definitions were followed for Mineral Resources.
  2. The Qualified Person for this Mineral Resource estimate is Tudorel Ciuculescu, P.Geo.
  3.  Mineral Resources are estimated at a cut-off grade of 0.028% U3O8.
  4. Mineral Resources are estimated using an average long-term uranium price of US$60 per lb, and a C$:US$ exchange rate of 0.95:1.00.
  5. Total Rare Earth Oxides include La2O3, CeO2, Pr6O11, Nd2O3, Sm2O3, Eu2O3, Gd2O3, Tb4O7, Dy2O3, Ho2O3, Er2O3, Tm2O3, Yb2O3, and Lu2O3. Y2O3  and Sc2O3  are also included in TREO.
  6. The resource wireframe at Eco Ridge contains both Indicated and Inferred U3O8 and TREO resources within the near surface portion of the Main Conglomerate Bed.
  7. The U3O8 resource estimate is based on a total of 237 drill holes. These comprise 152 recent drill holes drilled by Pele Mountain between 2006 and 2009, and 85 historic drill holes drilled between 1954 and 1974.
  8. The REO resource estimate is based on a total of 123 recent drill holes.
  9. Mineral resources that are not mineral reserves do not have demonstrated economic viability.

Pele recently announced the commencement of a 7,000-metre drill program.  As the mineralized reefs of the Elliot Lake mining camp are well known for their consistency and size, the mineral resources at Eco Ridge have excellent potential for improvement of classification and expansion. The program will include in-fill drilling within the existing Resource Wireframe with an objective of upgrading up to 5-million tonnes of Inferred Resources into the Indicated category. Indicated Resources may be converted to Mineral Reserves during the feasibility process, while Inferred Resources may not. The program will also include step-out drilling to the north of the Resource Wireframe with an objective of bringing up to 10-million additional tonnes of the mineralized reef into the Inferred Resource category.

The technical and economic information relating to the PEA in this press release has been reviewed and approved by Jason Cox, P.Eng., Director of Mine Engineering for RPA, an independent qualified person under NI 43-101. The PEA technical report will be filed on SEDAR in due course.

About Pele
Pele Mountain Resources is focused on the sustainable development of its 100-percent owned Eco Ridge Mine Rare Earths and Uranium Project.  Eco Ridge is one of very few North American Rare Earths deposits that has completed a NI 43-101 Preliminary Economic Assessment with robust economics and is located in Elliot Lake, the only Canadian mining camp to have ever achieved commercial REO production.  With well-understood geology, excellent regional infrastructure, and strong local support, Eco Ridge is an ideal location for a safe, secure, and reliable long-term supply of REO and U3O8.  Pele also holds interests in a portfolio of Northern Ontario gold properties at Highland and Ardeen.  Pele's shares are listed on the TSX Venture Exchange under the symbol "GEM" and on the OTCQX under the symbol "GOLDF".

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.  Some of the statements contained in this release are forward-looking statements, such as estimates and statements that describe Pele's future plans, objectives or goals, including words to the effect that Pele or management expects a stated condition or result to occur. Since forward-looking statements address future events and conditions, by their very nature, they involve inherent risks and uncertainties. Actual results in each case could differ materially from those currently anticipated in such statements. The economic viability of the 43-101 mineral resource at Pele's Elliot Lake Project has not yet been demonstrated by a preliminary feasibility study. 

For further information:

Al Shefsky, President, at (800) 315-7353, or visit the Pele website at www.pelemountain.com.


 
Sent to:.com
If you prefer not to receive
future e-mails of this type,
click here
Sent By:
Pele Mountain Resources
2200 Yonge Street
Suite 905
Toronto Ontario M4S 2C6
 
To view as a web pageTo view as a web page.
Data and Statistics for these countries : Canada | China | All
Gold and Silver Prices for these countries : Canada | China | All

Pele Mountain Resources Inc

DEVELOPMENT STAGE
CODE : GEM.V
ISIN : CA7059071034
Follow and Invest
Add to watch list Add to your portfolio Add or edit a note
Add Alert Add to Watchlists Add to Portfolio Add Note
ProfileMarket
Indicators
VALUE :
Projects & res.
Press
releases
Annual
report
RISK :
Asset profile
Contact Cpy

Pele Mountain Res. is a and uranium exploration company based in Canada.

Pele Mountain Res. develops rare earth in Canada, and holds various exploration projects in Canada.

Its main asset in development is ECO RIDGE in Canada and its main exploration properties are HIGHLAND (EAST / WEST), ARDEEN, ALLIANCE, SUDBURY and FESTIVAL in Canada.

Pele Mountain Res. is listed in Canada and in United States of America. Its market capitalisation is CA$ 5.3 millions as of today (US$ 3.8 millions, € 3.6 millions).

Its stock quote reached its highest recent level on December 31, 2007 at CA$ 1.62, and its lowest recent point on June 02, 2017 at CA$ 0.01.

Pele Mountain Res. has 210 000 000 shares outstanding.

Your feedback is appreciated, please leave a comment or rate this article.
Rate : Average note :0 (0 vote) View Top rated
 
In the News and Medias of Pele Mountain Resources Inc
10/24/2007 Advances Baseline Environmental Studies at Elliot Lake Uran...
Financings of Pele Mountain Resources Inc
9/23/2016Pele Mountain Enters Into Funding Agreement
4/13/2015Announces Closing of Private Placement
10/3/2013Announces Closing of Private Placement Offering
7/26/2013Announces Closing of Private Placement Offering
7/4/2013Announces Closing of Second Tranche of a Private Placement O...
Nominations of Pele Mountain Resources Inc
2/11/2014Nominates Janis Peleshok to its Board of Directors
11/27/2013John Wilkinson Former Ontario Cabinet Minister Joins Pele Mo...
11/7/2007 Appoints Fergus Kerr Vice-President of Uranium Operations t...
5/9/2007Appoints James Andersen as Chief Financial Officer and Renew...
Project news of Pele Mountain Resources Inc
10/9/2013Interview with Roger Payne P. Eng. Executive Vice President ...
9/12/2013(Eco Ridge)Reviews Economics at Its Eco Ridge Mine Rare Earth and Urani...
6/10/2013(Eco Ridge)Announces Major Increase in Uranium and Rare Earth Resources...
6/10/2013(Eco Ridge)Announces Major Increase in Uranium and Rare Earth Resources...
6/10/2013(Eco Ridge)Announces Major Increase in Uranium and Rare Earth Resources...
6/10/2013(Eco Ridge)Announces Major Increase in Uranium and Rare Earth Resources...
6/10/2013(Eco Ridge)Announces Major Increase in Uranium and Rare Earth Resources...
5/28/2013(Festival)Announces Reactivation of Festival Project Joint Venture Nea...
4/3/2013(Eco Ridge)to Update Eco Ridge Resource Estimate
1/29/2013Hits Higher Grade Uranium & Rare Earths at Elliot Lake
1/17/2013(Eco Ridge)Drilling Expands Eco Ridge Deposit
10/16/2012(Eco Ridge)Begins 6,500-Metre Drill Program at Its Eco Ridge Mine Rare ...
9/27/2012Samples High Grade Rare Earths at Mountain Pass
9/26/2012Closes Acquisition of Mining Claims 1800 Metres from Molycor...
5/15/2012(Eco Ridge)Closes Highland Project Sale Agreement; Will Focus on Eco Ri...
4/17/2012(Eco Ridge)Enters Agreement to Sell Highland Gold Projects; Will Focus ...
4/16/2012(Eco Ridge)Announces Robust Updated PEA for Eco Ridge Mine Rare Earths ...
3/6/2012Enters Agreement to Acquire Rare Earth Mining Claims Surroun...
10/13/2011(Eco Ridge)Announces Discovery of Continuous Rare Earths Mineralization...
9/7/2011(Eco Ridge)Files Preliminary Economic Assessment for Eco Ridge, Providi...
7/5/2011(Eco Ridge)Announces Preliminary Economic Assessment for Eco Ridge Mine...
5/26/2011(Eco Ridge)Launches 7,000 Metre Drill Program at Its Eco Ridge Mine Rar...
5/17/2011(Eco Ridge)Receives Mining Leases at Its Eco Ridge Mine Rare Earths and...
3/7/2011(Ardeen)Provides Gold Projects Update
2/24/2011(Eco Ridge)Announces Total Rare Earth Oxide Resources of 52-Million Pou...
1/24/2011(Eco Ridge)Announces Major Increase in Indicated Resources at its Eco R...
6/25/2010(Highland (east / West))Initiates Permitting Process to Mine Gold Bulk Sample
3/4/2010(Highland (east / West))Hits High Grade Gold at Highland’s A-Zone
1/18/2010(Highland (east / West))Begins Drilling at East Highland Gold Project
12/23/2009(Highland (east / West))Samples 14.76 g/t Gold Over 3.6 Metres at Its East Highland ...
12/11/2009(Highland (east / West))Samples 50 g/t Gold, 161 g/t Silver 4.3% Zinc, and 1.2% Lead...
11/10/2009(Highland (east / West))Discovers New Mineralized Zones, Expands Others, at East Hig...
9/17/2009Finds More High-Grade Gold at East Highland
9/1/2009(Ardeen)Coventry Resources Commences Diamond Drilling at Pele Mounta...
8/11/2009(Highland (east / West))High-Grade Gold Discovery at Its Highland Project
7/27/2009(Eco Ridge)Signs Agreement With the City of Elliot Lake for Surface Rig...
1/9/2009(Eco Ridge)Advances Eco Ridge Mine Project - Extensive Drill Program Re...
1/8/2009(Sudbury)Wallbridge Mining Company to Continue Exploration at Pele Mo...
9/9/2008(Eco Ridge)Initiates Permitting Process at Eco Ridge
8/26/2008(Eco Ridge)assembles team of uranium industry leaders to develop Eco Ri...
5/12/2008(Timmins - Whitney Township)Enters Into Option Agreement to Sell Its Timmins Nickel Proj...
5/2/2008(Eco Ridge)Launch Pre-Feasibility Study for Elliot Lake Uranium Mine Pr...
3/6/2008(Eco Ridge) Reports Additional Positive Drill Results from Its Elliot L...
2/13/2008(Eco Ridge)Identifies High Priority Geophysical Targets at its Elliot L...
1/25/2008(Eco Ridge)New Drill Results Expand Higher-Grade Zone at Pele Mountain'...
1/17/2008(Eco Ridge)Expands Exploration for Higher Grade Remobilized Uranium at ...
11/28/2007(Eco Ridge)Targets Remobilized Uranium at Elliot Lake
10/12/2007(Eco Ridge)Publishes Positive Scoping Study for Uranium Mine Project at...
10/4/2007Achieves Major Milestone with Positive Scoping Study for Ura...
10/2/2007Announces Scoping Study for Its Elliot Lake Uranium Project ...
9/19/2007(Eco Ridge)Achieves Positive Results from 5,600-Metre Drill Program at ...
7/9/2007(Eco Ridge)Advances Mine Planning and Scoping Studies on 33-Million Pou...
5/30/2007(Eco Ridge)Expands Drilling at Elliot Lake Uranium Project
5/7/2007(Eco Ridge)Intersects High-Grade Uranium In Basal Conglomerate Bed at E...
5/2/2007(Eco Ridge)Expands Elliot Lake Uranium Project
5/1/2007(Eco Ridge)Drilling Confirms Near-Surface, Higher-Grade Uranium at Pele...
1/26/2006hits more high grade gold at Talisker
Corporate news of Pele Mountain Resources Inc
7/5/2016Pele Mountain to Sell Its Ardeen Gold Project
5/4/2016Pele Mountain Provides Update on Development Plans and Progr...
1/15/2016Pele Mountain Resources Appoints Wayne Richardson as Chairma...
10/7/2015Pele Mountain Announces Option Grants
10/1/2015Pele Mountain Provides an Update on its Eco Ridge Monazite P...
7/28/2015Pele Mountain Advances Cogent Solution to Rare Earth Industr...
4/13/2015Pele Mountain Announces Closing of Private Placement
3/30/2015Pele Mountain Executes MOU with Major Chinese Rare Earth Pla...
3/30/2015IIROC Trading Resumption - GEM
3/30/2015Executes MOU with Major Chinese Rare Earth Player to Pursue ...
3/30/2015IIROC Trading Halt - GEM
3/5/2015Pele Mountain Shareholders Approve All Matters Presented at ...
3/5/2015Shareholders Approve All Matters Presented at the Annual and...
2/17/2015Pele Mountain Advances Monazite Recycling Strategy to Kick-S...
2/12/2015Pele Mountain Announces Option Grants
12/24/2014Pele Mountain Announces Closing of Private Placement
12/2/2014The Council of the City of Elliot Lake Supports Pele Mountai...
11/7/2014Pele Mountain Announces Proposed Shares for Debt Settlement
10/7/2014Pele Mountain Expands its Business Model to Include Recyclin...
9/25/2014Pele Mountain Appoints Martin S. Cooper As Vice President of...
9/11/2014Pele Mountain Acquires Key Mining Lease in Elliot Lake
9/2/2014Pele Mountain Announces Collaboration with Canmet to Advance...
7/8/2014Pele Mountain Participates in Regional Roundtable Discussion...
6/25/2014Parliamentary Committee on Natural Resources Publishes "The ...
6/24/2014Pele Mountain Announces Closing of Private Placement
5/9/2014Pele Mountain Announces Closing of Private Placement Offerin...
5/2/2014Pele Mountain Announces Closing of First Tranche of Private ...
5/1/2014Pele Mountain Announces Closing of First Tranche of Private ...
6/5/2013Shareholders Approve All Matters Presented at the Annual and...
1/29/2013Intersects Higher-Grade Uranium & Rare Earths; Discovers Wid...
1/17/2013CEO Interviewed by Jeb Handwerger
10/24/2012(Eco Ridge)Achieves Processing Milestone: Mixed Rare Earth Concentrate ...
7/4/2012(Eco Ridge)Files Updated Preliminary Economic Assessment for Eco Ridge ...
1/31/2012Updated PEA on Schedule for Q1 2012
9/12/2011(Eco Ridge)Drilling Expands Eco Ridge Deposit Northward, Demonstrates S...
7/27/2011Roger Payne Named Executive Vice-President at Pele Mountain
7/21/2011(Eco Ridge)to Separate Gold Assets from Eco Ridge
5/3/2011Commences Trading in the United States on OTCQX Internationa...
8/5/2010Dr. William Bird Joins Rare Metals Advisory Board
5/17/2010Begins Drilling Ni-Cu-PGE Targets at Pigeon River
4/29/2010to Drill Ni-Cu-PGE Targets at Pigeon River
5/3/2010Coventry Resources Reports Winter Drill Results from Pele Mo...
3/5/2010Completes VTEM Survey at Pigeon River, Identifies Several Pr...
1/7/2010Acquires Property in Thunder Bay Area with High Potential fo...
10/7/2009Confirms Significant Rare Earth Mineralization at Its Eco Ri...
8/5/2009Initiates Long-Term Research Study to Minimize Environmental...
2/5/2009Letter to Shareholders
2/5/2008Completes Acquisition of the Westward Extension of the Histo...
10/29/2007 Resumes Drilling at Its Elliot Lake Uranium Mine Project
7/26/2007Retains O&M Partners for Investor Relations
5/3/2007Announces Plan to Optimize Corporate Structure
4/27/2007Featured in Northern Miner Article
4/17/2007Expands Elliot Lake Uranium Project
3/29/2007Advances Mine Planning Studies on 33-Million Pound Uranium O...
Comments closed
 
Latest comment posted for this article
Be the first to comment
Add your comment
TSX-V (GEM.V)Other OTC (PMNHF)
0.025-16.67%0.040+0.00%
TSX-V
CA$ 0.025
04/25 10:30 -0.010
-16.67%
Prev close Open
0.030 0.025
Low High
0.025 0.025
Year l/h YTD var.
0.025 -  0.060 -58.33%
52 week l/h 52 week var.
0.025 -  0.080 -64.29%
Volume 1 month var.
158,750 -16.67%
24hGold TrendPower© : 22
Produces
Develops Rare earth
Explores for Diamonds - Gold - Platinum - Silver
 
 
 
Analyse
Interactive chart Add to compare
Interactive
chart
Print Compare Export
Last updated on : 11/13/2010
You must be logged in to use the porfolio and watchlists (free)
Top Newsreleases
MOST READ
Annual variation
DateVariationHighLow
2024-54.55%
202337.50%0.100.04
2022-70.37%0.180.04
202117.39%0.720.09
 
5 years chart
 
3 months chart
 
3 months volume chart
 
 
Mining Company News
Plymouth Minerals LTDPLH.AX
Plymouth Minerals Intersects Further High Grade Potash in Drilling at Banio Potash Project - Plannin
AU$ 0.12-8.00%Trend Power :
Santos(Ngas-Oil)STO.AX
announces expected non-cash impairment
AU$ 7.70-0.65%Trend Power :
Oceana Gold(Au)OGC.AX
RELEASES NEW TECHNICAL REPORT FOR THE HAILE GOLD MINE
AU$ 2.20+0.00%Trend Power :
Western Areas NL(Au-Ni-Pl)WSA.AX
Advance Notice - Full Year Results Conference Call
AU$ 3.86+0.00%Trend Power :
Canadian Zinc(Ag-Au-Cu)CZN.TO
Reports Financial Results for Q2 and Provides Project Updates
CA$ 0.12+4.55%Trend Power :
Stornoway Diamond(Gems-Au-Ur)SWY.TO
Second Quarter Results
CA$ 0.02+100.00%Trend Power :
McEwen Mining(Cu-Le-Zn)MUX
TO ACQUIRE BLACK FOX FROM PRIMERO=C2=A0
US$ 11.94+9.34%Trend Power :
Rentech(Coal-Ngas)RTK
Rentech Announces Results for Second Quarter 2017
US$ 0.20-12.28%Trend Power :
KEFIKEFI.L
Reduced Funding Requirement
GBX 0.54-2.55%Trend Power :
Lupaka Gold Corp.LPK.V
Lupaka Gold Receives First Tranche Under Amended Invicta Financing Agreement
CA$ 0.06+0.00%Trend Power :
Imperial(Ag-Au-Cu)III.TO
Closes Bridge Loan Financing
CA$ 2.69+13.03%Trend Power :
Guyana Goldfields(Cu-Zn-Pa)GUY.TO
Reports Second Quarter 2017 Results and Maintains Production Guidance
CA$ 1.84+0.00%Trend Power :
Lundin Mining(Ag-Au-Cu)LUN.TO
d Share Capital and Voting Rights for Lundin Mining
CA$ 15.60+1.83%Trend Power :
Canarc Res.(Au)CCM.TO
Canarc Reports High Grade Gold in Surface Rock Samples at Fondaway Canyon, Nevada
CA$ 0.24+0.00%Trend Power :
Havilah(Cu-Le-Zn)HAV.AX
Q A April 2017 Quarterly Report
AU$ 0.20+2.63%Trend Power :
Uranium Res.(Ur)URRE
Commences Lithium Exploration Drilling at the Columbus Basin Project
US$ 6.80-2.86%Trend Power :
Platinum Group Metals(Au-Cu-Gems)PTM.TO
Platinum Group Metals Ltd. Operational and Strategic Process ...
CA$ 1.87+5.65%Trend Power :
Devon Energy(Ngas-Oil)DVN
Announces $340 Million of Non-Core Asset Sales
US$ 52.61+0.98%Trend Power :
Precision Drilling(Oil)PD-UN.TO
Announces 2017Second Quarter Financial Results
CA$ 8.66-0.35%Trend Power :
Terramin(Ag-Au-Cu)TZN.AX
2nd Quarter Report
AU$ 0.04+5.56%Trend Power :