Argonaut Gold Announces Q2 Gold Production of 24,123 Ounces
Published : July 18, 2012

Developments at La Colorada and El Castillo Look to Build Production Profile in Second Half of 2012

( 0 vote, 0/5 ) Print article
  Article Comments Comment this article Rating Follow Company  
0
Send
0
comment

TORONTO, ONTARIO--(Marketwire - July 18, 2012) - Argonaut Gold Inc. ("Argonaut Gold" or the "Company") (News - Market indicators) announced today that the Company produced 24,123 gold ounces during the 2nd quarter ended June 30, 2012 at its 100% owned El Castillo Mine ("El Castillo") which is located 100 km north of the city of Durango, Mexico and its 100% owned La Colorada Mine ("La Colorada") which is located 50 kilometers southeast of Hermosillo, Mexico. Operational progress at El Castillo and La Colorada continue to ramp-up production.

SECOND QUARTER 2012 HIGHLIGHTS:

El Castillo

  • Quarterly production of 19,533 gold ounces represents a 10% improvement over Q1 2012.
  • 35,220 gold ounces loaded on the pad.
  • Leach pad 7A west side pad construction completed.
  • Conveying and stacking system on the east side pad expected to be commissioned this month.
  • Local community support programs implemented to assist with on-going drought conditions.

La Colorada

  • Production of 4,590 gold ounces and 25,796 silver ounces.
  • 10,173 gold ounces and 1,120,716 silver ounces loaded on the pad.
  • New crusher purchased for production of overliner for pad construction.
  • Desorption and refinery circuit fully commissioned.
  • New warehouse for reagent storage completed.
  • Final permits for mining expansion expected in third quarter.
  • Approximately half of Phase 1 run of mine material has been reprocessed.
  • New pad construction started on pads 8, 10 and 11.

Exploration

  • El Castillo sulphide samples obtained for continued metallurgical test work, with results expected in September.
  • More than 35,000 meters of drilling released at La Colorada.
  • More than 20,000 meters of drilling released at San Antonio.
  • Drilling continues at La Colorada and San Antonio.

Financial

  • Cash balance of $21 million as of June 30, 2012.
  • Majority of the 2012 capital program completed in the first half.
  • 23,247 ounces of gold sold.

SECOND QUARTER 2012 El CASTILLO OPERATING RESULTS:

Second quarter operating statistics showed improvement over 2011 second quarter results. Ore production from the first half of the year is currently at an annualized rate of approximately 11 million tonnes. On the west side of the property, construction was completed on cell 7A.

Third quarter production is expected to improve over the second quarter with the production of approximately 20-21,000 ounces of gold. Production at El Castillo is expected to move towards a 20-23,000 ounce production rate in the fourth quarter of this year. Full year guidance is 75,000-80,000 ounces of gold.

El Castillo Operating Statistics  
  3 Months Ended June 30  
  2012 2011 % Change  
Mining        
Total tonnes mined 5,037,401 4,970,835 +1 %
Tonnes ore mined 2,506,756 2,786,349 -10 %
Heap Leach Pad        
Direct ore tonnes to pad 1,533,188 1,920,657 -20 %
Crushed ore tonnes to pad 1,164,340 860,289 +35 %
Production        
Gold grade (g/t) 0.41 0.33 +24 %
Gold loaded to pad (oz) 35,220 29,555 +19 %
Gold loaded to carbon (oz) 19,533 17,453 +12 %
Gold sold (oz) 17,949 14,331 +25 %
1 "g/t" is grams per tonne      
2 "oz" means ounce      
   

Richard Rhoades, Chief Operating Officer of Argonaut Gold said: "The 10% improvement in gold production at El Castillo was a significant milestone at the mine. Two additional accomplishments for the quarter were the completion of leach pad 7A and the implementation of a stacking-conveying system that is to be commissioned later this month. Initially, day shifts will be utilized for training on the new conveying system, with the goal to implement a 24 hour conveying operation by Q3. The impact of adding the conveying system to the operation should be evident in the fourth quarter production numbers as we anticipate an increase in the material moved."

SECOND QUARTER 2012 LA COLORADA OPERATING RESULTS:

The second quarter operating statistics showed production from the reprocessing of existing run of mine leach pad material at La Colorada. To date, approximately half of the Phase I run of mine material to be reprocessed has been recrushed and stacked for leaching.

Construction has begun on pads 8, 10 & 11 and one half of the capacity is expected to be completed in the third quarter. In addition, during the third quarter the crusher will be down for approximately one month as it is relocated to a more permanent location, near the new pads currently under construction.

The next steps at La Colorada will involve reprocessing loose material in the pit, followed by full scale mining by Q1 of next year. Due to the crusher relocation, the third quarter production expectations are approximately 3,000 ounces of gold, while 2012 guidance at La Colorada remains at 13-17,000 ounces.

The desorption and recovery circuit has been commissioned, and carbon from El Castillo and La Colorada is being processed.

La Colorada Operating Statistics      
  3 Months Ended June 30  
  Q2 2012 Q1 2012 % Change  
Mining        
Total tonnes moved 840,241 678,310 +24 %
Ore tonnes moved 805,611 678,310 +19 %
Heap Leach Pad        
Crushed ore tonnes to pad 743,533 680,396 +9 %
Production        
Gold grade (g/t) 0.43 0.41 +5 %
Gold loaded to pad (oz) 10,173 8,886 +14 %
Gold loaded to carbon (oz) 4,590 3,085 +49 %
Silver loaded to carbon (oz) 25,796 17,182 +50 %
Gold sold (oz) 5,298 0 NA  
1 "g/t" is grams per tonne    
2 "oz" means ounce    
         

Discussing the Company's recent completion of the ADR plant at the La Colorada site Mr. Pete Dougherty, President and CEO said "the Company is now processing carbon from El Castillo and La Colorada on site. This important accomplishment has reduced the sales cycle time from approximately 6 weeks to 1 week. The long term goal is for the ADR circuit to handle the stripping and refining for the Company's primary Mexican operations. We are pleased with the improvement in our sales time as a result of implementing the ADR plant.

I'm proud of the team's accomplishments so far this year. By continually improving our processes in our daily operations we look to continue production growth, finishing the year strong."

About Argonaut Gold

Argonaut Gold is a Canadian gold company engaged in exploration, mine development and production activities. Its primary assets are the production-stage El Castillo Mine in the State of Durango, Mexico, the production stage La Colorada Mine in the State of Sonora, Mexico, the advanced exploration stage San Antonio project in the State of Baja California Sur, Mexico, and several exploration stage projects, all of which are located in Mexico.

Creating Value Beyond Gold

Cautionary Note Regarding Forward-looking Statements

This press release contains certain "forward-looking statements" and "forward-looking information" under applicable Canadian securities laws concerning the proposed transaction and the business, operations and financial performance and condition of Argonaut Gold Inc. ("Argonaut"). Forward-looking statements and forward-looking information include, but are not limited to, statements with respect to estimated production and mine life of the various mineral projects of Argonaut; synergies and financial impact of completed acquisitions; the benefits of the development potential of the properties of Argonaut; the future price of gold, copper, and silver; the estimation of mineral reserves and resources; the realization of mineral reserve estimates; the timing and amount of estimated future production; costs of production; success of exploration activities; and currency exchange rate fluctuations. Except for statements of historical fact relating to Argonaut, certain information contained herein constitutes forward-looking statements. Forward-looking statements are frequently characterized by words such as "plan," "expect," "project," "intend," "believe," "anticipate", "estimate" and other similar words, or statements that certain events or conditions "may" or "will" occur. Forward-looking statements are based on the opinions and estimates of management at the date the statements are made, and are based on a number of assumptions and subject to a variety of risks and uncertainties and other factors that could cause actual events or results to differ materially from those projected in the forward-looking statements. Many of these assumptions are based on factors and events that are not within the control of Argonaut and there is no assurance they will prove to be correct.

Factors that could cause actual results to vary materially from results anticipated by such forward-looking statements include changes in market conditions, variations in ore grade or recovery rates, risks relating to international operations, fluctuating metal prices and currency exchange rates, changes in project parameters, the possibility of project cost overruns or unanticipated costs and expenses, labour disputes and other risks of the mining industry, failure of plant, equipment or processes to operate as anticipated. Although Argonaut has attempted to identify important factors that could cause actual actions, events or results to differ materially from those described in forward-looking statements, there may be other factors that cause actions, events or results not to be anticipated, estimated or intended. There can be no assurance that forward-looking statements will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements. Argonaut undertakes no obligation to update forward-looking statements if circumstances or management's estimates or opinions should change except as required by applicable securities laws. The reader is cautioned not to place undue reliance on forward-looking statements. Statements concerning mineral reserve and resource estimates may also be deemed to constitute forward-looking statements to the extent they involve estimates of the mineralization that will be encountered if the property is developed. Comparative market information is as of a date prior to the date of this document.

Qualified Person

Preparation of this release was supervised by Thomas Burkhart, Argonaut Gold's Vice President of Exploration, and a Qualified Person under NI 43-101. For additional information on El Castillo please refer to the "NI 43-101 Technical Report on Resources and Reserves, Argonaut Gold Inc., El Castillo Mine, Durango State, Mexico" dated Nov. 6, 2010 and further information on La Colorada please refer to the "NI 43-101 Preliminary Economic Assessment La Colorada Project, Sonora, Mexico" dated December 30, 2011, both of which and available at Argonaut Gold's website and profile on www.sedar.com.



Argonaut Gold Inc.
Nichole Cowles
Investor Relations Manager
(775) 284-4422 x 101
nichole.cowles@argonautgoldinc.com
www.argonautgoldinc.com
Data and Statistics for these countries : Mexico | All
Gold and Silver Prices for these countries : Mexico | All

Argonaut Gold Inc.

PRODUCER
CODE : AR.TO
Follow and Invest
Add to watch list Add to your portfolio Add or edit a note
Add Alert Add to Watchlists Add to Portfolio Add Note
ProfileMarket
Indicators
VALUE :
Projects & res.
Press
releases
Annual
report
RISK :
Asset profile
Contact Cpy

Argonaut Gold is a gold producing company based in United states of america.

Argonaut Gold holds various exploration projects in Mexico.

Its main assets in production are EL SASTRE GOLD MINE, EL SASTRE, EL SASTRE - EL ARENAL, EL SASTRE BRIDGE ZONE and EL SASTRE - LUPITA ZONE in Guatemala and EL CASTILLO in Mexico and its main exploration property is SAN ANTIONIO in Mexico.

Argonaut Gold is listed in Canada. Its market capitalisation is CA$ 72.5 millions as of today (US$ 53.1 millions, € 49.8 millions).

Its stock quote reached its highest recent level on January 25, 2013 at CA$ 9.99, and its lowest recent point on November 18, 2022 at CA$ 0.33.

Argonaut Gold has 176 940 000 shares outstanding.

Your feedback is appreciated, please leave a comment or rate this article.
Rate : Average note :0 (0 vote) View Top rated
 
Nominations of Argonaut Gold Inc.
11/15/2013Announces New Chief Financial Officer
12/15/2011Announces New Chief Operating Officer
Financials of Argonaut Gold Inc.
3/16/2015Announces 2014 Revenue of $166.3M, $42.5M in Cash Flow from ...
8/6/2013Provides Notice of Second Quarter Financial Results on Augus...
7/25/2012Provides Notice of Second Quarter Financial Results on Augus...
3/19/2012Provides Notice of Fourth Quarter and Year End Financial Res...
8/5/2011Provides Notice of Second Quarter Financial Results on Augus...
Project news of Argonaut Gold Inc.
1/31/2014Confirms Filing of Prefeasibility Study for the Magino Proje...
1/20/2014CORRECTION FROM SOURCE - Argonaut Gold Announces Full Year 2...
1/20/2014Announces Full Year 2013 Gold Production of 120,224 gold equ...
12/31/2013Announces Completion of the San Agust=EDn project purchase f...
11/6/2013Announces Purchase of San Agust=EDn project from Silver Stan...
10/16/2013Announces Q3 Gold Production of 26,690 Ounces
7/15/2013Announces Record Q2 Gold Production of 33,586 Ounces
4/15/2013Announces Q1 Gold Production of 28,907 Ounces
2/25/2013Announces 2013 Production Guidance of 120-140,000 Ounces
1/17/2013Exceeds 2012 Guidance with Gold Production of 108,081 Ounces
1/17/2013Exceeds 2012 Guidance with Gold Production of 108,081 Ounces
7/18/2012Announces Q2 Gold Production of 24,123 Ounces
4/17/2012Announces Q1 Gold Production of 21,084 Ounces
7/15/2011Announces Q2 Gold Production of 17,453 Ounces
4/14/2011Announces Q1 Gold Production of 18,005 0unces
3/22/2011(San Antionio)Reports on Resource Expansion Drilling at San Antonio
2/14/2011(El Castillo)Provides 2011 Guidance on El Castillo Production of 70-75,00...
Corporate news of Argonaut Gold Inc.
5/25/2016Argonaut Gold Raises C$4.5M via Private Placement of Flow-Th...
5/4/2016Argonaut Gold Announces Results of Annual and Special Meetin...
5/3/2016Argonaut Gold Announces First Quarter 2016 Earnings per Shar...
4/29/2016Argonaut Gold Announces $30 Million Revolving Credit Facilit...
4/14/2016Argonaut Gold Announces First Quarter 2016 Production of 32,...
4/6/2016Argonaut Gold Further Strengthens Board and Management Team
1/18/2016Argonaut Gold Announces Updated Pre-Feasibility Study Result...
11/30/2015Mexus Gold is Pleased to Announce That Argonaut Gold Has Com...
11/24/2015Argonaut Gold Chairman Brian Kennedy Retiring; Jim Kofman to...
11/3/2015Argonaut Gold Announces Third Quarter 2015 Revenue of $32M; ...
11/2/2015Argonaut Gold El Castillo Update
10/22/2015Argonaut Gold El Castillo Update
10/19/2015Mexus Commences Drill Pad Construction for Argonaut
10/15/2015Argonaut Gold Announces Third Quarter 2015 Production of 28,...
9/17/2015Argonaut Gold Announces Updated Economic Parameters to the D...
9/14/2015Mexus Gold US Julio/Santa Elena Update
9/9/2015Mexus Gold US Press Release Correction
8/17/2015Argonaut Gold Updates Mexus Gold US on the Julio property
8/14/2015Argonaut Gold Announces Second Quarter 2015 Revenue of $44M;...
4/15/2015Announces First Quarter 2015 Production of 43,255 Gold Equiv...
3/16/2015Argonaut Gold Announces 2014 Revenue of $166.3M, $42.5M in C...
2/20/2015Argonaut Gold Confirms Filing of Technical Report and Prelim...
1/26/2015Argonaut Gold Receives TSX Acceptance of Shareholder Rights ...
1/20/2015Argonaut Gold Adopts Shareholder Rights Plan
1/13/2015Argonaut Gold Announces Full Year 2014 Gold Production of 13...
1/13/2015Argonaut Gold Announces Updates on the Magino and San Agusti...
1/12/2015Argonaut Gold Announces Updates on the Magino and San Agusti...
1/7/2015Argonaut Gold Announces Full Year 2014 Gold Production of 13...
11/6/2014Argonaut Gold Announces Third Quarter 2014 Revenue of $37.3M...
10/15/2014Argonaut Gold Announces Q3 Production of 32,122 Gold Equival...
10/3/2014Argonaut Gold Confirms Filing of National Instrument 43-101 ...
8/29/2014IIROC Trade Resumption - AR
11/12/2013Announces 3rd Quarter 2013 Revenue of $42.4M and Net Income ...
8/13/2013Announces 2nd Quarter 2013 Revenue of $44.9M and Net Income ...
5/14/2013Announces 1st Quarter 2013 Revenue of $43.1M and Net Income ...
4/26/2013Amends Annual Meeting Business in Response to ISS Comments
3/26/2013Announces 2012 Revenue of $187.1 Million and Net Income of $...
11/14/2012Announces Third Quarter 2012 Revenue of $72.9 Million and Ne...
10/15/2012and Prodigy Agree to Friendly Business Combination
10/15/2012and Prodigy Agree to Friendly Business Combination
10/15/2012and Prodigy Agree to Friendly Business Combination
9/4/2012Announces Updated PEA for the San Antonio Project, Projected...
8/15/2012Announces Record Production, Record Revenue and Record Earni...
5/15/2012Announces First Quarter 2012 Revenue of $24.4 Million and Ne...
5/8/2012Provides Exploration Update on San Antonio and La Colorada
4/25/2012for Annual and Special Meeting of Shareholders
3/30/2012Announces 2011 Revenue of $105 Million and Net Income of $26...
3/14/2012Added to the S&P/TSX Composite Index
2/27/2012Announces 2012 Project Initiatives
1/9/2012Announces the La Colorada Project on Track for Production in...
11/28/2011(El Castillo)Reports on Metallurgical Test Work for El Castillo Sulphide
10/24/2011Increases Measured and Indicated Resource at La Colorada to ...
9/14/2011to be Included in the S&P TSX SmallCap Index
8/15/2011Reports Q2 2011 Revenue of $21.6 Million Net Income of $5.2 ...
6/15/2011Provides Update on 2011 Drilling at La Colorada; Board Appro...
6/6/2011Reports Q1 2011 Revenue of $25.7 Million
5/20/2011Announces Intent to Terminate Registration Under U.S. Securi...
5/9/2011s Resource for San Antonio
4/7/2011Begins Resource Expansion Drilling at the La Colorada Projec...
3/31/2011Announces Q4 Revenue of $19.9 Million as Part of Year End Fi...
3/16/2011to Begin Trading on the S&P Canadian Index Operations
1/25/2011Shareholders and Pediment Gold Corp Shareholders Approve Bus...
Comments closed
 
Latest comment posted for this article
Be the first to comment
Add your comment
TORONTO (AR.TO)
0.410+2.50%
TORONTO
CA$ 0.410
04/23 17:00 0.010
2.5%
Prev close Open
0.400 0.405
Low High
0.400 0.415
Year l/h YTD var.
0.230 -  0.430 -2.38%
52 week l/h 52 week var.
0.230 -  0.720 -29.31%
Volume 1 month var.
3,188,874 32.26%
24hGold TrendPower© : -44
Produces Gold
Develops
Explores for
 
 
 
Analyse
Interactive chart Add to compare
Interactive
chart
Print Compare Export
Last updated on : 2/15/2010
You must be logged in to use the porfolio and watchlists (free)
Top Newsreleases
MOST READ
Annual variation
DateVariationHighLow
2024-32.79%
202317.31%0.770.42
2022-77.19%2.760.33
2021-16.79%4.091.90
202048.11%3.420.76
 
5 years chart
 
3 months chart
 
3 months volume chart
 
 
Mining Company News
Plymouth Minerals LTDPLH.AX
Plymouth Minerals Intersects Further High Grade Potash in Drilling at Banio Potash Project - Plannin
AU$ 0.12-8.00%Trend Power :
Santos(Ngas-Oil)STO.AX
announces expected non-cash impairment
AU$ 7.75+0.52%Trend Power :
Oceana Gold(Au)OGC.AX
RELEASES NEW TECHNICAL REPORT FOR THE HAILE GOLD MINE
AU$ 2.20+0.00%Trend Power :
Western Areas NL(Au-Ni-Pl)WSA.AX
Advance Notice - Full Year Results Conference Call
AU$ 3.86+0.00%Trend Power :
Canadian Zinc(Ag-Au-Cu)CZN.TO
Reports Financial Results for Q2 and Provides Project Updates
CA$ 0.12+4.55%Trend Power :
Stornoway Diamond(Gems-Au-Ur)SWY.TO
Second Quarter Results
CA$ 0.02+100.00%Trend Power :
McEwen Mining(Cu-Le-Zn)MUX
TO ACQUIRE BLACK FOX FROM PRIMERO=C2=A0
US$ 11.11+2.21%Trend Power :
Rentech(Coal-Ngas)RTK
Rentech Announces Results for Second Quarter 2017
US$ 0.20-12.28%Trend Power :
KEFIKEFI.L
Reduced Funding Requirement
GBX 0.56+2.55%Trend Power :
Lupaka Gold Corp.LPK.V
Lupaka Gold Receives First Tranche Under Amended Invicta Financing Agreement
CA$ 0.06-8.33%Trend Power :
Imperial(Ag-Au-Cu)III.TO
Closes Bridge Loan Financing
CA$ 2.47+3.78%Trend Power :
Guyana Goldfields(Cu-Zn-Pa)GUY.TO
Reports Second Quarter 2017 Results and Maintains Production Guidance
CA$ 1.84+0.00%Trend Power :
Lundin Mining(Ag-Au-Cu)LUN.TO
d Share Capital and Voting Rights for Lundin Mining
CA$ 15.25-3.42%Trend Power :
Canarc Res.(Au)CCM.TO
Canarc Reports High Grade Gold in Surface Rock Samples at Fondaway Canyon, Nevada
CA$ 0.24+0.00%Trend Power :
Havilah(Cu-Le-Zn)HAV.AX
Q A April 2017 Quarterly Report
AU$ 0.19+0.00%Trend Power :
Uranium Res.(Ur)URRE
Commences Lithium Exploration Drilling at the Columbus Basin Project
US$ 6.80-2.86%Trend Power :
Platinum Group Metals(Au-Cu-Gems)PTM.TO
Platinum Group Metals Ltd. Operational and Strategic Process ...
CA$ 1.79-3.76%Trend Power :
Devon Energy(Ngas-Oil)DVN
Announces $340 Million of Non-Core Asset Sales
US$ 52.57+0.84%Trend Power :
Precision Drilling(Oil)PD-UN.TO
Announces 2017Second Quarter Financial Results
CA$ 8.66-0.35%Trend Power :
Terramin(Ag-Au-Cu)TZN.AX
2nd Quarter Report
AU$ 0.04+0.00%Trend Power :