Asanko Gold Mine Construction Update

VANCOUVER, BRITISH COLUMBIA--(Marketwired - Jul 13, 2015) -

Highlights:

  • Phase 1 construction 60% complete and on schedule for first gold in Q1 2016.
  • Full mining fleet mobilized and achieving above planned production levels +/- 100,000 tonnes per day.
  • Pit dewatering over 55% complete and water levels reduced by 24.3 metres.
  • Installation of SAG & Ball Mills underway.
  • Project tracking budget with US$138 million of the US$295 million capital cost spent.

Asanko Gold Inc. ("Asanko" or the "Company") (AKG)(NYSE MKT:AKG) is pleased to provide a construction update on the fully funded Phase 1 of the Asanko Gold Mine ("AGM" or the "Project") in Ghana. Phase 1 will be a low cost, long life mine producing 190,000 ounces of gold per annum at steady state, with the first gold pour on track for Q1 2016.

Project construction remains on schedule with 60% of the overall project complete and around 2,443 employees and contractors on site, as at the end of June 2015. Concrete civils are 66% complete and steel, mechanical and platework 54% complete. All critical path items are in hand and on time. Procurement is practically complete with US$286 million committed out of the total capital budget of US$295 million. US$138 million has been spent up to June 30, 2015. The latest videos and photographs are available at http://www.asanko.com/projects/photo-gallery.

Peter Breese, President and CEO, commented: "Construction of Phase 1 continues to advance according to plan and budget, which is very encouraging. Mining operations have hit their stride with the entire PW mining fleet fully mobilized and current mining levels exceeding the plan. The plant site construction is progressing very well and with the Project now nearing 2/3rds completion, we remain confident that we will be able to deliver this project on time and within the capital budget of US$295 million."

Construction Update

The primary crusher foundations were completed in June and the structural, mechanical and platework installation has commenced. The installation of the Jaw crusher is expected to be completed by the end of July. The concrete work for the run-of-mine tip wall at the primary crusher, as well as the reinforced earth wall is still under construction and due for completion by the end of Q3 2015. The primary tip bin erection has commenced and will be completed in parallel.

Earthworks for the overland conveyor from the primary crusher to the stockpile tunnel were completed in June and the concrete precast sleeper foundations are being placed. The conveyor installation is expected to commence this month. Concrete work on the stockpile tunnel has been completed and installation of the apron feeder and other mechanical equipment is scheduled to commence in mid-July.

The foundations for the SAG and Ball Mills were completed in early June and installation of the mills has commenced with a planned completion date of November. Both the SAG and Ball Mills are on site, along with all the major ancillary pieces of equipment.

All seven CIL tanks and the cyanide detoxification tank have been fully erected, painted and welded. Interconnecting steel and platework is underway and due for completion by the end of Q3 2015. The mechanical installation of the agitators and inter-stage carbon screens will follow. Access to Electrical and Instrumentation ("E&I") and Piping contractors to this area is expected to be given at the end of July.

Steelwork on the pre-leach thickener has been completed and welding and platework are in the final stages, with completion expected in the next few weeks. The thickener bridge is scheduled to arrive on site mid-July and erection planned to take place in August.

The reagents building and store room are progressing well, all the steel work is erected and most of the tanks have been installed. Platework is over 90% complete and installation of the pipe and cable racks has commenced. The sheeting for the buildings is expected to arrive on site in July and be installed at that time.

The Gold Room platework is over half way towards completion and is expected to be fully complete in October.

The Tailings Storage Facility ("TSF") continues to progress well, with over 67% of earthworks complete and over 60% of the HDPE liner installed. The northern portion is complete and work is now focusing on the southern portion of the facility. The TSF is on track for completion during Q4 2015. The tailings pipeline trench construction is expected to commence in early August and is scheduled to be completed in November.

The E&I work has commenced in the Reagents area and on the pipe gantries. All remaining major equipment, such as elution heating, emergency generator, transformers, medium voltage switchgear, gravity concentrator and remaining structural steel is expected to arrive by mid-August, ahead of the final stages of installation. Terracing, drains and buried services for the entire plant site, including the footprint for the Phase 2 expansion project, are scheduled to be completed by the end of July. All other ancillary services, such as change house, workshop, raw water dam and pollution control dam, are on schedule.

Power

Bush clearing for the 161kV line has now been completed. Foundation work for the 82 towers along the 30km long power line is underway, with 65 tower foundations excavated and 55 tower foundations completed. 12 towers have already been erected and the remaining tower erection is due for completion in October. The medium voltage substation is well advanced and nearing completion.

In June 2015 Asanko signed a life of mine power purchase agreement with the independent power producer Genser Energy Ghana Limited ("Genser") which has considerably de-risked the supply of long term power to the mine. Genser will build and operate a 19.2 megawatts ("MW") liquid fuel power plant adjacent to the AGM site and supply 17MW of nominal power to Phase 1 on a fixed-price, life-of-mine contract. Until the on-site power plant is completed, which is expected by April 2016, Genser will provide interim power via temporary generating facilities. Bush clearing for the Genser power plant has been completed and construction of the terrace is underway and due for completion by the end of Q3 2015.

Mining

Pre-stripping of the Nkran Pit, the main mineral resource for Phase 1 continues to advance according to schedule. PW Ghana have now mobilized the entire mining fleet, consisting of four production shovels, 18 CAT 777, 8 CAT 773 trucks as well as seven drill rigs in readiness for drill and blast operations, which are due to commence during Q3 2015. Mining activities are operating 24 hours a day and production levels have reached 100,000 tonnes per day, which is approximately 10% above the planned mining rates.

The contractor has mined 7.9 million tonnes ("Mt") from the pit as at the end of June, representing 36% of the planned pre-strip. Approximately 20,803 tonnes of ore at a grade of 1.87 g/t have been mined during the pre-strip and have been placed on the run-of-mine pad. Prior to milling operations commencing in Q1 2016, it is planned to have 423,000 tonnes of ore grading 2.09 g/t on the stockpiles.

Pit dewatering has continued to advance ahead of the mining operations with 3.36 million cubic metres of the expected 6 million cubic metres of water now pumped from the Nkran pit (approximately 56%). Since the start of dewatering in December 2014, the water level has dropped by approximately 24.3 metres.

Health and Safety

Following the recent fatal accident within the pit all employees and contractors have undergone health and safety re-inductions. In addition, Asanko has investigated the accident and completed a full review of all of its safety and health procedures and processes. Appropriate remedial action plans have been fully implemented.

Procurement

Procurement is practically complete with approximately US$286 million committed to orders and contracts, of which US$138 million has been spent as at June 30 2015. All remaining equipment and materials deliveries, none of which are on the project critical path, are on schedule.

Partial Relocation of Nkran Village

The partial relocation of the Nkran village (88 building structures) continues to progress on schedule. Local contractors are undertaking the construction of the new buildings, with around 450 local villagers being employed on the project. The construction of the housing terraces is complete and 51 house structures have already been built, with 80% of these houses currently being fitted with plumbing and electrics. An additional 37 houses are between foundation and lintel level. Asanko is also building a community center, a school and a football field. The relocation remains on track for completion by the end of Q3 2015.

Funding

The Company has drawn the remaining amounts under the project debt facility with Red Kite Mine Finance so the full US$130 million facility is now drawn. The Company is fully funded to cash flow positive in Q2 2016 with approximately US$229 million in cash on-hand as at June 30, 2015 plus a US$20 million cost-overrun facility for total available funding of approximately US$249 million. The remaining use of funds is US$209 million which includes US$180 million for the project, US$23 million in working capital and US$6 million in corporate costs until commercial production is achieved. The Company therefore has a current funding buffer of US$40 million.

Enquiries:

For further information please visit: www.asanko.com, email: info@asanko.com.

About Asanko Gold Inc.

Asanko's vision is to become a mid-tier gold mining company that maximizes value for all its stakeholders. The Company's flagship project is the multi-million ounce Asanko Gold Mine located in Ghana, West Africa. The mine is being developed in phases. Phase 1 is fully financed, permitted and under construction. First gold is expected in Q1 2016, with steady state production of 190,000 ounces per annum in Q2 2016.

Asanko is managed by highly skilled and successful technical, operational and financial professionals. The Company is strongly committed to the highest standards for environmental management, social responsibility, and health and safety for its employees and neighbouring communities.

Forward-Looking and other Cautionary Information

This release includes certain statements that may be deemed "forward-looking statements". All statements in this release, other than statements of historical facts, that address estimated resource quantities, grades and contained metals, possible future mining, exploration and development activities, are forward-looking statements. Although the Company believes the forward-looking statements are based on reasonable assumptions, such statements should not be in any way construed as guarantees of future performance and actual results or developments may differ materially from those in the forward-looking statements. Factors that could cause actual results to differ materially from those in forward-looking statements include market prices for metals, the conclusions of detailed feasibility and technical analyses, the timely renewal of key permits, lower than expected grades and quantities of resources, mining rates and recovery rates and the lack of availability of necessary capital, which may not be available to the Company on terms acceptable to it or at all. The Company is subject to the specific risks inherent in the mining business as well as general economic and business conditions. For more information on the Company, Investors should review the Company's annual Form 20-F filing with the United States Securities Commission and its home jurisdiction filings that are available at www.sedar.com.

Neither Toronto Stock Exchange nor the Investment Industry Regulatory Organization of Canada accepts responsibility for the adequacy or accuracy of this release.

Cautionary Note to U.S. Investors Regarding Mineral Reporting Standards:

Asanko has prepared its disclosure in accordance with the requirements of securities laws in effect in Canada, which differ from the requirements of US securities laws. Terms relating to mineral resources in this press release are defined in accordance with National Instrument 43-101 - Standards of Disclosure for Mineral Projects under the guidelines set out in the Canadian Institute of Mining, Metallurgy, and Petroleum Standards on Mineral Resources and Mineral Reserves. The Securities and Exchange Commission (the "SEC") permits mining companies, in their filings with the SEC, to disclose only those mineral deposits that a company can economically and legally extract or produce. Asanko uses certain terms, such as, "measured mineral resources", "indicated mineral resources", "inferred mineral resources" and "probable mineral reserves", that the SEC does not recognize (these terms may be used in this press release and are included in the public filings of Asanko which have been filed with securities commissions or similar authorities in Canada).

Read the rest of the article at finance.yahoo.com
Data and Statistics for these countries : Canada | Ghana | All
Gold and Silver Prices for these countries : Canada | Ghana | All

Asanko Gold Inc.

CODE : AKG.TO
Follow and Invest
Add to watch list Add to your portfolio Add or edit a note
Add Alert Add to Watchlists Add to Portfolio Add Note
ProfileMarket
Indicators
VALUE :
Projects & res.
Press
releases
Annual
report
RISK :
Asset profile
Contact Cpy

Asanko Gold is a exploration company based in Canada.

Asanko Gold is listed in Canada and in United States of America. Its market capitalisation is CA$ 325.5 millions as of today (US$ 231.0 millions, € 211.7 millions).

Its stock quote reached its highest recent level on September 16, 2011 at CA$ 9.59, and its lowest recent point on December 15, 2017 at CA$ 0.55.

Asanko Gold has 203 450 000 shares outstanding.

Your feedback is appreciated, please leave a comment or rate this article.
Rate : Average note :0 (0 vote) View Top rated
 
Corporate news of Asanko Gold Inc.
7/8/2016Asanko Gold Conference Call Details for Q2 2016 Production R...
7/8/2016Annual General Meeting Vancouver, BC
6/17/2016Asanko Gold Results of Annual General Meeting
5/23/2016Asanko Gold Annual General Meeting Information
5/19/2016Asanko Gold Amends Debt Repayment Schedule in Preparation fo...
5/12/2016Asanko Gold Q1 2016 Results and Site Visit Presentations
5/2/2016Asanko Gold Refines Scope of Phase 2 Definitive Feasibility ...
4/27/2016Near Mine Exploration Yields Success At Asanko Gold Mine
4/6/2016Asanko Gold Anounces Commercial Production and Provides Oper...
1/27/2016Asanko Gold Mine Announces First Gold Production
1/27/2016Asanko Gold Mine Announces First Gold Production
12/21/2015Asanko Gold Mine Commissioning Underway
11/24/2015Here is What Hedge Funds Think About Luxfer Holdings PLC (LX...
10/16/2015Earnings Estimates Moving Higher for Asanko Gold (AKG): Time...
10/15/2015Asanko Gold (AKG) Shares March Higher, Can It Continue?
10/13/2015Commodity Strength Boosts Canadian Stocks: 5 Key Picks
10/13/2015The Zacks Analyst Blog Highlights: Alcoa, OCI Resources, Sol...
10/12/2015Forget Alcoa, Buy These 4 Mining Stocks Instead
10/6/2015Alcoa Inks $1B Contract with Airbus for Fastening Systems
9/30/2015ArcelorMittal Invests $11M in Mexican Tubular Plant
9/16/2015Asanko Gold Mine Construction Update
7/13/2015Asanko Gold Mine Construction Update
6/19/2015Asanko Gold Inc.: Results of Annual General Meeting of Share...
4/22/2015Global Demand Means the World's Most Important Base Metal Ma...
4/20/2015Royal Gold (RGLD) Issues Update on Mt. Milligan Mine - Analy...
4/20/2015Syngenta Reports Weak Q1 Sales, Maintains 2015 Outlook - Ana...
4/15/2015Gold Fields (GFI) Issues Cost and Production Outlook for Q1 ...
4/15/2015Vale S.A. Downgraded to Sell on Macro-Level Headwinds - Anal...
4/14/2015Monsanto Upgraded to Hold on Innovations & Market Tailwinds ...
4/13/2015Gold Field Inks Wage Agreement with South Deep for 3 Years -...
4/9/2015Newmont (NEM) to Construct Phase 1 of Long Canyon Mine - Ana...
4/9/2015Monsanto Retains Growth despite Short-Term Headwind Woes - A...
4/9/2015AllianceBernstein , Royal Gold, Pretium Resources, Asanko Go...
4/9/2015Bear of the Day: Royal Gold (RGLD) - Bear of the Day
4/9/2015Asanko Gold Mine Construction Update
4/6/2015Andersons' Results to Suffer on Weakening Ethanol Margin - A...
4/2/2015Kinross Temporarily Halts Maricunga Mine Operations - Analys...
4/1/2015Monsanto Q2 Earnings, Revenues Miss on Headwind Woes - Analy...
3/27/2015Cliffs Natural (CLF) Extends Exchange Offer for Senior Notes...
3/25/2015Asanko Initiates Near-Mine Exploration Program
3/24/2015Barrick's (ABX) Pascua-Lama Has Not Damaged Glaciers - Analy...
3/23/2015Syngenta Downgraded to Sell on Weak Business Milieu - Analys...
Comments closed
 
Latest comment posted for this article
Be the first to comment
Add your comment
TORONTO (AKG.TO)NYSE (AKG)
1.60+4.58%1.13+3.67%
TORONTO
CA$ 1.60
05/04 17:00 0.070
4.58%
Prev close Open
1.53 1.56
Low High
1.53 1.61
Year l/h YTD var.
 -  -
52 week l/h 52 week var.
- -  1.60 -%
Volume 1 month var.
218,400 -%
24hGold TrendPower© : -25
Produces
Develops
Explores for
 
 
 
Analyse
Interactive chart Add to compare
Interactive
chart
Print Compare Export
You must be logged in to use the porfolio and watchlists (free)
Top Newsreleases
MOST READ
Annual variation
DateVariationHighLow
202030.33%1.280.57
 
5 years chart
 
3 months chart
 
3 months volume chart
 
 
Mining Company News
Plymouth Minerals LTDPLH.AX
Plymouth Minerals Intersects Further High Grade Potash in Drilling at Banio Potash Project - Plannin
AU$ 0.12-8.00%Trend Power :
Santos(Ngas-Oil)STO.AX
announces expected non-cash impairment
AU$ 7.70-0.65%Trend Power :
Oceana Gold(Au)OGC.AX
RELEASES NEW TECHNICAL REPORT FOR THE HAILE GOLD MINE
AU$ 2.20+0.00%Trend Power :
Western Areas NL(Au-Ni-Pl)WSA.AX
Advance Notice - Full Year Results Conference Call
AU$ 3.86+0.00%Trend Power :
Canadian Zinc(Ag-Au-Cu)CZN.TO
Reports Financial Results for Q2 and Provides Project Updates
CA$ 0.12+4.55%Trend Power :
Stornoway Diamond(Gems-Au-Ur)SWY.TO
Second Quarter Results
CA$ 0.02+100.00%Trend Power :
McEwen Mining(Cu-Le-Zn)MUX
TO ACQUIRE BLACK FOX FROM PRIMERO=C2=A0
US$ 12.26+2.68%Trend Power :
Rentech(Coal-Ngas)RTK
Rentech Announces Results for Second Quarter 2017
US$ 0.20-12.28%Trend Power :
KEFIKEFI.L
Reduced Funding Requirement
GBX 0.53-1.87%Trend Power :
Lupaka Gold Corp.LPK.V
Lupaka Gold Receives First Tranche Under Amended Invicta Financing Agreement
CA$ 0.06+0.00%Trend Power :
Imperial(Ag-Au-Cu)III.TO
Closes Bridge Loan Financing
CA$ 2.64-1.86%Trend Power :
Guyana Goldfields(Cu-Zn-Pa)GUY.TO
Reports Second Quarter 2017 Results and Maintains Production Guidance
CA$ 1.84+0.00%Trend Power :
Lundin Mining(Ag-Au-Cu)LUN.TO
d Share Capital and Voting Rights for Lundin Mining
CA$ 16.23+4.04%Trend Power :
Canarc Res.(Au)CCM.TO
Canarc Reports High Grade Gold in Surface Rock Samples at Fondaway Canyon, Nevada
CA$ 0.24+4.26%Trend Power :
Havilah(Cu-Le-Zn)HAV.AX
Q A April 2017 Quarterly Report
AU$ 0.20+2.63%Trend Power :
Uranium Res.(Ur)URRE
Commences Lithium Exploration Drilling at the Columbus Basin Project
US$ 6.80-2.86%Trend Power :
Platinum Group Metals(Au-Cu-Gems)PTM.TO
Platinum Group Metals Ltd. Operational and Strategic Process ...
CA$ 1.88+0.53%Trend Power :
Devon Energy(Ngas-Oil)DVN
Announces $340 Million of Non-Core Asset Sales
US$ 52.71+0.19%Trend Power :
Precision Drilling(Oil)PD-UN.TO
Announces 2017Second Quarter Financial Results
CA$ 8.66-0.35%Trend Power :
Terramin(Ag-Au-Cu)TZN.AX
2nd Quarter Report
AU$ 0.04+5.56%Trend Power :