Peregrine Diamonds Ltd.

Published : March 06th, 2017

COMPLETES INTERNAL CH=2D6 OPEN PIT AND UNDERGROUND MINING STUDY AND REVISES 2017 WORK PROGRAM

( 0 vote, 0/5 ) Print article
  Article Comments Comment this article Rating Follow Company  
0
Send
0
comment
Peregrine Diamonds Ltd.
Press Release

March 6, 2017

PEREGRINE DIAMONDS COMPLETES INTERNAL CH-6 OPEN PIT AND UNDERGROUND MINING STUDY AND REVISES 2017 WORK PROGRAM


VANCOUVER, CANADA - Peregrine Diamonds Ltd. (TSX:PGD) (�Peregrine� or �the Company�) is pleased to announce that it has completed an internal concept study of a potential open-pit plus underground mining development at its 100% owned CH-6 kimberlite pipe at the Chidliak Diamond Project near Iqaluit, Nunavut, Canada. The study was completed in consultation with JDS Energy & Mining Inc. (�JDS�). The study has concluded there is the potential to substantially enhance the economics of the Chidliak Project by incorporating an underground mining operation below 260 metres of depth at CH-6, the current bottom of the open pit Inferred Resource defined in the August 2016 Preliminary Economic Assessment (�PEA�) (see below). As a result of this conceptual study, a drill program targeting this deeper kimberlite is planned to commence in June 2017 to expand the resource to depths up to 500 metres below surface. In addition to the resource expansion drilling, geotechnical work and environmental studies in the Chidliak Project area and proposed transportation corridor will continue.

CH-6 PEA AND OPEN PIT PLUS UNDERGROUND CONCEPT STUDY

JDS completed a positive preliminary economic assessment titled �Preliminary Economic Assessment Technical Report of the Chidliak Project, Nunavut, Canada� dated August 19, 2016 on a Phase-One open-pit only mining operation of the CH-6 and CH-7 kimberlite pipes.

The economics of a development at Chidliak are robust. Highlights of the 2016 Chidliak Phase-One, Open-Pit, Diamond Development PEA base case are:

  • Pre-tax Net Present Value (NPV) of C$743.7 million, at a 7.5% discount rate and a pre-tax Internal Rate of Return (IRR) of 38.1%.
  • After-tax NPV of C$471.2 million, at a 7.5% discount rate and an after-tax IRR of 29.8%.
  • Total Life of Mine (LOM) pre-tax Free Cash Flow of C$1.31 billion.
  • After-tax payback period of two years, LOM of ten years.
  • Operating margin of 72%.
  • LOM average production rate of 1.2 million carats per year, peaking at 1.8 million carats per year.
  • Estimated pre-production capital requirement of approximately C$434.9 million, including C$56.7 million in contingency.

The PEA is preliminary in nature and includes Inferred Mineral Resources that are considered too speculative geologically to have the economic considerations applied to them to be categorized as Mineral Reserves. Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability. There is no certainty that the PEA will be realized. All mine plan tonnes in the PEA are Inferred Mineral Resources.

The PEA concluded that the project was of sufficient merit to proceed to the Preliminary Feasibility Study (�PFS�) stage. The key components of the recommended work program include:

  • Core drilling at CH-6 to better quantify the target for further exploration (�TFFE�) and possibly convert that material to a Mineral Resource.
  • Bulk sampling of CH-6 to advance the resource to the Indicated level.
  • Engineering and geotechnical programs to better quantify process requirements and refine pit design.
  • Continued environmental monitoring and development of permitting management plans.

In December 2016, the Company engaged JDS to complete an internal, concept-level study on the project economic uplift that could be realized by developing the CH-6 kimberlite to a depth of 500 metres as a combined open-pit plus underground mining operation. The results of this study are excellent and have significantly changed the specifics for the 2017 work program. The study clearly demonstrates the benefit of focusing the 2017 program on proving the resource potential at CH-6 below 260 metres, the current bottom of the Inferred Resource in the PEA.

As a �concept study� does not conform with NI 43-101 requirements, the study, and its technical and economic details, cannot be publicly disclosed

CURRENT CH-6 TFFE

On April 7, 2016, the Company released updated independent estimates of TFFE for the CH-6 kimberlite below 260 metres of depth as shown in Table 1 below.

TABLE 1: CH-6 KIMBERLITE TFFE BELOW 260 METRES

Domain Depth
(metres below surface)
Low-case Tonnes (millions) High-case Tonnes (millions)
CH-6 KIM-L 260-380 1.27 2.40
CH-6 KIM-C 260-380 0.88 1.09
CH-6 TFFE 260-380 2.15 3.49

The KIM-L TFFE was estimated based on 112 metres of core logged as KIM-L in five vertical core holes extending below the 260 metre depth of the KIM-L resource, and on extrapolation to depth of the CH-6 pipe shell, which is well constrained at shallower depths. Vertical core hole CHI-050-11-DD24, drilled in August 2011, intersected KIM-L throughout the length of the hole to its terminal depth of 300 metres, and was sampled for caustic fusion Diamond assay over the 266 to 299 metre depth range. Diamond recovery results are presented in Table 2.

TABLE 2: DIAMONDS RECOVERED BY CAUSTIC FUSION FOR CH-6 KIM-L (TFFE) FROM HOLE DD24

Geological Unit Depth (m) Sample Weight (kg) Diamond count by sieve size (mm) Total Diamonds Carats(+0.85mm)
+0.106-0.150 +0.150-0.212 +0.212-0.300 +0.300-0.425 +0.425-0.600 +0.60-0.85 +0.85-1.18 +1.18-1.70 +1.70-2.36 +2.36-3.35 +3.35-4.75
CH-06
(KIM-L TFFE)
266 to 299 40.2 36 16 10 7 5 3 1 1 0 0 0 79 0.04

The caustic fusion result is consistent with a coarse Diamond size distribution within the KIM-L unit and with caustic fusion results for KIM-L from sampling within the current Inferred Resource. This fact, paired with the geological continuity identified within KIM-L throughout CH-6, emphasizes the importance of kimberlite below 260 metres being targeted by the 2017 drilling program.

The TFFE�s identified above are conceptual in nature and are not Mineral Resources. It is uncertain whether further exploration will result in any of these tonnages being delineated as Mineral Resources.

2017 CH-6 WORK PROGRAM

The 2017 work program at Chidliak will now focus on three main objectives:

  • Expansion of the current Inferred Resource at CH-6 � through Diamond core drilling of approximately 4,000-5,000 metres to further demonstrate geological continuity, establish pipe margin pierce-points and obtain spatially representative kimberlite samples for caustic fusion Diamond assay. The main objective will be to increase the depth of a categorized resource from 260 metres to 500 metres. Caustic fusion results will be used to model Diamond grade and grade distribution of the kimberlite to 500 metres.
  • Refine open pit geotechnical design parameters � as part of the 2017 drilling program, oriented HQ diameter core and other geotechnical data required to refine the open-pit parameters, particularly the pit slope angles, will be acquired. This data will enable assumptions regarding open pit design to be tested and further refined.
  • Advancing permitting � through continued environmental monitoring programs of the Chidliak Project area and the proposed transportation corridor.

The Company is currently working with Mineral Services Canada to finalize parameters for the 2017 drill program that would support robust future resource estimates. All necessary preparations to initiate this program, including equipment acquisition and camp preparation, were completed in 2016 and all permits have been obtained. The Company expects the microdiamond analyses to be completed in the third quarter of 2017 and anticipates an updated resource for CH-6 to be declared in the fourth quarter. If the resource at depths below 260 metres is of sufficient size and Diamond grade, a new PEA outlining an underground mining operation for this material, in addition to the existing open-pit operation, could be completed in the first quarter of 2018. Total cost for the 2017 work program is estimated at C$7.5 million.

FINANCING FOR THE 2017 PROGRAM

The Company is in discussions with various parties regarding financing for the 2017 program and is confident such financing will be obtained. Detailed information will be provided if and when a financing option is selected by the Company.

QUALIFIED PERSONS

Mr. Gord Doerksen of JDS Energy and Mining Inc. is a Professional Engineer and an independent, external Qualified Person that consults to Peregrine. Dr. Tom Nowicki of Mineral Services Canada Inc., is a Professional Geologist and is Peregrine�s independent, external Qualified Person for resource estimates. Dr. Herman Gr�tter, Peregrine�s Vice President, Technical Services, is a Qualified Person and is responsible for the design of the Diamond Resource Development Program at Chidliak.

Mr. Doerksen, Dr. Nowicki and Dr. Gr�tter have reviewed this release and approve of its contents.

About Peregrine DIAMONDS

Peregrine Diamonds is a TSX-listed Diamond exploration and development company with assets located in northern Canada and Botswana.

Peregrine�s core asset is its� 100 percent-owned, 513,000-hectare Chidliak Project, located 120 kilometres from Iqaluit, the capital of Nunavut where 71 kimberlites have been discovered to date with eight being potentially economic. A Preliminary Economic Assessment (�PEA�) of a Phase 1 Diamond Development (�CP1D�) has been completed. The PEA highlights that the CP1D represents a robust, high margin, ten-year, open-pit mining project with very attractive economics, including after tax NPV of C$471M, IRR of 29.8% and a two year payback. An Inferred Mineral Resource of 11.39 million carats in 4.64 million tonnes of kimberlite at an average grade of 2.45 carats per tonne has been defined for a portion of the CH-6 kimberlite. In addition, a Target for Further Exploration (�TFFE�) of 2.34 to 3.75 million tonnes of kimberlite to a depth of 380 metres below surface has been identified at CH-6. An independent Diamond valuation by WWW International Diamond Consultants of a 1,013 carat parcel of diamonds from CH-6 returned an average market price of US$213 per carat, and modeled prices that range from a minimum of US$162 per carat to a high of US$236 per carat, with a base model price of US$188 per carat (all using the February 24, 2014 price book). An Inferred Mineral Resource of 4.23 million carats in 4.99 million tonnes of kimberlite at an average grade of 0.85 carats per tonne has been defined for a portion of the CH-7 kimberlite. In addition, TFFE of 0.90 to 2.36 million tonnes for a depth range of 240-320 metres has been estimated for the CH-7 kimberlite. An independent Diamond valuation by WWW International Diamond Consultants, of a 735.75 carat parcel of diamonds from CH-7 returned an average market price of US$100 per carat and modelled prices that ranged from a minimum of US$94 per carat to a high of US$155 per carat, with a base model price of US$114 per carat (all using the February 1, 2016 price book). A TFFE of 1.27 to 3.19 million tonnes to 250 metres depth has been estimated for the CH-44 kimberlite pipe.

The Chidliak 2016 PEA is preliminary in nature and includes Inferred Mineral Resources that are considered too speculative geologically to have the economic considerations applied to them that would enable them to be categorized as Mineral Reserves. Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability. There is no certainty that the PEA will be realized.

The TFFEs identified above are conceptual in nature as there has been insufficient exploration to define a Mineral Resource. It is uncertain whether further exploration will result in any of these tonnages being delineated as Mineral Resources.

Peregrine holds eleven Diamond prospecting licenses in Botswana that cover 661,330 hectares.

Peregrine also controls the 8,493-hectare Lac de Gras Project in the Northwest Territories, located approximately 27 kilometres from the Diavik Diamond Mine. The nine-hectare 72.1%-owned DO-27 kimberlite, located at Lac de Gras, hosts an Indicated Mineral Resource of 18.2 million carats of diamonds in 19.5 million tonnes of kimberlite at a grade of 0.94 carats per tonne and it is open at depth.

For information on data verification, exploration information and resource estimation procedures see the NI 43-101 technical reports entitled �Mineral Resource Estimate for the Chidliak Project, Baffin Island, Nunavut� and dated effective June 3, 2016 and �Peregrine Diamonds Limited DO-27 Diamond Project Northwest Territories, Canada NI 43-101 Technical Report� dated August 7, 2008 which are available on SEDAR and the Company�s website.

For further information, please visit www.pdiam.com or contact Mr. Eric Friedland, Executive Chairman, Mr. Tom Peregoodoff, President and CEO, Dr. Herman Gr�tter, Vice President, Technical Services, or Peregrine Diamonds Investor Relations, at 604-408-8880 or at investorrelations@pdiam.com.

Forward-Looking Statements

This news release contains forward-looking statements within the meaning of Canadian securities legislation. All statements, other than statements of historical fact, that address activities, events or developments that the Company believes, expects or anticipates will or may occur in the future including, without limitation, statements relating to future management of the Company, proposed exploration and development programs, funding availability, anticipated exploration results, grade of diamonds and tonnage of material, resource estimates, anticipated Diamond valuations and future exploration and operating plans are forward-looking statements. These forward-looking statements reflect the current expectations or beliefs of the Company based on information currently available to the Company.

Forward-looking statements are made based upon certain assumptions by the Company and other important factors that, if untrue, could cause the actual results, performances or achievements of the Company to be materially different from future results, performances or achievements expressed or implied by such statements. Such statements and information are based on numerous assumptions regarding present and future business strategies and the environment in which the Company will operate in the future, including the availability and continuation of experienced leadership for the Company, the price of diamonds, anticipated costs and ability to achieve goals. Certain important factors that could cause actual results, performances or achievements to differ materially from those in the forward-looking statements include, but are not limited to: receipt of regulatory approvals; anticipated timelines for community consultations and the impact of those consultations on the regulatory approval process; market prices for rough diamonds and the potential impact on the Chidliak Project; and future exploration plans and objectives.

Forward-looking statements are subject to a number of risks and uncertainties that may cause the actual results of the Company to differ materially from those discussed in the forward-looking statements and, even if such actual results are realized or substantially realized, there can be no assurance that they will have the expected consequences to, or effects on, the Company. Factors that could cause actual results or events to differ materially from current expectations include, among other things, uncertainties relating to continuity and availability of executive management, availability and cost of funds, timing and content of work programs, results of exploration activities, interpretation of drilling results and other geological data, risks relating to variations in the Diamond grade and kimberlite lithologies; variations in rates of recovery and breakage; variations in Diamond valuations and future Diamond prices; the state of world Diamond markets, reliability of mineral property titles, changes to regulations affecting the Company�s activities, delays in obtaining or failure to obtain required project approvals, operational and infrastructure risk and other risks involved in the Diamond exploration and development business. Any forward-looking statement speaks only as of the date on which it is made and, except as may be required by applicable securities laws, the Company disclaims any intent or obligation to update any forward-looking statement, whether as a result of new information, future events or results or otherwise. Although the Company believes that the assumptions inherent in the forward-looking statements are reasonable, forward-looking statements are not guarantees of future performance and accordingly undue reliance should not be put on such statements due to their inherent uncertainty.



View in PDF Format

You can also view this News Relesae on our website at:
http://www.pdiam.com/news/news-releases/peregrine-diamonds-completes-internal-ch-6-open-pit-and-underground-mining-study-and-revises-2017-work-program







This email was sent to newsrelease@24hgold.com
why did I get this?        
PEREGRINE DIAMONDS LTD. � 201-1250 Homer Street � Vancouver, BC V6B 1C6 � Canada

Email Marketing Powered by MailChimp
Data and Statistics for these countries : Botswana | Canada | All
Gold and Silver Prices for these countries : Botswana | Canada | All

Peregrine Diamonds Ltd.

EXPLORATION STAGE
CODE : PGD.TO
ISIN : CA7139161045
Follow and Invest
Add to watch list Add to your portfolio Add or edit a note
Add Alert Add to Watchlists Add to Portfolio Add Note
ProfileMarket
Indicators
VALUE :
Projects & res.
Press
releases
Annual
report
RISK :
Asset profile
Contact Cpy

Peregrine Diamonds is a diamonds development stage company based in Canada.

Peregrine Diamonds holds various exploration projects in Argentina and in Canada.

Its main exploration properties are LAC DE GRAS EAST, CROSSWELL RIVER PROPERTY, MACKAY LAKE WEST, WEIR RIVER PROPERTY, NANUQ, LAC DE GRAS WEST, PELLATT LAKE PROPERTY, MIRAGE BAY - BAFFIN ISLAND, FOXE BASIN BAFFIN ISLAND, WO PROPERTY & DO-27 KIMBERLITE, NANUQ NORTH, CHIDIAK-BAFFIN ISLAND, QILAQ and MACKAY LAKE in Canada and ALTAR PORPHYRY in Argentina.

Peregrine Diamonds is listed in Canada. Its market capitalisation is CA$ 78.0 millions as of today (US$ 61.3 millions, € 51.0 millions).

Its stock quote reached its highest recent level on October 02, 2009 at CA$ 4.65, and its lowest recent point on February 12, 2016 at CA$ 0.09.

Peregrine Diamonds has 339 329 984 shares outstanding.

Your feedback is appreciated, please leave a comment or rate this article.
Rate : Average note :0 (0 vote) View Top rated
 
In the News and Medias of Peregrine Diamonds Ltd.
9/13/2018De Beers officially the new owner of Peregrine Diamonds
7/19/2018De Beers buys Canada's Peregrine Diamonds for $81 million
9/18/2007 bulk sample results from DO-27
8/1/2007Stockwatch article on some of Peregrine's 2007 diamond explo...
Financings of Peregrine Diamonds Ltd.
4/7/2015Reports on Warrant Exercise
6/5/2013Announces $3.5 Million Private Placement
10/25/2012Announces $10-Million Financing
12/8/2011Announces Closing of Rights Offering
Nominations of Peregrine Diamonds Ltd.
3/31/2017Announces Results of Voting for Election of Directors
2/2/2012Completes Chidliak Purchase and Announces Senior Management ...
Project news of Peregrine Diamonds Ltd.
6/3/2013Announces Completion of the CH-6 Kimberlite Bulk Sample Prog...
8/15/2012Provides Project Update and Discovers 61st Kimberlite at Chi...
3/1/2012Commences Lac De Gras Diamond Exploration Program
3/30/2011(Chidiak-baffin Island)Chidliak Joint Venture Approves $17.7 Million 2011 Diamond E...
2/24/2011(Chidiak-baffin Island)Announces Coarse Diamond Size Distribution in CH-20 Kimberli...
2/19/2008(Chidiak-baffin Island) Discovers Three Separate Areas with High Concentrations of ...
2/12/2008(Chidiak-baffin Island)Discovers Strong and Large Scale Uranium Anomalies on Baffin...
1/25/2008(Nanuq North) Nanuq North project
Corporate news of Peregrine Diamonds Ltd.
8/19/2016Peregrine Files Updated Technical Report for Chidliak Projec...
7/7/2016Peregrine Diamonds announces a positive Preliminary Economic...
6/20/2016Peregrine Files Updated Technical Report For Chidliak Projec...
5/17/2016Peregrine Announces Commencement of 2016 Drill Program in Bo...
5/5/2016Peregrine Announces Maiden Inferred Mineral Resource of 4.23...
4/7/2016PEREGRINE REPORTS 33% INCREASE IN CH-6 KIMBERLITE INFERRED D...
3/31/2016Peregrine Diamonds Reports Results of AGM
3/31/2016Peregrine Provides Botswana Exploration Program Update
1/28/2016Jan 28, 2016 Peregrine Diamonds Announces Closing Of Rights ...
1/22/2016Jan 22, 2016 Peregrine Announces Termination Of Chidliak Roy...
1/22/2016Peregrine Announces Termination of Chidliak Royalty
10/27/2015Canada's once-booming Arctic diamond sector loses luster
10/22/2015Oct 22, 2015 Peregrine to Commence Drilling Kimberlite Targe...
10/22/2015Peregrine to Commence Drilling Kimberlite Targets in Botswan...
9/9/2015Peregrine Provides Chidliak Update
7/31/2015Federal and Nunavut Governments to Fund Construction of Iqal...
7/21/2015Jul 21, 2015 Peregrine Provides Chidliak Bulk Sample Update ...
7/14/2015Jul 14, 2015 Peregrine Completes Botswana Transaction and Co...
7/14/2015Peregrine Completes Botswana Transaction and Commences 2015 ...
4/23/2015Apr 23, 2015 Peregrine Provides Update on 2015 Diamond Resou...
4/23/2015Peregrine Provides Update on 2015 Diamond Resource Developme...
4/7/2015Peregrine Reports on Warrant Exercise
3/30/2015Mar 30, 2015 Peregrine Diamonds Announces Acquisition Of Bot...
3/30/2015Announces Acquisition of Botswana Diamond Exploration Compan...
3/30/2015Peregrine Diamonds Announces Acquisition of Botswana Diamond...
3/27/2015Peregrine Diamonds Reports Results of AGM
3/24/2015Mar 24, 2015 Peregrine Diamonds Announces Transfer of Assets...
3/24/2015Announces Transfer of Assets to Peregrine Exploration and Co...
3/24/2015Peregrine Diamonds Announces Transfer of Assets to Peregrine...
3/23/2015Mar 23, 2015 Peregrine Provides Update on 2015 Diamond Resou...
3/23/2015Peregrine Provides Update on 2015 Diamond Resource Developme...
3/10/2015Mar 10, 2015 Peregrine Identifies New Zone with High Diamond...
3/10/2015Identifies New Zone With High Diamond Counts at Chidliak CH-...
3/10/2015Peregrine Identifies New Zone With High Diamond Counts at Ch...
2/25/2015Feb 24, 2015 Peregrine Files Updated Technical Report for Ch...
2/24/2015Files Updated Technical Report for Chidliak Project
2/12/2015Peregrine Diamonds Announces Corporate Reorganization and Ma...
1/27/2015Peregrine Clarifies January 26, 2015 News Release
1/26/2015Jan 26, 2015 Peregrine Reports 15% Increase In Ch-6 Kimberli...
1/26/2015Peregrine Reports 15% Increase in CH-6 Kimberlite Inferred D...
12/30/2014Dec 30, 2014 Peregrine Completes $2.19 Million Private Place...
12/30/2014Peregrine Completes $2.19 Million Private Placement
12/22/2014Dec 22, 2014 Peregrine Announces $2.19 Million Private Place...
12/22/2014Peregrine Announces $2.19 Million Private Placement
12/8/2014Dec 08, 2014 Peregrine Commences Chidliak Site Preparations ...
12/8/2014Peregrine Commences Chidliak Site Preparations for 2015 Diam...
10/24/2014Oct 24, 2014 Peregrine Diamonds Warrants to Begin Trading Mo...
9/2/2014Peregrine Provides Chidliak Diamond Project Update
7/24/2014Peregrine Files Technical Report for Lac de Gras Project and...
6/24/2014Peregrine Provides Chidliak Project Update and Encouraging D...
5/7/2014IIROC Trading Halt - PGD
5/7/2014IIROC Trade Resumption - PGD (all issues)
5/7/2014Peregrine Reports 7.47 Million Carat Inferred Resource for t...
10/23/2013Provides Update
10/11/2013De Beers Elects To Not Exercise Chidliak Option
7/29/2013Provides Corporate Update
6/21/2013Announces Closing of $3.5 Million Private Placement
4/23/2013Collects 508 Tonne Bulk Sample from CH-6
4/5/2013Media coverage of Peregrine Diamonds Ltd.
3/14/2013Peter Meredith Joins Peregrine Board
1/28/2013Announces $5 Million Work Plan at Chidliak, Commencement of ...
10/11/2012Closes Option Agreement and $2.5-Million Private Placement W...
9/5/2012De Beers Completes An Option To Joint Venture The Chidliak D...
8/29/2012Provides Corporate Update
7/24/2012Announces Discovery of 60th Kimberlite and Provides Chidliak...
4/24/2012Discovers Third Kimberlite This Year At Lac De Gras, Canada
4/16/2012Discovers Two Kimberlites at Lac de Gras, Canada
4/11/2012Commences Field Operations at Chidliak
4/2/2012Reports Tonnage Estimate and New Microdiamond Results for CH...
2/27/2012Reports New Microdiamond Results For CH-7 Kimberlite at Chid...
1/23/2012Announces 2012 Chidliak Program
1/18/2012Reports New Diamond Results From the CH-31 and CH-59 Kimberl...
12/20/2011Increases Ownership in Chidliak Diamond Project to 100 Perce...
11/29/2011Reports BHP Billiton is Reviewing its Diamonds Business
10/25/2011CH-28 Mini-Bulk Sample Returns Grade of 0.27 Carats Per Tonn...
10/6/2011Announces High Diamond Counts for CH-52 and CH-58 Kimberlite...
9/12/2011Comprehensive 2011 Field Program Sets Stage for 2012 Bulk Sa...
8/8/2011(Qilaq)Discovers Third Kimberlite at Qilaq; Pipe Size Estimated at ...
6/22/2011Discovers Three More Kimberlites at Chidliak
6/2/2011Discovers Four New Kimberlites and Completes 11,000 Line-Kil...
4/20/2011Discovers CH-51 Kimberlite at Chidliak
3/3/2011Confirms Coarse Diamond Size Distribution at the CH-1 Kimber...
2/22/2011Confirms Coarse Diamond Size Distribution in North and South...
7/26/2010Launches New Website
2/20/2009Announces Completion Of Rights Offering
2/21/2008Raise $5.0 Million
2/14/2008To Drill High Priority Kimberlite-Type Geophysical Anomalies...
12/17/2007Announces Modelled Values of US$43 to US$70 Per Carat for DO...
9/24/2007Discovers new diamondiferous Kimberlite Lithologies at DO-27
9/18/2007Teleconference Wednesday Sept 19 2007
9/18/20072007 DO-27 Bulk Sample Results Confirm Grade of Main Lobe at...
7/24/2007preliminary kimberlite scrubbing test results
7/10/2007Enters into a new Falcon™ system deployment agreement.
6/6/2007Final Total of 2,651 Tonnes of Kimberlite Recovered During 2...
4/18/2007Approximately 2,260 Tonnes of Kimberlite Recovered to Date i...
4/4/2007Northern Miner article on Peregrine Diamonds
3/21/2007Press Release March 21 2007
3/13/2007Stockwatch Article on Peregrine's Exploration Programs in th...
3/23/2006update on winter road and bulk sampling program at DO-27
Comments closed
 
Latest comment posted for this article
Be the first to comment
Add your comment
TORONTO (PGD.TO)
0.230+88.00%
TORONTO
Prev close Open
Low High
Year l/h YTD var.
 -  -
52 week l/h 52 week var.
- -  - -100.00%
Volume 1 month var.
-100.00%
Produces
Develops
Explores for Diamonds - Palladium - Platinum
 
 
 
Analyse
Interactive chart Add to compare
Interactive
chart
Print Compare Export
You must be logged in to use the porfolio and watchlists (free)
Top Newsreleases
MOST READ
Annual variation
DateVariationHighLow
 
5 years chart
 
3 months chart
 
3 months volume chart
 
 
Mining Company News
Plymouth Minerals LTDPLH.AX
Plymouth Minerals Intersects Further High Grade Potash in Drilling at Banio Potash Project - Plannin
AU$ 0.12-8.00%Trend Power :
Santos(Ngas-Oil)STO.AX
announces expected non-cash impairment
AU$ 7.05+0.43%Trend Power :
OceanaGold(Au)OGC.AX
RELEASES NEW TECHNICAL REPORT FOR THE HAILE GOLD MINE
AU$ 2.20+0.00%Trend Power :
Western Areas NL(Au-Ni-Pl)WSA.AX
Advance Notice - Full Year Results Conference Call
AU$ 3.86+0.00%Trend Power :
Canadian Zinc(Ag-Au-Cu)CZN.TO
Reports Financial Results for Q2 and Provides Project Updates
 0.12+4.55%Trend Power :
Stornoway Diamond(Gems-Au-Ur)SWY.TO
Second Quarter Results
CA$ 0.02+100.00%Trend Power :
McEwen Mining(Cu-Le-Zn)MUX
TO ACQUIRE BLACK FOX FROM PRIMERO=C2=A0
US$ 8.91-2.73%Trend Power :
Rentech(Coal-Ngas)RTK
Rentech Announces Results for Second Quarter 2017
US$ 0.20-12.28%Trend Power :
KEFIKEFI.L
Reduced Funding Requirement
GBX 0.59-3.26%Trend Power :
Lupaka Gold Corp.LPK.V
Lupaka Gold Receives First Tranche Under Amended Invicta Financing Agreement
CA$ 0.05+10.00%Trend Power :
Imperial(Ag-Au-Cu)III.TO
Closes Bridge Loan Financing
CA$ 2.06+0.00%Trend Power :
Guyana Goldfields(Cu-Zn-Pa)GUY.TO
Reports Second Quarter 2017 Results and Maintains Production Guidance
CA$ 1.84+0.00%Trend Power :
Lundin Mining(Ag-Au-Cu)LUN.TO
d Share Capital and Voting Rights for Lundin Mining
 12.67+0.88%Trend Power :
Canarc Res.(Au)CCM.TO
Canarc Reports High Grade Gold in Surface Rock Samples at Fondaway Canyon, Nevada
CA$ 0.34+6.25%Trend Power :
Havilah(Cu-Le-Zn)HAV.AX
Q A April 2017 Quarterly Report
AU$ 0.18+0.00%Trend Power :
Uranium Res.(Ur)URRE
Commences Lithium Exploration Drilling at the Columbus Basin Project
US$ 6.80-2.86%Trend Power :
Platinum Group Metals(Au-Cu-Gems)PTM.TO
Platinum Group Metals Ltd. Operational and Strategic Process ...
 1.77-2.21%Trend Power :
Devon Energy(Ngas-Oil)DVN
Announces $340 Million of Non-Core Asset Sales
US$ 40.37-0.22%Trend Power :
Precision Drilling(Oil)PD-UN.TO
Announces 2017Second Quarter Financial Results
CA$ 8.66-0.35%Trend Power :
Terramin(Ag-Au-Cu)TZN.AX
2nd Quarter Report
AU$ 0.04+0.00%Trend Power :
Take advantage of rising gold stocks
  • Subscribe to our weekly mining market briefing.
  • Receive our research reports on junior mining companies
    with the strongest potential
  • Free service, your email is safe
  • Limited offer, register now !
Go to website.