From Article appeared in the Monday’s release of the Resource Investor March 17, 2008-03-19

BAKU, Azerbaijan (ResourceInvestor.com) -- Things are shaping up well for Etruscan Resources [TSX:EET]. Diamonds are once again being produced at the Tirisano Diamond Mine in the alluvial diamond district of Ventersdorp – part of the Blue Gum Project -by 54%-owned subsidiary Etruscan Diamonds Ltd. of South Africa. The installation of four 16-foot pan plants effectively doubles production capacity to 100,000 cubic metres of gravel per month. When it is operating at full capacity, a rate expected within two months, management anticipates recovering more than 2,500 carats per month.

The company is also on the path to becoming a mid-tier gold producer. Etruscan expects its Youga mine in Burkina Faso to produce between 60,000 and 70,000 ounces of gold this year and 100,000 in 2009, its first full year of production. Mining is going on at five open pits and ore is being processed in a CIL gravity plant with a 1 million tonne per year design capacity.

“This first gold pour at Youga is a major milestone on Etruscan's path to becoming a mid-tier gold producer. The construction and operating teams at Youga have done a tremendous job in getting the Youga Project to where it is today. Over the coming months we will be ramping up to full production,” Gerald McConnell, Etruscan’s president and CEO stated in a March 12th media release.

South African Diamonds

Tirisano yielded more than 1,220 carats at an overall grade of 2.67 carats per hundred cubic metres in February. A total 1,311 carats sold at an average bid price US$854 for US$727,000 in gross proceeds in an early March tender, well in excess of the US$466 per carat projected value included in the Blue Gum Project’s NI 43-101 resource estimate, which was released February 1. February diamond sales averaged more than US$750 per carat.

Etruscan is also looking to expand vertically bringing it in line with recent regulatory changes in South Africa, which is looking to build up a diamond beneficiation industry. Etruscan held on to 357 carats from the March tender which will be cut and polished by its strategic partner, African Romance of Johannesburg’s Sandton suburb, South Africa’s first wholly Black-owned diamond cutting and polishing facility. Diamond cutting and polishing can add 40% or more to rough tender diamond prices, according to the company.

Blue Gum is estimated to contain indicated resources of 20.5 million cubic metres and inferred resources of 17 million cubic metres at grades ranging from 1.77 to 2.85 carats per hundred cubic metres, according to the company’s February NI 43-101 report, which was prepared by Explorations Unlimited.

Etruscan Diamonds is planning a public offering in order to finance further expansion that will bring Blue Gum’s diamond production rate to 260,000 cubic metres or gravel per month. A pre-feasibility study is expected to be completed in Q2.

West African Gold

Etruscan Resources is also producing gold. A first gold pour – a bar of approximately 100 ounces – took place at its 90%-owned Youga Mine in Burkina Faso, according to a March 3rd media release.

Commercial production – defined as 30 consecutive days of operation at 60% of designed capacity – is scheduled for April, according to the company. Some 49,694 tonnes of ore have been mined at Youga. Crushing, grinding and leach circuits are nearly complete. An elution circuit that will extract gold from carbon-in-leach (CIL) tanks is in its final stages of commissioning.

Youga’s current reserves total 6.6 million tonnes at an average grade of 2.7 grams per tonne containing 580,000 ounces of gold. The nearby White Volta River supplies the plant with water. An on-site diesel power plant provides a constant supply of electricity until a hook-up to the Volta River Authority grid in Ghana is completed, which is expected by the middle of this year. "Youga promises to be a robust project that will produce strong cash flow for the company,” McConnell stated.

Updated project economics incorporate a re-optimized mine plan based on a gold price of US$525 per ounce, a hedged gold price of US$700 per ounce for 40% of production (approximately 225,000 ounces), an unhedged gold price of US$850 per ounce for 60% of production (approximately 336,000 ounces), and a life-of-mine cash cost of US$396. Youga’s forecast cash cost for fiscal 2008, including ramping up operations, is US$490 per ounce.

If costs come in as expected, management has locked in profits of US$233 to US$304 per ounce for 40% of Youga’s production through a zero-cost collar hedging programme carried out by Noah’s Rule of Perth, Australia. The programme is was put in place by purchasing 456,000 puts struck at US$629 per ounce and selling 246,000 calls struck at US$700.

Updated project capital costs total US$75 million, and now include the addition of the power plant, spare mill motor and gearbox, as well as pre-production, financing and working capital costs. Total debt service, including interest of US$49.8 million, is to be paid off within the first four years.

Next on the company’s agenda is bringing the Agbaou Gold Mine in Cote d’Ivoire into production. A feasibility study is expected this summer with production slated to begin in 2010

.