SilverCrest Announces Santa Elena Expansion Pre-Feasibility Study; Base Case NPV @ $243.7 Million and 88% IRR 8 Years of Mine Life Added
Published : July 25, 2013
( 0 vote, 0/5 ) Print article
  Article Comments Comment this article Rating Follow Company  
0
Send
0
comment

VANCOUVER, BRITISH COLUMBIA--(Marketwired - July 25, 2013) - SilverCrest Mines Inc. (News - Market indicators)(NYSE MKT:SVLC) ("SilverCrest" or the "Company") is pleased to announce that it has filed its NI 43-101 Technical Report entitled "Santa Elena Expansion Pre-Feasibility Study and Open Pit Reserve Update" for its operating mine located in Sonora, Mexico. Summaries of the revised Life of Mine Plan (LOMP), operating costs, capital costs and Expansion project economics are presented in tables below. All dollar amounts are expressed in U.S. dollars unless otherwise specified. The effective date of this Technical Report is April 30, 2013.

The economic analyses use Base Case metal prices of $1450/ounces of gold and $28/ounces of silver (3 year average historical trend). On this basis, the following economic highlights for an additional 8 years of mine life beginning in January 2014 are;

  • Total operating revenue of $684.9 million from estimated sales of 12.11 million ounces of silver and 262,739 ounces of gold.

  • Total operating costs of $282.2 million with estimated cash operating costs averaging US$11/ounce AgEQ for mine life with lower costs in initial years.

  • Total capital costs of $87.8 million including contingency but excluding sunk costs up to April 30, 2013.

  • Total pre-tax cash flow of $302.5 million including estimated cost deductions for closure (US$ 5 million) and working capital (US$1.8 million).

  • Base Case pre-tax NPV (DCF @ 5%) of $243.7 million including 2013 estimated net cash flow of $20 million at $1250/ounce of gold and $19.50/ounce of silver after effective date of April 30, 2013.

  • IRR of 88% based on incremental project economics excluding sunk costs up to April 30, 2013.

  • Payback period of 1 year.

  • AgEQ based on a ratio of 70:1 which includes average metallurgical recoveries of 92% Au and 67.5% Ag for all milling ores.

Metal price sensitivities were completed including $1250/oz Au and $19.50/oz Ag which showed a pre-tax NPV (DCF @ 5%) of $128.7M (including 2013 est. net cash flow) and an IRR of 49%.

Updated Mineral Reserve and Resource estimations for Santa Elena Mine were announced in a news release dated May 29, 2013 which showed Probable Reserves (underground, open pit and leach pad) at an estimated 8.2 million tonnes grading 74.9 gpt Ag and 1.24 gpt Au containing 19.7 million ounces of silver and 327,430 ounces of gold. Updated Indicated Resources (exclusive of Probable Reserves) were estimated at 2.1 million tonnes grading 114.9 gpt Ag and 1.69 gpt Au containing 7.9 million ounce of silver and 116,000 ounces of gold. Only Mineral Reserves were used in the PFS mine plan, schedule and economic analysis. Mineralization at Santa Elena is open in most directions with excellent potential to further increase resources and reserves for increased production and mine life.

J. Scott Drever, Chairman and CEO commented: "We are extremely pleased with the results of the PFS which confirms our expectations that the transition from our open pit heap leach operation to a conventional mill and underground operation will represent a very attractive project with robust economics even at current reduced metal prices. The 8 year mine life will give SilverCrest a strong corporate cash flow providing a solid foundation for continued systematic and aggressive growth. We look forward to a banner year in 2014 with the commissioning of the new processing facility in the first quarter and the significant expansion of our annual metals production at Santa Elena."

EXPANSION LIFE OF MINE PLAN 

The Santa Elena mine life with updated Reserves is scheduled for an additional 8 years at nominal milling rate of 3,000 tonnes per day. The mine schedule is based on mining long hole stopes (69% by reserve volume) early in the mine life at attractive lower costs with higher cost cut and fill stopes (31% by reserve volume) being mined towards the end of the mine schedule. The average width of proposed stopes is 13.4 metres which is advantageous for lower cost bulk mining methods. SilverCrest envisions a blending strategy during operations at variable rates for mill feed to achieve optimum throughput. A summary of the mine and production schedule is presented below with proposed initial blending strategy.

Aspect of operations   2013   2014   2015   2016   2017 2018   2019   2020   2021   Total
Life of Mine
Total Tonnes Underground       127,707   392,412   535,520   646,088 708,359   684,604   580,407   245,225   3,920,322
Total Tonnes Leach Pad       335,426   615,588   472,480   361,912 299,641   323,396   427,593   8,495   2,844,531
Total Tonnes Open Pit   882,0401   544,867   -   -   - -   -   -   -   1,426,907
Total Tonnes Processed   882,040   1,008,000   1,008,000   1,008,000   1,008,000 1,008,000   1,008,000   1,008,000   253,720   8,191,760
Total Gold Ounces Sold       36,173   39,606   29,361   27,557 27,924   53,357   37,535   11,226   262,739
Total Silver Ounces Sold       1,345,248   1,594,643   1,409,639   1,742,741 1,556,867   1,951,279   1,816,118   702,392   12,118,927
1Included for Reserve declaration purposes only but not included in economic analyses for the Expansion

This plan excludes an estimated 750,000 tonnes of heap leach spent ore which will be placed on the pad in 2013 and accounted for in early 2014 as additional material for reprocessing during the mine life.

EXPANSION OPERATING COSTS

The operating cost estimates stated below were compiled using Santa Elena mine site operating experience, SilverCrest financial and operational reports, recent contractor quotes, other local producing mines and industry estimations in Mexico to a Pre-Feasibility level.

Mining Method   Open Pit   Open Pit   U/G
Long Hole
Average
  U/G
Cut & Fill
Average
  Leach Pad
Reprocess
Process Method   Heap Leach   CCD Mill   CCD Mill   CCD Mill   CCD Mill
Mining Cost/T ore   $2.42   $2.50   $17.001   $38.001   $0.62
Mining Cost/T waste   $1.52   $2.00   NA   NA   NA
Processing Cost/T2   $6.65   $20.50   $20.50   $20.50   $18.50
General & Administration3   $3.30   $3.60   $3.60   $3.60   $3.60
1Long hole stopes are 69% of designed stopes by volume and cut & fill stopes are 31% of designed stopes by reserve volume. Excludes ore development costs. $/t inclusive of ore dev. Is estimated at $21 to $48.
2Processing includes crushing, milling, site refining and dry stack tailings disposal.
3Estimated based on current operations and may vary on an annual basis.

EXPANSION CAPITAL COSTS

The capital cost estimates stated below were compiled using Santa Elena mine site experience, recent contractor quotes, other local producing mines and industry estimations in Mexico to a Pre-Feasibility level.

Capital Expense Item   Estimated Cost
Mining equipment purchases   2,343,810
Development - Underground   3,480,550
Process plant including EPCM   41,928,472
Electrical and services - Underground   72,042
Indirect services   243,000
Initial Capital (including contingency, excludes sunk costs)   48,067,874
Mining equipment purchases   5,144,587
Development   31,284,348
Electrical and services   2,283,346
Health and safety   143,442
Construction (incl. labour)   322,880
Indirect services   567,000
Sustaining Capital (including contingency)   39,745,603
Total Capital (including contingency) - Life of Mine   87,813,477

EXPANSION ECONOMIC ANALYSIS

Pre-Feasibility level economic analyses were completed for both pre-tax and post-tax. Base Case pre-tax results are stated as follows;

Aspects of Santa Elena Expansion Financial Analysis
(Base Case)
Production
Gold Ounces Sold - post refiner credit 262,739
Silver Ounces Sold - post refiner credit 12,118,927
Revenue $(000)
Gross Sales $684,931
Operating Expenses
Total Operating Costs1 $282,223
Freight & Refining $5,579
Capital Expenses
Total Capital Costs2 $87,813
Pre-Tax Cash Flow
Total Cash Flow3 $302,481
Pre-Tax Financial Results
Pre-Tax NPV, DCF @ 5%4 $243,670
Pre-tax IRR5 88%
1 Operating cost per AgEQ oz. sold varies between $9.6 and $12.6 over the life of mine
2 Excludes sunk costs, up to April 30, 2013, closure costs and working capital
3 Includes deductions of $5 million for closure costs and $1.8 million for working capital
4 Includes 2013 estimated net cash flow after effective date of April 30, 2013
5 The IRR presented here do not reflect total project economics but reflect incremental project economics as they do not include sunk costs for the Santa Elena expansion prior to April 30 2013

The economic analyses consider SilverCrest delivering a remaining 31,000 ounces of gold (2014 and beyond) to Sandstorm Gold Ltd. (Sandstorm) at a price of $350/oz under the Sandstorm Purchase Agreement executed on May14th, 2009. It does not include the option held by Sandstorm to participate in the future underground mine production which would require payment by Sandstorm of 20% (pro-rata of gold) of the capital costs with a subsequent increase of gold price for 20% of produced ounces to $450/oz Au. Sandstorm may elect to participate in the expansion, once SilverCrest provides a preliminary technical report that includes amongst other items; the required capital costs associated with the transition from open pit heap leaching to a conventional mill facility and underground mine.

EXPANSION PRE-FEASIBILTY RECOMMENDATIONS

Further optimization of the mine schedule is warranted to investigate grade optimization versus stoping costs (long hole or cut and fill), potential to expand and accelerate increased underground production with a second ramp for the bottom of the pit and expand milling capacity. These optimizations will be addressed in detail after successfully announcing commercial production for the new mill facility in 2014. Mineralization at Santa Elena is open in most directions with excellent potential to further increase resources and reserves for increased production and mine life. Further infill and expansion drilling is recommended.

The Qualified Persons for this Technical Report and who have reviewed and approved the contents of this news release are N. Eric Fier, CPG, P.Eng., President and Chief Operating Officer for the Company, James Barr., P.Geo., Mike Tansey, P.Eng. and Carlos Chaparro, P.Eng. from the consulting firm of EBA, a Tetra Tech Company, and John Fox, P.Eng. of Laurion Consulting Inc.

SilverCrest Mines Inc. (News - Market indicators)(NYSE MKT:SVLC) is a Canadian precious metals producer headquartered in Vancouver, BC. SilverCrest's flagship property is the 100%-owned Santa Elena Mine, located 150 km northeast of Hermosillo, near Banamichi in the State of Sonora, México. The mine is a high-grade, epithermal gold and silver producer, with an estimated life of mine cash cost of US$8 per ounce of silver equivalent (55:1 Ag: Au) for the open pit heap leach. SilverCrest anticipates that the 2,500 tonnes per day open pit heap leach facility at the Santa Elena mine should recover approximately 675,000 ounces of silver and 33,000 ounces of gold in 2013. An expansion plan is well underway to significantly increase the annual metals production in 2014 at the Santa Elena Mine (open pit and underground). Exploration programs have rapidly advanced the definition of a large polymetallic deposit at the La Joya property in Durango State with stated resources nearing 200 million ounces of Ag equivalent.

FORWARD-LOOKING STATEMENTS

This news release contains "forward-looking statements" within the meaning of Canadian securities legislation and the United States Securities Litigation Reform Act of 1995. Such forward-looking statements concern the Company's anticipated results and developments in the Company's operations in future periods, planned exploration and development of its properties, plans related to its business and other matters that may occur in the future. These statements relate to analyses and other information that are based on expectations of future performance, including silver and gold production and planned work programs. Statements concerning reserves and mineral resource estimates may also constitute forward-looking statements to the extent that they involve estimates of the mineralization that will be encountered if the property is developed and, in the case of mineral reserves, such statements reflect the conclusion based on certain assumptions that the mineral deposit can be economically exploited.

Forward-looking statements are subject to a variety of known and unknown risks, uncertainties and other factors which could cause actual events or results to differ from those expressed or implied by the forward-looking statements, including, without limitation: risks related to precious and base metal price fluctuations; risks related to fluctuations in the currency markets (particularly the Mexican peso, Canadian dollar and United States dollar); risks related to the inherently dangerous activity of mining, including conditions or events beyond our control, and operating or technical difficulties in mineral exploration, development and mining activities; uncertainty in the Company's ability to raise financing and fund the exploration and development of its mineral properties; uncertainty as to actual capital costs, operating costs, production and economic returns, and uncertainty that development activities will result in profitable mining operations; risks related to reserves and mineral resource figures being estimates based on interpretations and assumptions which may result in less mineral production under actual conditions than is currently estimated and to diminishing quantities or grades of mineral reserves as properties are mined; risks related to governmental regulations and obtaining necessary licenses and permits; risks related to the business being subject to environmental laws and regulations which may increase costs of doing business and restrict our operations; risks related to mineral properties being subject to prior unregistered agreements, transfers, or claims and other defects in title; risks relating to inadequate insurance or inability to obtain insurance; risks related to potential litigation; risks related to the global economy; risks related to the Company's status as a foreign private issuer in the United States; risks related to all of the Company's properties being located in Mexico and El Salvador, including political, economic, social and regulatory instability; and risks related to officers and directors becoming associated with other natural resource companies which may give rise to conflicts of interests. Should one or more of these risks and uncertainties materialize, or should underlying assumptions prove incorrect, actual results may vary materially from those described in the forward-looking statements. The Company's forward-looking statements are based on beliefs, expectations and opinions of management on the date the statements are made. For the reasons set forth above, investors should not place undue reliance on forward-looking statements.

The information provided in this news release is not intended to be a comprehensive review of all matters and developments concerning the Company. It should be read in conjunction with all other disclosure documents of the Company. The information contained herein is not a substitute for detailed investigation or analysis. No securities commission or regulatory authority has reviewed the accuracy or adequacy of the information presented.

J. Scott Drever, Chairman, CEO

SILVERCREST MINES INC.

Neither TSX Venture Exchange nor its Regulation Services Provider (as defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.

SilverCrest Mines Inc.
Fred Cooper
(604) 694-1730 ext. 108 or Toll Free: 1-866-691-1730
(604) 694-1761 (FAX)
info@silvercrestmines.com
www.silvercrestmines.com
Data and Statistics for these countries : El Salvador | Mexico | All
Gold and Silver Prices for these countries : El Salvador | Mexico | All

SilverCrest Mines

PRODUCER
CODE : SVL.V
ISIN : CA8283651062
CUSIP : 828365
Follow and Invest
Add to watch list Add to your portfolio Add or edit a note
Add Alert Add to Watchlists Add to Portfolio Add Note
ProfileMarket
Indicators
VALUE :
Projects & res.
Press
releases
Annual
report
RISK :
Asset profile
Contact Cpy

SilverCrest Mines is a silver and gold producing company based in Canada.

SilverCrest Mines develops silver, gold and zinc in El Salvador, and holds various exploration projects in Mexico.

Its main asset in production is SANTA ELENA in Mexico, its main asset in development is EL ZAPOTE in El Salvador and its main exploration properties are SILVER ANGEL, CRUZ DE MAYO and LA JOYA DURANGO in Mexico.

SilverCrest Mines is listed in Canada, in Germany and in United States of America. Its market capitalisation is CA$ 287.2 millions as of today (US$ 259.0 millions, € 188.5 millions).

Its stock quote reached its lowest recent point on December 17, 2002 at CA$ 0.08, and its highest recent level on March 02, 2012 at CA$ 3.17.

SilverCrest Mines has 107 952 000 shares outstanding.

Your feedback is appreciated, please leave a comment or rate this article.
Rate : Average note :0 (0 vote) View Top rated
 
Corporate Presentations of SilverCrest Mines
6/1/2010Greg McCoach - Mining Speculator June 2010
6/1/2010Corporate Presentation - June 2010
3/31/2010 Funding In Place, Construction on Schedule for 2010 Product...
1/1/2010Why invest in SilverCrest Mines?
6/10/2009Corporate report June 2009
3/31/2008New Recommendation
11/22/2006Corporate Presentation
In the News and Medias of SilverCrest Mines
3/14/2012Scott Drever=2C President of SilverCrest Interview on BNN
9/22/2008Objective Capital research
10/25/2007Analysis by David and Eric Coffin
11/17/2006Follow up N° 4
Annual reports of SilverCrest Mines
2009 Annual Report
2008 annual report
Annual Report 2006
Financings of SilverCrest Mines
5/20/2011Closes $30 Million Bought Deal Financing
4/28/2011Announces CAD$30.0 Million Bought Deal Common Share Financin...
3/20/2008Completes Private Placement; Amends $3.0 Million Macquarie F...
3/13/2008Announces First Closing Of Private Placement
Option Grants of SilverCrest Mines
3/29/2008 Engages Marketing Consultant and Grants Stock Options
Nominations of SilverCrest Mines
6/13/2013Reports Results of AGM Announces Officer and Director Appoin...
1/31/2013Appoints Vice President, Corporate Development
2/15/2011SilverCrest Appoints of Mr. Brent McFarlane Vice President, ...
Financials of SilverCrest Mines
8/13/2015Announces Q2, 2015 Financial Results; Operating Cash Flow of...
11/14/2013Reports Q3, 2013 Financial Results Cash Flow from Operations...
8/15/2013Reports Q2, 2013 Financial Results Cash Flow from Operations...
8/15/2013Reports Q2, 2013 Financial Results
5/15/2013Reports Q1, 2013 Financial Results Cash Flow from Operations...
3/14/2013Announces 2012 Financial Results Cash Flow from Operations o...
11/14/2012Reports Q3, 2012 Financial Results Cash Flow From Operations...
8/15/2012Reports Q2=2C 2012 Financial Results
5/15/2012Reports Q1 2012 Financial Results Cash Flow from Operations ...
4/10/2012Announces 2011 Financial Results Cash Flow from Operations o...
11/29/2011Reports $5.1 Million Third Quarter Cash Flow from Operation...
8/30/2011Announces Second Quarter Earnings of $790,000 and Cash Flow ...
8/2/2011Form 40-F Registration Statement Effective
Project news of SilverCrest Mines
2/25/2014(Santa Elena)Receives US$10 Million Commitment from Sandstorm Gold for Un...
1/14/2014Evrim Options Ermita=F1o Property to SilverCrest Mines
12/24/2013Files La Joya Preliminary Economic Assessment Report
10/21/2013Announces Positive La Joya Preliminary Economic Assessment ...
10/15/2013Announces Q3 Record Silver Production 202,736 Ounces Silver-...
9/5/2013(Santa Elena)Reports Additional Drill Results at Santa Elena Mine; Anothe...
7/25/2013(Santa Elena)Announces Santa Elena Expansion Pre-Feasibility Study; Base...
7/17/2013Announces Q2 Record Silver Production 194,022 Ounces Silver ...
5/29/2013(Santa Elena)Announces Updated Santa Elena Reserves and Resources; Silver...
4/24/2013Announces Q1 Production 153,481 Ounces Silver & 7,225 Ounces...
3/28/2013Files La Joya Technical Report Updated Resources & Positive ...
1/29/2013Announces Updated La Joya Resources
1/16/2013Exceeds 2012 Production Market Guidance Announces Q4 Results...
1/14/2013(Santa Elena)Expands Santa Elena Deposit; More High Grade Intercepts 13m ...
1/7/2013(Santa Elena)Discovers Bonanza Grades and New Zone at Santa Elena 15.6m ...
11/13/2012(Santa Elena)Drilling Update for Santa Elena Mine
11/7/2012Pays Out Gold Hedge Facility Gold and Silver Production Now ...
10/16/2012Announces Q3 Production 151,368 Ounces Silver & 7,184 Ounces...
7/23/2012Announces Q2 Production 139=2C850 Ounces Silver & 8=2C584 Ou...
7/6/2012(Santa Elena)=E2??s Santa Elena Mine Expansion Continues on Schedule
4/19/2012Announces Q1 Silver and Gold Production 134=2C528 Silver Ou...
3/20/2012(La Joya Durango)Reports 58m @ 164.7 gpt Ag Eq* at La Joya
2/16/2012(La Joya Durango)Reports Coloradito Target Results at La Joya Property=3B Pot...
1/23/2012(La Joya Durango)s Corporate Resources Silver Equivalent Inferred Resources ...
1/23/2012(Cruz De Mayo)s Corporate Resources Silver Equivalent Inferred Resources ...
1/23/2012(Cruz De Mayo)s Corporate Resources Silver Equivalent Inferred Resources ...
1/23/2012(Santa Elena)s Corporate Resources Silver Equivalent Inferred Resources ...
1/12/2012(Santa Elena)Reports Record Production in Q4 at Santa Elena=3B =E2?=A2 Si...
1/5/2012(La Joya Durango)Announces Initial Resources at La Joya Property=3B +100 mill...
11/30/2011(La Joya Durango)Commences Phase II Drilling at La Joya=3B Phase II Surface S...
10/14/2011(Santa Elena)Reports Increased Santa Elena Production in Q3 Silver Produc...
9/22/2011(Santa Elena)Begins Drilling at Cruz de Mayo, Reports on Santa Elena Nort...
9/22/2011(Cruz De Mayo)Begins Drilling at Cruz de Mayo, Reports on Santa Elena Nort...
8/10/2011(La Joya Durango)Video Tour of La Joya Mine Project, Durango Mexico
7/13/2011(Santa Elena)Declares Commercial Production at Santa Elena Mine; Pours 74...
6/7/2011(La Joya Durango)Reports Additional La Joya Drill Results, More High Grade Si...
4/26/2011(Santa Elena)Files NI 43-101 Technical Report for Santa Elena Reserve Up...
4/13/2011(Santa Elena)Santa Elena Mine Commissioning Phase Update, Silver And Gold...
4/12/2011(Santa Elena)Announces Santa Elena Expansion Plan Net Present Value of US...
3/13/2011(La Joya Durango)Reports La Joya Initial Drill Results; Up to 19.2 Metres of ...
1/6/2011(Santa Elena)Santa Elena Mine Start-Up Phase Update
12/1/2010(La Joya Durango)Acquires New Major Mexico Property
8/14/2009(Santa Elena)to Acquire 100% of the Santa Elena Project
6/9/2009(Santa Elena)Announces Agreement With MacQuarie Bank Limited For US12.5 M...
8/15/2008Receives Environmental Impact Assessment Approval; NI43-10...
6/30/2008(Santa Elena)Santa Elena prefeasibility study completed
6/26/2008(Santa Elena)Pre-Feasibility Results at Santa Elena, Mexico
6/5/2008(Santa Elena)Main Zone Expansion Drilling 11.2 metres (36.73 feet) gradin...
5/21/2008(Santa Elena) Submits Environmental Impact Assessment; Receives Land Use ...
4/8/2008(Santa Elena)Continues to Expand Main Zone at Santa Elena, Mexico
2/21/2008(Santa Elena)Updates Progress at the Santa Elena Project, Mexico
1/9/2008(Santa Elena)Continues to Intercept High Grade Gold and Silver at the San...
1/4/2008(Santa Elena)Resource Expansion at Santa Elena and Cruz de Mayo
12/20/2007(Santa Elena)Secures Surface Rights for Santa Elena Project, Mexico
11/29/2007(Santa Elena)Intercepts 32.9 Metres of 367 gpt (10.7 Ounces) Silver & Sil...
11/15/2007(Cruz De Mayo)SilverCrest Announces Resource Increase Indicated Resources ...
10/18/2007(Santa Elena)SilverCrest Intercepts 51.4 Metres of 1.53 gpt Gold and 126 ...
9/26/2007(Santa Elena) Continues to Expand Santa Elena Deposit, Northern Mexico
9/11/2007(Santa Elena)Mobilizes Second Drill Rig to Santa Elena Project, Mexico
9/6/2007(Santa Elena)Significantly Expands Mineralization at Santa Elena Project,...
7/26/2007(Cruz De Mayo)Reports Final RC Drill Results and Preliminary Metallurgy at...
7/5/2007(Cruz De Mayo)Reports More Silver at Cruz de Mayo, Mexico
5/24/2007(Cruz De Mayo)Reports New Silver Discovery at Cruz de Mayo, Mexico
5/10/2007(Cruz De Mayo)Updates Progress at the Santa Elena Project, Mexico
Corporate news of SilverCrest Mines
2/24/2014Graduates to Toronto Stock Exchange Trading Commences Februa...
2/20/2014Announces $20 Million Bought Deal
2/17/2014(Santa Elena)Confirms U/G High Grades at Santa Elena 11.6m @ 5.83 gpt Au ...
12/14/2013Announces Grant of Stock Options
11/19/2013SilverSeek LIVE! Wed. Nov, 20th @ 2PM EST -- David Morgan (S...
10/21/2013Announces Positive La Joya Preliminary Economic Assessment B...
7/12/2013Arranges $40 Million Credit Facility with Scotiabank
5/27/2013Completes Exercise of La Joya West Option
5/27/2013Completes Exercise of La Joya West Option
4/25/2013Announces 2013 Annual Meeting and Adoption of Corporate Gove...
4/8/2013(Santa Elena)Continues to Expand Santa Elena Deposit More High Grade Inte...
10/30/2012Closes $34.5 Million Prospectus Offering, Over-Allotment Opt...
10/5/2012Announces Increase in Bought Deal to $30 Million
10/5/2012Announces $26.1 Million Bought Deal
9/27/2012Reports High Grade Surface Sampling and Additional Drill Res...
8/22/2012ANNOUNCES TRADING ON NYSE MKT TO COMMENCE AUGUST 27=2C 2012
7/17/2012Reports 50m @ 151.8 gpt Ag Eq* at La Joya Main Mineralized...
6/29/2012Reports Annual General Meeting Results
5/7/2012Reports 127.4m @ 65.6 gpt Ag Eq* at La Joya Expands Main M...
2/21/2012Files NI43=2D101 Resource Report for La Joya Property
1/30/2012Presenting At the Silverseek Online Forum
1/9/2012Retires Bank Debt Ahead of Schedule
10/7/2011Commences Trading on OTCQX
6/17/2011Announces Appointment of New Director, Reconfirmation of Sha...
5/31/2011Files Form 40-F Registration Statement with SEC
7/29/2010Initial Gold & Silver Production Imminent
5/6/2010& Goldsource Appoint Director of Communications
9/22/2009Analyst Coverage by Jennings Capital
7/13/2009New office
6/24/2009Eric Fier on Newsmakers
11/17/2008At Hard Assets Conference, San Francisco
9/24/2008New Video Tour: Underground Silver Deposits at Santa Elena
7/13/2008Report
7/10/2008Signs Agreement For $3.0 Million Feasibility Finance Facilit...
4/21/2008Initiation Report
3/1/2008Announces US$3.0 Million Feasibility Finance Facility & Prop...
9/19/2007Intercepts 10.1 Metres of 6.53 gpt Gold and 218.7 gpt Silve...
3/8/2007Completes Second Phase Drill Program at Cruz de Mayo, Mexico
Comments closed
 
Latest comment posted for this article
Be the first to comment
Add your comment
TSX-V (SVL.V)Other OTC (STVZF)
2.66-0.37%1.89-4.55%
TSX-V
CA$ 2.66
02/21 17:00 -0.010
-0.37%
Prev close Open
2.67 2.69
Low High
2.63 2.71
Year l/h YTD var.
 -  -
52 week l/h 52 week var.
- -  2.66 -%
Volume 1 month var.
493,509 -%
24hGold TrendPower© : 27
Produces Gold - Silver
Develops Gold - Silver - Zinc
Explores for Silver
 
 
 
Analyse
Interactive chart Add to compare
Interactive
chart
Print Compare Export
Last updated on : 10/18/2010
You must be logged in to use the porfolio and watchlists (free)
Top Newsreleases
MOST READ
Annual variation
DateVariationHighLow
 
5 years chart
 
3 months chart
 
3 months volume chart
 
 
Mining Company News
Plymouth Minerals LTDPLH.AX
Plymouth Minerals Intersects Further High Grade Potash in Drilling at Banio Potash Project - Plannin
AU$ 0.12-8.00%Trend Power :
Santos(Ngas-Oil)STO.AX
announces expected non-cash impairment
AU$ 7.69-0.39%Trend Power :
Oceana Gold(Au)OGC.AX
RELEASES NEW TECHNICAL REPORT FOR THE HAILE GOLD MINE
AU$ 2.20+0.00%Trend Power :
Western Areas NL(Au-Ni-Pl)WSA.AX
Advance Notice - Full Year Results Conference Call
AU$ 3.86+0.00%Trend Power :
Canadian Zinc(Ag-Au-Cu)CZN.TO
Reports Financial Results for Q2 and Provides Project Updates
CA$ 0.12+4.55%Trend Power :
Stornoway Diamond(Gems-Au-Ur)SWY.TO
Second Quarter Results
CA$ 0.02+100.00%Trend Power :
McEwen Mining(Cu-Le-Zn)MUX
TO ACQUIRE BLACK FOX FROM PRIMERO=C2=A0
US$ 11.04+1.38%Trend Power :
Rentech(Coal-Ngas)RTK
Rentech Announces Results for Second Quarter 2017
US$ 0.20-12.28%Trend Power :
KEFIKEFI.L
Reduced Funding Requirement
GBX 0.54-2.53%Trend Power :
Lupaka Gold Corp.LPK.V
Lupaka Gold Receives First Tranche Under Amended Invicta Financing Agreement
CA$ 0.06+0.00%Trend Power :
Imperial(Ag-Au-Cu)III.TO
Closes Bridge Loan Financing
CA$ 2.52+6.78%Trend Power :
Guyana Goldfields(Cu-Zn-Pa)GUY.TO
Reports Second Quarter 2017 Results and Maintains Production Guidance
CA$ 1.84+0.00%Trend Power :
Lundin Mining(Ag-Au-Cu)LUN.TO
d Share Capital and Voting Rights for Lundin Mining
CA$ 16.05+2.62%Trend Power :
Canarc Res.(Au)CCM.TO
Canarc Reports High Grade Gold in Surface Rock Samples at Fondaway Canyon, Nevada
CA$ 0.24+2.13%Trend Power :
Havilah(Cu-Le-Zn)HAV.AX
Q A April 2017 Quarterly Report
AU$ 0.20+7.89%Trend Power :
Uranium Res.(Ur)URRE
Commences Lithium Exploration Drilling at the Columbus Basin Project
US$ 6.80-2.86%Trend Power :
Platinum Group Metals(Au-Cu-Gems)PTM.TO
Platinum Group Metals Ltd. Operational and Strategic Process ...
CA$ 1.90+1.60%Trend Power :
Devon Energy(Ngas-Oil)DVN
Announces $340 Million of Non-Core Asset Sales
US$ 51.43-0.46%Trend Power :
Precision Drilling(Oil)PD-UN.TO
Announces 2017Second Quarter Financial Results
CA$ 8.66-0.35%Trend Power :
Terramin(Ag-Au-Cu)TZN.AX
2nd Quarter Report
AU$ 0.03+0.00%Trend Power :