Crocodile Gold Announces Feasibility Study Results for the Big Hill Project With Pre-Tax IRR of 125% and Reserves of 145,000 Oz Gold

( 0 vote, 0/5 ) Print article
  Article Comments Comment this article Rating Follow Company  
0
Send
0
comment

Crocodile Gold Announces Feasibility Study Results for the Big Hill Project With Pre-Tax IRR of 125% and Reserves of 145,000 Oz Gold

TORONTO, ONTARIO--(Marketwired - Jun 4, 2014) - Crocodile Gold Corp. (CRK.TO)(TSX:CRK.DB)(TSX:CRK.WT)(CROCF)(XGC.F) ("Crocodile Gold" or the "Company) is releasing the results of the Feasibility Study for the Big Hill Enhanced Development Project (the "Project"), located adjacent to the Stawell Gold Mine (SGM), in the State of Victoria, Australia. The Feasibility Study has been completed in accordance with the CIM Definition Standards on Mineral Resources and Mineral Reserves referred to in the National Instrument 43-101 - Standards of Disclosure for Mineral Projects ("NI 43-101") and will be filed within 45 days of this release. All figures are in Australian dollars unless otherwise specified.

Key Project Elements

Financial Analysis Pre-Tax Post-Tax
Gold Price* A$1,415 A$1,415
Undiscounted Cash Flow (M) A$49.2 A$30.3
NPV @ 8% Discount (M) A$38.5 A$22.6
IRR 125.3 % 79.1 %
Payback Period (Years) 1.5 1.9
*Based on a USD$1,225 per gold ounce price and a USD:AUD exchange rate of 0.87
Capital Costs
Pre-production Capital (M) A$11.99
Total Project Capital (M) A$19.60
Operating Costs
Mining Cost (A$/t ore) A$4.83
Waste Rehandle (A$/m3 waste) A$4.98
Processing Costs (A$/t ore) A$14.75
Royalty (A$/oz) A$2.00
Unit Costs
Operating Cash Cost (A$/oz) A$886
All-in Sustaining Cash Cost (A$/oz) A$1,035
Operating Plan
Mining Duration (Years) 3.5 - 4
Mining (Days/Yr) 260
Landform Re-establishment (Years) 1-1.5
Processing
Metallurgical Recovery 90 %
Recovered Grade (g/t Au) 1.5
Recovered Gold (oz) 131,000

Operating Highlights and Project Performance

The Feasibility Study confirms the technical and economic viability of the Project and highlights the measures taken to achieve levels of compliance beyond that of conventional open pit mining because of the proximity to the Stawell community. Self-imposed modified practices have been adopted to mitigate environmental and social impacts, even if not economically optimal.

The Project is currently the subject of an Environmental Effects Statement and Ministerial Assessment. These modified work practices have been adopted in consideration for favourable permitting and works approval.

Substantial work has been done to confirm operational costs, technical support and social impacts. Based on a forecast gold price of A$1,415 per ounce, the Feasibility Study pre-tax NPV (8%) is A$39M with an IRR of 125%. The most positive characteristic of the Project is its high operating margin-economic sensitivity analyses demonstrate the Project NPV to be resilient to downward movement in gold price and potential upward movement in costs. Tables 1 and 2 highlight the Project's ability to withstand potential market pressures and capacity to capitalize on opportunities.

Table 1: Gold Price Sensitivity

Gold price sensitivity (Pre-tax)
A$/oz A$1,300 A$1,350 A$1,400 A$1,450 A$1,500
NPV (A$)(M) A$26.3 A$31.6 A$36.9 A$42.2 A$47.6
IRR (%) 97.7 % 110.2 % 121.9 % 133.1 % 143.7 %
Pre-Tax Payback Period Undiscounted (Years) 1.7 1.6 1.6 1.5 1.5

Table 2: Cost Sensitivity

Change in NPV Pre-tax (%) -20 -10 0 10 20
Capital costs (M) A$42.7 A$40.6 A$38.5 A$36.4 A$34.3
Operating costs (M) A$56.7 A$47.6 A$38.5 A$29.4 A$20.3

Capital Costs

The total pre-production capital cost is estimated at A$11.99 million and include costs associated with site establishment, relocation of existing infrastructure and environmental impact mitigation. The total capital cost for the Big Hill Enhanced Development Project is estimated at A$19.6 million which includes rehabilitation and end land use amenity consideration. Mine fleet requirements will be pursued through either leasing or dry hire arrangement.

Capital Cost Summary Unit Cost (M)
Permitting A$1.85
Project Site Set Up A$2.56
Public Infrastructure A$0.90
Town Water Infrastructures A$2.67
Communication and Fire Watch A$2.05
Mining Set Up A$1.62
Mining Equipment and Operation Fixed Capital A$0.34
Pre-production Capital Costs A$11.99
Environmental A$7.61
Total Project Capital Costs A$19.60

Environmental Bonds will reflect incremental payment at key stages of the project and will also reflect bond reduction on completion of progressive rehabilitative works.

Operating Costs

A comprehensive first principle mining cost model was developed to provide a shadow bid estimate and compared to the result of a formal tender process. This undertaking forms the basis of mine operating costs used in the Feasibility Study. Processing costs are based on actual costs as realized at Stawell Gold Mines for the treatment of Big Hill ore types.

At the end of mining operations, re-handling and rehabilitation of the pits and waste dumps will be undertaken. Approximately 3.6 million cubic meters of material will be re-handled back into the pit voids as part of the rehabilitation. This will complete the progressive rehabilitation program of events.

Operating Cost Summary Unit Cost
Mining cost (A$/t rock) A$4.83
Waste re-handle cost (A$/m3) A$4.98
Processing & Administration cost (A$/t ore) A$14.75

Additional operating cost allowances have been incorporated to reflect the adoption of leading practice mine operations and are estimated to be more than A$10.6 million over the life of the project (see cost details below). These initiatives are in addition to those environmental management initiatives included within capital costs, and are included within operating unit rates presented.

Big Hill Mineral Resource Estimate

The mineral resource model used in the Feasibility Study is current as at March 2014. Drill spacing over the considered resource area is largely 20m x 25m, with drilling inclusive of additional RC and Diamond drilling programs from 2008, 2012 and 2013. The estimate incorporates an updated geological interpretation, update of the resource estimate, review and update of historical void models, utilization of a pit shell (constrained) at A$1,425 gold price and an in situ cut off for reporting of 0.35g/t Au. The Indicated Mineral Resources are inclusive of those Mineral Resources modified to produce the Ore Reserves.

Big Hill Mineral Resources Estimate as of March 2014

Domain Tonnes
(Mt)
Gold Grade
(g/t Au)
Ounces Gold
(000's)
Big Hill Measured - - -
Big Hill Indicated 3.0 1.7 160
Total (Measured and Indicated) 3.0 1.7 160
Inferred 0.2 1.2 7
  1. All Mineral Resources and Mineral Reserves have been estimated in accordance with the JORC Code and have been reconciled to CIM Standards as prescribed by National Instrument 43-101.
  2. Mineral Resources are exclusive of Mineral Reserves.
  3. Mineral Resources were estimated using a gold price of A$1,425/oz and cut-off grade of 0.35g/t Au.
  4. Surface Mineral Resource estimates were prepared by Justine Tracey, Resource Geologist, Crocodile Gold, under the supervision of Mr Stuart Hutchin. Mr Hutchin is the Geology Manager for Mining One Consultants of Melbourne, Victoria and member of the Australasian Institute of Mining and Metallurgy and the member of the Australasian Institute of Geoscientists, and acts as the Qualified Person for Surface Resources under NI43-101.
  5. Mineral Resources and Mineral Reserves are rounded to 1,000 tonnes, 0.01 g/t Au and 1,000 ounces. Minor discrepancies in summations may occur due to rounding.
  6. Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability.

A series of dilution modelling routines were applied to the resource model to develop a model that would reflect the impact, on grade and tonnes, of practical mining constraints.

Big Hill Mineral Reserve Estimate

The pit optimization and design were developed considering, detailed slope parameter analysis, potential infrastructure interaction, safe operating widths for the proposed equipment, business objectives, rehabilitation commitments, previous mining activities (both open pit and underground), minimization of dust and noise impact on the surrounding community and rehabilitative commitments.

Big Hill Ore Reserves as of March 2014

Big Hill Enhanced Development Project Reserve Classification Tonnes (Mt) Gold Grade (g/t Au) Ounces Gold (000's)
North Pit Probable 1.4 1.7 77
South Pit Probable 1.5 1.4 68
Total 2.9 1.5 145
  1. All Mineral Resources and Mineral Reserves have been estimated in accordance with the JORC Code and have been reconciled to CIM Standards as prescribed by National Instrument 43-101.
  2. Mineral Reserves were estimated using a gold price of A$1,415/oz and cut-off grade of 0.4g/t Au.
  3. Mineral Reserve estimates were prepared by Dean Basille, Principal Mining Engineer with Mining One Consultants of Melbourne, Victoria. Mr. Basille is a member and Chartered Engineer of the Australasian Institute of Mining and Metallurgy, has over 18 years of relevant mining engineering experience and is the Qualified Person for Reserves under NI 43-101.
  4. Mineral Resources and Mineral Reserves are rounded to 1,000 tonnes, 0.01 g/t Au and 1,000 ounces. Minor discrepancies in summations may occur due to rounding.
  5. Mineral Reserves have demonstrated economic viability.

Geology, Mining, Metallurgy and Processing

Underground mining operations at Stawell Gold Mines has been continuous since 1981 with the extraction of gold bearing ore from the Magdala and Golden Gift systems to a vertical depth of -1200mRL and -1600mRL respectively.

Big Hill is the up dip extension of the Magdala system which has been historically mined from underground. It contains Basalt Contact mineralisation, Central Lode mineralisation and Stockwork mineralisation, all typically seen in the Magdala system. Big Hill geology and mineralisation can be broken into 4 main domains: Mariner's, Allen's, Iron Duke and Magdala Flank. All except Mariner's and Allen's are separated by faults (Figures 1 & 2).

The project proposes the mining of two open cut pits, the North Pit and the South Pit (Figure 3). The North Pit will be mined first and provide near immediate production contribution in light of outcropping ore zones. On completion of the North Pit, the pit will be filled and progressively rehabilitated as the South Pit is mined. The South Pit is effectively an extension to economic depth of the former "Davis Pit" which was mined in the late 80's and early 90's. On completion of the South Pit, all waste rock will be returned to the pit voids and a full re-establishment and rehabilitation program will be undertaken with additional waste rock and top soil contributions from historic stockpiles.

The mine life is anticipated to be in the order of 3.5 to 4 years (excluding backfilling of the South Pit) using a mining fleet consisting of one 120 tonne and one 190 tonne excavator coupled with an average of five 90t trucks. Test work indicates material can be extracted using a rip and dig or free dig mining methods, with some drill and blast planned in the lower 30m of both pits.

An extensive Metallurgical test work program has been completed for both the Big Hill northern and southern (Davis Extension) pit areas. This test work was based on the leaching of a large number of RC drill intercepts during the period of 1998 to early 1999 and several new Diamond drill holes drilled in 2013.

Overall, the gold recovery from testing averaged 91.7%, with recovery consistent with depth, level of weathering of the rock and mine section.

The processing plant at Stawell has been in operation since 1984 and has a well-established flow path to accommodate the treatment of both oxidized and fresh ore types.

Ore from the Davis Open Cut has been previously processed at SGM with close to 500kt milled, with an overall gold recovery of 90% achieved. Testing of the mineralization in Big Hill has demonstrated that the mineralisation elsewhere in the deposit will behave in a similar manner to the Davis Open Cut mineralisation previously processed. A gold recovery of 90% is forecast.

The tailings facility at SGM has a current approved work plan to cover all additional requirements for the Project.

Environmental, Permitting, Social and Community Considerations

To achieve leading practice operations, which mitigate environmental and social impacts, the project has taken into account a number of additional initiatives to conventional practice. Strategies associated with the mining method modification (eg. no blasting until the bottom portion of the Pits), alignment of ramps relative to residential dwellings, dust mitigation measures, pit development, waste dump construction, noise modelling and monitoring, re-establishment of Big Hill, back filling of the South Pit, etc. has required the mine plan to be delivered to a high level of detail.

Pit and stockpile benching configurations have been proposed that shield nearby residences from noise and dust emissions, reducing some overall efficiency of operations. A staged mining approach is to be used in the South Pit to reduce the active footprint and noise and dust emissions in the upper levels. Mining operations will be restricted to daylight hours only on Monday to Friday, with additional modified practices to mitigate social impact:

  • Reduced use of blasting
  • Sealing of haul roads, additional water carts and use of dust suppressants
  • Staged clearing and grubbing
  • Noise attenuation suppressant equipment
  • Real time weather monitoring and predictive management practices

Additional Operating Costs for Community and Environmental Considerations

Initiative Impact Cost Implication
Mining, stockpile and reconstruction sequence and schedule Decreased efficiency of mining, increased equipment moves, reduced equipment and schedule for the North Pit. Additional equipment for noise bunding and increased haulage distance for staged pit. A$4.9M
Reduced blasting Rip and Dig requirement increased to defer drill and blast activity. Costing allowance in ancillary equipment for an extra D11 bulldozer over normal project allowances. A$1.9M
Additional watering capacity Additional water carts required for project duration, ancillary fleet contains two additional water carts to contractor requirements. A$2.2M
Landform re-construction Additional bulldozer and compactor maintained during re-construction activities. Ancillary equipment for land form push-up and compaction. A$1.6M
Total A$10.6M

Notes/Technical Disclosure/Disclaimers

Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability. Environmental, permitting, legal, title, taxation, sociopolitical, marketing, or other relevant issues may materially affect the estimates of Mineral Resources.

The quantity and grade of reported Inferred Mineral Resources in the above estimations are uncertain in nature and there has been insufficient exploration to define these Inferred Resources as an Indicated or Measured Mineral Resource and it is uncertain if further exploration will result in upgrading them to an Indicated or Measured Mineral Resource category.

Technical reports prepared in accordance with NI 43-101 supporting the updated Mineral Resource and Mineral Reserve estimates will be available under the Company's profile on SEDAR (www.sedar.com) within 45 days of this news release.

Qualified Person

F. W. Nielsen, P.Geo, Technical Consultant to Crocodile Gold, is a "qualified person" as such term is defined in National Instrument 43-101 and has reviewed and approved the technical information and data included in this press release.

About Crocodile Gold

Crocodile Gold is a Canadian gold mining and exploration company with three operating mines in Australia in the State of Victoria and the Northern Territory. The Company has a combined land package in excess of 4,000 sq. km. The objective of Crocodile Gold is to continue production from its three operating mines, Cosmo, Fosterville, and Stawell, while also exploring and developing the Company's resources to ensure sustainable production in the future. For additional information, please visit our website www.crocgold.com.

Follow us on Twitter @crocgold_crk or Facebook www.facebook.com/CrocodileGoldCorp.

Cautionary Note

Certain information set forth in this press release contains "forward-looking statements", and "forward-looking information under applicable securities laws. Except for statements of historical fact, certain information contained herein constitutes forward-looking statements, which include the Company's expectations for future performance based on current drill results and past production, expected gold prices, and mineral resource and mineral reserve estimates, and are based on Crocodile Gold's current internal expectations, estimates, projections, assumptions and beliefs, which may prove to be incorrect. Some of the forward-looking statements may be identified by words such as "expects" "anticipates", "believes", "projects", "plans", and similar expressions. These statements are not guarantees of future performance and undue reliance should not be placed on them. Such forward-looking statements necessarily involve known and unknown risks and uncertainties, which may cause Crocodile Gold's actual performance and financial results in future periods to differ materially from any projections of future performance or results expressed or implied by such forward-looking statements. These risks and uncertainties include, but are not limited to: liabilities inherent in mine development and production; geological, mining and processing technical problems; Crocodile Gold's inability to obtain required mine licences, mine permits and regulatory approvals required in connection with mining and mineral processing operations; competition for, among other things, capital, acquisitions of reserves, undeveloped lands and skilled personnel; incorrect assessments of the value of acquisitions; changes in commodity prices and exchange rates; currency and interest rate fluctuations; various events that could disrupt operations and/or the transportation of mineral products, including labour stoppages and severe weather conditions; the demand for and availability of rail, port and other transportation services; the ability to secure adequate financing and management's ability to anticipate and manage the foregoing factors and risks. There can be no assurance that forward-looking statements will prove to be accurate, and actual results and future events could differ materially from those anticipated in such statements. Crocodile Gold undertakes no obligation to update forward-looking statements if circumstances or management's estimates or opinions should change except as required by applicable securities laws. The reader is cautioned not to place undue reliance on forward-looking statements.

To view the Figures associated with this release, please visit the following link: http://media3.marketwire.com/docs/CRKFig1-3.pdf.

Read the rest of the article at finance.yahoo.com
Data and Statistics for these countries : Australia | All
Gold and Silver Prices for these countries : Australia | All

Crocodile Gold Corp

PRODUCER
CODE : CRK.TO
ISIN : CA2270411002
Follow and Invest
Add to watch list Add to your portfolio Add or edit a note
Add Alert Add to Watchlists Add to Portfolio Add Note
ProfileMarket
Indicators
VALUE :
Projects & res.
Press
releases
Annual
report
RISK :
Asset profile
Contact Cpy

Crocodile Gold is a gold producing company based in Canada.

Crocodile Gold produces gold, copper, lead, silver and zinc in Australia, develops gold in Australia.

Its main assets in production are BROCKS CREEK, UNION REEFS MILL, HOWLEY and TOM'S GULLY in Australia, its main asset in development is MAUD CREEK in Australia and its main exploration properties are MARIO PERU in Peru and COSMO, BURNSIDE and THUNDERBALL in Australia.

Crocodile Gold is listed in Canada. Its market capitalisation is CA$ 532.9 millions as of today (US$ 515.1 millions, € 419.8 millions).

Its stock quote reached its lowest recent point on December 24, 2008 at CA$ 0.02, and its highest recent level on January 15, 2010 at CA$ 2.40.

Crocodile Gold has 475 820 000 shares outstanding.

Your feedback is appreciated, please leave a comment or rate this article.
Rate : Average note :0 (0 vote) View Top rated
 
Financings of Crocodile Gold Corp
3/28/2013Announces Amended Terms to Previously Announced Convertible ...
3/21/2013Announces Filing of Final Prospectus for Upsized Underwritte...
3/20/2013Announces Increase in Previously Announced Convertible Deben...
2/23/2010Receives Proceeds of C$32 Million from Accelerated Expiry of...
Nominations of Crocodile Gold Corp
7/3/2013Announces Appointment of New President and Chief Executive O...
5/24/2013Announces Resignation of CEO
2/29/2012Announces New Directors
12/15/2011Appoints Special Committee of the Board and Financial Adviso...
5/17/2011Announces Appointment of New
3/28/2011Announces Appointment of Bill
Financials of Crocodile Gold Corp
5/15/2013Reports Operating Cash Flow of $17.6 Million on Revenue of $...
1/30/2013Reports Fourth Quarter Revenue of $101.8 Million on the Sale...
8/16/2011Reports Revenue of $30 Million on the Sale of 20,200 Ounces ...
Project news of Crocodile Gold Corp
1/22/2014Crocodile Gold Exceeds Increased Production Guidance With 21...
10/10/2013Raises 2013 Production Guidance to 200,000-205,000 Ounces Go...
7/15/2013Posts Production of 48,261 Ounces in the Second Quarter of 2...
4/17/2013Posts Production of 48,539 Ounces in the First Quarter of 20...
10/10/2012Obtains Approval to Proceed at Its International Mine
5/9/2012Expects to Significantly Increase 2012 Production With the A...
5/4/2012Completes Acquisition of Fosterville and Stawell Mines from ...
3/28/2012and Aurico Gold Sign Definitive Agreement in Respect of Croc...
3/12/2012Iron Blow Massive Sulphide Deposit Returns Significant Assay...
1/23/2012Produces 68,019 Ounces of Gold in 2011 to Meet Production Gu...
12/20/2011(Maud Creek)Reports on Its Maud Creek Deposit
12/15/2011(Cosmo)Completes Main Ventilation Shaft for the Cosmo Underground M...
9/15/2011(Cosmo)Extracts First Development Ore from Cosmo Underground Mine o...
9/8/2011Intersects Significant High-Grade Mineralization at Union Re...
7/28/2011to Bring Rising Tide Deposit Into Near-Term Mine Plan
7/6/2011Continues Positive ExplorationResults Intersects High Grade ...
6/16/2011Intersects Extension to HighGrade Mineralized Structure 650 ...
5/30/2011Options the Mario Property in Peru to Fortuna Silver
4/14/2011Continues to Intersect High Grade Mineralised Structures Adj...
2/22/2011(Union Reefs Mill)Intersects 6=2E9 g/t Au Over 10 Metres Under Historic Prospe...
2/22/2011(Union Reefs Mill)Intersects 6.9 g/t Au Over 10 Metres Under Historic Prospect...
2/15/2011(Union Reefs Mill)Initiates Drill Program at Union Reefs Project Area Targetin...
2/15/2011(Union Reefs Mill)Initiates Drill Program at Union Reefs Project Area Targetin...
2/8/2011(Thunderball)Announces Initial Uranium Resource Estimate at Thunderball C...
4/14/2010Intersects 4.9 G/T Au Over 16 Metres at Cosmo Project 300 Me...
3/22/2010(Brocks Creek)Provides 2010 Production Guidance and Announces Major Explor...
3/22/2010(Tom's Gully)Provides 2010 Production Guidance and Announces Major Explor...
3/22/2010(Howley)Provides 2010 Production Guidance and Announces Major Explor...
Corporate news of Crocodile Gold Corp
6/23/2015Letter of Transmittal and Election Form
4/23/2015Announces Date for First Quarter 2015 Financial Earnings Rel...
4/23/2015Crocodile Gold Announces Date for First Quarter 2015 Financi...
4/10/2015Crocodile Gold Announces Strong Start to 2015 Producing 59,6...
4/1/20152014 Annual Information Form
4/1/2015Crocodile Gold Reports 2014 Year-End Mineral Reserves and Mi...
3/31/2015Crocodile Gold Reports 2014 Year-End Mineral Reserves and Mi...
3/16/2015Crocodile Gold Reports Record Operating Results in 2014; Com...
2/20/2015Crocodile Gold Announces Date for Fourth Quarter and Fiscal ...
2/19/2015Crocodile Gold Achieves Exploration Success on High-Grade Dr...
2/2/2015Crocodile Gold Reports Substantial High-Grade Drill Results ...
1/14/2015Crocodile Gold Announces Closing of Agreement to Terminate I...
1/14/2015Correction From Source: Crocodile Gold Announces Closing of ...
1/13/2015Retransmission: Crocodile Gold Achieves Record Gold Producti...
1/13/2015Crocodile Gold Achieves Record Gold Production in 2014 With ...
12/22/2014Crocodile Gold Successfully Negotiates Termination of Free C...
11/10/2014Crocodile Gold Reports Strong Operating Cash Flow of $18.2 M...
10/30/2014Crocodile Gold Reports on Ministerial Independent Panel's Re...
10/14/2014Crocodile Gold Produces 163,516 Ounces of Gold in First Nine...
7/31/2014Crocodile Gold Reports Revenue of $69.2 Million and Operatin...
6/4/2014Crocodile Gold Announces Feasibility Study Results for the B...
5/27/2014Crocodile Gold Files Technical Reports for Fosterville and C...
2/3/2014Crocodile Gold Executes Three Key Contracts for Its Northern...
11/13/2013Crocodile Gold Reports Operating Cash Flow of $18.3 Million ...
10/10/2013Crocodile Gold Increases Third Quarter Gold Production by Ov...
8/14/2013Reports Operating Cash Flow of $11.0 Million on Revenue of $...
7/24/2013s Northern Territory Mineral Reserve and Resource Estimates
4/5/2013Closes Previously Announced Convertible Debenture Offering o...
4/3/2013Enters Into an Amended and Restated Agreement and Announces ...
2/4/2013Files Its Big Hill Project Preliminary Economic Assessment T...
1/31/2013Announces Positive Preliminary Economic Assessment on the Bi...
1/18/2013Achieves 2012 Production Targets With 155,523 Ounces
10/19/2012Announces Disposition of Block Held by AuRico to New Shareho...
10/15/2012Production Increases 26% Sequentially to 45,963 Ounces Gold ...
10/1/2012Announces Management Changes
10/1/2012Announces Management Changes
8/30/2012Intersects 23.36 g/t Gold Over 5.70 Metres With the Potentia...
8/15/2012Reports Revenue of $56.8 Million on the Sale of 35,665 Ounce...
7/12/2012Triples Its Gold Production to 36,117 Ounces in the Second Q...
6/12/2012Closes Prepaid Swap Facility With Credit Suisse
5/23/2012Annual General Meeting to Be Held at the Sheraton Centre Tor...
5/15/2012Reports Revenue of $18.5 Million on the Sale of 10,900 Ounce...
5/15/2012Files Technical Reports on Fosterville and Stawell Mines, St...
5/10/2012Intersects 240.2 Grams Per Tonne Gold Over 2.52 Meters Below...
3/27/2012and Aurico Gold Sign Definitive Agreement in Respect of Croc...
3/20/2012Reports Revenue of $108 Million on the Sale of 68,601 Ounces...
3/19/2012(Cosmo)Commences Stope Ore Production at Cosmo Mine
2/22/2012Extracts 119,000 Tonnes of Ore in January 2012
2/16/2012Luxor Capital Group issues open letter to shareholders of Cr...
2/9/2012Announces Completion of Bid as Luxor Capital Group Becomes 7...
1/26/2012(Cosmo)Provides Outlook for 2012: Expected to Produce 75,000 to 85,...
1/26/2012Luxor Capital and Crocodile Gold Mail Materials to Sharehold...
1/23/2012Luxor Capital and Crocodile Gold Reach Agreement on Increase...
1/21/2012Intersects 27.96 Grams Per Tonne Gold Over 2.05 Meters Below...
1/9/2012Board Advises Shareholders to TAKE NO ACTION at This Time as...
1/9/2012Board Advises Shareholders to TAKE NO ACTION at This Time as...
12/28/2011Receives Unsolicited Bid by Luxor; Advises Shareholders to W...
12/21/2011Announces Update on Shareholder Rights Plan
12/14/2011Responds to Luxor Press Release
10/13/2011Intersects High-Grade Mineralization at The Crosscourse Depo...
9/12/2011S&P press release applied to Crocodile Gold website in error
8/31/2011Completes Major Airborne Geophysical Survey and Identifies N...
8/25/2011highlighted in The Gold Report
8/23/2011Intersects 7.1 g/t Au Over 4.5 Meters Including 11.2 g/t Au ...
8/9/2011now on Facebook and Twitter
7/11/2011(Thunderball)=?ISO-8859-1?Q?Crocodile=20Gold=27s=20Joint=20Venture=20Part...
6/7/2011Reports Results for Quarter Ended March 31, 2011
5/24/2011Crocodile Gold to Host Conference Call to Introduce New Pres...
4/26/2011=?ISO-8859-1?Q?Crocodile=20Gold=20Adds=20310,000=20Gold=20Ou...
3/31/2011Reports Results for the Year Ended December 31, 2010
3/24/2011=2E Announces Closing of
3/1/2011Announces C$85,050,000 Bought Deal Financing
2/28/2011Announces Appointment of Stephen Woodhead as Chief Financial...
3/22/2010Provides 2010 Production Guidance and Announces Major Explor...
Comments closed
 
Latest comment posted for this article
Be the first to comment
Add your comment
TORONTO (CRK.TO)
1.12-2.61%
TORONTO
Prev close Open
Low High
Year l/h YTD var.
 -  -
52 week l/h 52 week var.
- -  - -100.00%
Volume 1 month var.
-100.00%
Produces Copper - Gold - Lead - Silver - Zinc
Develops Gold
Explores for Gold - Silver - Uranium - Zinc
 
 
 
Analyse
Interactive chart Add to compare
Interactive
chart
Print Compare Export
Last updated on : 6/29/2010
You must be logged in to use the porfolio and watchlists (free)
Top Newsreleases
MOST READ
Annual variation
DateVariationHighLow
 
5 years chart
 
3 months chart
 
3 months volume chart
 
 
Mining Company News
Plymouth Minerals LTDPLH.AX
Plymouth Minerals Intersects Further High Grade Potash in Drilling at Banio Potash Project - Plannin
AU$ 0.12-8.00%Trend Power :
Santos(Ngas-Oil)STO.AX
announces expected non-cash impairment
AU$ 7.66-0.71%Trend Power :
Oceana Gold(Au)OGC.AX
RELEASES NEW TECHNICAL REPORT FOR THE HAILE GOLD MINE
AU$ 2.20+0.00%Trend Power :
Western Areas NL(Au-Ni-Pl)WSA.AX
Advance Notice - Full Year Results Conference Call
AU$ 3.86+0.00%Trend Power :
Canadian Zinc(Ag-Au-Cu)CZN.TO
Reports Financial Results for Q2 and Provides Project Updates
CA$ 0.12+4.55%Trend Power :
Stornoway Diamond(Gems-Au-Ur)SWY.TO
Second Quarter Results
CA$ 0.02+100.00%Trend Power :
McEwen Mining(Cu-Le-Zn)MUX
TO ACQUIRE BLACK FOX FROM PRIMERO=C2=A0
US$ 12.26+2.68%Trend Power :
Rentech(Coal-Ngas)RTK
Rentech Announces Results for Second Quarter 2017
US$ 0.20-12.28%Trend Power :
KEFIKEFI.L
Reduced Funding Requirement
GBX 0.53-1.87%Trend Power :
Lupaka Gold Corp.LPK.V
Lupaka Gold Receives First Tranche Under Amended Invicta Financing Agreement
CA$ 0.06+0.00%Trend Power :
Imperial(Ag-Au-Cu)III.TO
Closes Bridge Loan Financing
CA$ 2.64-1.86%Trend Power :
Guyana Goldfields(Cu-Zn-Pa)GUY.TO
Reports Second Quarter 2017 Results and Maintains Production Guidance
CA$ 1.84+0.00%Trend Power :
Lundin Mining(Ag-Au-Cu)LUN.TO
d Share Capital and Voting Rights for Lundin Mining
CA$ 16.23+4.04%Trend Power :
Canarc Res.(Au)CCM.TO
Canarc Reports High Grade Gold in Surface Rock Samples at Fondaway Canyon, Nevada
CA$ 0.24+4.26%Trend Power :
Havilah(Cu-Le-Zn)HAV.AX
Q A April 2017 Quarterly Report
AU$ 0.22+2.38%Trend Power :
Uranium Res.(Ur)URRE
Commences Lithium Exploration Drilling at the Columbus Basin Project
US$ 6.80-2.86%Trend Power :
Platinum Group Metals(Au-Cu-Gems)PTM.TO
Platinum Group Metals Ltd. Operational and Strategic Process ...
CA$ 1.88+0.53%Trend Power :
Devon Energy(Ngas-Oil)DVN
Announces $340 Million of Non-Core Asset Sales
US$ 52.71+0.19%Trend Power :
Precision Drilling(Oil)PD-UN.TO
Announces 2017Second Quarter Financial Results
CA$ 8.66-0.35%Trend Power :
Terramin(Ag-Au-Cu)TZN.AX
2nd Quarter Report
AU$ 0.04+5.56%Trend Power :