Ivanhoe Mines Ltd.

Published : November 18th, 2013

announces updated independent
Preliminary Economic Assessment of its Kamoa copper discovery

( 0 vote, 0/5 ) Print article
  Article Comments Comment this article Rating Follow Company  
0
Send
0
comment
Keywords :   Bushveld | Canada | Cobalt |

www.ivanhoemines.com
November 18, 2013

Ivanhoe Mines announces updated independent
Preliminary Economic Assessment of its Kamoa copper discovery

Kamoa mine projected to have the highest grade among the world's
largest copper mines and also to be one of the world's
lowest-cost copper producers

Estimated pre-tax NPV of US$4.3 billion and an 18.5% IRR



LUBUMBASHI, DEMOCRATIC REPUBLIC OF CONGO � Robert Friedland, founder and Executive Chairman of Ivanhoe Mines (TSX: IVN), and Lars-Eric Johansson, Chief Executive Officer, today welcomed the positive findings of an independent, Preliminary Economic Assessment of the company's major Kamoa copper discovery near the mining centre of Kolwezi in the Democratic Republic of Congo's southern province of Katanga.

"The assessment confirms that Kamoa truly is in a class by itself in terms of the world's known, undeveloped copper deposits," said Mr. Friedland.

"Kamoa has the rare combination of a very high copper grade and very large tonnage, qualities that position Kamoa to become a substantial copper producer with one of the lowest cash costs anywhere in the world. This thorough, independent assessment gives us added confidence as we proceed with the planning of our next steps to advance Kamoa's development into a world-class copper mine."

Highlights of the Preliminary Economic Assessment (PEA):
  • A large mine and smelter would be developed using a two-phased approach.
  • A smaller-scale start-up would establish an operating platform to support expansion.
  • Early cash flows would be generated from the sale of high-grade copper concentrate.
  • Low pre-production capital requirement of approximately US$1.4 billion.
  • Steady-state production target of 300,000 tonnes per year of blister copper, which would establish Kamoa as one of the world's largest copper mines, with the highest grade.
  • Cash costs of US$1.18 per pound of copper would rank Kamoa near the bottom of the global cash-cost curve.
  • Pre-tax Net Present Value, at an 8% discount rate, of US$4.3 billion.
  • After-tax Net Present Value, at an 8% discount rate, of US$2.5 billion.
  • Pre-tax internal rate of return of 18.5%; after-tax IRR of 15.2%.
The PEA, which conforms with the requirements of Canada's National Instrument 43-101, was prepared by AMC Consultants, AMEC E&C Services (AMEC), SRK Consulting, Stantec Consulting International, Hatch and Golder Associates Africa. The full technical report will be filed on SEDAR at www.sedar.com and Ivanhoe Mines' website at www.ivanhoemines.com within 45 days of the issuance of this news release.

Two-phased approach to the development of a large mine and smelter

The PEA reflects a two-phased approach to development of the Kamoa Project. The first phase of mining would target high-grade copper mineralization from shallow, underground resources to yield a high-value concentrate. The second phase would entail a major expansion of the mine and mill and construction of a smelter to produce blister copper.

The PEA contemplates the establishment of a conventional copper mine and concentrator complex at Kamoa with an initial mining rate and concentrator capacity of three million tonnes per year. Initial mill feed would come from the Kansoko Sud mineralized zone and lead into the Centrale area of Kamoa's mineralized zones.

The initial mining rate and concentrate feed capacity of three million tonnes per year would be followed in Year 5 by an additional expansion of eight million tonnes per year in concentrator capacity and the construction of an on-site smelter with a capacity to produce 300,000 tonnes per year of blister copper. In addition, an estimated 1,600 tonnes of sulphuric acid per day would be produced as a by-product in the copper smelting process.The PEA contemplates that the sulphuric acid produced at Kamoa would be sold to copper-oxide mining operations on the Central African Copperbelt that currently purchase acid from Zambia or from overseas.

The production scenario schedules 326 million tonnes to be mined and milled at an average copper grade of 3.0% copper over a 30-year mine life, producing 7.8 million tonnes of payable blister copper (plus 0.5 million tonnes of payable copper in concentrate, in the initial concentrate phase) over the life of the project.

The PEA is preliminary in nature and includes an economic analysis that is based, in part, on Inferred Mineral Resources. Inferred Mineral Resources are considered too speculative geologically to have the economic considerations applied to them that would allow them to be categorized as Mineral Reserves, and there is no certainty that the results will be realized. Mineral Resources do not have demonstrated economic viability and are not Mineral Reserves.

Positive preliminary economic analysis demonstrates Kamoa's exceptional nature

The preliminary economic analysis is based on a long-term price assumption of US$3.00 per pound for copper and a sales price for sulphuric acid of US$250 per tonne. The economic analysis returns an after-tax Net Present Value (NPV), at an 8% discount rate, of US$2.55 billion. It has an after-tax internal rate of return (IRR) of 15.2% and a payback period of 8.4 years. The life-of-mine average total cash cost, after credits, is US$1.18 per pound of copper.

Table 1: Summary of financial results.
    Before After
    Taxation Taxation
Net Present Value (US$ billion) Undiscounted 25.57 17.70
4.0% 10.37 6.85
6.0% 6.68 4.23
8.0% 4.29 2.55
10.0% 2.70 1.44
12.0% 1.64 0.71
IRR - 18.5% 15.2%
Project Payback (years) - 7.64 8.43


Table 2: Mining and processing production statistics.
  Total LOM Conc. Phase Average* Blister Phase Average* LOM Average
 
 
Total Plant Feed Mined ('000 t) 326,064 2,417 12,183 10,869
Quantity Plant Feed Treated ('000 t) 326,064 3,000 12,243 10,869
Copper Feed Grade (%) 3.00 4.00 2.94 -
Copper Recovery (%) 85.91 85.87 85.91 -
Concentrate Produced ('000 t) 21,802 258 805 727
Copper Concentrate Grade (%) 39.00 40.40 38.91 -
Contained Metal in Concentrate
Copper ('000t) 8,502 104 313 283
Copper (Mlb) 18,744 230 691 625
Payable Metal
Copper ('000t) 8,312 103 306 277
Copper (Mlb) 18,325 227 675 611

* Excludes Year 5 (2022), which is a transition year between concentrate and blister production. Mining averages on Conc. Phase includes Years -2 and -1.

Table 3: Unit operating costs.
  US$/lb Payable Copper
  LOM Average Conc. Phase* Blister Phase*
 
Mine Site Cash Cost 1.05 0.85 1.07
Realization Cost 0.33 0.91 0.29
Total Cash Costs Before Credits 1.38 1.76 1.36
Acid Credits 0.20 - 0.21
Total Cash Costs After Credits 1.18 1.76 1.15

* Concentrate and blister averages exclude Year 5 (2022), which is a transition year between concentrate and blister.

Steady-state production from Year 6 onward of 306,000 tonnes per year of blister copper would establish the Kamoa Project as one of the world's largest copper mines. Kamoa also would have the highest average grade among the 20 largest copper mines currently in production or expected to be in production, according to data from Wood Mackenzie, an international industry research and consulting group.

Figure 1: Annual copper production for top 20 mines and undeveloped projects globally.

Source: Wood Mackenzie

Figure 2: Annual copper production for all undeveloped projects globally.

Source: Wood Mackenzie

Average cash costs of US$1.18 per pound of copper (after sulphuric acid credit), over the life of the mine, rank the Kamoa Project near the bottom of the 2013 cash-cost curve for copper mines globally.

Figure 3: 2013E copper cash costs.


(1) Represents C1 cash costs that reflect the direct cash costs of producing paid metal incorporating mining, processing and offsite realization costs, having made appropriate allowance for the co-product revenue streams.

Source: Wood Mackenzie

The estimated capital costs for the Kamoa Project are detailed in Table 4, below.

Table 4: Capital investment summary.
US$M Concentrate Phase Blister Phase Sustaining Total
Mining
Underground Mining 259 1,125 1,864 3,248
Capitalized Pre-Production 41 - - 41
Subtotal 301 1,125 1,864 3,290
Power & Smelter
Smelter - 539 297 836
Power 141 100 - 241
Subtotal 141 639 297 1,077
Concentrate & Tailings
Concentrator 214 312 207 734
Subtotal 214 312 207 734
Infrastructure
Infrastructure 81 133 61 274
TSF 73 181 - 254
Accommodations 75 10 25 111
Rolling Stock & Spur - 46 - 46
Subtotal 229 370 86 685
Indirects
EPCM 79 220 - 299
Temporary Facilities 43 78 - 121
Subtotal 122 298 - 420
Owners Cost (incl. Drilling & Studies)
Owners Cost 103 67 - 171
Closure - - 166 166
Subtotal 103 67 166 337
Capital Expenditure Before Contingency 1,110 2,812 2,621 6,543
Contingency 292 717 - 1,009
Capital Expenditure After Contingency 1,402 3,529 2,621 7,552


Kamoa discovery forms an extension of the Central African Copperbelt

Ivanhoe Mines' Kamoa copper project, located in the Democratic Republic of Congo's (DRC) Province of Katanga, is a newly discovered, very large, stratiform copper deposit with adjacent prospective exploration areas within the Central African Copperbelt, approximately 25 kilometres west of the town of Kolwezi and about 270 kilometres west of the provincial capital of Lubumbashi.

Ivanhoe holds its 95% interest in the Kamoa Project through a subsidiary company, African Minerals Barbados Limited SPRL (AMBL). A 5%, non-dilutable interest in AMBL was transferred to the DRC government on September 11, 2012, for no consideration, pursuant to the DRC Mining Code.

The company also has offered to sell an additional 15% interest to the DRC on commercial terms to be negotiated.

Access to the Kamoa Project from Kolwezi is via unsealed roads. The road network throughout the project area has been upgraded by Ivanhoe to provide reliable drill and logistical access. A portion of the 1,500-kilometre-long railway line and electric power line from Lubumbashi to the Angolan town of Lobito passes approximately 10 kilometres to the north of the project area.

Kamoa was discovered by Ivanhoe in 2008, west of the known limit of the Central African Copperbelt in the DRC. The deposit lies under cover and does not outcrop. The copper mineralization identified at Kamoa is typical of sediment-hosted stratiform copper deposits and is similar to the Polish Kupferschiefer and Zambian Ore Shale deposits. The Kamoa discovery occurs within a regional, northeast-southwest-trending structural corridor that has been traced for approximately 35 kilometres. Copper mineralization at Kamoa has been defined over an area of 20 kilometres by 15 kilometres. The dip of the mineralized body ranges from 0� to 10� near-surface above the Kamoa dome, to 15� to 20� on the flanks of the dome.

In August 2012, the DRC approved Ivanhoe's application to convert three exploration permits at Kamoa to exploitation permits (mining licences). The Kamoa Mining Licences, covering a total of 400 square kilometres, allow the company to develop and exploit copper and other minerals for a renewable, 30-year term.

A regional exploration program is ongoing, with drilling planned at prospective targets on the more than 9,000 square kilometres of exploration tenements held by Ivanhoe in a variety of geological settings within Katanga Province.

Estimating Kamoa's Mineral Resources

Resources were classified using a nominal, 400-metre drillhole spacing for classification of Indicated and a nominal, 800-metre spacing for Inferred.

AMEC used a 1% copper cut-off grade as a base case to declare Mineral Resources. This choice of cut-off is based on many years of experience on the Zambian Copperbelt at mines with similar mineralization, such as Konkola, Nchanga, Nkana and Mufulira, where the 1% cut-off is a natural cut-off. The 1% copper cut-off also is a "natural" cut-off for the Kamoa deposit, with most single mineralized zone (SMZ) intercepts (selected using the criteria of a minimum copper grade of 1% copper and a minimum downhole length of three metres) grading a few tenths of a percent copper above and below the composite and well over 1% copper within the SMZ composite. To test the 1% cut-off grade and various sensitivity cases for the purposes of assessing reasonable prospects of economic extraction, AMEC performed a conceptual analysis based on the metallurgical recovery algorithms, operating costs and economic parameters.

The Mineral Resources have been defined taking into account the 2010 CIM Definition Standards for Mineral Resources and Mineral Reserves. Dr. Harry Parker, SME Registered Member, and Gordon Seibel, SME Registered Member, both employees of AMEC, are the Qualified Persons for the Mineral Resource estimates.

Mineral Resources are stated in terms of total copper (Cu). Mineral Resources are reported at a base-case, total copper cut-off grade of 1% copper and a minimum vertical thickness of three metres, and are summarized in Table 5.

Table 5: Indicated and Inferred Mineral Resources, Domain 1.
Category Tonnage
(Mt)
Area
(km2)
Cu
(%)
True Thickness (m) Contained Copper
(kt)
Contained Copper (billion lbs)
Indicated 739 50.5 2.67 5.20 19,700 43.5
Inferred 227 20.5 1.96 3.84 4,460 9.8
Notes:
  1. Domain 1 at 1% Cu cut-off grade.
  2. Mineral Resources have an effective date of 10 December 2012. Harry M. Parker and Gordon Seibel, both SME Registered Members, are the Qualified Persons responsible for the Mineral Resource estimates. The Mineral Resource estimate was prepared by Mr. Seibel.
  3. Mineral Resources are reported using a total copper (Cu) cut-off grade of 1% Cu and a minimum assumed thickness of 3 metres. A 1% Cu cut-off grade is typical of analogue deposits in Zambia. There are reasonable prospects for economic extraction under assumptions of a copper price of US$3.30/lb; sulphuric acid credits of US$300/t of acid produced; employment of underground mechanized room-and-pillar mining methods; and that copper concentrates will be produced and smelted.
  4. Reported Mineral Resources contain no allowances for hanging wall or footwall contact boundary loss and dilution. No mining recovery has been applied.
  5. The Mineral Resources include the mineralization above a 1% total copper cut-off that is potentially amenable to open-pit mining.
  6. Tonnage and grade measurements are in metric units. Contained copper tonnes are reported using metric units; contained copper pounds use imperial units.
  7. True thickness ranges from 2.4 metres to 17.6 metres for Indicated Mineral Resources and 2.8 metres to 8.4 metres for Inferred Mineral Resources.
  8. Depth of mineralization below the surface ranges from 10 metres to 1,320 metres for Indicated Mineral Resources and 20 metres to 1,560 metres for Inferred Mineral Resources. Indicated Mineral Resources are supported by drilling at a =400-metre spacing; Inferred Mineral Resources are supported by drilling at 400-metre to 800-metre spacing.
  9. Tonnages are rounded to the nearest million tonnes; grades are rounded to two decimal places.
  10. Rounding as required by reporting guidelines may result in apparent summation differences between tonnes, grade and contained metal content.
  11. Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability.
Additional tonnage estimated in exploration target

The area inside the model perimeter surrounding the Indicated and Inferred Mineral Resources is considered an exploration target. The ranges of the exploration target tonnages and grades are summarized in Table 6.

Tonnage and grade ranges were estimated using an inverse distance to the fifth power for Domain 2 and applying a �20% variance to the resulting tonnage and grade estimate.

AMEC cautions that the potential quantity and grade of exploration targets are conceptual in nature and that it is uncertain if additional drilling will result in the exploration targets being delineated as a Mineral Resource.

Table 6: Tonnage and grade ranges for Exploration Targets.
Target Low-range Tonnage (Mt) High-range Tonnage (Mt) Low-range Grade (% Cu) High-range Grade (% Cu)
Total 520 790 1.6 2.5


Figure 4: Kamoa plan map showing total copper grade for Indicated and Inferred Mineral Resources.

The area between the Resources (colored blocks) and model limit is considered to be the Exploration Target.

Figure 5: Contained copper in high-grade deposits (Measured & Indicated Mineral Resources, inclusive of Mineral Reserves, and Inferred Mineral Resources; with grades above 2.5% copper).

Source: Wood Mackenzie

Figure 6: Contained copper in undeveloped deposits (Measured & Indicated Mineral Resources, inclusive of Mineral Reserves, and Inferred Mineral Resources).

Source: Wood Mackenzie

Focus of current drilling program

Ivanhoe is undertaking a drilling program that encompasses metallurgical, geotechnical, civil geotechnical and hydro-geological holes. Additional planned holes will be a combination of exploration, infill and delineation to target potential upgrades in Mineral Resource confidence categories and zones of additional mineralized material. The focus of this drilling will be down-dip expansion of the Kansoko trend, extension of the mineralization to the western extents of the mining licence and exploration drilling at Kakula for hypogene and shallow, open-pittable supergene targets.

Additional engineering drill holes, including metallurgical drilling, will be completed. Sterilization drilling using a Land Cruiser-mounted Diamond-drill rig is planned. Drill holes that will target sources of aggregate for construction purposes also are planned.

Large-scale underground mining to use room-and-pillar and drift-and-fill methods

Given the favourable mining characteristics of the Kamoa Deposit as derived from the December 2012 mineral resource - including its relatively undeformed, continuous mineralization, local continuity between closely spaced drillholes and flat-to-moderate dips - it is considered amenable to large-scale, mechanized, room-and-pillar or drift-and-fill mining. The low dip and the flat, geometry of the resource make it conducive to room-and-pillar mining in the shallow portions of the deposit, transitioning to drift-and-fill mining in the deeper sections. These conventional mining methods are the accepted standards for mining deposits such as Kamoa.

A minimum mining thickness of 3.5 metres was used for the PEA. Any blocks less than 3.5 metres thick were diluted to 3.5 metres using the average grade of the adjacent hanging wall and footwall blocks. Room-and-pillar panels are designed to be 80 metres wide and 500 metres long, with in-panel extraction ratios ranging from 60%-80%, depending on the panel depth below surface. Partial extraction of the barrier pillars (up to 50%) is planned at the end of mining of each section. The overall extraction ratio in the room-and-pillar areas is expected to be between 56%-82%, depending on the depth below surface. Higher in-panel extraction ratios of up to 95% are expected within the drift-and-fill areas, with an overall extraction ratio of 85% after partial extraction of barrier pillars.

A strategy of prioritizing higher-grade mining areas early in the mine's life, and then returning to the lower-grade areas later in the mine's life, has been built into the mine plan.

Figure 7: Mining panel layout by mining section.

Source: Stantec

Infrastructure to support a 30-year mine plan

The mine infrastructure for the Kamoa Project has been designed to support a 30-year mine plan, which produces a total of 326 million tonnes to support an annual blister-copper production rate of 300,000 tonnes. The facility design incorporates early access to the Kansoko Sud and the southern portion of Kansoko Centrale, which are higher-grade areas within the deposit. Development of the Kamoa Sud access begins in Year 1 and provides access to Kamoa Sud, Kansoko Centrale and Kansoko Nord mining sections. Later in the mine's life, at Year 16, as the production from the Kansoko Sud mining section is ramping down, production from the Kamoa Nord mining section is scheduled to begin.

The planned accesses to each mining section include a conveyor decline and two access declines. Additional infrastructure requirements, such as surface and underground offices, surface and underground maintenance facilities, ventilation raises and paste backfill plants, are designed to support operations at the blister-copper production rate of 300,000 tonnes per year.

Since the separation between the three portals ranges from 2.2 kilometres to 5.8 kilometres, each site will require separate infrastructures.

Development of the main access declines will be in mineralized material whenever possible, but some of the development will be in unmineralized waste.
Building of underground mine-access decline planned to begin early next year

Excavation of the first mine-access decline at Kansoko Sud is expected to begin early next year. The decline will provide access to high-grade, near-surface copper resources that are targeted for the planned first phase of production.

Metallurgical testwork and concentrator design

Circuit development work during 2011 to 2013 primarily was conducted at Xstrata Process Support (XPS) Laboratories in Sudbury, Ontario. A flow sheet was developed that was tailored to the fine-grained nature of the deposit. The circuit relied on a traditional mill-float-mill-float (MF2) approach to partially liberate particles, followed by fine regrinding of concentrates to achieve a concentrate grade suitable for smelting. Separate treatment of the primary and secondary rougher concentrates allowed for separately-optimized cleaner flotation of fast and slow species.

This configuration became known as the Milestone flow sheet and forms the basis of the Net Smelter Return (NSR) model and mine plan. The circuit was tested on various composites from across the resource and was able to achieve a recovery of 85.4% and a copper grade of 32.8% for hypogene material, and a recovery of 83.2% and copper grade of 45.1% for supergene material.

In the first half of 2013, the focus of development work shifted toward a reduction in the silica content of the final concentrate. Adjustments were made to the re-agent dosages, as well as the grinding media type, resulting in an improvement to 86.7% recovery at a 37.0% copper grade for hypogene material, and 82.9% recovery at a 51.4% copper grade for supergene material. Silica levels in the final concentrate also dropped from 19.1% to 13.1% for hypogene and from 26.0% to 18.1% for supergene.

Although these improvements were not realized in time to be incorporated into the mine plan and NSR, the updated hypogene results were incorporated into the design basis for the concentrator and smelter and form the basis of the PEA and associated economic results.

The concentrator is expected to be constructed in two phases and consists of a three million tonnes per year run-of-mine concentrator during the first four years of operation, followed by the commissioning of an additional eight million tonnes per year run-of-mine concentrator in Year 5.

The design incorporates a three-stage crushing circuit (underground primary crushing, run-of-mine stockpiling and secondary and tertiary crushing at the concentrator) to feed the primary mill-feed stockpile. The primary and secondary ball mills would operate in closed circuit with hydrocyclones. The flotation circuit would consist of primary and secondary rougher flotation, with a secondary grind stage located between the primary and secondary rougher flotation stages. The cleaner flotation circuit would consist of primary cleaners with scavengers and re-cleaners, and secondary cleaners with re-cleaners. The cleaner circuit would incorporate concentrate regrind stages for both the primary and secondary circuits. The final concentrate would be thickened before it is pumped to the concentrate filter(s).

During the initial years of production, the concentrate would be bagged in a bagging plant to facilitate transport. Following commissioning of the smelter, the concentrate filter cake would be conveyed to the smelter's concentrate storage and blending area. The secondary rougher tails and multiple non-float streams from the secondary cleaner circuit report to the final tailings facility.

Smelter and acid plant details

The smelting process proposed in the PEA is based on the use of Direct-to-Blister flash smelting technology (DBF). For slag cleaning, a two-stage electric furnace process is applied. The smelter has a concentrate smelting capacity of 800,000 tonnes per year, which corresponds to a copper product capacity of 300,000 tonnes per year.

In the DBF concept, copper concentrate is processed by flash smelting to produce blister copper (approximately 98% copper) in a single smelting stage. Blister copper is transferred via launders to refining furnaces, after which it is cast as final product.

The function of the sulphuric-acid plant is to receive the SO2 and SO3 containing process gases from the direct-to-blister and refining furnaces and to produce concentrated sulphuric acid from these gases. The estimated average sulphuric-acid production is 1,600 tonnes per day and the estimated product quality is 98.5% sulphuric acid. A detailed marketing study has been carried out for the DRC's Province of Katanga and the Zambian Copperbelt. The Congolese Copperbelt is a net acid-consuming area. The majority of the copper and cobalt in the area is in the form of copper or cobalt oxides, and a leach solvent extraction-electrowinning process is utilized to produce final product. This process consumes acid and a number of the operations on the Copperbelt run sulphur-burning acid plants to produce acid; others purchase acid from Zambia or from overseas. Operators in the DRC reportedly are paying US$300-$400 per tonne and prices have been up to $800 per tonne in previous years. It is estimated that the full production cost of producing sulphuric acid in a sulphur-burning acid plant in Katanga is approximately US$246 per tonne, excluding the capital cost of the sulphur-burning acid plant. For the purpose of the Kamoa PEA, a long-term acid credit of US$250 per tonne was used.

Agreement to ensure supply of electrical power from DRC grid

Power for the Kamoa Project is planned to be sourced from the DRC grid following the rehabilitation of three existing hydro power plants: Koni, Mwadingusha and Nzilo 1. A financing agreement between Ivanhoe Mines and DRC's state-owned power company, La Soci�t� Nationale d'Electricit� (SNEL), has been finalized and initialled by the two parties for the rehabilitation of these plants to secure a sustainable power supply to meet the requirements of Kamoa's planned mine and smelter development. Kamoa will be powered by electricity from the national grid and on-site diesel generators until rehabilitation of the existing plants has been completed.

Qualified persons, quality control and assurance

The following companies have undertaken work in preparation of the PEA:
  • AMC Consultants - Overall report preparation, open-pit potential and financial model.
  • AMEC - Mineral Resource estimation.
  • SRK Consulting - Mine geotechnical recommendations.
  • Stantec Consulting International - Underground mine plan.
  • Hatch - Process and infrastructure.
  • Golder Associates Africa - Environmental, hydrology, hydrogeology, geochemistry and Tailings Storage Facility (TSF).
The independent qualified persons responsible for preparing the Kamoa Preliminary Economic Assessment are Bernard Peters, B. Eng. (AMC); Dr. Harry Parker (AMEC); Gordon Seibel (AMEC); Jarek Jakubec, C. Eng., (SRK); Mel Lawson, B. Eng. (Stantec); Arne Weissenberger, P.Eng. and Francois Marais, P.Eng. (Golder).

The scientific and technical information in this release has been reviewed and approved by Stephen Torr, P.Geo., Ivanhoe Mines' Vice President, Project Geology and Evaluation, a Qualified Person under the terms of National Instrument 43-101. Mr. Torr has verified the technical data disclosed in this news release.

Data verification

AMEC reviewed the sample chain of custody, quality assurance and control procedures, and qualifications of analytical laboratories. AMEC is of the opinion that the procedures and QA/QC are acceptable to support Mineral Resource estimation. AMEC also audited the assay database, core logging, and geological interpretations on a number of occasions between 2009 and 2013 and found no material issues with the data as a result of these audits.

In the opinion of the AMEC QPs, the data verification programs undertaken on the data collected from the Kamoa Project support the geological interpretations, and the analytical and database quality and the data collected can support Mineral Resource estimation.

About Ivanhoe Mines

Ivanhoe Mines, with offices in Canada, the United Kingdom and South Africa, is advancing and developing its three principal projects:
  • The Kamoa copper discovery in a previously unknown extension of the Central African Copperbelt in the DRC's Province of Katanga.
  • The Platreef Discovery of platinum, palladium, nickel, copper, gold and rhodium on the Northern Limb of the Bushveld Complex in South Africa.
  • The historic, high-grade Kipushi zinc, copper and germanium mine, also on the Copperbelt in the DRC, that is being dewatered and upgraded to support a future return to production of copper, zinc and other metals following a care-and-maintenance program conducted between 1993 and 2011.
Ivanhoe Mines also is evaluating other opportunities as part of its objective to become a broadly based, international mining company.

Information contacts

Investors
    Bill Trenaman +1.604.331.9834

Media
    North America: Bob Williamson +1.604.512.4856
    South Africa: Jeremy Michaels +27.11.088.4300

Website www.ivanhoemines.com


FORWARD-LOOKING STATEMENTS

Statements in this release that are forward-looking statements are subject to various risks and uncertainties concerning the specific factors disclosed here and elsewhere in the company's periodic filings with Canadian securities regulators. When used in this document, the words such as "could," "plan," "estimate," "expect," "intend," "may," "potential," "should" and similar expressions, are forward-looking statements. Information provided in this document is necessarily summarized and may not contain all available material information.

The results of the PEA represent forward-looking information. Statements in this release that constitute forward-looking statements or information include, but are not limited to: statements regarding the Kamoa mine is projected to have the highest grade among the world's largest copper mines; statements regarding Kamoa to be one of the world's lowest cost copper producers; statements regarding early cash flows from the sale of high-grade copper concentrate; statements regarding cash costs of US$1.18/lb of copper would rank Kamoa near the bottom of the global cash-cost curve; statements regarding estimated NPVs and IRRs; statements regarding the additional planned drilling in the current drill program; statements regarding mine infrastructure; statements regarding the excavation of the first mine-access decline at Kansoko Sud is expected to begin early next year; statements regarding metallurgical testwork and concentrator design; statements regarding planned smelter and acid plant; statements regarding the planned supply of electrical power.

The forward-looking information also includes metal price assumptions, cash flow forecasts, projected capital and operating costs, metal recoveries, mine life and production rates, and other assumptions used in the PEA. Readers are cautioned that actual results may vary from those presented. The factors and assumptions used to develop the forward-looking information, and the risks that could cause the actual results to differ materially are presented in the body of the Technical Report that will be filed on SEDAR at www.sedar.com and Ivanhoe Mines' website at www.ivanhoemines.com within 45 days of this news release.

All such forward-looking information and statements are based on certain assumptions and analyses made by Ivanhoe Mines' management in light of their experience and perception of historical trends, current conditions and expected future developments, as well as other factors management believes are appropriate in the circumstances. These statements, however, are subject to a variety of risks and uncertainties and other factors that could cause actual events or results to differ materially from those projected in the forward-looking information or statements. Important factors that could cause actual results to differ from these forward-looking statements include those described under the heading "Risk Factors" in the company's most recently filed MD&A. Readers are cautioned not to place undue reliance on forward-looking information or statements.


Click here to read the news release in PDF Format


HOME CORPORATE PROJECTS NEWS CONTACT

SUBSCRIBE |
� Copyright 2013, Ivanhoe Mines Ltd. All Rights Reserved.
Data and Statistics for these countries : Canada | South Africa | United Kingdom | Zambia | All
Gold and Silver Prices for these countries : Canada | South Africa | United Kingdom | Zambia | All

Ivanhoe Mines Ltd.

PRODUCER
CODE : IVN.TO
CUSIP : 46579N 103
Follow and Invest
Add to watch list Add to your portfolio Add or edit a note
Add Alert Add to Watchlists Add to Portfolio Add Note
ProfileMarket
Indicators
VALUE :
Projects & res.
Press
releases
Annual
report
RISK :
Asset profile
Contact Cpy

Ivanhoe Mines is a gold and copper development stage company based in Singapore.

Ivanhoe Mines produces gold, copper, iron in Australia and in Kazakhstan, develops copper and gold in Mongolia, and holds various exploration projects in Australia.

Its main assets in production are SAVAGE RIVER in Australia and BAKYRCHIK in Kazakhstan, its main asset in development is OYU TOLGOI in Mongolia and its main exploration properties are MONYWA in Myanmar and CLONCURRY in Australia.

Ivanhoe Mines is listed in Canada, in Germany and in United States of America. Its market capitalisation is CA$ 16.0 billions as of today (US$ 11.7 billions, € 10.9 billions).

Its stock quote reached its lowest recent point on January 29, 2016 at CA$ 0.53, and its highest recent level on April 26, 2024 at CA$ 20.36.

Ivanhoe Mines has 785 229 952 shares outstanding.

Your feedback is appreciated, please leave a comment or rate this article.
Rate : Average note :0 (0 vote) View Top rated
 
In the News and Medias of Ivanhoe Mines Ltd.
11/14/2018Ivanhoe Mines jumps as it finds new copper-rich area in Cong...
Annual reports of Ivanhoe Mines Ltd.
Annual Report 2007
Financings of Ivanhoe Mines Ltd.
9/23/2013announces non-brokered private placement
7/27/2012closes successful rights offering yielding US$1.8 billion i...
7/27/2012Closes Successful Rights Offering Yielding US$1.8 Billion in...
6/8/2012Files Final Prospectus for Rights Offering
5/23/2012Files Preliminary Prospectus for Rights Offering and Amends ...
4/19/2012announces agreement to proceed with a US$1.8 billion rights ...
1/18/2012Negotiates an Additional US$1.8 Billion Bridge Financing as ...
Nominations of Ivanhoe Mines Ltd.
6/29/2012shareholders appoint two new directors and approve new compa...
5/11/2012appoints new chairman and additional director
5/8/2012Appoints Four New Directors and Accepts Resignation of Three...
5/2/2012Board of Directors appoints new chief executive officer and ...
1/27/2012Expects to Maintain a Majority of Independent Directors on t...
7/14/2011Announces Appointment of Rio Tinto Executive Dan Larsen to C...
Financials of Ivanhoe Mines Ltd.
11/16/2015Announces Financial Results And Review Of Operations For The...
11/12/2013Announces Financial Results and Review of Operations for the...
5/16/2012announces financial results and review of operations for the...
3/20/2012Announces 2011 Financial Results and Review of Operations
8/16/2011Announces Financial Results and Review of Operations for the...
5/16/2011Announces Financial Results and Review of Operations for the...
3/29/2011Announces 2010 Financial Results and Review of Operations
5/15/2010Announces Financial Results and Review of Operations for the...
3/29/2008Announces 2007 Financial Results and Review of Operations
3/31/20072006 Financial Results
Project news of Ivanhoe Mines Ltd.
7/5/2016(Kamoa Copper)Excellent copper recoveries and concentrate grades confirmed...
6/20/2016June 20th, 2016 Exceptional grades and widths of mineralizat...
5/19/2016(Kamoa Copper)Kamoa Copper Project initiates major drilling program at the...
5/19/2016May 19th, 2016 Kamoa Copper Project initiates major drilling...
4/19/2016April 6th, 2016 Ivanhoe Mines announces an accelerated infil...
4/6/2016Ivanhoe Mines announces an accelerated infill drilling progr...
3/30/2016Ivanhoe Mines files NI 43-101 technical report for the indep...
1/25/2016Ivanhoe Mines’ exploration team makes major new copper disco...
1/25/2016Ivanhoe Mines’ exploration team makes major new copper disco...
1/25/2016Ivanhoe Mines’ exploration team makes major new copper disco...
9/9/2015Ivanhoe Mines, Laurentian University and the University of L...
6/17/2015Ivanhoe Mines addresses concern of two D.R. Congo ministers ...
6/17/2015Ivanhoe Mines addresses concern of two D.R. Congo ministers ...
6/17/2015Ivanhoe Mines addresses concern of two D.R. Congo ministers ...
6/17/2015Ivanhoe Mines addresses concern of two D.R. Congo ministers ...
6/17/2015Ivanhoe Mines addresses concern of two D.R. Congo ministers ...
6/17/2015Ivanhoe Mines addresses concern of two D.R. Congo ministers ...
6/17/2015Ivanhoe Mines addresses concern of two D.R. Congo ministers ...
6/17/2015Ivanhoe Mines addresses concern of two D.R. Congo ministers ...
6/17/2015Ivanhoe Mines addresses concern of two D.R. Congo ministers ...
6/17/2015Ivanhoe Mines addresses concern of two D.R. Congo ministers ...
6/17/2015Ivanhoe Mines addresses concern of two D.R. Congo ministers ...
6/17/2015Ivanhoe Mines addresses concern of two D.R. Congo ministers ...
6/17/2015Ivanhoe Mines addresses concern of two D.R. Congo ministers ...
6/17/2015Ivanhoe Mines addresses concern of two D.R. Congo ministers ...
6/17/2015Ivanhoe Mines addresses concern of two D.R. Congo ministers ...
5/26/2015Zijin strikes deals with western miners
4/13/2015Ivanhoe Mines reports additional high-grade zinc, copper, si...
3/23/2015China-based Zijin Mining Group to acquire a 9.9% stake in Iv...
1/29/2015Ivanhoe Mines and Ivanplats expand challenge of errors and m...
1/12/2015Ivanhoe Mines backlashes report on its Platreef platinum min...
1/12/2015Ivanhoe Mines and Ivanplats challenge Globe & Mail story abo...
12/18/2013reports dewatering progress at historic Kipushi Mine in D.R....
10/30/2013reports ongoing dewatering at historic Kipushi Mine
10/16/2013reports unprecedented 90-metre intersection of 4.51 grams of...
9/9/2013to begin sinking bulk-sample shaft at its Platreef platinum-...
8/2/2012and Chalco Agree to 30-day Extension for Proportional Takeov...
4/2/2012Aluminum Corporation of China announces its intention to mak...
8/22/2011(Oyu Tolgoi)Gold and Silver to Generate up to 50% of Total Annual Revenu...
8/3/2011(Monywa)Receives Proceeds of US$103 Million from Monywa Trust
6/9/2011(Oyu Tolgoi)by Ivanhoe Mines Reports Construction of the Oyu Tolgoi Copp...
3/14/2011(Oyu Tolgoi)New copper-molybdenum-gold zone discovered on Ivanhoe Mines-...
3/3/2011(Oyu Tolgoi)Silver Production at Ivanhoe Mines' Oyu Tolgoi Project is Ex...
2/22/2011(Bakyrchik)Altynalmas Gold Announces a 50% Increase in Indicated Minera...
2/3/2011(Oyu Tolgoi)Successful Ivanhoe Mines rights offering yields US$1.18 bill...
3/12/2008(Oyu Tolgoi)Reports an Initial 760 Million Tonne Inferred Resource Estim...
3/31/2007(Oyu Tolgoi)Oyu Tolgoi Mineral Reserves and Resources March 2007
Corporate news of Ivanhoe Mines Ltd.
7/11/2016July 11th, 2016 Ivanhoe Mines receives second US$41.2 millio...
7/5/2016July 5th, 2016 Excellent copper recoveries and concentrate g...
6/24/2016June 24th, 2016 Ivanhoe Mines files NI 43-101 technical repo...
5/27/2016May 27th, 2016 Ivanhoe Mines files NI 43-101 technical repor...
5/20/2016May 19th, 2016 Ivanhoe Mines announces results of voting for...
5/19/2016May 19th, 2016 Ivanhoe Mines condemns promotion of false and...
5/12/2016May 12th, 2016 Ivanhoe Mines Announces Financial Results and...
5/2/2016May 2nd, 2016 Ivanhoe Mines announces a positive preliminary...
4/19/2016March 30th, 2016 Ivanhoe Mines files NI 43-101 technical rep...
4/19/2016March 24th, 2016 Ivanhoe Mines Issues 2015 Year-End Results ...
3/24/2016Ivanhoe Mines Issues 2015 Year-End Results And Review Of Ope...
1/27/2016Ivanhoe Mines reports Independent Mineral Resource estimate ...
1/27/2016Ivanhoe Mines reports Independent Mineral Resource estimate ...
1/27/2016Ivanhoe Mines Reports Independent Mineral Resource Estimate ...
1/25/2016Ivanhoe Mines' Exploration Team Makes Major New Copper Disco...
1/22/2016Ivanhoe Mines to release final tranche of locked-up shares
1/19/2016Ivanhoe congratulates Robert Friedland for his induction int...
12/10/2015Ivanhoe Mines and Zijin Mining Group complete deal for Zijin...
12/10/2015Ivanhoe Mines and Zijin Mining Group complete deal for Zijin...
12/10/2015Ivanhoe Mines and Zijin Mining Group complete deal for Zijin...
12/10/2015Ivanhoe Mines and Zijin Mining Group complete deal for Zijin...
12/10/2015Ivanhoe Mines and Zijin Mining Group complete deal for Zijin...
12/10/2015Ivanhoe Mines and Zijin Mining Group complete deal for Zijin...
12/10/2015Ivanhoe Mines and Zijin Mining Group complete deal for Zijin...
9/23/2015Ivanhoe Mines welcomes DR Congo Government's support for Iva...
9/22/2015Congo drops objections to Ivanhoe Mines' copper deal
8/31/2015Ivanhoe Mines, Fio Corporation and Chemonics International j...
8/12/2015Ivanhoe Mines Announces Financial Results and Review of Oper...
8/4/2015Ivanhoe Mines and Zijin Mining Group extend completion date ...
5/26/2015Ivanhoe Mines and China's Zijin Mining Group sign landmark a...
5/26/2015Ivanhoe Mines and China's Zijin Mining Group sign landmark a...
5/26/2015Ivanhoe Mines and China's Zijin Mining Group sign landmark a...
5/26/2015Ivanhoe Mines and China's Zijin Mining Group sign landmark a...
5/26/2015Ivanhoe Mines and China's Zijin Mining Group sign landmark a...
5/26/2015Ivanhoe Mines and China's Zijin Mining Group sign landmark a...
5/26/2015Ivanhoe Mines and China's Zijin Mining Group sign landmark a...
5/26/2015Ivanhoe Mines and China's Zijin Mining Group sign landmark a...
4/20/2015China-based Zijin Mining Group completes private placement a...
3/27/2015Ivanhoe Mines Issues 2014 Year-End Results And Review Of Ope...
3/27/2015Ivanhoe Mines Issues 2014 Year-End Results And Review Of Ope...
3/27/2015Ivanhoe Mines Issues 2014 Year-End Results And Review Of Ope...
3/27/2015Ivanhoe Mines Issues 2014 Year-End Results And Review Of Ope...
3/27/2015Ivanhoe Mines Issues 2014 Year-End Results And Review Of Ope...
3/27/2015Ivanhoe Mines Issues 2014 Year-End Results And Review Of Ope...
3/27/2015Ivanhoe Mines Issues 2014 Year-End Results and Review of Ope...
3/26/2015Ivanhoe Mines appoints Livia Mahler as an independent direct...
3/24/2015CANADA STOCKS-TSX futures up as weak U.S. dollar lifts commo...
3/23/2015China-Based Zijin Mining Group to Acquire a 9.9% Stake in Iv...
3/3/2015' Exploration Team Receives the 2015 Thayer Lindsley Interna...
3/3/2015Ivanhoe Mines' Exploration Team Receives the 2015 Thayer Lin...
2/17/2015Ivanhoe Mines Reports Additional High-Grade Zinc, Copper, Si...
2/11/2015Ivanplats Is Platinum Sector's Top Performer in South Africa...
1/28/2015Ivanhoe Mines and Ivanplats Expand Challenge of Errors and M...
1/26/2015Ivanhoe Mines comments on share price
1/26/2015Ivanhoe Mines Comments on Share Price
1/16/2015Ivanhoe Mines files NI 43-101 prefeasibility study technical...
1/16/2015Ivanhoe Mines Files NI 43-101 Prefeasibility Study Technical...
1/12/2015OPEN LETTER: Ivanhoe Mines and Ivanplats Challenge Globe & M...
1/8/2015Ivanhoe Mines Releases Positive Results of Independent Pre-F...
12/9/2014Total job creation exceeds 650 following the resumption of s...
11/18/2013announces updated independent
Preliminary Economic Asses...
9/3/2013The New Ivanhoe Mines begins trading under the symbol IVN on...
8/28/2013Ivanplats changes its name to Ivanhoe Mines
8/3/2012changes name to Turquoise Hill ResourcesNew trading symbol "...
7/16/2012Rights to Cease Trading on New York Stock Exchange and NASDA...
6/27/2012"Regular Way" Trading of Ivanhoe Mines Rights Begins in the ...
6/13/2012Trading in Ivanhoe Mines Rights Begins June 14, 2012
4/25/2012Chalco and Ivanhoe Mines Note Status Of SouthGobi Resources
4/18/2012Photobook of Operations 2011
2/27/2012Altynalmas Gold Announces a Feasibility Mineral Reserve Esti...
2/22/2012CEO Robert Friedland a Keynote Speaker At International Mini...
12/13/2011receives decision in arbitration with Rio Tinto
10/3/2011Joint response from Ivanhoe Mines and Rio Tinto delivered to...
9/21/2011(Oyu Tolgoi)Challenges Unauthorized Remarks by Rio Tinto Representatives...
6/21/2011to Receive US$502 Million from Rio Tinto's Exercise of All O...
4/12/2011New Ivanhoe Mines Photobook of Operations
1/27/2011announces successful completion of rights offering
8/5/2008Australia Completes A$125 Million IPO
3/31/2008SouthGobi Energy Resources Receives Permit to Mine for the O...
8/2/2007issues clarification on Oyu Tolgoi Investment Agreement appr...
4/10/2007And Mongolian Government Reach Agreement In Principle On Dra...
3/19/2007Google Earth virtual tour of Ivanhoe's Oyu Tolgoi Copper & G...
Comments closed
 
Latest comment posted for this article
Be the first to comment
Add your comment
TORONTO (IVN.TO)FRANKFURT (IHM.F)
20.36+5.93%0.688+5.20%
TORONTO
CA$ 20.36
04/26 17:00 1.14
5.93%
Prev close Open
19.22 19.62
Low High
19.48 20.45
Year l/h YTD var.
12.83 -  20.36 58.69%
52 week l/h 52 week var.
9.94 -  20.36 67.02%
Volume 1 month var.
7,077,403 29.19%
24hGold TrendPower© : 34
Produces Gold - Iron
Develops Copper - Gold
Explores for Copper - Gold - Uranium
 
 
 
Analyse
Interactive chart Add to compare
Interactive
chart
Print Compare Export
Last updated on : 4/1/2010
You must be logged in to use the porfolio and watchlists (free)
Top Newsreleases
MOST READ
Annual variation
DateVariationHighLow
202468.40%
202312.99%14.0110.24
20228.35%9.9810.05
202143.95%9.9910.00
202068.97%6.961.80
 
5 years chart
 
3 months chart
 
3 months volume chart
 
 
Mining Company News
Plymouth Minerals LTDPLH.AX
Plymouth Minerals Intersects Further High Grade Potash in Drilling at Banio Potash Project - Plannin
AU$ 0.12-8.00%Trend Power :
Santos(Ngas-Oil)STO.AX
announces expected non-cash impairment
AU$ 7.70-0.65%Trend Power :
Oceana Gold(Au)OGC.AX
RELEASES NEW TECHNICAL REPORT FOR THE HAILE GOLD MINE
AU$ 2.20+0.00%Trend Power :
Western Areas NL(Au-Ni-Pl)WSA.AX
Advance Notice - Full Year Results Conference Call
AU$ 3.86+0.00%Trend Power :
Canadian Zinc(Ag-Au-Cu)CZN.TO
Reports Financial Results for Q2 and Provides Project Updates
CA$ 0.12+4.55%Trend Power :
Stornoway Diamond(Gems-Au-Ur)SWY.TO
Second Quarter Results
CA$ 0.02+100.00%Trend Power :
McEwen Mining(Cu-Le-Zn)MUX
TO ACQUIRE BLACK FOX FROM PRIMERO=C2=A0
US$ 12.26+2.68%Trend Power :
Rentech(Coal-Ngas)RTK
Rentech Announces Results for Second Quarter 2017
US$ 0.20-12.28%Trend Power :
KEFIKEFI.L
Reduced Funding Requirement
GBX 0.53-1.87%Trend Power :
Lupaka Gold Corp.LPK.V
Lupaka Gold Receives First Tranche Under Amended Invicta Financing Agreement
CA$ 0.06+0.00%Trend Power :
Imperial(Ag-Au-Cu)III.TO
Closes Bridge Loan Financing
CA$ 2.64-1.86%Trend Power :
Guyana Goldfields(Cu-Zn-Pa)GUY.TO
Reports Second Quarter 2017 Results and Maintains Production Guidance
CA$ 1.84+0.00%Trend Power :
Lundin Mining(Ag-Au-Cu)LUN.TO
d Share Capital and Voting Rights for Lundin Mining
CA$ 16.23+4.04%Trend Power :
Canarc Res.(Au)CCM.TO
Canarc Reports High Grade Gold in Surface Rock Samples at Fondaway Canyon, Nevada
CA$ 0.24+4.26%Trend Power :
Havilah(Cu-Le-Zn)HAV.AX
Q A April 2017 Quarterly Report
AU$ 0.20+2.63%Trend Power :
Uranium Res.(Ur)URRE
Commences Lithium Exploration Drilling at the Columbus Basin Project
US$ 6.80-2.86%Trend Power :
Platinum Group Metals(Au-Cu-Gems)PTM.TO
Platinum Group Metals Ltd. Operational and Strategic Process ...
CA$ 1.88+0.53%Trend Power :
Devon Energy(Ngas-Oil)DVN
Announces $340 Million of Non-Core Asset Sales
US$ 52.71+0.19%Trend Power :
Precision Drilling(Oil)PD-UN.TO
Announces 2017Second Quarter Financial Results
CA$ 8.66-0.35%Trend Power :
Terramin(Ag-Au-Cu)TZN.AX
2nd Quarter Report
AU$ 0.04+5.56%Trend Power :