Shear Announces Work Plan for the Jericho Project
Published : February 28, 2011

( 0 vote, 0/5 ) Print article
  Article Comments Comment this article Rating Follow Company  
0
Send
0
comment
Keywords :   Canada | Diamond | Market | Recovery | Water |

EDMONTON, ALBERTA--(Marketwire - Feb. 28, 2011) - Shear Diamonds Ltd. (News - Market indicators) announces the 2011 work plan with an approved $4.6 million Phase 1 budget for its Jericho Diamond Project, Nunavut. At site, a five-person crew was mobilized to prepare the facilities the spring drilling program planned to commence in early April.

Shear has identified three main exploration and development priorities for 2011:

  • To prove-up and expand the current resource at the Jericho kimberlite complex,
  • To explore for new diamondiferous kimberlites proximal to the Jericho mine, and
  • To begin work on determining if Jericho is economically feasible with a new National Instrument 43-101 resource for Jericho and any additional nearby kimberlites.

In addition, Shear is focusing on the renewal of its water license and other permits, leases and regulatory instruments.

"Our entire team at Shear has worked very hard these past months to design and develop the strategies needed to best understand and upgrade the known resources at Jericho. We will also be exploring to identify further resources at Jericho and the surrounding claims which host targets of significance" said Pamela Strand, President and CEO. "We have designed the exploration program with important milestones and goals that we believe are attainable within the next 12-18 months."

"The purchase of the Jericho Diamond Mine was a company transforming acquisition. However, that was just the beginning," said Julie Lassonde, Executive Chairman of Shear. "The past few months since the acquisition have been extremely busy with planning and the sourcing and hiring of the best people for the Shear team. The scope of this year's various programs demonstrates the significant work needed to fully understand the Jericho kimberlite complex and area. We at Shear are looking forward to an important and pivotal year."

As a result of a comprehensive ongoing data compilation and interpretation of the historic data from Jericho and the surrounding area, experienced crews will integrate all aspects of the Jericho dataset to assist in determining perspective targets. Details of the Phase 1 approved exploration program (until end of June) will include:

  • Ground magnetic and electromagnetic surveys with selected ground gravity surveys over priority geophysical targets, many with indicator mineral anomalies,
  • Approximately 5,000 m of core drilling to test:
    • Up to five new exploration targets suggestive of new kimberlites,
    • 12 angled exploration holes within the Jericho kimberlite complex to test for additional tonnage and to firm up the volume model, and
    • 2,500m of vertical pilot holes within the Jericho kimberlite for geological modeling,
  • Till sampling, prospecting and structural interpretation targeting high interest areas,
  • Ongoing care & maintenance of the site, and,
  • Ongoing evaluation of the Jericho resource, as detailed below.

Jericho Resource Study Update

Shear has engaged the services of Mineral Services Canada Inc ("MSC") of North Vancouver, BC to assist in the development of a new geological model for Jericho. MSC are widely recognized as expert consultants to the Diamond exploration industry. MSC was involved with Shear previously and were instrumental in assisting Shear in pinpointing its exploration priorities at the Churchill Diamond Project. Today, Churchill has one of the largest distribution of known kimberlites in Canada.

The Jericho resource estimate, provided in the July 2010 National Instrument 43-101 technical report authored by SRK Consulting (Canada) Inc. (the "SRK Report") (see Shear's press release on July 22, 2010) provided an indication of the potential for a viable mining project at Jericho. The SRK Report included an estimate for Jericho of 1,773,000 tonnes indicated and 1,724,000 tonnes inferred resources. The indicated resources have been categorized on the basis of all then available sampling data, including samples collected during the years of Tahera's production along with general production data, and taking into account further SRK's experience and observations at Jericho between 1999 and 2010. Following a comprehensive review of available historic mining and resource evaluation records, a number of recommendations that largely echo those made in the SRK Report have been made with a view to increasing Shear's level of certainty associated with the current Jericho resource.

The Jericho kimberlite is internally complex with a degree of geological and associated grade variability. As a result, the SRK Report recommended that further drilling and investigation into all data, including sampling, geology and processing/metallurgical characteristics, to be done in order to allow for a future production decision.

Shear's work plan is intended to establish the full tonnage potential and recoverable Diamond grade of the Jericho complex at a level of confidence sufficient to provide a basis for an economic assessment of project viability. Shear's work plan will focus firstly on firming up the geological model to better constrain the extent of the resource and the degree of continuity within different portions of it; secondly on representative sampling of the Jericho resource; and thirdly on evaluating mineral processing options for improving Diamond recovery.

The resource work will encompass the following:

  • Geological review: re-logging available historic drill core supported by systematic petrographic analysis for a preliminary assessment of the internal geology. This will be undertaken as part of Phase 1.
  • In-pit delineation core drilling (12 holes, 2,000m) to better understand and define areas below the current pit floor that lack definitive constraints on the kimberlite/country rock contacts. This drilling will provide the required confidence for kimberlite tonnage modelling, as well as advance the internal geological modelling. All of these holes are approved for Phase 1.
  • Large diameter reverse circulation drilling (~22 holes) and sampling (total sample size of approximately 1,000 tonnes) to provide spatially representative grade data for the major resource domains. Prior to the large diameter drilling, pilot core holes will be completed for detailed geological and geotechnical information. Eleven pilot holes totalling 2,500m of drilling are approved for Phase 1.
  • Geological interpretation, geology and Diamond grade modelling and updated resource estimation.
  • Ore dressing studies on stockpiled kimberlite material to determine the optimal processing strategy for Diamond recovery.

Preliminary results of Diamond size-frequency analysis by MSC of available microdiamond and bulk sampling / production data for Jericho provides support for the results of recent tailings audit work (see Shear's press release on Feb 8, 2011) indicating a significant loss of diamonds during historical production. To the extent that recovery efficiency can be improved, this represents significant upside on potential recoverable grade. Further work will be undertaken to better quantify the nature and extent of Diamond loss as well as the potential for mitigating this in a future production plant.

Once results from the Phase 1 program have been received and interpreted, Shear will be able to finalize the scope and budgets for the next phase. Shear has more than sufficient resources to complete Phase I of its work plan.

About Shear Diamonds

Shear is a Canadian-based company focused on Diamond exploration and development in Canada's North, where it explores established Diamond districts and has discovered new ones. Shear currently has a portfolio of eight Diamond projects, including three advanced projects with development potential. Shear holds a 100% interest in its recently acquired Jericho Diamond Mine and surrounding exploration assets, located in the Kitikmeot region of Nunavut. Jericho is Nunavut's first and only Diamond mine.

Pamela Strand, P. Geol., Shear's President and Chief Executive Officer, and Jennifer Burgess, P. Geol. Shear's VP Exploration, are qualified persons for purposes of National Instrument 43-101 who supervised the preparation of the information forming the basis for this press release.

On behalf of the Board of SHEAR DIAMONDS LTD.

Pamela Strand, P. Geol., President & CEO

Julie Lassonde, Executive Chairman

This news release may contain forward looking statements, being statements which are not historical facts, including, without limitation, statements regarding potential mineralization, exploration results, resource or reserve estimates, anticipated production or results, sales, revenues, costs, "best-efforts" financings or discussions of future plans and objectives. There can be no assurance that such statements will prove accurate. Such statements are necessarily based upon a number of estimates and assumptions that are subject to numerous risks and uncertainties that could cause actual results and future events to differ materially from those anticipated or projected. Important factors that could cause actual results to differ materially from Shear's expectations are in its documents filed from time to time with the TSX or the TSX Venture Exchange and provincial securities regulators, most of which are available at www.sedar.com. Shear disclaims any intention or obligation to revise or update such statements.

The TSX Venture Exchange has not reviewed and does not accept responsibility for the adequacy or accuracy of this release.

For more information, please contact

Shear Diamonds Ltd.
780-435-0045 or 1-866-298-9695
www.shearminerals.com
Data and Statistics for these countries : Canada | All
Gold and Silver Prices for these countries : Canada | All

Shear Diamonds Ltd

EXPLORATION STAGE
CODE : SRM.V
ISIN : CA8209792016
Follow and Invest
Add to watch list Add to your portfolio Add or edit a note
Add Alert Add to Watchlists Add to Portfolio Add Note
ProfileMarket
Indicators
VALUE :
Projects & res.
Press
releases
Annual
report
RISK :
Asset profile
Contact Cpy

Shear Diamonds is a diamonds exploration company based in Canada.

Shear Diamonds holds various exploration projects in Canada and in Philippines.

Its main exploration properties are CHURCHILL, MIMINISKA LAKE, CANOE LAKE, EDSON, JERICHO MINE, AFRIDI LAKE, AYLMER LAKE and AYLMER LAKE WEST in Canada.

Shear Diamonds is listed in Canada. Its market capitalisation is CA$ 2.4 millions as of today (US$ 2.2 millions, € 1.6 millions).

Its stock quote reached its highest recent level on December 31, 2003 at CA$ 1.70, and its lowest recent point on November 02, 2012 at CA$ 0.04.

Shear Diamonds has 53 329 000 shares outstanding.

Your feedback is appreciated, please leave a comment or rate this article.
Rate : Average note :0 (0 vote) View Top rated
 
Corporate Presentations of Shear Diamonds Ltd
11/15/2007 stock sparkles - Edmonton Journal
Financings of Shear Diamonds Ltd
8/10/2010Announces Pricing and Terms for its Private Placement Offeri...
1/7/2010Closes Additional $80,000 Private Placement
12/14/2009Announces Private Placement
1/2/2009Closes Additional $500,000 Private Placement
12/19/2008Closes $1.18 Million Private Placement
12/11/2008Announces Private Placement Offering
12/1/2008News Release - Application to Extend Term of Warrants
12/1/2008News Release - Application to Extend Term of Warrants
8/16/2008Closes $1.14 Million Private Placement
7/22/2008Announces Private Placement Offering
12/20/2007 Closes Private Placement
12/7/2007Shear Announces Private Placement
11/16/2007Expiry of Warrants Extended
11/13/2007Application to Extend Term of Warrants
6/12/2007Closes $6 Million Brokered Private Placement
5/16/2007Announces Brokered Private Placement
Option Grants of Shear Diamonds Ltd
4/25/2008 Announces Grant of Options
Nominations of Shear Diamonds Ltd
4/5/2011Announces Appointment of David Prince to Board of Directors
3/29/2011Announces Appointment of Gregory Rieveley to Board of Direct...
Project news of Shear Diamonds Ltd
2/28/2011(Jericho Mine)Announces Work Plan for the Jericho Project
2/14/2011Signs Agreement with Nunavut Resources Corp.
2/8/2011(Jericho Mine)Reports Diamond Content Range Up To 11.3 cpt From Recovery R...
8/12/2010(Churchill)Files NI 43-101 on SEDAR in respect of the Jericho Diamond P...
7/22/2010(Jericho Mine)Reports NI 43-101 Resource Estimate for Jericho Diamond Proj...
9/24/2008(Churchill)discovers nine new kimberlites at the Churchill Diamond Proj...
9/15/2008(Churchill)ANNOUNCES NEW KILLIQ KIMBERLITE AT CHURCHILL DIAMOND PROJECT...
7/2/2008(Churchill)announces 2008 program underway at the Churchill Diamond Pro...
6/27/2008(Churchill)REPORTS ADDITIONAL HIGH INTEREST MINERAL DISPERSIONS AT CHUR...
5/14/2008(Afridi Lake)ANNOUNCES COMPLETION OF SPRING AFRIDI LAKE EXPLORATION DRILL...
3/26/2008(Afridi Lake) ANNOUNCES 2008 AFRIDI LAKE DRILL PROGRAM
2/20/2008(Churchill)SHEAR REPORTS ADDITIONAL DIAMONDS FROM KAHUNA
1/31/2008(Churchill) REPORTS HIGH DIAMOND COUNTS FROM FOUR KIMBERLITES DISCOVERE...
12/3/2007(Churchill West) Recovers 337 Carats from 356 Tonne Kahuna Bulk Sample: News...
11/30/2007(Sakari Diamond)SAKARI PROJECT UPDATE
11/20/2007(Afridi Lake) ANNOUNCES HIGH PRIORITY KIMBERLITE TARGETS AT THE AFRIDI PR...
11/14/2007(Churchill West)SHEAR RECOVERS 5.43 CARAT DIAMOND FROM CHURCHILL'S KAHUNA KI...
10/11/2007(Churchill West) DISCOVERS 31 NEW KIMBERLITES AT CHURCHILL
5/17/2007(Afridi Lake)Announces Exploration Plans for Afridi Lake Diamond Property
Corporate news of Shear Diamonds Ltd
10/22/2012s Financial and Operational Status; Continues to Seek Transa...
7/13/2011Announces Beginning of Process Evaluation at Jericho Diamond...
7/6/2011Announces Additional 75,000 Acres in Mineral Rights and Expl...
5/31/2011Announces Engagement of DRA Americas to Evaluate Jericho Dia...
5/5/2011Commences Drilling at Jericho Diamond Project in Nunavut and...
4/26/2011featured in the Toronto Star April 25, 2011
3/15/2011Reports Overall Diamond Recovery of 0.35 cpt From 25.6 Tonne...
3/8/2011Announces Extension of Type A Water Licence for Jericho Diam...
7/23/2010July 23, 2010
5/25/2010receives the Thomas Kudloo Memorial Award
5/10/2010Press Release - May 2010
5/3/2010$550,000 program for 2010 at Chesterfield Inlet Project
3/17/2010Finalizes agreement with Rio Tinto report on fall fieldwork ...
3/8/2010Press Release March 8, 2010
1/15/2010Commences drilling at Liege Diamond Project, Alberta
1/12/2010Invite to Investing in Nunavut Reception - January 17, 2009
10/14/2009From Shear Minerals Ltd.
9/18/2009COMMENTS ON TRADING ACTIVITY
8/10/2009AND STORNOWAY OPTION CHESTERFIELD INLET CLAIMS, NUNAVUT
1/23/2009Featured on 'Innovations in the North'
7/17/2008Announces Road Accessible Drill Ready Targets
7/7/2008Announces Earn into Alberta Potash Permits
1/25/2008To the Life & Memory of BRIAN ELKOW
9/18/2007CONFIRMS HIGH COMMERCIAL DIAMOND CONTENT AT CHURCHILL'S KAHU...
8/1/2007 REPORTS AN ADDITIONAL 31 DIAMONDS WEIGHING 1.74 CARATS FROM...
7/18/2007and Stornoway Announce the Acquisition of Additional Interes...
3/15/2007 Recipient of Environmental Award
Comments closed
 
Latest comment posted for this article
Be the first to comment
Add your comment
TSX-V (SRM.V)
0.045+0.00%
TSX-V
CA$ 0.045
04/17 15:43 -
0%
Prev close Open
0.045 -
Low High
0.045 0.045
Year l/h YTD var.
 -  -
52 week l/h 52 week var.
- -  0.045 -10.00%
Volume 1 month var.
0 -10.00%
24hGold TrendPower© : 24
Produces
Develops
Explores for Copper - Diamonds - Gold - Lead - Natural gas - Oil - Silver - Uranium - Zinc
 
 
 
Analyse
Interactive chart Add to compare
Interactive
chart
Print Compare Export
You must be logged in to use the porfolio and watchlists (free)
Top Newsreleases
MOST READ
Annual variation
DateVariationHighLow
 
5 years chart
 
3 months chart
 
3 months volume chart
 
 
Mining Company News
Plymouth Minerals LTDPLH.AX
Plymouth Minerals Intersects Further High Grade Potash in Drilling at Banio Potash Project - Plannin
AU$ 0.12-8.00%Trend Power :
Santos(Ngas-Oil)STO.AX
announces expected non-cash impairment
AU$ 7.72+0.39%Trend Power :
Oceana Gold(Au)OGC.AX
RELEASES NEW TECHNICAL REPORT FOR THE HAILE GOLD MINE
AU$ 2.20+0.00%Trend Power :
Western Areas NL(Au-Ni-Pl)WSA.AX
Advance Notice - Full Year Results Conference Call
AU$ 3.86+0.00%Trend Power :
Canadian Zinc(Ag-Au-Cu)CZN.TO
Reports Financial Results for Q2 and Provides Project Updates
CA$ 0.12+4.55%Trend Power :
Stornoway Diamond(Gems-Au-Ur)SWY.TO
Second Quarter Results
CA$ 0.02+100.00%Trend Power :
McEwen Mining(Cu-Le-Zn)MUX
TO ACQUIRE BLACK FOX FROM PRIMERO=C2=A0
US$ 11.04+1.38%Trend Power :
Rentech(Coal-Ngas)RTK
Rentech Announces Results for Second Quarter 2017
US$ 0.20-12.28%Trend Power :
KEFIKEFI.L
Reduced Funding Requirement
GBX 0.54-2.53%Trend Power :
Lupaka Gold Corp.LPK.V
Lupaka Gold Receives First Tranche Under Amended Invicta Financing Agreement
CA$ 0.06+0.00%Trend Power :
Imperial(Ag-Au-Cu)III.TO
Closes Bridge Loan Financing
CA$ 2.52+6.78%Trend Power :
Guyana Goldfields(Cu-Zn-Pa)GUY.TO
Reports Second Quarter 2017 Results and Maintains Production Guidance
CA$ 1.84+0.00%Trend Power :
Lundin Mining(Ag-Au-Cu)LUN.TO
d Share Capital and Voting Rights for Lundin Mining
CA$ 16.05+2.62%Trend Power :
Canarc Res.(Au)CCM.TO
Canarc Reports High Grade Gold in Surface Rock Samples at Fondaway Canyon, Nevada
CA$ 0.24+2.13%Trend Power :
Havilah(Cu-Le-Zn)HAV.AX
Q A April 2017 Quarterly Report
AU$ 0.20+7.89%Trend Power :
Uranium Res.(Ur)URRE
Commences Lithium Exploration Drilling at the Columbus Basin Project
US$ 6.80-2.86%Trend Power :
Platinum Group Metals(Au-Cu-Gems)PTM.TO
Platinum Group Metals Ltd. Operational and Strategic Process ...
CA$ 1.90+1.60%Trend Power :
Devon Energy(Ngas-Oil)DVN
Announces $340 Million of Non-Core Asset Sales
US$ 51.43-0.46%Trend Power :
Precision Drilling(Oil)PD-UN.TO
Announces 2017Second Quarter Financial Results
CA$ 8.66-0.35%Trend Power :
Terramin(Ag-Au-Cu)TZN.AX
2nd Quarter Report
AU$ 0.03+0.00%Trend Power :