CHANGES TO MINING PLAN



The Board of Hillgrove Resources Limited (the Company) wishes to advise that the Annual Report of the Company, which we expect to lodge later today, will contain some significant comments in the Events Subsequent to Reporting a Date and Going Concern note. Those comments are reflected below.


Since February 2016, Hillgrove has not achieved the budgeted production levels at its Kanmantoo copper / gold mine for the following reasons:


  • As advised in late 2015, the independent evaluation of the orebody led to the deferral of revenue;


  • To address this deferral the previous life of mine plan was amended, which intensified mining in a smaller footprint;


  • Following detailed implementation, planning and analysis of recent actual performance, it has been determined that the planned mining sequence was too aggressive; and


as a result of this, the life of mine (LOM) plan has been revised to one which has a simpler sequence and is based upon currently achieved mining rates, but which brings forward waste removal and in consequence defers copper production.


In February 2016, as a consequence of this lower production, current liabilities increased during the month and Hillgrove was in breach of its month end, $25,000,000 trade creditor financial covenant. Subsequent to the end of February, Hillgrove obtained a waiver from its financiers that removed the $25,000,000 month end limit for February 2016.


The waiver required the Group to achieve 95% (formerly 85%) of its payable copper production target, as set out in its LOM plan, for the three month period from March to May 2016. During March 2016 Hillgrove determined that, for the reasons outlined above, the LOM plan was too aggressive and the 95% of its payable copper production target would not be achieved.


As a consequence Hillgrove revised its LOM plan to lower targets in line with recent performance. While this revised LOM plan still shows Kanmantoo will generate significant value and has exploration potential, the anticipated near term production levels coupled with the need to continue the pre-strip and cut-back of the Giant pit are likely to result in a cash shortfall in 2016 and 2017 at current performance levels and commodity prices unless cost-reduction measures are implemented to improve cashflow from operations.


IIII

HILLGROVE RESOURCES LIMITED ACN 004 297 116 www.hillgroveresources.com

5-7 King William Road, Unley SA 5061, Australia T +61 8 7070 1698 F +61 8 8538 5255

The Board has agreed a process to address the anticipated cashflow shortfall. As part of this, an independent review of the Company's revised plans and forecasts is to be undertaken and a range of measures are being implemented to reduce costs and generate proceeds from asset sales. Hillgrove has begun discussions with its key stakeholders including employees, major contractors, suppliers and service providers, financiers and the South Australian Government to seek their assistance with this process to ensure the Company can bridge any cashflow gaps this year and into 2017.


If Hillgrove can successfully implement the package of measures with these stakeholder groups, it should be able to generate sufficient cashflow from operations to continue operating the Kanmantoo Mine. Considerable progress had been made in these stakeholder discussions. The Company's financiers are generally supportive of the pre-emptive action being taken.


The directors remain confident that there is significant value in the mine and believe that the best outcome for the company as a whole is achieved by implementing the revised LOM plan and reducing costs with the cooperation and support of all stakeholders.


In considering the impact of the above outlined changes in the mine plan, the Board has determined that no adjustments are needed to carrying values of non-current assets as at 31 December 2015. Further, there are no changes to the previously reported unaudited financial results for 2015.


Outlook for 2016


As a result of the revision to the mine and financial plan (referred to above), the CY16 guidance issued on 26 February for the Kanmantoo Copper Mine is revised as follows:


Guidance

Previous

Updated

Ore Mined

2,900kt to 3,100kt

2,500kt to 2,700kt

Ore Processed

3,350kt to 3,550kt

2,850kt to 3,050kt

Copper contained in concentrates produced

16,500t to 18,500t

14,500t to 16,500t

Gold contained in concentrates produced

11,000oz to 13,500oz

8,000oz to 10,000oz

C1 Costs (at a 0.75 exchange rate)

US$1.75 to US$2.05 per lb

US$1.85 to US$2.15 per lb

Capital expenditure (excludes pre-strip but see comments on pre-strip below)


$1.0 million to $1.4 million


No change



For the reasons outlined above, the tonnes mined and processed have been revised downwards.


As a result of the lower ore tonnes to be mined and processed, copper and gold production is now forecast to be lower in CY16, as some of the previous forecast CY16 copper and gold metal production is deferred to later years (i.e. there is no change to the expected total LOM copper and gold production, but there is deferral to later years).

While lower than the previous guidance, gold production is forecast to be significantly higher this financial year relative to prior years (by approximately 2,000 ounces or 500 tonnes of copper equivalent based on existing spot prices).


In addition to the above forecast capital expenditure, Hillgrove will continue to undertake capital development in pre-strip operations for the Giant Pit ($20.5 million in CY16). Deferred mining is forecast to be $10.8 million in CY16.


As previously reported, following the closure of the Sydney corporate office and placing the Indonesian projects on care and maintenance, the company's focus is on the Kanmantoo operation and advancing the Giant Pit cutback to provide a solid footing for building production rates and improving cash flow beyond this year. As part of this year's plan, Hillgrove aims to assess the potential for resource expansion with evaluation of targets on the Kanmantoo mining lease and the surrounding regional tenement.


The Company will provide updates to the market on the progress in implementing the revised mine plan and aims to get feedback from key stakeholders by mid-April 2016.


For more information contact:

Mr Steven McClare Mr Paul Kiley

CEO & Managing Director CFO and Company Secretary

Tel: +61 (0)8 7070 1698 Tel: +61 (0)8 7070 1698

Read the rest of the article at www.publicnow.com
Data and Statistics for these countries : Australia | All
Gold and Silver Prices for these countries : Australia | All

Hillgrove Resources

CODE : HGO.AX
ISIN : AU000000HGO6
Follow and Invest
Add to watch list Add to your portfolio Add or edit a note
Add Alert Add to Watchlists Add to Portfolio Add Note
ProfileMarket
Indicators
VALUE :
Projects & res.
Press
releases
Annual
report
RISK :
Asset profile
Contact Cpy

Hillgrove Res. is a zinc development stage company based in Australia.

Hillgrove Res. holds various exploration projects in Australia and in Indonesia.

Its main exploration properties are WHEAL ELLEN in Australia and SUMBA and BIRD'S HEAD in Indonesia.

Your feedback is appreciated, please leave a comment or rate this article.
Rate : Average note :0 (0 vote) View Top rated
 
Nominations of Hillgrove Resources
5/31/2007Appointment of John Gooding as an Independent Non-Executive ...
Financials of Hillgrove Resources
9/9/2009Half Year Financial Results
Project news of Hillgrove Resources
1/29/2009(Bird's Head)Alpha Prospect Shapes up as Major Gold Target
8/15/2007(Wheal Ellen)Drilling recommences at Wheal Ellen project, Sth Aust
7/25/2007(Wheal Ellen)High Grade Lead Zinc Drill Hits at Wheal Ellen, Sth Aust
6/27/2007(Wheal Ellen)Drilling commences at Wheal Ellen Zinc Project, Sth Aust
6/25/2007More significant high grade copper-gold zones encountered at...
4/23/2007More High Grade Copper-Gold Zones drilled at Kanmantoo Proje...
Corporate news of Hillgrove Resources
7/27/2016Activity Report for Quarter Ended 30 June 2016
7/14/2016Lapse of Performance Rights
7/4/2016Balance Sheet Restructure Update
6/29/2016Succesful Balance Sheet Restructure
5/27/2016Hillgrove Resources Results of AGM
5/26/2016MD's Presentation to AGM
5/26/20162016 Mineral Resource Statement
5/26/2016Chairman's Address to AGM
4/18/2016Change to Mine Plan Update
3/31/2016Hillgrove Resources 2015 Annual Report
3/31/2016Change to Mine Plan
3/29/2016Trading Halt Request
1/29/2016Activity Report for Quarter Ended 31 Dec 2015
12/15/2015Change of Registered Office Address
9/11/2015Results for Half Year Ended 30 June 2015
8/20/2015SACOME Breakfast Presentation
7/29/2015Activity Report for Quarter Ended 30 June 2015
7/3/2015Hillgrove Announces Change of CFO
7/3/2015Despatch of Rights Issue Statements
7/3/2015Results of Non Renounceable Entitlement Offer
4/27/2015Hillgrove Executes Additional Waiver
4/26/2015Notice of Annual General Meeting
3/31/2015Annual Report to 31 December 2014
3/31/2015Hillgrove Audited Annual Report Released
2/26/2015Annual Company Update Presentation
2/26/2015Preliminary Final Results - CY14
2/26/2015Hillgrove Reports Profits
2/2/2015Activity Report for Quarter Ended 31 December 2014
2/2/2015Fourth Quarter Presentation
1/22/2015Wilson HTM - Hedging Expands Hedge Book
1/22/2015Market Update on Strong Copper Hedge Position
12/11/2014New Exploration Underway on SA Tenements
12/11/2014Unmarketable Parcel Sale Facility Concluded
10/20/2014Activity Report for Quarter Ended 30 Sep 2014
3/3/2014Fourth Quarter FY14 Presentation
3/3/2014Quarterly Production Report - Record Production
3/3/2014Activity Report for Quarter Ended 31 January 2014
11/25/2013Activity Report for Quarter Ended 31 October 2013
3/17/2010Indonesia Announcement
3/1/2010Kanmantoo Announcement
2/26/2010Quarterly Report to 31/01/10
2/11/2010Indonesia Announcement
1/18/2010Placement and SPP Annoucement
12/18/2009Kanmantoo Announcement
12/3/2009Kanmantoo Announcement
11/30/2009Quarterly Report to 31/10/09
10/1/2009Annoucement
9/7/2009Indonesia Announcement
8/31/2009Quarterly Report to 31/07/09
8/10/2009Kanmantoo Announcement
7/15/2009Completion of Sale of Eastern Star Gas Investment
7/2/2009Eastern Star Gas Annoucement
5/21/2009Indonesia
2/27/2009Quarterly Report to 31/01/09
2/18/2009Eastern Star Gas Annoucement
2/9/2009Raises $4.1M from SPP and Placement
7/16/2007Minerals Partnership in Madagascar
6/12/2007 Molybdenum, Cobalt, Uranium hits at Alford
5/23/2007Significant New Geophysical Anomalies Discovered at Wheal El...
5/22/2007Potential Olympic Dam Style Mineralisation at Alford
5/14/2007Dale Ferguson appointed to the Board as Executive Director -...
4/30/2007Significant resource upgrade at Kanmantoo Copper Gold Mine, ...
4/19/2007Drilling starts at Alford Project, Hillgrove investing $4m i...
4/18/2007 Kanmantoo targetting early 2009 for first copper gold produ...
4/4/2007posts maiden $10.8 million NPAT for 2006/ Cashed up to progr...
Comments closed
 
Latest comment posted for this article
Be the first to comment
Add your comment
AUSTRALIA (HGO.AX)
0.053-1.85%
AUSTRALIA
AU$ 0.053
09/19 12:16 -
-1.85%
Prev close Open
0.054 0.054
Low High
0.053 0.054
Year l/h YTD var.
0.047 -  0.090 -41.11%
52 week l/h 52 week var.
0.047 -  0.090 -15.87%
Volume 1 month var.
534,324 -10.17%
24hGold TrendPower© : 15
Produces
Develops
Explores for
 
 
 
Analyse
Interactive chart Add to compare
Interactive
chart
Print Compare Export
You must be logged in to use the porfolio and watchlists (free)
Top Newsreleases
MOST READ
Annual variation
DateVariationHighLow
2024-41.11%0.100.05
202366.67%0.090.04
20220.00%0.090.00
202168.75%0.090.03
2020-46.67%0.070.03
 
5 years chart
 
3 months chart
 
3 months volume chart
 
 
Mining Company News
Plymouth Minerals LTDPLH.AX
Plymouth Minerals Intersects Further High Grade Potash in Drilling at Banio Potash Project - Plannin
AU$ 0.12-8.00%Trend Power :
Santos(Ngas-Oil)STO.AX
announces expected non-cash impairment
AU$ 7.03-0.28%Trend Power :
OceanaGold(Au)OGC.AX
RELEASES NEW TECHNICAL REPORT FOR THE HAILE GOLD MINE
AU$ 2.20+0.00%Trend Power :
Western Areas NL(Au-Ni-Pl)WSA.AX
Advance Notice - Full Year Results Conference Call
AU$ 3.86+0.00%Trend Power :
Canadian Zinc(Ag-Au-Cu)CZN.TO
Reports Financial Results for Q2 and Provides Project Updates
 0.12+4.55%Trend Power :
Stornoway Diamond(Gems-Au-Ur)SWY.TO
Second Quarter Results
CA$ 0.02+100.00%Trend Power :
McEwen Mining(Cu-Le-Zn)MUX
TO ACQUIRE BLACK FOX FROM PRIMERO=C2=A0
US$ 8.91-2.73%Trend Power :
Rentech(Coal-Ngas)RTK
Rentech Announces Results for Second Quarter 2017
US$ 0.20-12.28%Trend Power :
KEFIKEFI.L
Reduced Funding Requirement
GBX 0.59-3.26%Trend Power :
Lupaka Gold Corp.LPK.V
Lupaka Gold Receives First Tranche Under Amended Invicta Financing Agreement
CA$ 0.05+10.00%Trend Power :
Imperial(Ag-Au-Cu)III.TO
Closes Bridge Loan Financing
CA$ 2.06+0.00%Trend Power :
Guyana Goldfields(Cu-Zn-Pa)GUY.TO
Reports Second Quarter 2017 Results and Maintains Production Guidance
CA$ 1.84+0.00%Trend Power :
Lundin Mining(Ag-Au-Cu)LUN.TO
d Share Capital and Voting Rights for Lundin Mining
 12.67+0.88%Trend Power :
Canarc Res.(Au)CCM.TO
Canarc Reports High Grade Gold in Surface Rock Samples at Fondaway Canyon, Nevada
CA$ 0.34+6.25%Trend Power :
Havilah(Cu-Le-Zn)HAV.AX
Q A April 2017 Quarterly Report
AU$ 0.19+2.70%Trend Power :
Uranium Res.(Ur)URRE
Commences Lithium Exploration Drilling at the Columbus Basin Project
US$ 6.80-2.86%Trend Power :
Platinum Group Metals(Au-Cu-Gems)PTM.TO
Platinum Group Metals Ltd. Operational and Strategic Process ...
 1.77-2.21%Trend Power :
Devon Energy(Ngas-Oil)DVN
Announces $340 Million of Non-Core Asset Sales
US$ 40.37-0.22%Trend Power :
Precision Drilling(Oil)PD-UN.TO
Announces 2017Second Quarter Financial Results
CA$ 8.66-0.35%Trend Power :
Terramin(Ag-Au-Cu)TZN.AX
2nd Quarter Report
AU$ 0.04+0.00%Trend Power :
Take advantage of rising gold stocks
  • Subscribe to our weekly mining market briefing.
  • Receive our research reports on junior mining companies
    with the strongest potential
  • Free service, your email is safe
  • Limited offer, register now !
Go to website.