TORONTO, ONTARIO--(Marketwire - Jan. 17, 2013) - Argonaut Gold Inc. ("Argonaut Gold" or the "Company") (News - Market indicators), announced today that the Company achieved record gold production of 32,000 ounces during the 4th quarter ended December 31, 2012. This included 25,805 ounces at its 100% owned El Castillo Mine ("El Castillo") in Durango, Mexico and 6,195 ounces at its 100% owned La Colorada Mine ("La Colorada") in Sonora, Mexico. All dollar amounts are in US dollars except as otherwise noted.

FOURTH QUARTER 2012 HIGHLIGHTS:

El Castillo

  • Record production of 25,805 gold ounces (+31% improvement over Q4 2011)
  • 39,329 gold ounces loaded on the pad (+30% improvement over Q4 2011)
  • West Side Pad 8 construction moving forward; first cell to be loaded starting in Q2 of 2013

La Colorada

  • Production of 6,195 gold ounces and 47,890 silver ounces
  • 8,845 gold ounces and 815,219 silver ounces loaded on the pad
  • Phase 2 pad construction is 65% complete
  • Crushing circuit relocated and fully operational
    • Final crushing circuit expansion scheduled for early in Q2 of 2013
  • Overburden removal commenced in the La Colorada/Gran Central pit 

Financial

  • Year-end cash balance was $191 million as of December 31, 2012, of which C $115 million for warrant exercises was included
  • Fourth Quarter sales of 29,500 ounces of gold and 70,910 ounces of silver

Full year 2012

  • Total production of 108,081 ounces of gold (+50% over 2011)
    • El Castillo 87,712 ounces (+22% over 2011)
    • La Colorada 20,369 ounces

El Castillo In Pit Sulphide Mineralization

  • Over 360,000 gold ounces have been added to El Castillo's in-pit resources. The additional sulfide mineralization is divided into two categories including non-silicified sulphides and silicified sulphides; this provides 22.6 million tonnes at a grade of 0.504 g/t. The majority of the mineralization falls in the non-silicified category which has an average grade of 0.47 g/t with recoveries ranging from 25% to over 50%. The smaller silicified zone of mineralization is mainly confined to a higher grade breccia pipe averaging 0.80 g/t. yielding recoveries of 11% to 28%. 
  • Results encompass approximately 5,000 meters of core drilling for 32 holes completed in multiple programs over the last three years. All metallurgical testing was completed by Kappes, Cassidy & Associates ("KCA") in Reno, Nevada. 
Measured and Indicated Resource Table
Sulphide non-silicified Sulphide silicified
Cutoff Tonnes Au g/t Au oz cont. Tonnes Au g/t Au oz cont.
0.15 24,032,586 0.428 330,392 2,801,142 0.717 64,590
0.20 22,639,932 0.443 322,310 2,599,320 0.759 63,388
0.25 20,200,020 0.469 304,655 2,415,744 0.799 62,064
0.30 17,337,720 0.501 279,379 2,085,348 0.882 59,127
0.40 10,978,344 0.589 208,000 1,680,330 1.013 54,715
For economic evaluation, the non-silicified sulphide zone is based upon 30% recovery; the silicified sulphide zone is based upon 17% recovery.
  • Global Sulphide Resource:
    • El Castillo's global measured and indicated ("M&I") sulphide resource shows 1.5 million ounces of gold at an average grade of 0.296 g/t; it lies below the oxide and transitional gold resource at El Castillo. It is the Company's current interpretation that the silicified sulphides make up a relatively low percentage of the total sulfides and is largely limited to the silicified breccia pipe.

Please visit www.argonautgold.com for a full table of metallurgical results and images related to the sulphides.

FOURTH QUARTER 2012 El CASTILLO OPERATING RESULTS

Fourth quarter 2012 operating statistics showed improvement over fourth quarter 2011 results. Ore production is now at an annualized rate of approximately 13 million tonnes.

El Castillo Operating Statistics    
         
    3 Months Ended       Year End    
    12/31/2012   12/31/2011   Change   12/31/2012   12/31/2011   Change
Mining (000)                        
Total tonnes mined   6,695   5,437   23%   24,052   20,009   20%
Tonnes ore   3,321   2,912   14%   11,962   11,145   7%
Heap Leach Pad (000)                        
Direct ore tonnes to leach pad   2,033   2,098   -3%   7,561   8,114   -7%
Crushed Ore tonnes to pad   1,282   839   53%   4,555   3,041   50%
Production                        
Gold grade (g/t)   0.37   0.32   15%   0.39   0.33   18%
Gold loaded to pad (oz)   39,329   30,162   30%   151,462   117,939   28%
Gold loaded to carbon(oz)   25,805   19,698   31%   87,712   72,049   22%
Gold sold (oz)   23,595   20,468   15%   89,881   66,521   35%
1 "g/t" is grams per tonne
2 "oz" means troy ounce

Richard Rhoades, Chief Operating Officer of Argonaut Gold said "Year-end production at El Castillo of 87,712 gold ounces came in above increased guidance of 85,000 ounces for the year. The team at El Castillo team delivered yet another quarter of continued improvement, providing a 10% increase over the initial 2012 guidance. In addition to exceeding guidance expectations, the Company has seen dramatic improvement in crushing at the operation. The operation is now crushing at a rate of approximately 5 million tonnes per year."

Production has approached a near steady state at El Castillo. Higher grade material during the fourth quarter of 2012 provided for production of over 25,000 ounces against to guidance of 21-22,000 ounces for the quarter. In 2013, the operation anticipates lower grades, offset by higher volumes of material, for an estimated 5-10% increase over total 2012 production.

FOURTH QUARTER 2012 LA COLORADA OPERATING RESULTS

Overburden removal continues at La Colorada in preparation for full scale mining. During the fourth quarter, the crusher was relocated with a minimal impact to the production plan. Fourth quarter production provided 6,195 ounces of gold, for a total 2012 production of 20,369 ounces. Final production exceeded expectations due to higher than anticipated recoveries from the reprocessing of material and positive grade reconciliation.

La Colorada Operating Statistics
3 Months Ended Year Ended
  12/31/2012 12/31/2012
Mining (000)    
Total Tonnes mined 2,945 7,173
Tonnes ore 922 3,332
Heap Leach Pad (000)    
Crushed ore tonnes to pad 623 2,895
Production    
Gold grade (g/t) 0.43 0.43
Gold loaded to pad (oz) 8,845 40,180
Gold loaded to carbon(oz) 6,195 20,369
Silver loaded to carbon (oz) 47,890 132,805
Gold sold (oz) 5,907 19,900
Silver sold (oz) 54,108 116,717
1 "g/t" is grams per tonne
2 "oz" means troy ounce

In discussing the Company's fourth quarter and year end highlights, Mr. Pete Dougherty, President and CEO said "2012 has been a year of significant accomplishments for Argonaut Gold's employees. The Company has delivered on operational production expectations and added an important project, Magino, for future growth and development. 

The El Castillo production rate has shown continual improvement quarter over quarter. La Colorada has exceeded initial expectations while forming the foundation for the future. There is still more work to be done to elevate the Company to the status of a mid-tier producer and I am grateful for what has been accomplished so far."

Argonaut Gold Q4 and Year End Financial Results Conference Call and Webcast:

The Q4 and year end financial results call is set to take place on March 26, 2013 at 8:30 am ET. Details for the call in participation are included below:

Q4 and Year-End Conference Call Information:
  Toll Free (North America): 1-866-226-1792
  International: 1-416-340-2216
     
  Webcast:  www.argonautgold.com 
     
Q4 and Year End Conference Call Replay:
  Toll Free Replay Call (North America): 1-800-408-3053
  International Replay Call: 1-905-694-9451
    Passcode: 7979249

The conference call replay will be available from 10:30 a.m. ET on March 26, 2013 until April 2, 2013.

About Argonaut Gold

Argonaut Gold is a Canadian gold company engaged in exploration, mine development and production activities. Its primary assets are the production stage El Castillo Mine in Durango, Mexico and, the La Colorada Mine in Sonora, Mexico, the advanced exploration stage San Antonio project in Mexico, the recently acquired advanced exploration stage Magino project in Ontario, Canada and several exploration stage projects, all of which are located in North America.

Creating Value Beyond Gold

Cautionary Note Regarding Forward-looking Statements

This press release contains certain "forward-looking statements" and "forward-looking information" under applicable Canadian securities laws concerning the proposed transaction and the business, operations and financial performance and condition of Argonaut Gold Inc. ("Argonaut"). Forward-looking statements and forward-looking information include, but are not limited to, statements with respect to estimated production and mine life of the various mineral projects of Argonaut; synergies and financial impact of completed acquisitions; the benefits of the development potential of the properties of Argonaut; the future price of gold, copper, and silver; the estimation of mineral reserves and resources; the realization of mineral reserve estimates; the timing and amount of estimated future production; costs of production; success of exploration activities; and currency exchange rate fluctuations. Except for statements of historical fact relating to Argonaut, certain information contained herein constitutes forward-looking statements. Forward-looking statements are frequently characterized by words such as "plan," "expect," "project," "intend," "believe," "anticipate", "estimate" and other similar words, or statements that certain events or conditions "may" or "will" occur. Forward-looking statements are based on the opinions and estimates of management at the date the statements are made, and are based on a number of assumptions and subject to a variety of risks and uncertainties and other factors that could cause actual events or results to differ materially from those projected in the forward-looking statements. Many of these assumptions are based on factors and events that are not within the control of Argonaut and there is no assurance they will prove to be correct.

Factors that could cause actual results to vary materially from results anticipated by such forward-looking statements include changes in market conditions, variations in ore grade or recovery rates, risks relating to international operations, fluctuating metal prices and currency exchange rates, changes in project parameters, the possibility of project cost overruns or unanticipated costs and expenses, labour disputes and other risks of the mining industry, failure of plant, equipment or processes to operate as anticipated. Although Argonaut has attempted to identify important factors that could cause actual actions, events or results to differ materially from those described in forward-looking statements, there may be other factors that cause actions, events or results not to be anticipated, estimated or intended. There can be no assurance that forward-looking statements will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements. Argonaut undertakes no obligation to update forward-looking statements if circumstances or management's estimates or opinions should change except as required by applicable securities laws. The reader is cautioned not to place undue reliance on forward-looking statements. Statements concerning mineral reserve and resource estimates may also be deemed to constitute forward-looking statements to the extent they involve estimates of the mineralization that will be encountered if the property is developed. Comparative market information is as of a date prior to the date of this document.

Technical Information and Mineral Properties Reports

The technical information contained in this document has been prepared under supervision of, and reviewed and approved by Mr. Thomas H. Burkhart, Argonaut's Vice President of Exploration, and a qualified person as defined by National Instrument 43-101 ("NI 43-101"). For further information on the Company's properties discussed herein please see the reports as listed below on the Company's website or on www.sedar.com:

El Castillo Mine NI 43-101 Technical Report on Resources and Reserves, Argonaut Gold Inc.,
El Castillo Mine, Durango State, Mexico dated November 6, 2010
La Colorada Mine NI 43-101 Preliminary Economic Assessment La Colorada Project, Sonora, Mexico dated December 8, 2011


Argonaut Gold Inc.
Nichole Cowles
Investor Relations Manager
(775) 284-4422 x 101
nichole.cowles@argonautgold.com
www.argonautgold.com
Data and Statistics for these countries : Canada | Mexico | All
Gold and Silver Prices for these countries : Canada | Mexico | All

Argonaut Gold Inc.

PRODUCER
CODE : AR.TO
Follow and Invest
Add to watch list Add to your portfolio Add or edit a note
Add Alert Add to Watchlists Add to Portfolio Add Note
ProfileMarket
Indicators
VALUE :
Projects & res.
Press
releases
Annual
report
RISK :
Asset profile
Contact Cpy

Argonaut Gold is a gold producing company based in United states of america.

Argonaut Gold holds various exploration projects in Mexico.

Its main assets in production are EL SASTRE GOLD MINE, EL SASTRE, EL SASTRE - EL ARENAL, EL SASTRE BRIDGE ZONE and EL SASTRE - LUPITA ZONE in Guatemala and EL CASTILLO in Mexico and its main exploration property is SAN ANTIONIO in Mexico.

Argonaut Gold is listed in Canada. Its market capitalisation is CA$ 72.5 millions as of today (US$ 53.1 millions, € 49.8 millions).

Its stock quote reached its highest recent level on January 25, 2013 at CA$ 9.99, and its lowest recent point on November 18, 2022 at CA$ 0.33.

Argonaut Gold has 176 940 000 shares outstanding.

Your feedback is appreciated, please leave a comment or rate this article.
Rate : Average note :0 (0 vote) View Top rated
 
Nominations of Argonaut Gold Inc.
11/15/2013Announces New Chief Financial Officer
12/15/2011Announces New Chief Operating Officer
Financials of Argonaut Gold Inc.
3/16/2015Announces 2014 Revenue of $166.3M, $42.5M in Cash Flow from ...
8/6/2013Provides Notice of Second Quarter Financial Results on Augus...
7/25/2012Provides Notice of Second Quarter Financial Results on Augus...
3/19/2012Provides Notice of Fourth Quarter and Year End Financial Res...
8/5/2011Provides Notice of Second Quarter Financial Results on Augus...
Project news of Argonaut Gold Inc.
1/31/2014Confirms Filing of Prefeasibility Study for the Magino Proje...
1/20/2014CORRECTION FROM SOURCE - Argonaut Gold Announces Full Year 2...
1/20/2014Announces Full Year 2013 Gold Production of 120,224 gold equ...
12/31/2013Announces Completion of the San Agust=EDn project purchase f...
11/6/2013Announces Purchase of San Agust=EDn project from Silver Stan...
10/16/2013Announces Q3 Gold Production of 26,690 Ounces
7/15/2013Announces Record Q2 Gold Production of 33,586 Ounces
4/15/2013Announces Q1 Gold Production of 28,907 Ounces
2/25/2013Announces 2013 Production Guidance of 120-140,000 Ounces
1/17/2013Exceeds 2012 Guidance with Gold Production of 108,081 Ounces
1/17/2013Exceeds 2012 Guidance with Gold Production of 108,081 Ounces
7/18/2012Announces Q2 Gold Production of 24,123 Ounces
4/17/2012Announces Q1 Gold Production of 21,084 Ounces
7/15/2011Announces Q2 Gold Production of 17,453 Ounces
4/14/2011Announces Q1 Gold Production of 18,005 0unces
3/22/2011(San Antionio)Reports on Resource Expansion Drilling at San Antonio
2/14/2011(El Castillo)Provides 2011 Guidance on El Castillo Production of 70-75,00...
Corporate news of Argonaut Gold Inc.
5/25/2016Argonaut Gold Raises C$4.5M via Private Placement of Flow-Th...
5/4/2016Argonaut Gold Announces Results of Annual and Special Meetin...
5/3/2016Argonaut Gold Announces First Quarter 2016 Earnings per Shar...
4/29/2016Argonaut Gold Announces $30 Million Revolving Credit Facilit...
4/14/2016Argonaut Gold Announces First Quarter 2016 Production of 32,...
4/6/2016Argonaut Gold Further Strengthens Board and Management Team
1/18/2016Argonaut Gold Announces Updated Pre-Feasibility Study Result...
11/30/2015Mexus Gold is Pleased to Announce That Argonaut Gold Has Com...
11/24/2015Argonaut Gold Chairman Brian Kennedy Retiring; Jim Kofman to...
11/3/2015Argonaut Gold Announces Third Quarter 2015 Revenue of $32M; ...
11/2/2015Argonaut Gold El Castillo Update
10/22/2015Argonaut Gold El Castillo Update
10/19/2015Mexus Commences Drill Pad Construction for Argonaut
10/15/2015Argonaut Gold Announces Third Quarter 2015 Production of 28,...
9/17/2015Argonaut Gold Announces Updated Economic Parameters to the D...
9/14/2015Mexus Gold US Julio/Santa Elena Update
9/9/2015Mexus Gold US Press Release Correction
8/17/2015Argonaut Gold Updates Mexus Gold US on the Julio property
8/14/2015Argonaut Gold Announces Second Quarter 2015 Revenue of $44M;...
4/15/2015Announces First Quarter 2015 Production of 43,255 Gold Equiv...
3/16/2015Argonaut Gold Announces 2014 Revenue of $166.3M, $42.5M in C...
2/20/2015Argonaut Gold Confirms Filing of Technical Report and Prelim...
1/26/2015Argonaut Gold Receives TSX Acceptance of Shareholder Rights ...
1/20/2015Argonaut Gold Adopts Shareholder Rights Plan
1/13/2015Argonaut Gold Announces Full Year 2014 Gold Production of 13...
1/13/2015Argonaut Gold Announces Updates on the Magino and San Agusti...
1/12/2015Argonaut Gold Announces Updates on the Magino and San Agusti...
1/7/2015Argonaut Gold Announces Full Year 2014 Gold Production of 13...
11/6/2014Argonaut Gold Announces Third Quarter 2014 Revenue of $37.3M...
10/15/2014Argonaut Gold Announces Q3 Production of 32,122 Gold Equival...
10/3/2014Argonaut Gold Confirms Filing of National Instrument 43-101 ...
8/29/2014IIROC Trade Resumption - AR
11/12/2013Announces 3rd Quarter 2013 Revenue of $42.4M and Net Income ...
8/13/2013Announces 2nd Quarter 2013 Revenue of $44.9M and Net Income ...
5/14/2013Announces 1st Quarter 2013 Revenue of $43.1M and Net Income ...
4/26/2013Amends Annual Meeting Business in Response to ISS Comments
3/26/2013Announces 2012 Revenue of $187.1 Million and Net Income of $...
11/14/2012Announces Third Quarter 2012 Revenue of $72.9 Million and Ne...
10/15/2012and Prodigy Agree to Friendly Business Combination
10/15/2012and Prodigy Agree to Friendly Business Combination
10/15/2012and Prodigy Agree to Friendly Business Combination
9/4/2012Announces Updated PEA for the San Antonio Project, Projected...
8/15/2012Announces Record Production, Record Revenue and Record Earni...
5/15/2012Announces First Quarter 2012 Revenue of $24.4 Million and Ne...
5/8/2012Provides Exploration Update on San Antonio and La Colorada
4/25/2012for Annual and Special Meeting of Shareholders
3/30/2012Announces 2011 Revenue of $105 Million and Net Income of $26...
3/14/2012Added to the S&P/TSX Composite Index
2/27/2012Announces 2012 Project Initiatives
1/9/2012Announces the La Colorada Project on Track for Production in...
11/28/2011(El Castillo)Reports on Metallurgical Test Work for El Castillo Sulphide
10/24/2011Increases Measured and Indicated Resource at La Colorada to ...
9/14/2011to be Included in the S&P TSX SmallCap Index
8/15/2011Reports Q2 2011 Revenue of $21.6 Million Net Income of $5.2 ...
6/15/2011Provides Update on 2011 Drilling at La Colorada; Board Appro...
6/6/2011Reports Q1 2011 Revenue of $25.7 Million
5/20/2011Announces Intent to Terminate Registration Under U.S. Securi...
5/9/2011s Resource for San Antonio
4/7/2011Begins Resource Expansion Drilling at the La Colorada Projec...
3/31/2011Announces Q4 Revenue of $19.9 Million as Part of Year End Fi...
3/16/2011to Begin Trading on the S&P Canadian Index Operations
1/25/2011Shareholders and Pediment Gold Corp Shareholders Approve Bus...
Comments closed
 
Latest comment posted for this article
Be the first to comment
Add your comment
TORONTO (AR.TO)
0.410+2.50%
TORONTO
CA$ 0.410
04/23 17:00 0.010
2.5%
Prev close Open
0.400 0.405
Low High
0.400 0.415
Year l/h YTD var.
0.230 -  0.430 -2.38%
52 week l/h 52 week var.
0.230 -  0.720 -29.31%
Volume 1 month var.
3,188,874 32.26%
24hGold TrendPower© : -44
Produces Gold
Develops
Explores for
 
 
 
Analyse
Interactive chart Add to compare
Interactive
chart
Print Compare Export
Last updated on : 2/15/2010
You must be logged in to use the porfolio and watchlists (free)
Top Newsreleases
MOST READ
Annual variation
DateVariationHighLow
2024-32.79%
202317.31%0.770.42
2022-77.19%2.760.33
2021-16.79%4.091.90
202048.11%3.420.76
 
5 years chart
 
3 months chart
 
3 months volume chart
 
 
Mining Company News
Plymouth Minerals LTDPLH.AX
Plymouth Minerals Intersects Further High Grade Potash in Drilling at Banio Potash Project - Plannin
AU$ 0.12-8.00%Trend Power :
Santos(Ngas-Oil)STO.AX
announces expected non-cash impairment
AU$ 7.71-0.39%Trend Power :
Oceana Gold(Au)OGC.AX
RELEASES NEW TECHNICAL REPORT FOR THE HAILE GOLD MINE
AU$ 2.20+0.00%Trend Power :
Western Areas NL(Au-Ni-Pl)WSA.AX
Advance Notice - Full Year Results Conference Call
AU$ 3.86+0.00%Trend Power :
Canadian Zinc(Ag-Au-Cu)CZN.TO
Reports Financial Results for Q2 and Provides Project Updates
CA$ 0.12+4.55%Trend Power :
Stornoway Diamond(Gems-Au-Ur)SWY.TO
Second Quarter Results
CA$ 0.02+100.00%Trend Power :
McEwen Mining(Cu-Le-Zn)MUX
TO ACQUIRE BLACK FOX FROM PRIMERO=C2=A0
US$ 11.11+2.21%Trend Power :
Rentech(Coal-Ngas)RTK
Rentech Announces Results for Second Quarter 2017
US$ 0.20-12.28%Trend Power :
KEFIKEFI.L
Reduced Funding Requirement
GBX 0.55-0.90%Trend Power :
Lupaka Gold Corp.LPK.V
Lupaka Gold Receives First Tranche Under Amended Invicta Financing Agreement
CA$ 0.06-8.33%Trend Power :
Imperial(Ag-Au-Cu)III.TO
Closes Bridge Loan Financing
CA$ 2.47+3.78%Trend Power :
Guyana Goldfields(Cu-Zn-Pa)GUY.TO
Reports Second Quarter 2017 Results and Maintains Production Guidance
CA$ 1.84+0.00%Trend Power :
Lundin Mining(Ag-Au-Cu)LUN.TO
d Share Capital and Voting Rights for Lundin Mining
CA$ 15.25-3.42%Trend Power :
Canarc Res.(Au)CCM.TO
Canarc Reports High Grade Gold in Surface Rock Samples at Fondaway Canyon, Nevada
CA$ 0.24+0.00%Trend Power :
Havilah(Cu-Le-Zn)HAV.AX
Q A April 2017 Quarterly Report
AU$ 0.19+0.00%Trend Power :
Uranium Res.(Ur)URRE
Commences Lithium Exploration Drilling at the Columbus Basin Project
US$ 6.80-2.86%Trend Power :
Platinum Group Metals(Au-Cu-Gems)PTM.TO
Platinum Group Metals Ltd. Operational and Strategic Process ...
CA$ 1.79-3.76%Trend Power :
Devon Energy(Ngas-Oil)DVN
Announces $340 Million of Non-Core Asset Sales
US$ 52.57+0.84%Trend Power :
Precision Drilling(Oil)PD-UN.TO
Announces 2017Second Quarter Financial Results
CA$ 8.66-0.35%Trend Power :
Terramin(Ag-Au-Cu)TZN.AX
2nd Quarter Report
AU$ 0.04+5.88%Trend Power :