Century Reports 2010 Third Quarter Results and Operational Update For Lamaque and San Juan Gold Mine

( 0 vote, 0/5 ) Print article
  Article Comments Comment this article Rating Follow Company  
0
Send
0
comment
 
Monday, November 15, 2010 Press Release

Century Reports 2010 Third Quarter Results and Operational Update For Lamaque and San Juan Gold Mines

Century Mining Corporation ("Century" or the "Company") (TSX-V: CMM) reports its financial and operating results for the third quarter and nine months ending September 30, 2010. See below for key highlights:

Highlights of Q3
(1) Gold production and revenues above only reflect data from the San Juan mine operation in Peru as all costs related to the Lamaque project, net of any related gold revenues, have been deferred until commercial production has been reached, which is expected in the first half of 2011.

(Canadian $ except as noted)


Third Quarter Ending September 30, 2010 Discussion

The Company reported a net loss of $3.9 million, or $(0.01) per share, in the third quarter of 2010 compared to net earnings of $2.6 million, or $0.01 per share, for the same quarter of 2009. Third quarter results were impacted by lower than anticipated production at the Company's San Juan operation, combined with the delivery, under the Deutsche Bank AG Forward Gold Purchase Agreement, of 2,001 ounces of gold at a price of $561 per ounce, and higher general and administrative expenses.

Earnings from mine operations were down as a result of a lower recovery at the San Juan mine, resulting from campaigning transition ore through the mill, and higher mine cash costs resulting from the CIL plant operating on restricted tonnage.

General and administrative costs in the third quarter of 2010 increased to $4.6 million from $0.3 million in the corresponding period of 2009. Included in the third quarter are a provision of $1.0 million pertaining to the resignation of its previous president and CEO, in July 2010, increased legal and professional fees, increased depreciation, the majority of which related to the depletion of depletable producing properties, and stock-based compensation.

Cash used in operating activities was $5.5 million in the third quarter, compared to cash flow from operating activities of $0.2 million in 2009. In addition to the net loss, the Company repaid $2.8 million of accounts payable during the quarter.

The Company invested $8.7 million during the quarter ended September 30, 2010, of which $5.3 million was used for the purchase of new low profile underground equipment and the completion of the refurbishment of the mill and crusher at the Lamaque project.

In the third quarter 2010, the Company raised $13.1 million in equity, of which $6.2 million was from equity private placements and $6.9 million was from the exercise of warrants. In addition, the Company completed new lease obligations with respect to the equipment of $4.1 million.

As of September 30, 2010 Century has delivered 3,668 ounces under the terms of the agreement and has an obligation to deliver 57,515 ounces in future periods in accordance with the Deutsche Bank AG Forward Gold Purchase Agreement.

Nine Months Ending September 30, 2010 Discussion

The Company reported a net loss of $4.2 million, or a loss per share of $(0.01) for the nine months ended September 30, 2010, as compared to earnings of $5.4 million, or earnings per share of $0.01 for the corresponding period of 2009. Revenues were higher for the period, due in part to increased production on a year-to-date basis for the San Juan operation and higher realized gold prices, offset by the delivery under the Deutsche Bank AG Forward Gold Purchase Agreement of 3,668 ounces of gold at $561 per ounce.

General and administrative expenses for the nine months ended September 30, 2010, were $8.4 million, up from $2.3 million reported for the corresponding period in 2009. In addition to the $1.0 million provision for the resignation of the Company's president and CEO, additional legal and professional fees, increased depreciation, the majority of which related to the depletion of depletable producing properties, and stock-based compensation were recorded.

Cash used in operating activities was $11.4 million, as compared to $0.8 million for the corresponding period in 2009.

In addition to the operating loss, inventories at the two facilities increased by $2.2 million, the bulk of which pertains to the in-process gold at the Lamaque facility during its ramp-up phase, and the repayment of $5.8 million of trade accounts payable.

The Company spent $18.6 million on new equipment, as well as the refurbishment of the mill and crusher at the Lamaque project. The Company also received $5.0 million from Deutsche Bank AG, having successfully achieved Performance Hurdle A in the second quarter of 2010.

For the nine months ended September 30, 2010, the Company raised $13.9 million from the exercise of shareholder warrants and equity private placements. The Company has entered into lease arrangements for the purchase of the low profile underground equipment and the crusher and conveyors, in the amount of $7.5 million, expiring in 2015.

Keith Hulley, Interim CEO of Century commented, "The Lamaque third quarter operational results were below expectations, but the Company is confident that the operational issues will improve as we accelerate development and production, control dilution, and mine underground zones that are more representative of the expected head grade and reserve grades. The recent hiring of key personnel and procurement of key underground equipment have contributed to production increases in the most recent four weeks, bringing the operation to in excess of 1,000 tonnes per day ("TPD"). After enduring significant delays during the commissioning of the mine, the Company anticipates reaching commercial production in the first half of 2011, and has kept its guidance for the Lamaque operation at 80,000 to 90,000 ounces for 2011."

Mine Operational Statistics (Nine Months Ending September 30, 2010):

 

Lamaque Gold Mine
Qu�bec, Canada

San Juan Gold Mine
Peru

 

 

 

Tonnes Milled

84,083

83,627

Head grade (g/t Au)

3.25

6.36

Recovery (%)

95.47

80.31

Recovered gold (oz)

8,401

14,526

Realized price (US$/oz gold)

n/a

1,178

Mine Site Cash cost (US$/oz gold)

n/a

573


Lamaque Operational Update and Guidance

In the first quarter of 2010, the Company initiated underground development at the Lamaque gold project to re-open and advance the operation to gold production by the second quarter of 2010. The operation commenced the execution of the underground mine plan by focusing on three separate mining zones, each accessed via the existing open pit. The production zones, named the Lamaque Flats, Bedard Dyke, and North Wall, will contribute the combined production tonnage leading to commercial gold production by the first half of 2011.

During the start-up of the operation, the Lamaque Flats zone commenced production on schedule in the second quarter of 2010, and has produced near its expected rate of production of between 400 -- 700 TPD, pouring its first gold in late April 2010. During the commissioning of the Lamaque project, the Company encountered setbacks in the start-up of the operation, including delayed permitting of the Bedard Dyke, late delivery of underground mine equipment, and late hiring of key senior operations management personnel.

The Company continues mining underground in the Lamaque Flats zone utilizing three low profile jumbo drills and three low profile scooptrams, among other mine equipment. Within the Lamaque Flats, the underground development team continues its ramping efforts to reach the North Wall zone in preparation for mining in the first quarter of 2011. At the Bedard Dyke, the contractor's work force continues the underground development of the ramp system and the concurrent completion of the sublevel infrastructure to prepare for long-hole stoping of the mineralized zone in the fourth quarter of 2010. The Company is currently removing ore from the Bedard Dyke through slashing out and sill cutting of the sublevels.

During the months of September and October 2010, the Company was successful in opening up the Bedard Dyke, hiring the senior operations staff, and receiving the necessary underground mine equipment to accelerate development and increase production to approximately 1,000 TPD by November 2010. The Company anticipates reaching 1,500 TPD by the first quarter of 2011 and reaching a steady state production rate in excess of 2,100 TPD by the fourth quarter of 2011.

Mine infrastructure facilities, including the upgrade to the crusher facility, offices, warehouse, mine dry, core logging and sample preparation areas are completed and fully-operational. The current underground workforce includes 170 full time Century Mining employees, along with 25 contract miners. Century's workforce will continue to grow, and will displace the majority of the contract workforce by 2012.

Recent underground definition drilling at the Bedard Dyke continues to confirm the zone of mineralization in the mine plan that will form part of the initial underground production in this second area of the mine development plan. Ongoing underground definition drilling continues and results will be released when modeling and resource confirmation is complete.

The Lamaque mine has produced 8,401 ounces of gold through September 30, 2010, of which 4,457 ounces were produced during the third quarter of 2010. The revenues associated with the sales of these ounces have been offset against the deferred development costs, and this treatment will continue until the project reaches commercial production in 2011. The delays identified earlier have contributed to lower than anticipated production from the Lamaque operation, and the need to lower its 2010 gold production guidance to 18,000 to 20,000 ounces from 40,000 to 45,000 ounces. The guidance remains unchanged for 2011 at 80,000 to 90,000 ounces, and the Lamaque operation is expected to reach an annualized gold production run rate of 100,000 ounces by the end of 2012, with a mine life of 11 years and life of mine cash costs forecast to be within the range of US$450 to US$550 per ounce.

San Juan Operational Update and Guidance

During the first nine months of 2010, San Juan produced 14,526 ounces of gold at an average mine site cash cost of $573 per ounce, with 4,531 ounces of gold in the third quarter at a mine site cash cost of $658 per ounce. The San Juan operation is expected to produce at approximately 4,500 to 5,000 ounces of gold per quarter, and production guidance remains at 18,000 to 20,000 ounces for 2010.

In the first nine months of 2010, cash costs increased due to additional expenses related to the construction of a new cyanide tailings pond facility, and an associated shut down of the mill circuits for a period of time during the past two quarters. The shutdown of one of the San Juan primary 6 x 6 mills was for refurbishing of the mill and installation of a new liner system. The mill continued operating on the smaller standby 5 x 6 mill, however at a lower mill throughput. The CIL plant operated on restricted tonnage in the third quarter and the project was completed in July 2010. Also, transition ore from mining at the Jessica vein system required campaigning through the mill and produced a lower recovery. The average mine site cash cost for the San Juan mine for 2010 has consequently increased from $550-$570 per ounce to $575-$625 per ounce, but is expected to decrease in 2011 back to the $550-$570 range.

The Company plans to make capital investments at the San Juan operation over the next 12 months to increase production up to 24,000 ounces in 2011. The mine is continuing with improvements of the tailings dam to increase tailings storage capacity for the planned future production increases. Gold production at San Juan is expected to reach 30,000 ounces of gold per year by the end of 2012.

Conference Call: November 16, 2010 11:00am Pacific Standard Time (PST)

The Company's senior management will host a conference call on Tuesday, November 16, 2010 at 11:00 AM (P.S.T.) to discuss financial results and provide an update of the Company's activities. Mining analysts, investors and the media are invited to dial toll-free 1-888-942-9044 in Canada and the United States, or 1-517-308-9426 from international locations (normal toll rates do apply) and state the verbal passcode "CenturyMining". To ensure participation, please dial approximately 5 minutes before the scheduled start of the call.

The conference call will be archived for later playback and may be accessed by dialing 1-888-562-7623 or 1-402-220-6504 and entering the pass code 1324#, or via www.centurymining.com via a downloadable audio file. The archived playback will be available until November 30, 2010.

The third quarter Financial Statements and Management's Discussion & Analysis are available on the Company's website at www.centurymining.com and have been filed on www.sedar.com.

About Century Mining Corporation

Century Mining Corporation is a Canadian junior gold producer and holds strategic land positions in Canada, the United States and Peru. The consolidated production outlook for the Company is approximately 36,000 to 40,000 ounces in 2010, 105,000 ounces in 2011, and 120,000 in 2012. The Company's strategy is to grow to an intermediate gold producer through existing mine expansions and acquisitions of other strategic and synergistic gold opportunities.

On behalf of Century Mining Corporation,

"Keith Hulley"

Interim CEO

For further investor information, please contact:

Peter A. Ball, Vice President Investor Relations
E-mail: pball@centurymining.com
Phone: (360) 332-4653
Toll Free: (877) 284-6535
Website: www.centurymining.com

Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.

Caution Concerning Forward-Looking Information

This press release contains forward looking statements within the meaning of the United States Private Securities Litigation Reform Act of 1995 and forward-looking information within the meaning of applicable Canadian securities laws. We use words such as "may", "will", "should", "anticipate", "plan", "expect", "believe", "estimate" and similar terminology to identify forward-looking statements and forward-looking information. Such statements and information are based on assumptions, estimates, opinions and analysis made by management in light of its experience, current conditions and its expectations of future developments as well as other factors which it believes to be reasonable and relevant. Forward-looking statements and information involve known and unknown risks, uncertainties and other factors that may cause our actual results to differ materially from those expressed or implied in the forward-looking statements and information and accordingly, readers should not place undue reliance on such statements and information. Risks and uncertainties that may cause actual results to vary include but are not limited to the speculative nature of mineral exploration and development, including the uncertainty of reserve and resource estimates; operational and technical difficulties; the availability to the Company of suitable financing alternatives; fluctuations in gold and other commodity prices; changes to and compliance with applicable laws and regulations, including environmental laws and obtaining requisite permits; political, economic and other risks arising from our South American activities; fluctuations in foreign exchange rates; as well as other risks and uncertainties which are more fully described in our annual and quarterly Management's Discussion and Analysis included in this Annual Report, in our Annual Information Form and in other filings made by us with the Securities and Exchange Commission and with Canadian securities regulatory authorities and available at www.sedar.com.

While the Company believes that the expectations expressed by such forward-looking statements and forward-looking information and the assumptions, estimates, opinions and analysis underlying such expectations are reasonable, there can be no assurance that they will prove to be correct. In evaluating forward-looking statements and information, readers should carefully consider the various factors which could cause actual results or events to differ materially from those expressed or implied in the forward-looking statements and forward-looking information.



View this News Release in PDF:
Associated File: http://www.centurymining.com/i/pdf/2010-11-15_NR.pdf
71 KB in size, approx. 14 seconds to download at 56.6Kbps
 
Home | Corporate | Operations | Investors | News | Careers | Contact | Disclaimer | Subscribe |
This email was sent to .com

 
Data and Statistics for these countries : Canada | Peru | All
Gold and Silver Prices for these countries : Canada | Peru | All

Century Mining Corporation

PRODUCER
CODE : CMM.V
CUSIP : 15662P
Follow and Invest
Add to watch list Add to your portfolio Add or edit a note
Add Alert Add to Watchlists Add to Portfolio Add Note
ProfileMarket
Indicators
VALUE :
Projects & res.
Press
releases
Annual
report
RISK :
Asset profile
Contact Cpy

Century Mining is a gold producing company based in United states of america.

Century Mining holds various exploration projects in Canada.

Its main assets in production are LAMAQUE and SIGMA-LAMAQUE in Canada and SAN JUAN in Peru and its main exploration properties are BOURLAMAQUE, JUNEAU, LOUVICOURT, TREADWELL, NORTH BELT LEASES, YAKIMA, EAGLE RIVER, SWEETHEART, PATTON, PETERSON, DREAM and BESSIE in Canada and COLINA DORADA in Peru.

Century Mining is listed in Canada and in United States of America. Its market capitalisation is CA$ 26.2 millions as of today (US$ 20.8 millions, € 16.9 millions).

Its stock quote reached its highest recent level on December 29, 2006 at CA$ 1.89, and its lowest recent point on November 28, 2008 at CA$ 0.01.

Century Mining has 37 960 000 shares outstanding.

Your feedback is appreciated, please leave a comment or rate this article.
Rate : Average note :0 (0 vote) View Top rated
 
Annual reports of Century Mining Corporation
2007 Annual report
Financings of Century Mining Corporation
9/6/2013Castle Mountain Announces Closing of Private Placement
8/16/2013Castle Mountain Announces Private Placement
6/13/2011Closes Flow-Through Financing and Receives Working Capital L...
12/1/2010Closes $2.5 Million Flow-Through Private Placement
9/18/2008ANNOUNCES UP TO $3.7 MILLION OF FINANCINGS
6/6/2008ANNOUNCES UP TO C$6 MILLION IN FINANCINGS
5/20/2008 CLOSES FLOW-THROUGH AND UNIT FINANCINGS
3/28/2008ANNOUNCES UP TO C$4.5 MILLION IN FLOW-THROUGH AND UNIT FINAN...
1/11/2008CLOSES FLOW-THROUGH SHARE FINANCINGS
Option Grants of Century Mining Corporation
5/16/2011Engages Terre Partners as Investor Relations Consultants
Nominations of Century Mining Corporation
6/2/2010Appoints VP Geology
1/12/2010Appoints New Members to Board of Directors January 12, 2010
2/20/2008APPOINTS NEW CHIEF FINANCIAL OFFICER
11/7/2007APPOINTS NEW GENERAL MANAGER AT LAMAQUE COMPLEX
Financials of Century Mining Corporation
6/25/2008REPORTS 2007 FULL YEAR FINANCIAL RESULTS
12/1/2007Third quarter results confirm decision to accelerate shift i...
5/31/2007Reports First Quarter Net Income of $2.0 Million and Operati...
4/16/2007Achieves Fourth Quarter Net Income of C$2.6 Million and Reco...
Project news of Century Mining Corporation
5/2/2011(Lamaque)Lamaque Mine Receives Certificate of Authorization to Expand...
3/8/2011(Lamaque)Provides Operational and Financial Update for Lamaque Mine
2/3/2011(San Juan)Reports on 2010 Gold Production and Guidance for 2011 Produc...
2/3/2011(Lamaque)Reports on 2010 Gold Production and Guidance for 2011 Produc...
7/6/2010(Lamaque)Provides Operational Progress Update
4/28/2010(Lamaque)Lamaque Mill Facility Fully Operational & Provides Further P...
4/13/2010(Lamaque)Employees Ratify Terms of Collective Agreement at Lamaque Go...
2/2/2010(San Juan)Workforce Takes Illegal Strike Action
7/3/2008(Sigma-lamaque)ANNOUNCES TEMPORARY CURTAILMENT OF LAMAQUE UNDERGROUND PRODU...
2/27/2008(Sigma-lamaque)FILES FULL LAMAQUE TECHNICAL REPORT
1/14/2008Announces Updated NI 43-101 Reserves and Technical Report
11/6/2007(Bourlamaque)Converts Sigma-Lamaque to Full Underground Operation
2/21/2006forecasts production of 90,000 ounces of gold at a cash cost...
Corporate news of Century Mining Corporation
6/29/2015Castle Mountain Announces Name Change to NewCastle Gold Ltd....
4/2/2015Castle Mountain Announces Director Resignation from the Boar...
3/11/2015Castle Mountain Announces Positive Initial Results from Meta...
12/11/2014Castle Mountain Mining Provides Corporate Update
11/4/2014OTC Markets Group Welcomes Castle Mountain Mining to OTCQX®
11/3/2014Castle Mountain Mining to Trade on OTCQX
9/8/2014Castle Mountain Mining Board Appoints Mark Wayne as Chairman
8/20/2014Castle Mountain Mining Reports 7.46 g/t Gold Over 102.1 Metr...
8/7/2014Castle Mountain Announces Grant of Stock Options
7/31/2014Castle Mountain Mining Selects M3 Engineering as Lead on Fea...
7/7/2014Castle Mountain Mining Provides Corporate Update
6/5/2014Castle Mountain Mining Files Preliminary Economic Assessment...
4/24/2014Castle Mountain Mining's Preliminary Economic Assessment Del...
7/30/2013CMM Granted Five Year Extension to Mining Permit at Castle M...
7/16/2013Castle Mountain Reports 74 m of 1.44 g/t Au From Final Resul...
6/20/2013Initial Results from the Phase 1 Drill Program at Castle Mou...
7/12/2011(San Juan)Estimates Second Quarter Production at Lamaque and San Juan
6/20/2011White Tiger Gold and Century Mining Announce Further Update ...
6/7/2011(Lamaque)Provides Gold Production Update on the Lamaque Mine
5/26/2011White Tiger Gold and Century Mining Announce Update to Propo...
4/26/2011White Tiger Gold Ltd. and Century Mining Corporation Announc...
4/18/2011Grants Stock Options
4/11/2011Reports Year-End 2010 Results
4/6/2011(San Juan)Estimates First Quarter Production and Discusses Peruvian Or...
3/22/2011Announces Receipt of Deutsche Bank Consent to the Proposed B...
3/14/2011White Tiger Gold Ltd. and Century Mining Corporation Announc...
7/13/2010Union Securities Initiates Analyst Coverage of Century Minin...
6/15/2010Annual Meeting Results
5/22/2010Trading To Be Reinstated On May 25, 2010
5/15/20102009 Year End Financial Statements
1/6/2009REPORTS SIGNIFICANT PRIVATE PURCHASE OF CENTURY SHARES BY IN...
3/21/2008 PROVIDES UPDATE ON REGULATORY ISSUES
2/21/2008Receives Updated Lamaque Underground Permit
2/4/2008ANNOUNCES CHANGES TO BOARD OF DIRECTORS
1/17/2008RESPONDS TO SULLIDEN PRESS RELEASE
11/28/2007ANNOUNCES TAKEOVER BID FOR SULLIDEN EXPLORATION
10/31/2007EXTENDS MATURITY OF ITS OUTSTANDING LONG TERM DEBT
10/22/2007POSTS COURT DOCUMENTS THAT SUPPORT ALGAMARCA’S LEGAL POSITIO...
10/4/2007ANNOUNCES TAKEOVER BID FOR SULLIDEN EXPLORATION INC.
8/15/2007PERUVIAN COURT RULES IN ALGAMARCA’S FAVOR KEY ADVANCE FOR CE...
8/7/2007)Agrees to buy advanced exploration property in Peru
8/2/2007WELCOMES NEW CHIEF FINANCIAL OFFICER
7/10/2007Continues to create unnecessary delays in the legal proceedi...
6/28/2007Completes Acquisition of Third Mine
6/6/2007Provides an update on the Poderosa litigation in Peru
5/31/2007Algamarca Refutes Sulliden Press Release And Accurately Stat...
5/16/2007Breaking News Alert from Century Mining
5/15/2007Breaking News Alert from Century Mining
4/20/2007Breaking News Alert from Century Mining
5/19/2006reports 1st quarter operating profit of $1,9 million at Sigm...
3/13/2006debenture holders convert oustanding debentures into common ...
Comments closed
 
Latest comment posted for this article
Be the first to comment
Add your comment
TSX-V (CMM.V)Other OTC (CMNZF)
0.690+0.00%0.260+18.18%
TSX-V
CA$ 0.690
02/20 09:30 -
0%
Prev close Open
0.690 0.690
Low High
0.690 0.690
Year l/h YTD var.
 -  -
52 week l/h 52 week var.
- -  0.690 -%
Volume 1 month var.
0 -%
Produces Gold
Develops
Explores for Copper - Gold - Silver - Zinc
 
 
 
Analyse
Interactive chart Add to compare
Interactive
chart
Print Compare Export
Last updated on : 1/20/2010
You must be logged in to use the porfolio and watchlists (free)
Top Newsreleases
MOST READ
Annual variation
DateVariationHighLow
 
5 years chart
 
3 months chart
 
3 months volume chart
 
 
Mining Company News
Plymouth Minerals LTDPLH.AX
Plymouth Minerals Intersects Further High Grade Potash in Drilling at Banio Potash Project - Plannin
AU$ 0.12-8.00%Trend Power :
Santos(Ngas-Oil)STO.AX
announces expected non-cash impairment
AU$ 7.75+0.52%Trend Power :
Oceana Gold(Au)OGC.AX
RELEASES NEW TECHNICAL REPORT FOR THE HAILE GOLD MINE
AU$ 2.20+0.00%Trend Power :
Western Areas NL(Au-Ni-Pl)WSA.AX
Advance Notice - Full Year Results Conference Call
AU$ 3.86+0.00%Trend Power :
Canadian Zinc(Ag-Au-Cu)CZN.TO
Reports Financial Results for Q2 and Provides Project Updates
CA$ 0.12+4.55%Trend Power :
Stornoway Diamond(Gems-Au-Ur)SWY.TO
Second Quarter Results
CA$ 0.02+100.00%Trend Power :
McEwen Mining(Cu-Le-Zn)MUX
TO ACQUIRE BLACK FOX FROM PRIMERO=C2=A0
US$ 11.96+9.54%Trend Power :
Rentech(Coal-Ngas)RTK
Rentech Announces Results for Second Quarter 2017
US$ 0.20-12.28%Trend Power :
KEFIKEFI.L
Reduced Funding Requirement
GBX 0.54-2.55%Trend Power :
Lupaka Gold Corp.LPK.V
Lupaka Gold Receives First Tranche Under Amended Invicta Financing Agreement
CA$ 0.06+0.00%Trend Power :
Imperial(Ag-Au-Cu)III.TO
Closes Bridge Loan Financing
CA$ 2.64+10.92%Trend Power :
Guyana Goldfields(Cu-Zn-Pa)GUY.TO
Reports Second Quarter 2017 Results and Maintains Production Guidance
CA$ 1.84+0.00%Trend Power :
Lundin Mining(Ag-Au-Cu)LUN.TO
d Share Capital and Voting Rights for Lundin Mining
CA$ 15.67+2.28%Trend Power :
Canarc Res.(Au)CCM.TO
Canarc Reports High Grade Gold in Surface Rock Samples at Fondaway Canyon, Nevada
CA$ 0.24+0.00%Trend Power :
Havilah(Cu-Le-Zn)HAV.AX
Q A April 2017 Quarterly Report
AU$ 0.19+0.00%Trend Power :
Uranium Res.(Ur)URRE
Commences Lithium Exploration Drilling at the Columbus Basin Project
US$ 6.80-2.86%Trend Power :
Platinum Group Metals(Au-Cu-Gems)PTM.TO
Platinum Group Metals Ltd. Operational and Strategic Process ...
CA$ 1.87+5.65%Trend Power :
Devon Energy(Ngas-Oil)DVN
Announces $340 Million of Non-Core Asset Sales
US$ 52.38+0.54%Trend Power :
Precision Drilling(Oil)PD-UN.TO
Announces 2017Second Quarter Financial Results
CA$ 8.66-0.35%Trend Power :
Terramin(Ag-Au-Cu)TZN.AX
2nd Quarter Report
AU$ 0.04+0.00%Trend Power :