VANCOUVER, Sept. 8, 2014 /PRNewswire/ - Bear Creek Mining (TSX Venture: BCM) ("Bear Creek" or the "Company") is pleased to provide an update on progress made on optimization studies at its Corani Silver-Lead-Zinc deposit as the project advances towards detailed engineering and permitting.  The optimization studies, involving three engineering firms led by Global Resource Engineering of Denver, Colorado, have been underway for six months and trade-off studies have identified several design modifications enhancing the project performance that will now be carried forward into the detailed engineering.  The project optimizations are not expected to require a new Environmental and Social Impact study ("ESIA") and it is expected that the Corani project can be moved forward with modifications to the ESIA approved in September, 2013 (see News Release dated September 25, 2013).  The modifications, targeting reductions in initial and sustaining CapEx while maintaining low OpEx (very low cash costs/ounce Ag on a by-product basis) and expected high annual silver output, include:

  • In-pit tailings deposition beginning as early as year 5 of operations combined with dry-stacking filtered tailings at start-up, either eliminating the tailings dam requirement entirely or, at a minimum, reducing the footprint. This design, for which technology has advanced significantly over recent years, is expected to substantially reduce the CapEx while expected to only marginally increase OpEx.  In addition to the economic benefits, permitting is expected to be facilitated by this design as the project footprint (impact area) will be reduced and mine-closure procedures and associated costs are expected to be reduced.

  • Tailings pumping over the 22 year projected mine life are expected to be reduced or eliminated improving operating efficiencies and reducing OpEx, more than off-setting the expected increase in OpEx related to tailings filtration and dry stacking.

  • Water demands will be reduced as opposed to conventional wet-tailings disposal, eliminating the need for a fresh-water storage dam, which is expected to reduce CapEx by as much as $30M.

  • New data regarding acid generating potential indicates that over 50% of the waste rock is not acid generating which allows for in-pit disposal of waste material, reducing haulage distances, CapEx (smaller mine fleet equipment) and OpEx.

  • Smaller SAG and ball mill components have been identified for the 22,500 tonnes per day throughput rate while not impacting the metal output of 13.4M ounces silver per year as stated in the 2011 feasibility study filed on SEDAR by the Company on December 22, 2011 entitled "Corani Project, Form 43-101F1 Technical Report, Feasibility Study" (the "FS" or "Feasibility Study").

  • Further studies are underway to consider contract mining for the first 3-5 years.  Trade-off studies will consider CapEx savings versus OpEx increases.  Innovations in contract mining agreement structures will consider if purchasing the fleet in Year 5 can improve financial performance of the Corani project.

Andrew Swarthout, CEO and President, stated "we are very encouraged by the optimization phases of the detailed engineering which have identified significant opportunities that are expected to maintain the project CapEx in the $600M range of 2011 feasibility, maintain very low operating costs and minimize the environmental footprint.  To be able to negate the capital cost creep of the last four years, and preserve the very low cash costs per ounce of silver expected to be produced net of base metal credits (negative for the first seven years of the projected 22 year mine life) is a very important achievement for our Company.  The driving factor is that we can minimize, or even potentially eliminate, the tailings impoundment dam, which is the largest capital and sustaining cost item in the 2011 Feasibility Study.  These opportunities are being verified by ongoing engineering test work and will be incorporated into the detailed engineering and revised mine plan immediately for preparation of an updated Feasibility Study, expected to be completed by year-end 2014.  The improved project design, as well as enhancing the project economics, is also expected to facilitate permitting by defining a lower impact project."

All scientific and technical information contained in this news release has been reviewed and approved by Andrew Swarthout, P.Geo., the Chief Executive Officer of the Company, who is a "qualified person" within the meaning of National Instrument 43-101 ("NI 43-101").

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.

Cautionary Note regarding Technical and Scientific Disclosure and Forward-Looking Statements:

Please refer to the NI 43-101 technical report dated December 22, 2011 entitled "Corani Project, Form 43-101F1 Technical Report, Feasibility Study" available under the Company's profile at www.sedar.com, as well as the Company's news releases dated November 9, 2011 and January 4, 2012, for further details of the mineral reserves, mineral resources and the Feasibility Study in respect of the Company's Corani project.

Cautionary Note regarding Forward-Looking Statements:

This document contains "forward-looking information" within the meaning of Canadian securities legislation and "forward-looking statements" within the meaning of the United States Private Securities Litigation Reform Act of 1995. This information and these statements, referred to herein as "forward-looking statements" are made as of the date of this news release or as of the date of the effective date of information described in this news release, as applicable. Forward-looking statements relate to future events or future performance and reflect current estimates, predictions, expectations or beliefs regarding future events and include, without limitation, statements with respect to: (i) modifications, if any, and timing of the ESIA; (ii) the planned development of the Corani project or any of the Company's other projects, including the timing thereof, and (iii) preparation of a updated Feasibility Study, including the timing thereof. Any statements that express or involve discussions with respect to predictions, expectations, beliefs, plans, projections, objectives, assumptions or future events or performance (often, but not always, using words or phrases such as "expects", "anticipates", "plans", "projects", "estimates", "envisages", "assumes", "intends", "strategy", "goals", "objectives" or variations thereof or stating that certain actions, events or results "may", "could", "would", "might" or "will" be taken, occur or be achieved, or the negative of any of these terms and similar expressions) are not statements of historical fact and may be forward-looking statements.

All forward-looking statements are based on the Company's or its consultants' current beliefs as well as various assumptions made by and information currently available to them. These assumptions include, without limitation: (i) the presence of and continuity of metals at the project at modeled grades; (ii) the capacities of various machinery and equipment; (iii) the availability of personnel, machinery and equipment at estimated prices; (iv) exchange rates; (v) metals and minerals sales prices; (vi) appropriate discount rates; (vii) tax rates and royalty rates applicable to the proposed mining operation; (viii) financing structure and costs; (ix) anticipated mining losses and dilution; * metals recovery rates, (xi) reasonable contingency requirements; and (xiii) receipt of regulatory approvals on acceptable terms and in the timeframes expected by the Company, including, without limitation, in relation to a modified ESIA or updated Feasibility Study, if any. Although management considers these assumptions to be reasonable based on information currently available to it, they may prove to be incorrect. Many forward-looking statements are made assuming the correctness of other forward looking statements, such as statements of net present value and internal rate of return, which are based on most of the other forward-looking statements and assumptions herein. The cost information is also prepared using current values, but the time for incurring the costs will be in the future and it is assumed costs will remain stable over the relevant period.

By their very nature, forward-looking statements involve inherent risks and uncertainties, both general and specific, and risks exist that estimates, forecasts, projections and other forward-looking statements will not be achieved or that assumptions do not reflect future experience. We caution readers not to place undue reliance on these forward-looking statements as a number of important factors could cause the actual outcomes to differ materially from the beliefs, plans, objectives, expectations, anticipations, estimates assumptions and intentions expressed in such forward-looking statements. These risk factors may be generally stated as the risk that the assumptions and estimates expressed above do not occur, but specifically include, without limitation, risks relating to variations in the mineral content within the material identified as mineral reserves and mineral resources from that predicted; variations in rates of recovery and extraction; developments in world metals and minerals markets; risks relating to fluctuations in the Canadian dollar relative to other currencies; increases in the estimated capital and operating costs or unanticipated costs; difficulties attracting the necessary work force; increases in financing costs or adverse changes to global market conditions and the terms of available financing, if any; tax rates or royalties being greater than assumed; changes in development or mining plans due to changes in logistical, technical or other factors, changes in project parameters as plans continue to be refined; risks relating timing and to receipt of regulatory approvals; adverse changes to government approval processes; the effects of competition in the markets in which the Company operates; operational and infrastructure risks; and the additional risks described in the Company's Annual Information Form, annual financial statements and management's discussion and analysis for the year ended December 31, 2013 and in the feasibility study entitled "Corani Project, Form 43-101F1 Technical Report, Feasibility Study" filed by the Company on December 22, 2011 filed on the SEDAR website in Canada (available at www.sedar.com). The foregoing list of factors that may affect future results is not exhaustive.

When relying on our forward-looking statements, investors and others should carefully consider the foregoing factors and other uncertainties and potential events. The Company does not undertake to update any forward-looking statement, whether written or oral, that may be made from time to time by the Company or on behalf of the Company, except as required by law.

Read the rest of the article at finance.yahoo.com
Data and Statistics for these countries : Canada | Peru | All
Gold and Silver Prices for these countries : Canada | Peru | All

Bear Creek Mining Corporation

DEVELOPMENT STAGE
CODE : BCM.V
ISIN : CA07380N1042
Follow and Invest
Add to watch list Add to your portfolio Add or edit a note
Add Alert Add to Watchlists Add to Portfolio Add Note
ProfileMarket
Indicators
VALUE :
Projects & res.
Press
releases
Annual
report
RISK :
Asset profile
Contact Cpy

Bear Creek Mining is a silver development stage company based in Canada.

Bear Creek Mining develops silver, lead and zinc in Peru, and holds various exploration projects in Peru.

Its main assets in development are SANTA ANA PERU and CORANI in Peru and its main exploration properties are LA YEGUA, DON MARCELO PERU, ATASPACA and TASSA in Peru.

Bear Creek Mining is listed in Canada and in United States of America. Its market capitalisation is CA$ 38.1 millions as of today (US$ 27.9 millions, € 26.1 millions).

Its stock quote reached its lowest recent point on September 17, 2004 at CA$ 0.29, and its highest recent level on October 06, 2006 at CA$ 9.99.

Bear Creek Mining has 103 090 000 shares outstanding.

Your feedback is appreciated, please leave a comment or rate this article.
Rate : Average note :0 (0 vote) View Top rated
 
Annual reports of Bear Creek Mining Corporation
Annual Report 2006
Annual Report 2005
2004 Annual Report
Option Grants of Bear Creek Mining Corporation
3/24/2011 Grants 893,000 Stock Options at $10,77
Nominations of Bear Creek Mining Corporation
8/6/2013Announces Promotion of Peruvian GM Elsiario Antunez De Mayol...
3/16/2012Announces Appointment of New CFO
Financials of Bear Creek Mining Corporation
4/22/2016Board Approves Adoption of Shareholder Rights Plan
Project news of Bear Creek Mining Corporation
8/15/2014Peru hopes to revive Bear Creek mine, avoid legal battle
1/13/2014Announces Start Of Phase I Drilling At Its Carito Gold Proje...
4/15/2013(Corani)Announces Positive Corani Public Hearing and Life of Mine Co...
12/11/2012(Corani)submits Corani ESIA; silver project on track for approval
8/16/2012(Corani)Provides Corani Project and Exploration Update, Peru
10/13/2011(Tassa)Provides Corporate Update; Corani Feasibility Study on Sched...
10/13/2011(Corani)Provides Corporate Update; Corani Feasibility Study on Sched...
7/13/2011(Santa Ana Peru)Announces the Filing of Legal Actions to Protect its Santa A...
6/1/2011(Santa Ana Peru)Reports Peruvian Government Resolution Which Potentially Fur...
2/28/2011(Santa Ana Peru)AWARDS EPCM CONTRACT AND COMPLETES MILESTONE PUBLIC HEARING ...
1/24/2008 Announces First Santa Ana Leachable Silver Deposit Resource...
1/17/2008(Corani)Announces Positive Scoping Study And Updated Resource Estima...
1/15/2008(Corani) Completes Earn-In On Corani Silver Deposit; Final Payment T...
Corporate news of Bear Creek Mining Corporation
7/26/2016Bear Creek Mining Announces Closing of $30 Million Bought De...
7/6/2016Bear Creek Mining Corporation Annolunces Bought Deal Financi...
7/5/2016Bear Creek Mining Addresses Share Price Movement
6/20/2016Bear Creek Mining Grants Incentive Stock Options
4/22/2016Bear Creek Mining Board Approves Adoption of Shareholder Rig...
4/18/2016Bear Creek Mining Addresses Share Price Movement
1/27/2016Bear Creek Mining Provides An Update On Corporate Activities
7/20/2015Bear Creek Mining Files NI 43-101 Technical Report for Coran...
2/23/2015Bear Creek Grants Incentive Stock Options
2/23/2015Bear Creek grants incentive stock options
2/19/2015Bear Creek Provides Update on Feasibility Study, Corani, Per...
2/19/2015Bear Creek provides update on Feasibility Study, Corani, Per...
10/15/2014Bear Creek Provides Corporate Update
10/15/2014Bear Creek Provides Corporate Update
9/8/2014Bear Creek provides update on Corani, Peru optimization and ...
8/12/2014Bear Creek announces its intent to commence an arbitration a...
6/23/2014Bear Creek provides corporate update
5/14/2014Bear Creek says Peru court renews right to revive silver pro...
5/14/2014IIROC Trading Resumption - BCM
5/14/2014Bear Creek Mining Announces Conference Call Details
5/14/2014Bear Creek Announces Favorable Judicial Decision in the Sant...
5/12/2014IIROC Trading Halt - BCM
2/7/2014Files Notice Of Intent To Arbitrate With Peruvian Government...
9/25/2013(Corani)Announces Approval of Corani ESIA, Peru
8/28/2013(Corani)Announces Official Submission Of Responses To Comments; Cora...
6/17/2013Announces Appointments of Three New Officers
5/7/2013Announces Senior Management Change
4/2/2013Announces Adoption of Advance Notice Policy for Future Share...
3/18/2013Announces The Acquisition Of Two New Precious Metals Explora...
3/13/2013Announces Positive Drill Results on Its Sumi Gold Project, P...
2/6/2013Grants Incentive Stock Options
2/5/2013Announces Favorable Ruling In Santa Ana Civil Case, Peru
6/12/2012Grants Incentive Stock Options
4/20/2012Retains Renmark Financial Communications Inc.
1/24/2012Grants Incentive Stock Options
9/2/2011Grants Incentive Stock Options
6/30/2011Expresses Condolences Over the Loss of Karen Swarthout
6/26/2011Peruvian Unrest at Juliaca Airport Occurring 160KM from Proj...
5/24/2011Reports on Peruvian Government Study on Mining Permit Proces...
4/8/2011Provides Update On Its Exploration Programs Including Two Ne...
Comments closed
 
Latest comment posted for this article
Be the first to comment
Add your comment
TSX-V (BCM.V)Other OTC (BCEKF)
0.370-2.63%0.271-3.56%
TSX-V
CA$ 0.370
04/25 16:59 -0.010
-2.63%
Prev close Open
0.380 0.380
Low High
0.365 0.385
Year l/h YTD var.
0.170 -  0.420 105.56%
52 week l/h 52 week var.
0.160 -  0.720 -42.19%
Volume 1 month var.
260,232 68.18%
24hGold TrendPower© : -6
Produces
Develops Lead - Silver - Zinc
Explores for Copper - Gold - Molybdenum
 
 
 
Analyse
Interactive chart Add to compare
Interactive
chart
Print Compare Export
Last updated on : 12/26/2010
You must be logged in to use the porfolio and watchlists (free)
Top Newsreleases
MOST READ
Annual variation
DateVariationHighLow
2024-18.68%
2023-40.13%0.920.41
2022-40.16%1.370.37
2021-59.42%3.370.92
20209.82%4.170.75
 
5 years chart
 
3 months chart
 
3 months volume chart
 
 
Mining Company News
Plymouth Minerals LTDPLH.AX
Plymouth Minerals Intersects Further High Grade Potash in Drilling at Banio Potash Project - Plannin
AU$ 0.12-8.00%Trend Power :
Santos(Ngas-Oil)STO.AX
announces expected non-cash impairment
AU$ 7.70-0.65%Trend Power :
Oceana Gold(Au)OGC.AX
RELEASES NEW TECHNICAL REPORT FOR THE HAILE GOLD MINE
AU$ 2.20+0.00%Trend Power :
Western Areas NL(Au-Ni-Pl)WSA.AX
Advance Notice - Full Year Results Conference Call
AU$ 3.86+0.00%Trend Power :
Canadian Zinc(Ag-Au-Cu)CZN.TO
Reports Financial Results for Q2 and Provides Project Updates
CA$ 0.12+4.55%Trend Power :
Stornoway Diamond(Gems-Au-Ur)SWY.TO
Second Quarter Results
CA$ 0.02+100.00%Trend Power :
McEwen Mining(Cu-Le-Zn)MUX
TO ACQUIRE BLACK FOX FROM PRIMERO=C2=A0
US$ 11.94+9.34%Trend Power :
Rentech(Coal-Ngas)RTK
Rentech Announces Results for Second Quarter 2017
US$ 0.20-12.28%Trend Power :
KEFIKEFI.L
Reduced Funding Requirement
GBX 0.54-2.55%Trend Power :
Lupaka Gold Corp.LPK.V
Lupaka Gold Receives First Tranche Under Amended Invicta Financing Agreement
CA$ 0.06+0.00%Trend Power :
Imperial(Ag-Au-Cu)III.TO
Closes Bridge Loan Financing
CA$ 2.69+13.03%Trend Power :
Guyana Goldfields(Cu-Zn-Pa)GUY.TO
Reports Second Quarter 2017 Results and Maintains Production Guidance
CA$ 1.84+0.00%Trend Power :
Lundin Mining(Ag-Au-Cu)LUN.TO
d Share Capital and Voting Rights for Lundin Mining
CA$ 15.60+1.83%Trend Power :
Canarc Res.(Au)CCM.TO
Canarc Reports High Grade Gold in Surface Rock Samples at Fondaway Canyon, Nevada
CA$ 0.24+0.00%Trend Power :
Havilah(Cu-Le-Zn)HAV.AX
Q A April 2017 Quarterly Report
AU$ 0.20+2.63%Trend Power :
Uranium Res.(Ur)URRE
Commences Lithium Exploration Drilling at the Columbus Basin Project
US$ 6.80-2.86%Trend Power :
Platinum Group Metals(Au-Cu-Gems)PTM.TO
Platinum Group Metals Ltd. Operational and Strategic Process ...
CA$ 1.87+5.65%Trend Power :
Devon Energy(Ngas-Oil)DVN
Announces $340 Million of Non-Core Asset Sales
US$ 52.61+0.98%Trend Power :
Precision Drilling(Oil)PD-UN.TO
Announces 2017Second Quarter Financial Results
CA$ 8.66-0.35%Trend Power :
Terramin(Ag-Au-Cu)TZN.AX
2nd Quarter Report
AU$ 0.04+5.56%Trend Power :