Globestar Mining Corporation

Published : August 16th, 2007

CERRO DE MAIM'N PROJECT

( 0 vote, 0/5 ) Print article
  Article Comments Comment this article Rating Follow Company  
0
Send
0
comment
 
 

      

GLOBESTAR'S CERRO DE MAIM?N PROJECT:   

Proven and Probable Reserves Tonnage Increase by 82%, 36% Increase in Cu Production, 14% Decrease in Operating Costs to US$0.42/lb Cu
   

TORONTO, Ontario - August 16th, 2007 -- GlobeStar Mining Corporation ("GlobeStar" or the "Company") (TSX: GMI) announced today that it has received and will file shortly an independent National Instrument 43-101 compliant technical report ("Technical Report") updating the mineral resource and reserve estimates for its wholly owned Cerro de Maim?n Project currently under construction. The Project, which is slated to commence operation in the summer of 2008, will initially produce copper concentrates from the sulphide flotation circuit and gold and silver as dor? from the oxide cyanidation circuit.  The Technical Report also details the Project's updated capital and operating cost estimates, as well as incorporating scope changes from the last Technical Report filed by the Company on September 19th, 2006.

 

 "Recent drilling results, plus exceptional work by GlobeStar's development team and their consultants, has resulted in an increase in size, profitability and longevity of the Company's flagship project," commented Bill Fisher, GlobeStar's CEO, "The Company's value is underpinned by Cerro de Maim?n's independently prepared Technical Report, coupled with considerable upside potential from its aggressive nickel and copper/gold exploration programs."

 

The Technical Report was prepared for the Company by Micon International Limited ("Micon") in Toronto.  All currency amounts are in US dollars ("$") unless otherwise stated.

 

Highlights of the Technical Report

 

Highlights of this Technical Report are set out below. Data from the Project's earlier Technical Report dated September 19th, 2006 are in brackets for comparison:

 

?         Proven and probable reserves have increased by 82% to 6 million tonnes (3.3 million)

?         Mine life increased by 34% to 9 years, spanning 10 calendar years at a higher annual throughput (6.7 years);

?         Pre-tax net present value at an 8% discount rate is projected at $172 million ($36 million) and after-tax net present value at the same discount rate is projected at $131 million ($23 million);

?         Internal rate of return (IRR), after-tax, is estimated at 58% (26%);

?         15 month capital pay-back (29 months);

?         Life-of-mine production is anticipated to total 229 million pounds of copper (169 million pounds) a 36% increase, 130,000 ounces of gold (83,000 ounces) a 57% increase and 4.1 million ounces of silver  (2.8 million ounces), a 46% increase;

?         Operating costs, including site costs, freight, and maintenance are expected to increase to an average of approximately $15 million per year ($11 million) due to higher production levels.  The total life-of-mine average cost of production for copper from the sulphide plant is expected to decrease by 14% to $0.42 per lb ($0.48 per pound), net of  by-product credits;

?         Total project capital expenditure over the life-of-mine is estimated to be $68.6 million ($47 million);and

?         Metal price assumptions used in the Technical Report were $2.45 per pound of copper ($1.15), $543 per ounce of gold ($392), and $10.00 per ounce of silver ($5.98).  On August 9, 2007, the Company announced that as part of its mandatory hedging program, it hedged 57,900 ounces of gold at $650 per ounce, and 1,440,000 ounces of silver at $11.50 per ounce. The gold price achieved is $107 per ounce higher and the silver price is $1.50 per ounce higher than the assumptions in the Technical Report's reserve and revenue calculations, a positive difference of US$ 8.36 million.

 

Project Summary

 

GlobeStar is currently developing its 100% owned Cerro de Maim?n project through its wholly-owned subsidiary, Corporaci?n Minera Dominicana ("CMD"). The project falls entirely within the Maim?n Mining Block ("Mining Block C1"), which was part of the Quisqueya No. 1 exploitation concession originally held by Falconbridge Dominicana C. por A. GlobeStar has acquired, through CMD, exclusive rights to explore and develop Mining Block C1 from Falconbridge Dominicana on March 1, 2002.  The project is located in the Dominican Republic approximately 75 kilometers northwest of the capital city of Santo Domingo. It is near the town of Maim?n in Monse?or Nouel Province.

 

All of the permits for construction and operation of the mine are in place, and the Company is fully financed through construction, having raised C$61.8 million equity and debt of US$45 million over the last 12 months (see recent release of August 9, 2007). Construction of the processing plants began in April 2007.  GlobeStar's current construction schedule received from the Company's engineers Met-Chem Canada Inc. ("MetChem") and construction manager, RSW International, Inc., (both companies located in Montreal) targets commissioning and start-up of the Project in the summer of 2008. 

 

 

Technical Report

 

Micon was retained to review, audit and take responsibility for an "in-house" mineral resource and updated mineral reserve estimate prepared for the Cerro de Maim?n Project.  Messrs. Paul Roos, PGeo., Harry Burgess, PEng., and Ian Ward, PEng. of Micon are the "Qualified Persons" responsible for the Technical Report prepared in accordance with National Instrument 43-101.  Mr. Roos was responsible for the resource estimation. Mr. Ward for the metallurgy, mill operating costs and capital costs sections, and Mr. Burgess was responsible for the mineral reserve estimates, mine operating costs, project capital costs, and financial sections of the Technical Report.

 

Production Plan

 

The sulphide mineral reserves have been increased to 4.8 million tonnes (previously 2.8 million tonnes), an increase of 71%. In addition, the oxide reserve has been increased to approximately 1.2 million tonnes (previously 0.6 million tonnes), an increase of 100%.  These changes result in an increase in mine life to 9 years, with the plant expansions detailed below. The annual throughput of the oxide circuit has been increased by 200 tonnes per day to 700 tonnes per day or 252,000 tonnes per year, a result of the oxide reserve increase. The oxide circuit is to be converted around year five to a second sulphide circuit once the oxide reserve is completely processed, increasing the annual sulphide milling rate by 44% from 1,300 tonnes per day or 468,000 tonnes per year to 1,875 tonnes per day or 675,000 tonnes per year.  

 

 


 

Estimated Mineral Reserves and Resources

 

The estimated mineral reserves and resources have been prepared in accordance with National Instrument 43-101 Standards and CIM definitions.

 

The mineral resource estimate was prepared using an electronic block model and MineSight? software.  The deposit consists of two parts, a Cu-Zn-Au-Ag bearing massive sulphide and an overlying Au-Ag bearing oxide deposit that formed by weathering of the massive sulphide. Data in sufficient quantities to model variograms were found in both domains; hence grade interpolation was performed by ordinary kriging as well as inverse distance weighting methods.  A summary of the mineral resource prepared by GlobeStar, and verified by Micon, is set out in Table 1 below. The estimate is as of June 30th, 2007:

 

Table 1
Cerro de Maim?n Deposit Mineral Resource

 

Mineral Resource - Oxide

Class

Tonnes

Au(g/t)

Ag(g/t)

AuEquiv

Ounces Au

Ounces Ag

Measured (M)

985,172

1.86

33.2

2.40

58,828

1,051,146

Indicated (I)

261,407

1.39

23.4

1.78

11,713

196,929

M + I

1,246,579

1.76

31.1

2.27

70,541

1,248,075

Oxide Resource is summarized at a 0.50 g/t equivalent gold cut-off grade (AuEquiv), where

AuEquiv = Au + Ag * AgFactor   [AgFactor = 0.01630] 

 

 

Mineral Resource - Sulphide

Class

Tonnes

Cu(%)

Au(g/t)

Ag(g/t)

Zn(%)

Pounds Cu

Ounces Au

Ounces Ag

Pounds Zn

Measured (M)

5,628,632

2.30

0.91

33.3

1.46

285,868,560

164,955

6,030,179

181,517,189

Indicated (I)

1,739,214

1.25

0.73

28.7

1.31

47,862,876

40,634

1,603,996

50,063,877

M + I

7,367,846

2.05

0.87

32.2

1.43

333,731,436

205,589

7,634,175

231,581,065

Inferred

142,283

1.20

0.71

34.6

1.12

3,758,520

3,249

158,491

3,522,333

Sulphide Resource is summarized at a 0.30% Cu cut-off grade 

 

Estimated mineral resources that are not mineral reserves do not have demonstrated economic viability.

 

Pit shells have been determined using the Lerchs-Grossmann algorithm, based on mining blocks, which include all mining and haulage costs for waste and all mining, processing, transport, off-site treatment and administration costs for ore. Typical pit rim costing is applied to determine the ore/waste split. Allowance for mining recovery and waste dilution is included in the resource estimation procedure. The combined oxide and sulphide mineral reserve tonnage, determined by the current mining planning, is 6 million tonnes, at a grade of 2.08% Cu, 34.56 g/t Ag and 1.13 g/t Au. The total waste to be removed is estimated at 46 million tonnes, rendering a strip ratio of approximately 7.7:1. The individual oxide and sulphide mineral reserves estimates are presented below in Table 2. The estimate is current as of June 30th, 2007.


 

 

Table 2
Cerro de Maim?n Deposit Estimated Mineral Reserves

 

Mineral Reserves - Oxide

 

Tonnes

Ag(g/t)

Au(g/t)

Proven

927,274

37.1

1.95

Probable

230,093

23.9

1.48

Total

1,157,367

34.5

1.86

 

Mineral Reserves - Sulphide

 

Tonnes

Cu(%)

Ag(g/t)

Au(g/t)

Proven

4,285,800

2.66

35.7

0.98

Probable

538,760

1.52

28.7

0.78

Total

4,824,560

2.54

34.9

0.96

 

The mineral reserve estimates presented in Table 2 are included in the mineral resource estimates described above and presented in Table 1.

 

Metallurgical Recoveries

 

There have been no changes to the metallurgical recoveries previously determined for the Project.  Recoveries used in the Technical Report are summarized in the table below:

 

Table 3

Cerro de Maim?n Recoveries

 

Sulphide Flotation Recoveries

Cu Met Recovery

85.0%

Ag Met Recovery

55.0%

Au Met Recovery

45.0%

 

 

Oxide Mill Recoveries

Recovery Au

90.8%

Recovery Ag

87.1%

 

 

The Project currently has no credit for zinc, which is treated as a penalty in the copper concentrates.  The Company is currently conducting a metallurgical test program at SGS Lakefield under the supervision of Micon to optimize revenues. The Proven and Probable reserves contain 160 million pounds of zinc in the sulphide portion.

 

 


 

Capital Costs Estimate

 

As part of the detailed engineering, the capital costs have been estimated by GlobeStar and Met-Chem, the Company's engineers, and were verified by Micon.  The capital costs are considered to be within an accuracy range of +/- 10%. To date, all of the major equipment has been ordered and the delivery incorporated into the Project schedule.  The estimated capital costs are summarized in Table 4 below.

 

The current capital costs estimate are higher than the September 19th, 2006 Technical Report, but represent several significant scope changes as well as increased prices due to general cost escalation since the previous Technical Report. Significant scope changes include:

 

?         Installation of a 6.8 MW generating plant onsite to ensure a stable source of electricity from which to run the processing plants and related infrastructure;

?         A conventional and fixed crushing system as opposed to the previously scoped portable crushing system.  The conventional crushing system is intended to ensure increased operating time and lower overall operating costs due to lower maintenance costs;

?         Increase of oxide circuit throughput from 500 tonnes per day to 700 tonnes per day and subsequent conversion of the oxide circuit for sulphide processing, resulting in an increase of sulphide ore  throughput from 1,300 tonnes per day to 1,875 tonnes per day;

?         An increase in pre-production stripping of waste and overburden reflecting an increase in estimated mineral reserves;

?         Additional land purchases to accommodate a larger footprint of the operations;

?         Surface water collection pond sufficient to handle a 24 hour, 25 year storm event; and

?         Additional geotechnical and environmental studies to ensure an environmentally and technically sound project.

 

The following table summarizes the pre-production capital costs estimate.  Costs include direct and in-direct costs, owner's costs, as well as capitalized pre-stripping mining costs, taxes and duties, and a 10% contingency.

 

Table 4
CMD Capital Expenditure
s

($000s, Q1 2007 Value)

 

Total Project Capital Costs Estimate in $000s

Mining

5,878

Site Earthworks

4,352

Crushing

2,971

Sulphide Plant

8,280

Oxide Plant

6,087

Generating Plant

5,477

Tailings Disposal

1,125

Reagents

248

Surface Water

4,156

Plant Air

206

Mobile Equipment

250

Inventory & Spares

1,122

Owner's Overhead & Indirect

14,631

Subtotal Before Contingency & Taxes

54,783

Contingency

5,477

Taxes

8,374

Total Project Capital Costs Estimate

68,634

 

The sustaining estimated capital requirements, as estimated by GlobeStar are summarized in Table 5 below.

 

Table 5

Project Life-of-Mine Estimated Sustaining Capital Costs

(in $000s, Q1 2007 Value)

 

Project Life-Of-Mine Estimated  Sustaining Capital Costs

 

2007P

2008P

2008/09

2009/10

2010/11

2011/12

2012/13

2013/14

2014/15

2015/16

2016/17

Total

Mill

 -

 -

 -

 -

 -

 -

 -

 -

 -

 -

 -

 -

Sulphide Mill Exp

 

 

 

 

 -

 -

 200

50

 -

 -

 -

 250

Mine Dewatering

 -

 

50

 -

 -

50

 -

 -

50

 -

 -

 150

Pit Drain Holes

 -

 

25

25

25

25

25

25

25

25

 -

 200

Mobile Equipment

 -

 

25

 -

25

 -

 -

 -

 -

 -

 -

50

Vehicles

 -

 -

50

 

50

 -

50

 

50

 

 -

 200

Tailing Cell # 2

 -

 

 225

 -

 -

 -

 -

 -

 -

 -

 -

 225

Tailing Cell # 3

 -

 

 

 225

 -

 -

 -

 -

 -

 -

 -

 225

Total

 -

 -

375

250

100

75

275

75

125

25

 -

1,300

 

Operating Cost Estimates

 

Life-of-mine estimated operating costs were developed by GlobeStar, and verified by Micon, based on previously defined reagent consumptions modified to reflect current unit costs, onsite power generation costs, fuel costs, labor and burden costs, and contractor mining costs. GlobeStar received firm bids on all major costs and incorporated these figures in the engineering estimates.

 

The life-of-mine estimated operating costs are summarized in Table 6 below:

 

Table 6

Summary of Life-Of-Mine Estimated Unit Operating Costs

 

Unit Estimated Operating Costs, in $/tonne Milled

Area

Pre Exp*

Post Exp**

 LOM

Mining Cost***

         13.63

         13.63

         13.63

Oxide Milling

           7.69

           7.69

           7.69

Sulphide Milling

         12.72

         12.35

         12.51

Admin

           1.89

           2.09

           2.04

Con F,S & R****

         18.05

         16.68

         17.28

Dore F,S & R

           0.86

               -  

           0.86

 

 

 

Notes:

*"Pre Exp" is when both the oxide and sulphide plants are operating at their designed tonnages.

**"Post Exp" is when the oxide plant is shut down and the sulphide plant is increased to 1,875 tonnes/day.

***Based on a stripping ratio of 7.7 to 1.0.

****F,S & R means Freight, Smelting & Refining costs.

 

 

 

Financial Analysis

 

The overall economic potential of the Project has been evaluated using conventional discounted cash flow techniques on a 100% equity basis. This procedure has been used for the purpose of estimating the financial returns expected to accrue to CMD as the owner of 100% of the mining, processing and concentrate transportation operations. Metal price assumptions used in the Technical Report were $2.45 per pound of copper, $543 per ounce of gold, and $10.00 per ounce of silver. 

 

The life-of-mine Project financial metrics based on the metal prices used in calculating the estimated mineral reserves are summarized in Table 7:

 

Table 7

Project Estimated Financial Metrics

 

Estimated Financial Metrics (US$ millions)

Gross Revenue

623.8

Net Revenue

523.4

Operating Income Before Depreciation

364.8

Operating Income Before Income Tax

315.1

Net Income

248.2

Pretax Project Cash Flow

294.9

Post tax Project Cash Flow

228.0

IRR - Pre Tax %

68.7

IRR - Post Tax %

58.3

Project Payback Period

15 Months

Pretax NPV @ 8%

172.3

Post Tax NPV @ 8%

130.6

 

 

 

 

Sensitivity Analysis

 

A sensitivity analysis was completed on key variables, including copper price, revenue, capital cost, and operating costs.  The results of this analysis are summarized in Table 8 and Figure 1 below:

 

Table 8
Before-Tax Sensitivity Analysis

 

NPV(8%) (US$ millions)

 

Revenue

$

Capex

$

OpCost

$

Cu Price

$

-20%

   94.1

  183.3

   192.1

    107.9

-10%

 133.2

  177.8

   182.2

    140.1

Base

 172.3

  172.3

   172.3

    172.3

10%

 211.5

  166.8

   162.5

    204.5

20%

 250.6

  161.3

   152.6

    236.7

 


 

 

Figure 1
Before-Tax Sensitivity Analysis

 

 

 

The Project's before-tax NPVs for various copper prices are summarized in Figure 2 below:

 


 

 

Figure 2
Before-Tax NPVs at Various Copper Prices

 

 

 

 

Project Risks

 

The Cerro de Maim?n Project has been drilled to such an extent that Micon considers the risk associated with any resource estimates to be low to moderately-low. Many programs to update and revise grade and tonnage estimates have been performed on the Project. 

 

The development of the Cerro de Maim?n Project is subject to a number of risks that could affect the successful completion and/or the financial performance relative to the results set out in the Technical Report and summarized in this release.  Some of these risks are common to all mining projects, including: changes in commodity prices, adverse changes in exchange rates and concentrate treatment costs, shortages of critical supplies, equipment, and qualified professionals, delays in construction due to weather or equipment deliveries and unforeseen mining or metallurgical difficulties.  With respect to the Project's development, GlobeStar has attempted to mitigate these risks to the extent possible by purchasing long lead-time equipment and second hand crushers and ball mills in advance, and having the project reviewed by outside engineers and consultants.

 

 

 


 

Technical Report

 

As required by National Instrument 43-101, GlobeStar will file the Technical Report on SEDAR shortly and it will be available at www.sedar.com and the Company's website at www.globestarmining.com .

 

Ian Ward, PEng., a Qualified Person as defined by NI 43-101, supervised the preparation and verified the technical information contained in this release.  This news release was prepared by GlobeStar under the supervision of Bill Fisher, PGeo. and A Eric Olson, MAusIMM, both Qualified Persons as defined by NI 43-101.

 

About GlobeStar

 

GlobeStar Mining Corp. is a well funded mine development company, developing the permitted Cerro de Maim?n copper/gold project, with commissioning and start-up currently expected in the summer of 2008. The Company is also aggressively exploring an extensive base and precious metals exploration portfolio in the Dominican Republic with a $4 million exploration budget for nickel and copper/gold exploration, including a 207-hole nickel drilling program.

 

Contact:

 

GlobeStar Mining Corporation                                             

William Fisher                                       or                     JP Chauvin                              

CEO                                                                             President and COO                  

Email: wfisher@globestarmining.com                              Email: jp.chauvin@globestarmining.com

Tel.: (416) 868-6678                                                      Tel.: (416) 868-6678

                                                           

 

Bay Street Connect                                                    Coal Harbor Communications

Gus Garisto                                                                   Dale Paruk

Email: gus@baystreetconnect.com                                 Email: dale@coal-harbor.com

Tel.:  (416) 607 6023                                                      Tel.: (604) 662-4505

Fax:  (604) 662-4547

 

 

Reader Advisory

 

The information in this news release may include certain information and statements about management's view of future events, expectations, plans and prospects that constitute forward-looking statements. Assumptions that are subject to significant risks and uncertainties are the basis for these statements. Because of these risks and uncertainties and, as a result of a variety of factors, the actual results, expectations, achievements or performance may differ materially from those anticipated and indicated by these forward looking statements. Although GlobeStar believes that the expectations reflected in forward looking statements are reasonable, we can give no assurances that the expectations of any forward-looking statements will prove to be correct. GlobeStar disclaims any intention, and assumes no obligation, to update or revise any forward-looking statements to reflect actual results, whether as a result of new information, future events, changes in assumptions, changes in factors affecting such forward-looking statements or otherwise, except as required pursuant to applicable securities laws.

 

 

 

 

 

 

 

 

Data and Statistics for these countries : Canada | Dominican Republic | All
Gold and Silver Prices for these countries : Canada | Dominican Republic | All

Globestar Mining Corporation

PRODUCER
CODE : GMI.TO
Follow and Invest
Add to watch list Add to your portfolio Add or edit a note
Add Alert Add to Watchlists Add to Portfolio Add Note
ProfileMarket
Indicators
VALUE :
Projects & res.
Press
releases
Annual
report
RISK :
Asset profile
Contact Cpy

Globestar Mining is a nickel and gold producing company based in Canada.

Globestar Mining produces nickel, gold, cobalt, copper and silver in Dominican Republic, develops copper, gold, lead, silver and zinc in Dominican Republic, and holds various exploration projects in Canada, in Dominican Republic and in Greenland.

Its main assets in production are CUMPIE HILL, BAYAGUANA CONCESSIONS, DOÑA LORETTA, DOÑA AMANDA and CERRO KIOSKO in Dominican Republic, its main asset in development is CERRO DE MAIMON in Dominican Republic and its main exploration properties are MOBLAN, WEMINDJI, POSTE LEMOYNE, GUERCHEVILLE, INMONT and LAC SHEEN in Canada, CERCADILLO, LA LEONORA RIVER AREA, CUANCE / LOS HOJANCHOS, MAIMÓN CONCESSION and COROZAL in Dominican Republic and CITRONEN FJORD in Greenland.

Globestar Mining is listed in Canada. Its market capitalisation is CA$ 173.7 millions as of today (US$ 175.0 millions, € 131.8 millions).

Its stock quote reached its highest recent level on December 31, 2007 at CA$ 2.54, and its lowest recent point on December 24, 2008 at CA$ 0.29.

Globestar Mining has 105 924 000 shares outstanding.

Your feedback is appreciated, please leave a comment or rate this article.
Rate : Average note :0 (0 vote) View Top rated
 
In the News and Medias of Globestar Mining Corporation
11/21/2006QIS Research
Annual reports of Globestar Mining Corporation
Annual Report 2007
Financials of Globestar Mining Corporation
2/24/2010Reports Strong 2009 Operating Results & Record Quarterly Gol...
8/17/2009Reports Second Quarter 2009 Results
Project news of Globestar Mining Corporation
9/17/2009(Moblan)GlobeStar's Lithium Project
5/29/2009(Cerro De Maimon) Provides Update on Exploration
1/14/2009(Cerro De Maimon)Declares Commercial Production
2/25/2008(Cumpie Hill)Update on Mineral Resource Estimate for Cumpié
1/17/2008(Corozal) Update on Nickel Exploration Program in Dominican Republic:...
12/11/2007(Loma De Payabo)Update On Dominican Republic Nickel Exploration
11/29/2007(Cumpie Hill)New Mineral Resource Estimate
11/14/2007(Cerro De Maimon) Announces That Mining Construction has been Restored
10/17/2007(Cumpie Hill) Drills 14 Metres Grading 1.8% Nickel at Cumpie Hill, Domini...
9/13/2007(Cumpie Hill)drills 27.4 m of 1.78% Ni at Cumpie Hill
8/22/2007(Cumpie Hill)Reports 23 Nickel Exploration Holes Including 39
8/16/2007(Cerro De Maimon)CERRO DE MAIM'N PROJECT
5/3/2007(Cerro De Maimon)Cerro de Maimon Development Update: Pre-production Drill Pro...
Corporate news of Globestar Mining Corporation
12/1/2010Announces Extension of Offer by Perilya
4/5/2010Conference Call for Investors
3/11/2010Reports Increased Cash Balances at December 31, 2009 and Pro...
5/26/2009annual general and special meeting of shareholders on Thursd...
3/19/2008Update on Nickel Exploration Program in Dominican Republic
12/4/2007and Everton Trench up to 22m grading 1.07 g/t Gold at Cuance...
11/1/2007 Construction Delayed by Tropical Storm Noel
8/20/2007Cash Position and No Exposure To Commercial Paper
8/9/2007 Closes US$45 Million Debt Facility For Cerro De Maimon Proj...
6/12/200711 Holes Including 16.5 Metres Grading 1.66% Nickel
5/31/2007Announces Closing Of $31.8 Million Financing
5/10/2007New Director Appointed
5/8/2007Adopts Shareholder Rights Plan
3/21/2007Extends Surface Soil Anomalies to over 1.5 km on the Cuance ...
3/23/2007200+ Hole Diamond Drill Program Underway on the Company's Ni...
Comments closed
 
Latest comment posted for this article
Be the first to comment
Add your comment
TORONTO (GMI.TO)
1.64-0.61%
TORONTO
CA$ 1.64
01/17 10:28 -0.010
-0.61%
Prev close Open
1.65 1.65
Low High
1.64 1.65
Year l/h YTD var.
 -  -
52 week l/h 52 week var.
- -  1.64 -%
Volume 1 month var.
2,950 -%
24hGold TrendPower© : 13
Produces Copper - Gold - Nickel - Silver
Develops Copper - Gold - Silver
Explores for Copper - Diamonds - Gold - Lead - Lithium - Nickel - Silver - Zinc
 
 
 
Analyse
Interactive chart Add to compare
Interactive
chart
Print Compare Export
Last updated on : 11/24/2010
You must be logged in to use the porfolio and watchlists (free)
Top Newsreleases
MOST READ
Annual variation
DateVariationHighLow
 
5 years chart
 
3 months chart
 
3 months volume chart
 
 
Mining Company News
Plymouth Minerals LTDPLH.AX
Plymouth Minerals Intersects Further High Grade Potash in Drilling at Banio Potash Project - Plannin
AU$ 0.12-8.00%Trend Power :
Santos(Ngas-Oil)STO.AX
announces expected non-cash impairment
AU$ 7.64-0.33%Trend Power :
Oceana Gold(Au)OGC.AX
RELEASES NEW TECHNICAL REPORT FOR THE HAILE GOLD MINE
AU$ 2.20+0.00%Trend Power :
Western Areas NL(Au-Ni-Pl)WSA.AX
Advance Notice - Full Year Results Conference Call
AU$ 3.86+0.00%Trend Power :
Canadian Zinc(Ag-Au-Cu)CZN.TO
Reports Financial Results for Q2 and Provides Project Updates
CA$ 0.12+4.55%Trend Power :
Stornoway Diamond(Gems-Au-Ur)SWY.TO
Second Quarter Results
CA$ 0.02+100.00%Trend Power :
McEwen Mining(Cu-Le-Zn)MUX
TO ACQUIRE BLACK FOX FROM PRIMERO=C2=A0
US$ 12.22-0.33%Trend Power :
Rentech(Coal-Ngas)RTK
Rentech Announces Results for Second Quarter 2017
US$ 0.20-12.28%Trend Power :
KEFIKEFI.L
Reduced Funding Requirement
GBX 0.52-0.76%Trend Power :
Lupaka Gold Corp.LPK.V
Lupaka Gold Receives First Tranche Under Amended Invicta Financing Agreement
CA$ 0.06+0.00%Trend Power :
Imperial(Ag-Au-Cu)III.TO
Closes Bridge Loan Financing
CA$ 2.64+0.00%Trend Power :
Guyana Goldfields(Cu-Zn-Pa)GUY.TO
Reports Second Quarter 2017 Results and Maintains Production Guidance
CA$ 1.84+0.00%Trend Power :
Lundin Mining(Ag-Au-Cu)LUN.TO
d Share Capital and Voting Rights for Lundin Mining
CA$ 16.48+1.54%Trend Power :
Canarc Res.(Au)CCM.TO
Canarc Reports High Grade Gold in Surface Rock Samples at Fondaway Canyon, Nevada
CA$ 0.26+4.08%Trend Power :
Havilah(Cu-Le-Zn)HAV.AX
Q A April 2017 Quarterly Report
AU$ 0.22-2.17%Trend Power :
Uranium Res.(Ur)URRE
Commences Lithium Exploration Drilling at the Columbus Basin Project
US$ 6.80-2.86%Trend Power :
Platinum Group Metals(Au-Cu-Gems)PTM.TO
Platinum Group Metals Ltd. Operational and Strategic Process ...
CA$ 1.90+1.06%Trend Power :
Devon Energy(Ngas-Oil)DVN
Announces $340 Million of Non-Core Asset Sales
US$ 53.08+0.70%Trend Power :
Precision Drilling(Oil)PD-UN.TO
Announces 2017Second Quarter Financial Results
CA$ 8.66-0.35%Trend Power :
Terramin(Ag-Au-Cu)TZN.AX
2nd Quarter Report
AU$ 0.04+5.56%Trend Power :