MINERA ANDES ANNOUNCES PROGRESS
AND PLANS AT SAN JOSE MINE

  
TSX: MAI   
NASD-OTCBB: MNEAF    
   

SPOKANE, WA – August 15, 2007 – Minera Andes (TSX: MAI and US OTC: MNEAF) reports that the board of Minera Santa Cruz ("MSC"), a joint venture company owned 49% by Minera Andes and 51% by a wholly-owned subsidiary of Hochschild Mining plc ("Hochschild") (London Stock Exchange, LSE: HOC), the project operator, has made the formal decision to double production capacity from 750 tonnes per day (tpd) to 1,500 tpd at the San José mine in southern Argentina. The cost of the expansion will be financed primarily from cash flow from the existing mine and unsecured local bank financing.

The San José mine celebrated its inaugural ceremony in June 2007 and the first production of gold and silver came from the mine in July 2007. During construction approximately 1,100 people were working at the site and now that construction is complete the mine is staffed by approximately 450 personnel.  We anticipate full commercial production to be achievable within six to twelve months.

Planning ahead for expansion while constructing the current mine, mill capacity was designed to be scaleable from 750 tpd to 1,500 tpd. In anticipation of possible production growth, some equipment with expanded capacity has already been installed. Surface facilities have also been expanded and upgraded. With the decision to expand the operations it will be necessary to add more equipment and infrastructure to handle increased production. An independent economic analysis on the expansion plans will be provided to the partners by MSC.

An exploration drilling program is underway and is designed to test new targets and to develop new reserves and resources on the property to increase mine life and facilitate the expansion of production at the San José project.  Over eight thousand meters of drilling have been completed on this program to date and assays are pending.  In addition, a new NI 43-101 technical report that adds the Kospi vein to the San José resources is to be completed shortly.  

Construction completion of the 750 tpd operation is currently estimated to cost $94.1 million, plus value added tax (IVA).  Pre-completion mine expansion costs and costs related to the change in scope to the original mine plan incurred to date are approximately $11 million, plus IVA.  At the end of the second quarter of 2006, when the decision to place the mine into production, Minera Andes reported the mine cost was estimated at $78.3 million, plus IVA. The amounts paid for IVA tax are refundable to MSC ratably based on production.

The 20% cost increase for completing construction of the mine arises from increases due to inflation of equipment and materials costs, construction delays, and increased contractor costs. Mine expansion costs and costs related to the change in scope to the original mine plan of approximately $11 million include the expansion of facilities, purchase of over-dimensioned equipment, mining engineering studies for the Kospi vein, the commencement of construction of the ramp for the Kospi vein, and additional underground workings. Also the processing operation at the mine is using an intensive leaching reactor (ILR), in lieu of the Merryl-Crowe plant described in the 2005 feasibility study.
 
The current project loan facility for $61 million with Hochschild was expanded to $65 million at the end of the second quarter of 2007 to cover additional mine completion costs and we are currently finalizing the terms and conditions of the formal loan documentation. The loan will be repaid from MSC cash flow and there is no hedging of the project’s gold and silver production (which had been required under the previously arranged bank financing facility). To accelerate the mine expansion and provide necessary funds from mine cash flow, Hochschild has agreed to extend the payback of the project loan facility until after completion of the expansion (except for expected repayment of $4 million from the proceeds of local bank loans to MSC in October, 2007). MSC estimates completion of the mine expansion is expected to occur in late 2008. 

Minera Andes is currently in discussions with Hochschild as to the timing and amounts of the additional financing to be put into MSC for the cost overruns and sustaining capital while the mine ramps up production.  Separately, Minera Andes will be paying a cash call of $4.9 million during September from its own resources.

Minera Andes is a gold, silver and copper exploration company working in Argentina. The Corporation holds about 410,000 acres of mineral exploration land in Argentina including the co-owned San José silver/gold mine that has started initial production.  Minera Andes is also exploring the Los Azules copper project in San Juan province, where an exploration program is underway to define a resource. Other exploration properties, primarily silver and gold, are being evaluated in southern Argentina.  The Corporation presently has 166,700,767 shares issued and outstanding.

Allen V. Ambrose, Minera Andes' President, who is an appropriately qualified person as defined by National Instrument 43-101, has reviewed the information used in this news release.

This news release is submitted by Allen V. Ambrose, President and Director of Minera Andes Inc.



For further information, please contact: Art Johnson at the Spokane office, or Krister A. Kottmeier, investor relations – Canada, at the Vancouver office. Visit our Web site: www.minandes.com.

Spokane Office
111 East Magnesium Rd.,
Spokane, WA 99208 USA
Phone: (509) 921-7322
E-mail: mineraandes@minandes.com

Vancouver Office
Suite 911 - 470 Granville St,
Vancouver, BC. V6C 1V5
Phone: (604) 689-7017 / 877-689-7018
E-mail: ircanada@minandes.com

Caution Concerning Forward-Looking Statements:
This press release contains certain "forward-looking statements", including, but not limited to, the statements regarding the Company's strategic plans, evolution of mineral resources and reserves, work programs, development plans and exploration budgets at the Company's San José Project. Investors should be aware that the introduction of new technology such as ILR can create added risk in achieving metallurgical performance. The forward-looking statements express, as at the date of this press release, the Company's plans, estimates, forecasts, projections, expectations or beliefs as to future events and results. Forward-looking statements involve a number of risks and uncertainties, and there can be no assurance that such statements will prove to be accurate. Therefore, actual results and future events could differ materially from those anticipated in such statements. In particular, there can be no assurance that commercial production at the San José mine will be achieved on a timely basis, or at all, that production capacity at the San José mine will be successfully increased, that resources and reserves at the San José mine will be increased or that Minera Andes will successfully raise the funds necessary to maintain its interest in the San José mine. Risks and uncertainties that could cause results or future events to differ materially from current expectations expressed or implied by the forward-looking statements include, but are not limited to, factors associated with fluctuations in the market price of precious metals, mining industry risks, risks associated with foreign operations, the state of the capital markets, environmental risks and hazards, uncertainty as to calculation of mineral reserves and other risks. Reference is made to the risk factors and uncertainties described in the Company's continuous disclosure record, a copy of which is available under the Company's profile at www.sedar.com. In addition, Minera Andes' joint venture partner, a subsidiary of Hochschild Mining plc, and its affiliates do not accept responsibility for the use of project data or the adequacy or accuracy of this release.


THE TSX VENTURE EXCHANGE HAS NOT REVIEWED AND DOES NOT ACCEPT RESPONSIBILITY FOR THE ADEQUACY OR ACCURACY OF THIS RELEASE.

 

Forward email

This email was sent to .com, by ircanada@minandes.com
Update Profile/Email Address | Instant removal with ™ | Privacy Policy.

Kris Kottmeier - Minera Andes Inc. | 911 - 470 Granville St. | Vancouver | British Columbia | V6C 1V5 | Canada

Data and Statistics for these countries : Argentina | Canada | All
Gold and Silver Prices for these countries : Argentina | Canada | All

Minera Andes Inc

CODE : MAI.TO
ISIN : CA6029101012
CUSIP : 602910101
Follow and Invest
Add to watch list Add to your portfolio Add or edit a note
Add Alert Add to Watchlists Add to Portfolio Add Note
ProfileMarket
Indicators
VALUE :
Projects & res.
Press
releases
Annual
report
RISK :
Asset profile
Contact Cpy

Minera Andes is a silver producing company based in Canada.

Minera Andes is listed in Canada and in United States of America. Its market capitalisation is CA$ 730.0 millions as of today (US$ 728.7 millions, € 555.9 millions).

Its stock quote reached its lowest recent point on February 06, 2009 at CA$ 0.32, and its highest recent level on April 15, 2011 at CA$ 3.39.

Minera Andes has 282 959 000 shares outstanding.

Your feedback is appreciated, please leave a comment or rate this article.
Rate : Average note :0 (0 vote) View Top rated
 
In the News and Medias of Minera Andes Inc
3/23/2006New Analysis
10/16/2006Learning from the Iconoclast
Annual reports of Minera Andes Inc
2008 Annual report
2006 Annual Report
Financings of Minera Andes Inc
2/26/2009COMPLETES SECOND TRANCHE OF PRIVATE PLACEMENT WITH ROB McEWE...
2/17/2009revised C$40.0 million private placement with Robert R. McEw...
Financials of Minera Andes Inc
8/11/2011Announces Second Quarter 2011 Financial Results
6/6/2011Announces First Quarter 2011 Financial Results and Restated ...
3/30/2011Announces 2010 Full Year Financial Results and Record Earnin...
7/17/2009(San Jose Argentina)second quarter 2009 San José Production
5/16/2009REPORTS FIRST QUARTER 2009 FINANCIAL RESULTS
1/23/2009(San Jose Argentina)ANNOUNCES FOURTH QUARTER GOLD/SILVER PRODUCTION INCREASES AT...
11/14/2008REPORTS THIRD QUARTER 2008 RESULTS
11/11/2008(San Jose Argentina)ANNOUNCES THIRD QUARTER GOLD/SILVER SALES AT THE SAN JOSE MI...
8/15/2008REPORTS NET INCOME FOR SECOND QUARTER OF $0.05 PER SHARE
7/30/2008ANNOUNCES SECOND QUARTER GOLD/SILVER SALES AT THE SAN JOSE M...
5/9/2008(San Jose Argentina)ANNOUNCES FIRST QUARTER 2008 PRODUCTION FOR SAN JOSE MINE TO...
Project news of Minera Andes Inc
12/7/2011(San Jose Argentina)Provides Update On Exploration Drilling at the San Jose Mine
8/30/2011(San Jose Argentina)Provides Update on Exploration Drilling at the San Jose Mine
6/27/2011(Los Azules Argentina)Reports Drill Results and Development Update for the Los Azu...
5/17/2011(Los Azules Argentina)on Litigation With TNR Gold Corp.
5/4/2011(San Jose Argentina)Announces Work Resumption at San Jose Mine
3/13/2011(San Jose Argentina)Announces Outstanding 2010 Exploration Drill Results at the ...
10/5/2009(San Jose Argentina) Production Has Resumed At TheSan Jos=E9 Mine
10/2/2009(Los Azules Argentina)Provides Confirmation of its 100% Earn-In on the Los Azules ...
6/6/2009(San Jose Argentina) Announces completion of NI 43-101 Technical report on the J...
6/6/2009(Los Azules Argentina) Announces delivery of Earn-in notice under option agreement...
1/16/2009(San Jose Argentina)ANNOUNCES INCREASE IN FORECAST PRODUCTION AT THE SAN JOSE GO...
1/10/2009(San Jose Argentina)Announces Remaining Results From 2008 San Jose Drilling
9/25/2008(Los Azules Argentina)ANNOUNCES EXCELLENT METALLURGICAL TESTING RESULTS FOR LOS AZ...
9/8/2008(Los Azules Argentina)announces a mineral resource estimate of 922 million tonnes ...
8/13/2008(San Jose Argentina)REPORTS SAN JOSE PRODUCTION CASH COSTS AT $322/oz GOLD AND $...
6/27/2008(Los Azules Argentina)Exploration Program Increases The Size Of The Los Azules Por...
4/16/2008(Los Azules Argentina)DRILLING CUTS 132 METERS (433FT) OF 1.11 PERCENT COPPER AT L...
3/28/2008(San Jose Argentina) PROVIDES SAN JOSE MINE UPDATE
3/12/2008(Los Azules Argentina)ANNOUNCES 113 METERS OF +1 PERCENT COPPER IN DRILLING AT LOS...
3/7/2008(San Jose Argentina)ANNOUNCES 1.69 OZ/TON GOLD AND 37 OZ/TON SILVER FROM SAN JOS...
12/11/2007(Los Azules Argentina) ANNOUNCES DRILLING COMMENCES AT LOS AZULES COPPER PROJECT
10/26/2007(San Jose Argentina) ENGAGES MACQUARIE BANK LIMITED FOR DEBT FINANCING FOR SAN J...
8/15/2007(San Jose Argentina)ANNOUNCES PROGRESS AND PLANS AT SAN JOSE MINE
5/31/2007(Los Azules Argentina)drills significant copper at Los Azules Project, Argentina
Corporate news of Minera Andes Inc
3/22/2012Files Annual 2011 Financial Statements and MD&A and Project ...
1/18/2012Announces Fourth Quarter and Full Year 2011 San Jose Mine Pr...
1/13/2012(Los Azules Argentina).: Response to TNR Gold Corp. News Release Regarding Los Azu...
12/21/2011Rob McEwen Letter to Shareholders of US Gold and Minera Ande...
10/3/2011(San Jose Argentina)Announces Full Repayment of Loans From San Jose Mine
9/22/2011US Gold and Minera Andes Enter Into Arrangement Agreement to...
7/20/2011Announces Second Quarter 2011 San Jose Mine Production
4/20/2011Announces First Quarter 2011 San Jose Mine Production
2/7/2011' Treasury Increases by $19 Million
1/24/2011Reminds Warrant Holders of Accelerated Expiry on January 31,...
7/3/2009'AGM Presentation On Video
2/23/2009Rob McEwen becomes Executive Chairman of Minera Andes - Two ...
2/6/2009Announces Results Of Preliminary Assessment At Los Azules Co...
10/1/2008Recent Media Coverage on Minera Andes Inc.
9/2/2008ANNOUNCES 2.05 OZ/TON GOLD AND 37 OZ/TON SILVER FROM ONGOING...
8/6/2008ADDS ROB MCEWEN AND OTHER MINING INDUSTRY EXECUTIVES TO ITS ...
7/30/2008Welcomes Lundin Mining Executive To Board
12/22/2007ANNOUNCES 1st CLOSING ON FINANCING
12/19/2007 ANNOUNCES PROPOSED FINANCING
11/27/2007 ANNOUNCES THE SAN JOSE MINE INCREASES SILVER AND GOLD MINE...
11/15/2007SIGNS DEFINITIVE AGREEMENT AT LOS AZULES COPPER PROJECT WITH...
11/9/2007 ANNOUNCES SAN JOSE UPDATE
10/12/2007SAN JOSE PROJECT DRILLING HITS 3.22 OUNCES PER TON GOLD AND ...
9/18/2007ANNOUNCES THE SAN JOSE MINE INCREASES SILVER AND GOLD RESOUR...
9/6/2007SAN JOSE PROJECT DRILLING HITS 1.86 OUNCES PER TON GOLD AND ...
Comments closed
 
Latest comment posted for this article
Be the first to comment
Add your comment
TORONTO (MAI.TO)OTC BB (MNEAF.OB)
2.58-2.64%2.54-3.05%
Last quotes and information before delisting
Prev close Open
2.65 2.71
Low High
2.48 2.73
Year l/h YTD var.
 -  -
52 week l/h 52 week var.
- -  2.58 -%
Volume 1 month var.
2,733,962 -%
Produces
Develops
Explores for
 
 
 
Analyse
Interactive chart Add to compare
Interactive
chart
Print Compare Export
Last updated on : 9/7/2010
You must be logged in to use the porfolio and watchlists (free)
Top Newsreleases
MOST READ
Annual variation
DateVariationHighLow
 
5 years chart
 
3 months chart
 
3 months volume chart
 
 
Mining Company News
Plymouth Minerals LTDPLH.AX
Plymouth Minerals Intersects Further High Grade Potash in Drilling at Banio Potash Project - Plannin
AU$ 0.12-8.00%Trend Power :
Santos(Ngas-Oil)STO.AX
announces expected non-cash impairment
AU$ 7.82+1.69%Trend Power :
Oceana Gold(Au)OGC.AX
RELEASES NEW TECHNICAL REPORT FOR THE HAILE GOLD MINE
AU$ 2.20+0.00%Trend Power :
Western Areas NL(Au-Ni-Pl)WSA.AX
Advance Notice - Full Year Results Conference Call
AU$ 3.86+0.00%Trend Power :
Canadian Zinc(Ag-Au-Cu)CZN.TO
Reports Financial Results for Q2 and Provides Project Updates
CA$ 0.12+4.55%Trend Power :
Stornoway Diamond(Gems-Au-Ur)SWY.TO
Second Quarter Results
CA$ 0.02+100.00%Trend Power :
McEwen Mining(Cu-Le-Zn)MUX
TO ACQUIRE BLACK FOX FROM PRIMERO=C2=A0
US$ 11.20+1.45%Trend Power :
Rentech(Coal-Ngas)RTK
Rentech Announces Results for Second Quarter 2017
US$ 0.20-12.28%Trend Power :
KEFIKEFI.L
Reduced Funding Requirement
GBX 0.55+2.59%Trend Power :
Lupaka Gold Corp.LPK.V
Lupaka Gold Receives First Tranche Under Amended Invicta Financing Agreement
CA$ 0.06+0.00%Trend Power :
Imperial(Ag-Au-Cu)III.TO
Closes Bridge Loan Financing
CA$ 2.46-2.38%Trend Power :
Guyana Goldfields(Cu-Zn-Pa)GUY.TO
Reports Second Quarter 2017 Results and Maintains Production Guidance
CA$ 1.84+0.00%Trend Power :
Lundin Mining(Ag-Au-Cu)LUN.TO
d Share Capital and Voting Rights for Lundin Mining
CA$ 15.80-1.56%Trend Power :
Canarc Res.(Au)CCM.TO
Canarc Reports High Grade Gold in Surface Rock Samples at Fondaway Canyon, Nevada
CA$ 0.24+0.00%Trend Power :
Havilah(Cu-Le-Zn)HAV.AX
Q A April 2017 Quarterly Report
AU$ 0.19-7.32%Trend Power :
Uranium Res.(Ur)URRE
Commences Lithium Exploration Drilling at the Columbus Basin Project
US$ 6.80-2.86%Trend Power :
Platinum Group Metals(Au-Cu-Gems)PTM.TO
Platinum Group Metals Ltd. Operational and Strategic Process ...
CA$ 1.82-4.21%Trend Power :
Devon Energy(Ngas-Oil)DVN
Announces $340 Million of Non-Core Asset Sales
US$ 51.80+0.73%Trend Power :
Precision Drilling(Oil)PD-UN.TO
Announces 2017Second Quarter Financial Results
CA$ 8.66-0.35%Trend Power :
Terramin(Ag-Au-Cu)TZN.AX
2nd Quarter Report
AU$ 0.03+0.00%Trend Power :