Atlantic Limited

Published : July 16th, 2008

Construction on Schedule for Completion in Q4 2008

( 0 vote, 0/5 ) Print article
  Article Comments Comment this article Rating Follow Company  
0
Send
0
comment

 

 

 

 

 

 

 

ASX / MEDIA ANNOUNCEMENT

 

 16 July 2008

 

 

MARKET UPDATE

 

Windimurra Construction on Schedule for Completion in Q4 2008

 

 

Key points

?                                         The Project remains on target for mechanical completion later this year

?                                         Operational procurement and recruitment is well underway

?                                         Funding remains sufficient to complete construction and commissioning

?                                         The Project construction remains within budget parameters

?                                         Varanus Island gas disruptions expected to have no effect on the Project

?                                         Project economics supported by strong vanadium prices

 

Windimurra Vanadium Limited (ASX:WVL) is pleased to provide an update on the development of its world class vanadium project near Mt Magnet, where it continues to make excellent progress with construction and remains on schedule for completion later this year.

 

Windimurra Managing Director, Dr Iain Scott said the Company expected to complete construction of the plant by Q4 2008, with the plant to finish commissioning in early 2009.

 

?We are on schedule, and by the first quarter of 2009 expect to recommence as one of the world?s premier suppliers of high grade ferrovanadium,? Dr Scott said.

 

?Despite operating in an environment that is subject to significant cost pressures, the project remains within key budget parameters, and the Company has sufficient cash to take the project into production,? Dr Scott said.

 

 

Construction and Procurement

At the end of June, 41% of the total budget had been spent, with a further 34% committed under contract awards bringing the total amount spent or committed to 75% of the overall project construction budget.

 

Construction activity on site continues to increase in line with schedule.  Windimurra currently has more than 290 people working on site with numbers expecting to peak at over 400 after July.

 

All critical long lead items have been procured.  The kiln off-gas equipment, the reduction furnace and the electric arc furnace has been completed on time and on budget.  This equipment is currently being loaded for shipping from South Africa at the end of July.

 

Mineral Resources Limited (MRL), the beneficiation plant Build Own Operate and Transfer (BOOT) contractor, is currently ahead of schedule and approximately 55% complete.  Primary, secondary and tertiary crushers are installed.  The stockpile tunnel installation is complete, the HPGR is on site and work is underway on the ball mill foundation and the beneficiation area.  The fixed price nature of the beneficiation plant contract assists in containing any cost pressures in this area.

 

 

All major construction contracts have been awarded.  Recent awards include:

?                                         Electrical and Instrumentation;

?                                         Gas Inlet Delivery Station and Interface;

?                                         Kiln Mechanical Refurbishment;

?                                         Kiln Refractory Supply and Installation;

?                                         Borefield Pipelines Supply and Installation; and

?                                         Construction of Tailings, Calcine and Barren Liquor Storage Facilities.

?                                          

 

Operational Readiness

Over the last quarter the remaining key operational contracts were let including the:

?                                         Mining Contract;

?                                         Supply of Aluminium Granules;

?                                         Supply of Soda Ash; and

?                                         Operational Transportation and Logistics Agreement.

 

The operational contracts awarded to date, including the BOOT beneficiation plant contract with MRL, represent approximately 72% of the Project?s operating costs, 90% at fixed prices, mitigating the risk of significant cost increases in these areas.

 

In order to mitigate risk on US dollar denominated ferrovanadium sales, the Company has put in place foreign currency call options at 86 cents, sufficient to cover 75% of the Company?s Australian dollar operating costs for the first three years of operation to December 2011.

 

Senior operational recruiting is ongoing with key appointments completed:

?                                         General Manager Operations;

?                                         Processing Manager;

?                                         Technical Services Manager;

?                                         Chief Mine Geologist;

?                                         Environmental Manager;

?                                         OHS Superintendant;

?                                         Survey Manager; and

?                                         Quarry Manager.

 

The recruitment of the remainder of the technical workforce and the operational staff is underway.  The response to-date to job advertisements has been very positive.

 

 

Finance

The Company is in a very strong cash position, with $179 million in the bank at the end of June. 

 

Based on the latest cost-to-complete forecast, this funding remains sufficient to complete construction and commissioning.

 

 

Consistent with the funding plan for the project, the Company has secured approximately $40 million of lease financing for the accommodation camp, power station assets and mining fleet.

 

As part of its risk mitigation process the Company has entered into an interest rate swap agreement to effectively fix the interest rate on the existing US$90m senior loan for a period of three years.

 

 

Varanus Island Gas Incident

The Company has been closely monitoring the June 2008 gas incident at Varanus Island.  The gas for the Project will be sourced from the John Brookes field facilities on Varanus.

 

Based on current information, the Company understands that partial gas deliveries from the John Brookes facilities on Varanus Island will commence in August 2008, ramping up to full production.

 

In these circumstances and given that the project will require its first commissioning gas in November 2008, at this point in time it does not appear that Windimurra?s operations will be affected by the Varanus Island outage.

 

 

Vanadium Market

The Project economics continue to be boosted by the strength of global vanadium prices.  During 2008, vanadium prices have traded at 20 year highs, fuelled by continuing strong world demand and tightening of global supply. Global production has been disrupted by power shortages in South Africa, which have lead to the cancellation of some growth projects, and look set to continue for a number of years.  Robust vanadium market fundamentals have resulted in the current historically high price levels in excess of US$60/kg. 

 

Marketing activities of the Company?s vanadium product have commenced via the off-take agreement with Noble Group. The Company has already received strong market interest from a number of steel mills, and negotiations with these mills have commenced.

 

 

 

For further enquiries call:

 

Dr Iain Scott                                                                                                          Warrick Hazeldine

Managing Director                                                                                           Purple Communications

Tel: +61 (0) 8 9423 1900                                                                                  Tel +61 (0) 89485 1254

                                                                                                                                                                                                                                                                                                                                                                    0417 944 616

 

 

 

 

Windimurra Construction Site in late June

 

 

Background

 

Windimurra Vanadium Limited (WVL) is a mining company based in Perth, Western Australia and is listed on the Australian Stock Exchange (ASX:WVL). The Company?s focus is the development of the world class Windimurra Vanadium Mine, located 600km north east of Perth in WA?s Mid-West region.

 

WVL has a strategic alliance and off-take agreement with leading global supply chain manager, Noble Group Limited, based in Hong Kong. Noble has agreed to purchase the total vanadium output of the Windimurra mine, at prevailing market prices for the life of the mine. 

 

Windimurra contains one of the largest reported proven vanadium Ore Reserves in the world with current mineable reserves of 79.0 million tonnes at a bulk grade of 0.47% V205 (vanadium pentoxide), which will underpin an initial mine life of 20 years at the proposed mining rate of 3.9mtpa. A total of 148 million tonnes of resources have been modelled at a bulk grade of 0.46%.

 

The quality of the ore body, the opportunity to use the latest proven technology and the scale of the project, that will produce 8% of the worlds? vanadium, combine to ensure that Windimurra will be a low cost producer.

 

The Windimurra mine was originally built by the Company with a joint venture partner in 1999, and, whilst operating, was the world?s largest primary vanadium mine, gaining recognition as one of the highest-quality sources of vanadium in the world market.

 

Since 2003, world demand for vanadium and the price of the commodity have increased strongly, largely driven by growth in Chinese steel production. Marketing studies commissioned by WVL forecast that vanadium demand will continue to increase through 2015 at a compound annual growth rate of 7.8%.

 

For more information, please visit www.windimurra.com.au

 

Windimurra Vanadium Limited   ABN 65 009 131 533

Level 4, 76 Kings Park Road, West Perth, Western Australia 6005   Tel: +61 8 9423 1900   Fax: +61 8 9423 1999

 

 

 

***

The new Spam Act commenced on 10 April 2004. This Act is aimed at reducing the amount of unauthorised emails you receive.  You have been receiving e-mails containing information and news releases from us on behalf of our clients because you are an important contact of Purple Communications, a boutique stakeholder communications consultancy.   If you do not wish to receive such emails from Purple, please click mailto: purple@purplecom.com.au subject=UNSUBSCRIBE or reply to this email and put UNSUBSCRIBE in the subject line and we will not email you again.

 If you do not reply, we will continue sending you relevant news and information via email. However, all future emails will allow you to unsubscribe.

 

Issued by

Purple Communications

Level 3, 28 Kings Park Road, WEST PERTH WA 6005

Ph: 08 9485 1254     Fax: 08 6263 0455

purple@purplecom.com.au    

 

 

 



Message protected by MailGuard: e-mail anti-virus, anti-spam and content filtering.
http://www.mailguard.com.au/mg
 
 
Data and Statistics for these countries : Australia | Hong Kong | South Africa | All
Gold and Silver Prices for these countries : Australia | Hong Kong | South Africa | All

Atlantic Limited

CODE : ATI.AX
ISIN : AU000000ATI6
Follow and Invest
Add to watch list Add to your portfolio Add or edit a note
Add Alert Add to Watchlists Add to Portfolio Add Note
ProfileMarket
Indicators
VALUE :
Projects & res.
Press
releases
Annual
report
RISK :
Asset profile
Contact Cpy

Atlantic Ltd is a vanadium exploration company based in .

Atlantic Ltd is listed in Australia. Its market capitalisation is AU$ 27.1 millions as of today (US$ 20.4 millions, € 18.3 millions).

Its stock quote reached its highest recent level on April 15, 2011 at AU$ 2.45, and its lowest recent point on May 03, 2013 at AU$ 0.12.

Atlantic Ltd has 154 760 000 shares outstanding.

Your feedback is appreciated, please leave a comment or rate this article.
Rate : Average note :0 (0 vote) View Top rated
 
Nominations of Atlantic Limited
10/2/2007APPOINTS MERRILL LYNCH FOR DEBT FINANCING
Project news of Atlantic Limited
1/4/2008(Windimurra Project)PROJECT UPDATE
12/31/2007(Windimurra Project)2007 Technical report
12/31/2007(Windimurra Project)Key Of Life Mine Plan Parameters
10/29/2007(Windimurra Project)SECURES GAS SUPPLY
5/29/2007(Windimurra Project)Secures Windimurra Gas Supply
Corporate news of Atlantic Limited
8/12/2015Officials feud over potential new Atlantic City tax receipts
1/30/2015Quarterly Cashflow Report
1/30/2015Quarterly Activities Report
1/16/2015Successful Consent Vote - Forbearance to 16 Jan 2015
12/22/2014Monthly Production and Sales Report
12/22/2014Extension of Forbearance Period
12/15/2014Successful Consent Solicitation Vote
11/19/2014Monthly Production and Sales Report
10/31/2014Quarterly Activities Report
10/31/2014Quarterly Cashflow Report
10/20/2014Design and Construct Tender Award
3/25/2014Grant of Waiver from ASX Listing Rule 10.1
3/21/2014Monthly Production and Sales Report
3/18/2014Initial Director's Interest Notice
3/18/2014Final Director's Interest Notice
3/10/2014Atlantic Secures New Funding Facility
2/27/2014Corporate Update
2/21/2014Standard and Poors Rating Review
2/19/2014New $32.6 Million Funding Facility
2/18/2014Corporate Update
1/30/2009Activities Report Quarter Ended 31 December 2008
7/16/2008Construction on Schedule for Completion in Q4 2008
4/23/2008Construction on Schedule for Completion in 2008
3/28/2008raises $25.2m through share placement
1/14/2008SECURES US$127.5M DEBT FUNDING
1/4/2008Resignation of Roderick Smith as a Director
10/26/2007 RECEIVES ENVIRONMENTAL APPROVALS
10/16/2007 CHANGES NAME
10/9/2007PRECIOUS METALS (ASX:PMA) PMA CONCLUDES MAJOR DEVELOPMENT CO...
6/27/2007FOUNDING DIRECTORS IN SHARE SALE DISCUSSIONS
6/21/2007Board and Management Changes
4/30/2007Activity Report
Comments closed
 
Latest comment posted for this article
Be the first to comment
Add your comment
AUSTRALIA (ATI.AX)
0.175+0.00%
AUSTRALIA
AU$ 0.175
03/24 02:36 -
0%
Prev close Open
0.175 0.175
Low High
0.175 0.175
Year l/h YTD var.
 -  -
52 week l/h 52 week var.
- -  0.175 -%
Volume 1 month var.
0 -%
24hGold TrendPower© : -37
Produces
Develops
Explores for
 
 
 
Analyse
Interactive chart Add to compare
Interactive
chart
Print Compare Export
Last updated on : 7/21/2010
You must be logged in to use the porfolio and watchlists (free)
Top Newsreleases
MOST READ
Annual variation
 
5 years chart
 
3 months chart
 
3 months volume chart
 
 
Mining Company News
Plymouth Minerals LTDPLH.AX
Plymouth Minerals Intersects Further High Grade Potash in Drilling at Banio Potash Project - Plannin
AU$ 0.12-8.00%Trend Power :
Santos(Ngas-Oil)STO.AX
announces expected non-cash impairment
AU$ 7.72+0.72%Trend Power :
OceanaGold(Au)OGC.AX
RELEASES NEW TECHNICAL REPORT FOR THE HAILE GOLD MINE
AU$ 2.20+0.00%Trend Power :
Western Areas NL(Au-Ni-Pl)WSA.AX
Advance Notice - Full Year Results Conference Call
AU$ 3.86+0.00%Trend Power :
Canadian Zinc(Ag-Au-Cu)CZN.TO
Reports Financial Results for Q2 and Provides Project Updates
CA$ 0.12+4.55%Trend Power :
Stornoway Diamond(Gems-Au-Ur)SWY.TO
Second Quarter Results
CA$ 0.02+100.00%Trend Power :
McEwen Mining(Cu-Le-Zn)MUX
TO ACQUIRE BLACK FOX FROM PRIMERO=C2=A0
US$ 11.35+4.13%Trend Power :
Rentech(Coal-Ngas)RTK
Rentech Announces Results for Second Quarter 2017
US$ 0.20-12.28%Trend Power :
KEFIKEFI.L
Reduced Funding Requirement
GBX 0.66-5.75%Trend Power :
Lupaka Gold Corp.LPK.V
Lupaka Gold Receives First Tranche Under Amended Invicta Financing Agreement
CA$ 0.06+0.00%Trend Power :
Imperial(Ag-Au-Cu)III.TO
Closes Bridge Loan Financing
CA$ 2.44+2.52%Trend Power :
Guyana Goldfields(Cu-Zn-Pa)GUY.TO
Reports Second Quarter 2017 Results and Maintains Production Guidance
CA$ 1.84+0.00%Trend Power :
Lundin Mining(Ag-Au-Cu)LUN.TO
d Share Capital and Voting Rights for Lundin Mining
CA$ 16.66+0.73%Trend Power :
Canarc Res.(Au)CCM.TO
Canarc Reports High Grade Gold in Surface Rock Samples at Fondaway Canyon, Nevada
CA$ 0.24-2.04%Trend Power :
Havilah(Cu-Le-Zn)HAV.AX
Q A April 2017 Quarterly Report
AU$ 0.22-2.27%Trend Power :
Uranium Res.(Ur)URRE
Commences Lithium Exploration Drilling at the Columbus Basin Project
US$ 6.80-2.86%Trend Power :
Platinum Group Metals(Au-Cu-Gems)PTM.TO
Platinum Group Metals Ltd. Operational and Strategic Process ...
CA$ 2.45+2.51%Trend Power :
Devon Energy(Ngas-Oil)DVN
Announces $340 Million of Non-Core Asset Sales
US$ 48.15-0.17%Trend Power :
Precision Drilling(Oil)PD-UN.TO
Announces 2017Second Quarter Financial Results
CA$ 8.66-0.35%Trend Power :
Terramin(Ag-Au-Cu)TZN.AX
2nd Quarter Report
AU$ 0.03-6.25%Trend Power :