Banro Corporation

Published : January 26th, 2009

Feasibility Study Of Twangiza Gold Project Indicates Gold Production Of 320,000 Ounces Per Year

( 0 vote, 0/5 ) Print article
  Article Comments Comment this article Rating Follow Company  
0
Send
0
comment

Contact Us

Monday, January 26, 2009
Banro's Feasibility Study Of Its Twangiza Gold Project Indicates Gold Production Of 320,000 Ounces Per Year At An Average Total Operating Cash Cost Of Us$274 Per Oz Over First Three Years Of Production



TORONTO, January 26, 2009 - Banro Corporation ("Banro" or the "Company") (TSX - "BAA"; NYSE Alternext US - "BAA";) is pleased to announce results of the Feasibility Study ("FS") of its wholly-owned Twangiza project, located on the Twangiza-Namoya gold belt in the Democratic Republic of the Congo (the "DRC").

This follows the Pre-Feasibility Study ("PFS") of the Twangiza Project, the results of which were announced in a press release issued on July 7, 2008.

Highlights include:
  • Average annual production of 319,962 ounces of gold per annum for the first 3 years of operation at average total operating cash costs of US$274 per ounce;
  • Average annual production of 261,965 ounces of gold per annum for the first 5 years of operation at average total operating cash costs of US$358 per ounce;
  • Total gold production of 2,615,807 ounces over 15 years life of mine, based on current resources, at average total operating cash costs US$429 per ounce;
  • Extensions of the current zone and neighbouring gold targets at Twangiza have the potential to add significant oxide resources to the project;
  • Twangiza Project capital expenditure of US$409.6 million (which includes a contingency of US$38.9 million);
  • A separate stand alone 30MW Hydro Electric scheme (the Ulindi II site) to supply power to the Twangiza Project will cost US$133.8 million (including a contingency of US$20.1 million) to be funded in whole or in part by third party financing;
  • Total Project capital expenditure of US$409.6 million, increasing to US$476.5 million assuming that Banro funds 50% (US$66.9 million) of the Hydro Electric plant;
  • Project post tax net present value ("NPV") of US$342 million based on a gold price of US$850 per ounce and a discount rate of 5%;
  • Total Project capital expenditure payback of 2.53 years from start of production, yielding an IRR of 20.5%. (These figures assume that Banro funds US$66.9 million or 50% of the Hydro Electric plant);
  • Total Project net cash flows after tax and after capital spending of US$593 million.
Banro President and CEO Mike Prinsloo said: "We are very pleased with the robustness of the Twangiza Project as demonstrated by this Feasibility Study. On the back of this outcome and the further upside which the neighbouring deposits on the Twangiza property offer to increase the oxide and transitional resources, we will now actively seek a strategic partner to assist us in adding ounces and to further strengthen the Twangiza Project economics through to development of this open pit project."

The Feasibility Study has been prepared with input from a number of independent consultants including SRK Consulting (United Kingdom) - (Mineral Resource), SRK Consulting (South Africa) - (Mining, Mineral Reserves, Environmental and Social), SGS Lakefield (South Africa) - (Metallurgical testwork), Mintek (South Africa) - (Metallurgical test work), Knight Pi�sold (Canada) - (Hydro Power), AMEC Earth & Environmental (United Kingdom) - (Tailings and Water facilities) and SENET (South Africa) - (Processing Plant and Infrastructure). SENET also undertook the economic valuation and report compilation for the study.

Comparison with the July 7, 2008 Pre-Feasibility Study

The above mentioned independent consultants were also responsible for preparing the Pre-Feasibility Study, the results of which were published on July 7, 2008.

In order to provide a comparative base to the Pre-Feasibility Study of July 7, 2008, the key financial drivers and assumptions have been largely maintained. (See comparative table, Table VI, on page 14 of this release).

Twangiza Project Overview

The Twangiza Project is located in the South Kivu Province of the DRC, 41 kilometers to the south-southwest of Bukavu, the provincial capital. The Twangiza property consists of six exploitation permits totaling 1,164 square kilometers which are wholly-owned by Banro through a DRC subsidiary, Twangiza Mining SARL. The current exploration commenced in October 2005 and up to November 2008, more than 330 Diamond drill holes have been completed. Gold mineralization is hosted in sediments (mudstones and siltstones) which have been intruded by a series of feldspar porphyry sills along the hinge of a major anticlinal structure.

Mr. Prinsloo said: "With the completion of the resource upgrade, the infill drilling program and the core technical and consulting work for this Feasibility Study, we will now turn our attention to adding more resource ounces to Twangiza. Further exploration work is planned on a number of flanking structures, identified by SRK, that remain open along strike. We expect to prove up additional ounces, especially in the oxide and transitional categories, on the four neighbouring targets on the Twangiza Project which are within trucking distance of the proposed Twangiza plant site, namely Luhwindja (adjacent to Twangiza North), Kaziba, Mufwa and Tshondo. These deposits are expected to strengthen the robustness of the Twangiza project and boost the ounce profile over and above the numbers we released today."

Mineral Resources

SRK Consulting (UK) Ltd. ("SRK (UK)") prepared updated independent estimates of the Mineral Resources at Twangiza which were announced by Banro in a press release dated January 14, 2009 and are also set out in Table I below. A copy of the press release can be obtained from SEDAR at www.sedar.com and EDGAR at www.sec.gov.

The Mineral Resource estimates are reported according to the definitions and guidelines given in the Canadian Institute of Mining, Metallurgy and Petroleum ("CIM") Definition Standards on Mineral Resources and Mineral Reserves. These estimates have an effective date of January 9, 2009 and are based on sampling and assay data available as at November 19, 2008. SRK (UK) has used a cut-off grade of 0.5 g/t gold. The Mineral Resources are considered to have reasonable prospects for economic extraction by open pit mining and have been restricted to an optimum pit shell which uses a US$1,000/oz gold price assumption.

Martin Pittuck, who is an employee of SRK (UK), is the "Qualified Person" (as such term is defined in National Instrument 43-101) for the purpose of the Mineral Resource estimates.

Table I below presents the Mineral Resource estimates by confidence category.

Table I - Summary of SRK (UK)'s Twangiza Mineral Resources Statement (January 9, 2009)

Mineral Resource Category Tonnes (Million) Grade (g/t Au) Ounces (Million)
Measured 17.2 2.40 1.32
Indicated 90.3 1.50 4.28
Measured & Indicated 107.5 1.60 5.60
Inferred 8.2 1.70 0.40
(Above 0.5 g/t Au cut-off)

The infill drilling program that was completed since the previous estimates of June 23, 2008, targeted Inferred Resources within the Pre-Feasibility limiting pit shell and confirmed the geometry of the mineralized bodies. This infill drilling and the inclusion of the 20 holes, which were drilled by CME Consulting Ltd. in 1997-1998 (excluded from the previous estimates), has also increased confidence in the estimates at depth. SRK (UK)'s updated model for this Feasibility Study is slightly wider than the Pre-Feasibility Study model, incorporating additional low grade material and therefore producing a slightly lower grade than the previous model. Changes in estimation parameters have influenced the estimation of block grades to a small extent with more samples being used in the current estimation.

SRK (UK) has reported the Mineral Resources using a block cut-off grade of 0.5 g/t gold to reflect the technical and economic parameters used in the Feasibility Study and is consistent with the Pre-Feasibility Study.

The increased resource at Twangiza Main is mostly in the Indicated fresh rock material. Reconciliation work between the Pre-Feasibility model and the current estimates shows that the significant increase in the resources is due to the infill drilling program intercepting certain additional high grade intersections at depth, which has resulted in material being transferred from the Inferred and unclassified categories into the Indicated Mineral Resource category.

SRK (UK) has applied high grade capping of certain values during the estimation process as consistent with the Pre-Feasibility model (in the oxide, transitional and fresh domains and capped to 20 g/t gold, 25 g/t gold and 10 g/t gold respectively). SRK (UK)'s Mineral Resource estimates have been limited to a pit shell based on an upside potential of US$1,000/oz gold price. The pit shell represents a 10% increase in the price used for the Pre-Feasibility Study pit shell.

Given the importance associated with the lithological model, SRK (UK) has updated and in some places reinterpreted the lithological model for the deposit. SRK (UK) recommends further work be completed on the interpretation at the north east of the main deposit to further define the presence of a syncline structure, which is open at depth. A number of flanking structures remain open along strike and these may add incremental oxide and transitional Mineral Resources if further drilling supports their extensions.

Mine Planning

SRK Consulting (South Africa) (Pty) Ltd, ("SRK (SA)") undertook the mine planning process, based on the Measured and Indicated Mineral Resources delineated to date at Twangiza. Pit optimizations were undertaken on the two principal deposits at Twangiza, namely Twangiza Main and Twangiza North, using the following estimates and factors:

Gold price US$750/oz (downside)
US$850/oz (base case)
US$950/oz (upside)
Diesel fuel price US$ 1.20/litre
Mining dilution 5% at zero grade
Mining recovery 95%
Pit slopes Minus 28 to 55 degrees
Metallurgical recovery Oxide ore: Twangiza Main 90.2%
  Oxide ore: Twangiza North 91.2%
  Transitional porphyry: Twangiza Main 79.5%
  Transitional porphyry: Twangiza North 93.2%
  Fresh porphyry: Twangiza Main 74.8%
  Fresh porphyry: Twangiza North 81.4%
  Transitional sedimentary 36.4%
  Fresh sedimentary 51.7%

The following Mineral Reserves were estimated by SRK (SA) to be contained in a practical pit design:

Table II - Summary of Twangiza Mineral Reserve Estimates (January 12, 2009)

Reserve Category

Deposit

Tonnes
(Million)

Grade
(g/t Au)

Ounces
(Million)

Proven Twangiza Main and North

14.46

2.45

1.14

Probable Twangiza Main and North

46.42

1.69

2.53

Total Proven and Probable Reserves Twangiza Project

60.88

1.87

3.67


SRK (SA)'s independent estimates of the Twangiza Mineral Reserves are based on the Mineral Resource estimates set out above in Table I of this release. The Mineral Reserves were estimated by Wally Waldeck and Mark Sturgeon, both of whom are employees of SRK (SA) and "Qualified Persons" (as such term is defined in National Instrument 43-101). The Mineral Reserve Statement uses the definitions and guidelines given in CIM Definition Standards on Mineral Resources and Mineral Reserves and is reported in accordance with National Instrument 43-101 requirements.

The two deposits at Twangiza are planned to be mined simultaneously to provide throughput of 5 million tonnes of oxide ore to the processing plant in the initial years. The transitional and fresh ore types are planned to be stock piled during this period and processed once the oxide ore production begins decreasing.

The Twangiza Project has a favourable stripping ratio of 2.34, which is an important contributing factor to Twangiza's low operating costs.

The estimated total open pit mine operating cost of US$5.31 per tonne of ore is equivalent to US$1.59 per tonne of rock mined, based on an owner operated mining option.

This Feasibility Study of Twangiza does not include Inferred Mineral Resources in the open pit outlines.

"The highest gold production from the open pits and the lowest cost production occur in the early years, because of the higher throughput of the oxide ore and the low strip ratio. Hence our objective is to add additional oxide and porphyry transitional ounces to maximize and uplift the production profile over the first 7 years of production life, to a production profile in excess of 300,000 ounces, with as much oxide as possible from the neighboring deposits." said Mr. Prinsloo.

This study has been done with specific focus on the non-refractory portion of the ore body by SRK at Banro's request. SRK has however included some of the transitional and fresh sedimentary ore types in the measured and indicated categories. Owing to their refractory nature, these reflect lower processing plant recoveries (36% for the transitional sedimentary and 52% for the fresh sedimentary).

Processing

Metallurgical test work, including recovery and comminution studies on composite drill core samples, has been undertaken on the oxide, transitional (non-refractory) and fresh rock (non-refractory sulfide) ore categories by SGS Lakefield. The results indicate that the oxide sediments and porphyry, transitional and fresh rock feldspar porphyry host rock are all non-refractory, while some of the transitional and fresh rock sedimentary ores are of a refractory nature or contain some refractory material.

This Feasibility Study treats all of this sedimentary rock as refractory, as not enough drilling and delineation has been done to date, to define the non-refractory percentage portion of the ore. Additional drill holes for further metallurgical testwork and definition of the sedimentary rock, to clearly define the refractory portion thereof, will be completed going forward. For this Feasibility Study, the conservative position has been taken of categorizing all the transitional sedimentary and fresh sedimentary as refractory at recovery percentages of 36% and 52% respectively. This approach should give further upside to Twangiza in the latter years of production.

Optimization and variability metallurgical results to date indicate the following metallurgical overall recoveries for the various ore types (with reserve tonnages and yields shown):

  • Twangiza Oxide Main: 90.2% (13.8 Mt at 2.14 g/t gold)
  • Twangiza Oxide North: 91.2% (3.8 Mt at 2.12 g/t gold)
  • Twangiza Transitional Main (non-refractory): 79.5% (4.8 Mt at 1.86 g/t gold)
  • Twangiza Transitional North (non-refractory): 93.2% (2.2 Mt at 2.06 g/t gold)
  • Twangiza Fresh Main (non-refractory): 74.8% (18.4 Mt at 1.32 g/t gold)
  • Twangiza Fresh North (non-refractory): 81.4% (1.4 Mt at 2.19 g/t gold)
Based on the comminution testwork, leach optimization and variability testwork performed, SENET designed a comminution circuit consisting of single stage crushing followed by a SAG and ball mill operating in closed circuit with hydrocyclones. A conventional Gravity-CIL (carbon-in-leach) processing facility was allowed for with an annual throughput of 5.0 million tonnes of oxides or 3.75 million tonnes of transitional and fresh ore, or combinations thereof. The gravity circuit will recover 20-25% of the feed to the plant as free gold. This Feasibility Study is based on an optimized single stream CIL plant as compared to the Pre-Feasibility Study which was based on a 3 stream CIL plant. Metallurgical testwork has begun on alternative processing routes, such as Leachox, to pursue the extraction of gold from the refractory ores in the transitional and fresh sedimentary ore types as described above.

Scouting bottle-roll test work was performed at excess conditions on the transitional and fresh refractory sedimentary Main and North ores. The following overall recoveries were obtained and used for design purposes, for all the deeper tonnage in both pits.

  • Twangiza Transitional Main (refractory): 36.4% (3.2 Mt at 3.13 g/t gold)
  • Twangiza Transitional North (refractory): 36.5% (0.4 Mt at 2.91 g/t gold)
  • Twangiza Fresh Main (refractory): 51.7% (12.6 Mt at 1.87 g/t gold)
  • Twangiza Fresh North (refractory): 51.8% (0.3 Mt at 1.85 g/t gold)
Site Selection and Related Infrastructure

Due to the non-availability of an appropriate drill rig towards the end of 2008, some geohydrological and surface geotechnical drill holes have not been drilled and therefore a conclusive geotechnical investigation and geohydrological investigation to a "Bankable Feasibility Study" level could not be completed within the planned timeframe. These holes will however be drilled and the associated laboratory and interpretive analysis will be conducted as soon as practically possible, to ensure confirmation of the assumptions used for this Feasibility Study. By strict definition this Feasibility Study is therefore not complete and as such may not be considered at the time of this press release to be at a "Bankable Feasibility level". The pre-feasibility work and conclusions in both of these areas, have however been further strengthened with additional assumptions and work, over the past seven months.

The mineral resources, selected process route and other areas are however conclusive to the "Bankable Feasibility level". Subject to any implications (positive or negative) of the respective geotechnical and geohydrological investigations, the financial analysis is also conclusive.

All sites have at this stage been selected to optimum technical and economical considerations. The final site selection could however be influenced by the outcomes of the geotechnical and geohydrological investigations. However, with all the work completed at Twangiza to date, it is not expected to change significantly. The tailings dam site selection is still under review in an endeavour to further reduce project capital costs.

Power

Knight Piesold Ltd. of Vancouver, Canada, has undertaken studies to investigate the potential for a stand-alone hydroelectric power generation for the Twangiza Project. These investigations/studies have indicated that the development of a hydroelectric facility to supply power to the Twangiza Project is both feasible and viable. The study is based on a 30 MW, run-of-river hydroelectric scheme on the Ulindi River (Ulindi II site, 35 km from Twangiza site), utilizing a 600 meter natural drop in the river over a distance of approximately 8 kilometers.

Although capital costs are higher (for the hydroelectric alternative compared to diesel generation), operating costs are significantly lower, (especially processing power costs) resulting in cost savings over the life of the project, which gives Twangiza a competitive advantage.

In addition, the hydroelectric facility, besides having a residual value on mine closure also has the potential to obtain carbon credits which can claw back on the capital investment for the power project. This carbon credit benefit has not been reflected in the financials as it has not been concluded at this stage. Although it is anticipated that a hydroelectric facility could satisfy the majority of the project's power requirements, back up diesel power generating facilities of 6MW would be required for essential processing plant equipment and for emergencies. The cost of these diesel facilities has been included in the project's capital cost.

The capital to fund the hydroelectric power facility is planned to be raised as a separate exercise to the Project capital and will be housed in a Banro subsidiary that will supply power to the Twangiza mine over its life. The hydroelectric project is planned to be developed separately but in parallel to the Twangiza mine development.

"Going the hydroelectric route not only complements Banro's environmental friendly policies, but also presents an opportunity to reduce costs over the life of the Twangiza Project. The access to its own stand-alone hydro power plant, supplying a cheaper form of power, is a distinct competitive advantage for the Twangiza Project. We will seek third party funding for all or part of the hydroelectric power plant, which will be repaid on a kWh rate over the first 10 years of the project. The hydro cost of US$0.084/kWh compares very favorably to the US$0.54/kWh of diesel generated power," said Mr. Prinsloo.

Water

AMEC (UK) undertook the water supply dam design, which suggests that a robust process water supply can be achieved through the joint operation of a fresh water dam facility, designed to intercept surface runoff (rainfall) for gravity discharge to the process plant, together with supernatant water reclaimed from the tailings management facility pond.

Tailings Management

AMEC (UK) undertook studies to confirm civil arrangements for a robust tailings management facility ("TMF"). A preferred surface site aligned within a natural river valley close to the plant site, has been selected to safely retain up to 66 Mt of slurried tailings. Appropriate river diversion arrangements have been appraised to safely route the upstream catchment water and storm water events around the TMF. In due consideration of the region's high seismicity, the main embankment has been designed as a downstream gravity dam, with internal drainage arrangements and an upstream low permeability zone. The utilization of approved construction material won from the open pit works has consequently been assumed. Upon completion of the geotechnical, geochemical and hydrogeological investigations, with their associated laboratory analysis, the TMF study will be further optimized, with respect to its arrangement and costs, by addressing potential co-disposal of dried tailings with stripped waste, operated in parallel with a reduced slurry TMF scheme.

Accessibility and Transport/Logistics

SENET and FH Bertling Logistics have undertaken surveys with detailed analysis of access routes to the Twangiza project for plant and equipment as well as ongoing production materials and consumables. As part of the Feasibility Study the following routes were investigated:

  1. Mombasa (Kenya)-Nairobi-Kampala (Uganda) - Kigali (Rwanda) - Bukavu (DRC) and then en-route to Site via the N2 road in South Kivu Province - by road.
  2. Dar es Salaam (Tanzania) to Kigomo by road or rail - travel north through Tanzania crossover into the Burundi border and again into Rwanda en-route to Bukavu - N2 through to Site - by road.
  3. Road from Johannesburg (RSA) on the Great North road through Zambia to Mpulungu (southern most point of Lake Tanganyika) - barge to Bujumbura (Burundi - northern point of Lake Tanganyika) and truck over the Rwandan border - Bukavu (DRC) N2 through to Site - by road.
The upgraded section of the N2 road from Bukavu to Kasongo has passed the Twangiza turnoff and the Ulindi 2 hydro site turnoff, and is being extended toward Kamituga, Lugushwa and Namoya, three of Banro's other projects.

The study findings propose option 1 as the preferred choice of access to the Twangiza project, with options 2 & 3 as alternatives and back-up. Option 1 remains the most viable based on the optimization of a number of considerations, including port facility capacities, long-term political stability of transit countries as well as the suitability of existing roads and infrastructure.

Refining

There is no gold refining capability in East Africa and thus dor� produced at Twangiza is to be refined off-shore, either in South Africa, Europe or Dubai. Initial discussions have been held with refineries and although no agreements have been entered into, it is anticipated that the dor� will be treated at the Rand Refinery in South Africa. It is estimated that collection and transport from the mine, insurance and refining of the dor� will be charged at $US5.00 per ounce.

Environmental and Social Aspects

SRK (SA) is implementing baseline environmental surveys at Twangiza. The present phase of the environmental assessment work comprises detailed characterization of the environmental baseline, quantification of impacts and development of management plans. Field surveys or seasonal measurement of relevant parameters in the fields of hydrology, soils, air quality, noise, aquatic ecology and terrestrial flora and fauna were undertaken by appropriate specialists. The air quality and noise impacts of the project have also been modeled.

Socio-economic studies included developing a social baseline and impact assessment, and health and safety study, as a basis for developing management plans. Through a process of census survey and public consultation, the refinement of social impact management plans has been completed, and the following products having been developed:

  • Social Baseline and Impact Assessment (SIA);
  • Resettlement Action Plan (RAP);
  • Stakeholder Engagement Plan (SEP);
  • Community Development Plan (CDP).
All the data and material collated in the course of all these studies, in combination with the outstanding requirements regarding water supply and project water balance, ground water modeling, geotechnical and geochemical test work, will be compiled into an Equator Principles compliant environmental, socio-economic, health and safety impact assessment (ESHIA). The impact assessment will inform an environmental and social management plan (ESMP) which will set standards for the project compliant with both DRC mining legislation and the World Bank's Pollution Abatement and Control Handbook.

Capital Costs

The tables below summarize the estimated capital costs for the Twangiza Project and the Hydroelectric project as estimated by the independent consultants, and includes preliminary quotations from equipment providers, further substantiated by their experience on current projects in Africa.

The Feasibility Study costs currently utilize an owner-operated mining fleet, although contractor mining was investigated. This investigation into the contractor mining option reflected considerably lower financial returns than the owner-operated mining fleet. At this stage the contractor mining option, although having a lower initial capital cost, results in considerably higher operating costs, a function of the current inflated contractor rates quoted for work in Eastern DRC.

All financial analysis for the Life of Mine includes the total design, construction and commissioning, production and closure. Additionally, the assumption is made that a dedicated hydroelectric facility would be developed within a Banro subsidiary and the total costs have been highlighted separately from the Twangiza project below.

Table IIIa - Total Project Capital Costs (excluding hydroelectric power plant)
TWANGIZA PROJECT CAPEX SUMMARY

Feasibility Study

Pre-Feasibility Study

Mining

US$ 000

US$ 000

Plant & Equipment

62,924

57,789

Haul Roads

1,397

3,500

Pre-strip Costs

7,803

6,646

Other

3,994

2,944

Total Mining

76,118

70,879

Process Plant

 

 

Earthworks & Civils

31,866

49,348

Mechanical Equipment, Structural & Piping

56,556

87,699

Electrical & Instrumentation

7,560

14,790

Tailings Dam

31,030

16,848

Other

48,412

22,699

Total Process Plant

175,424

191,383

Mine Infrastructure

 

 

Standby Diesel Generators, Fuel Farm & First Fill

5,315

10,817

Buildings & Accommodation Facilities

12,684

8,382

Access Roads

25,827

17,298

Light Vehicles & Mobile Equipment

2,730

2,784

Other

7,383

9,000

Total Infrastructure

53,940

48,281

Management Costs

 

 

EPCM (Engineering, Procurement, Construction Management)

32,332

34,661

Working Capital (Stock holding, Production Build-Up Costs)
Relocation Costs (Resettlement)
Owners Preproduction Costs (Banro Project / Construct Team)

6,546
13,115
5,717

6,783
11,316
8,034

Administration Tax & Insurances

7,580

10,650

Total Management Costs

65,290

71,445

Contingency

38,881

50,503

TOTAL MINE INITIAL PROJECT CAPITAL COSTS

409,654

432,490


Table IIIb - Hydroelectric Power Plant Capital Costs

CAPEX SUMMARY HYDROELECTRIC POWER

Feasibility Study

US$ '000

Pre-Feasibility Study
US$ '000

Power Plant

100,585

81,738

EPCM

8,047

6,539

Contingency

20,117

16,348

HEP Admin Tax

5,029

4,087

Total Hydroelectric Power Costs

133,778

108,711

Banro's 50% contribution

66,889

N/A


Table IIIc - Total Project Capital Costs (Including 50% of Hydroelectric Power Plant)

CAPEX GRAND TOTAL PROJECT COSTS

Feasibility Study

US$ '000

Pre-Feasibility Study
US$ '000

Total Mine Initial Project Capital Costs

409,654

432,490

Total Hydro Power Costs

66,889

108,711

TOTAL PROJECT INITIAL COSTS

476,543

541,202

Ongoing/ Sustaining Capital (Tailings Dam Raises, Mine Equipment & Mine Closure Costs)*

0

39,380

GRAND TOTAL PROJECT COST

476,543

580,582

*The Ongoing/Sustaining Cost of US$67.583 million for this Feasibility Study has not been capitalized, as it was in the Pre-Feasibility Study. The financial analysis in the Feasibility Study includes this as an operating cost, which is reflected in the total operating cash costs.

Operating Cash Costs

The following operating cash costs were estimated and incorporated into the financial analysis:

Table IV - Total Operating Cash Costs for Initial 7 years

 

Feasibility Study

Pre-Feasibility Study

OPEX : First 7 Years

US$/t

US$/oz

US$/t

US$/0z

Mining

6.48

136.08

5.39

109.67

Processing

11.56

243.12

8.72

191.31

G & A

1.07

22.14

2.09

44.89

Refining

0.26

5.00

0.26

5.00

Total

19.37

406.34

16.46

350.87


Table V - Life of Mine Total Operating Costs

 

Feasibility Study

Pre-Feasibility Study

OPEX : LoM : HEP

US$/t

US$/oz

US$/t

US$/0z

Mining

5.31

121.90

4.32

91.76

Processing

11.92

273.65

9.48

201.29

G & A

1.26

28.93

2.19

46.60

Refining

0.22

5.00

0.24

5.00

Total

18.71

429.47

16.23

344.65


In preparing this Feasibility Study there have been a number of assumptions and material factors that have been employed. Some of these are shown in Tables VI and VII below.

Table VI - Financial Assumptions

 

Unit

Banro Assumptions January 2009
Feasibility Study

Banro Assumptions July 2008
Pre-Feasibility Study

Revenue

 

 

 

Gold Price

(US$/oz)

850

850

Discount Rate

(%)

5

5

Fuel Prices

 

 

 

Diesel

US$/liter

1.2

1.6

Power Costs

 

 

 

HEP Costs (Before Payback)

US$/kWh

0.084

0.025

HEP Costs (After Payback)

US$/kWh

0.028

0.025

Fiscal

 

 

 

Tax Free Holiday

Years

10

10

Tax Rate Year 0 -10

(%)

0

0

Tax Rate > 10 years

(%)

30

30

Royalty (Government)

(%)

0

0

Administration Tax

(%)

5

5

Depreciation

(%)

0

0

Depreciation Period

Years

10

10

Conversions Factors

 

 

 

Kilograms to Ounces

(kg/troy oz)

32.1505

32.1505

Diesel Fuel Density

(t/ m3)

0.85

0.85

Hydro Density

(t/ m3)

0.97

0.97

Exchange Rate

Rand: US$

9

8

 

 

 

 

Refining Charges, Dore Transport and Insurance

US$/oz

5

5

 

 

 

 

Percent Capital Expenditure (Year 1)

%

30

30

Process Plant Residual Value

%

5

5

Power Plant Residual Value

%

30

30

Mining Equipment Residual Value

%

5

5

Vehicles

%

10

10


Table VII below shows the percentage variances of the key components causing the differences between the Pre-Feasibility Study and this Feasibility Study.

Table VII - Material Factors
  Approximate % Price Increase / Decrease since Pre-Feasibility Study of July 2008 Current Feasibility Study of January 2009
1. Diesel Costs - Price Per Litre -25%
2. Transport (Logistics) - Total Capital Costs -7.2%
  - 20 Foot Container Price for Freight +1.4%
  - 40 Foot Container Price for Freight -2.2%
3. Civils and Infrastructure  
  - Earthworks (Decreased Process Plant footprint)  
   

: Total Costs

-43.9%
  - Civils (Decreased Process Plant footprint)  
   

: Total Costs

-21.1%
  - Access Roads (including Earthworks, Layers, Drainage & Bridges etc.) +49.3%
4. Steel Costs (Total) -63.3%
  - Structural Steelwork Costs Per Tonne -40.6%
5. Reagents  
  - Lime Costs - Costs Per Delivered Tonne +23.8%
  - Cyanide - Costs Per Delivered Tonne +31.2%
6. Power ( 30mW Unchanged Output From PFS) +23.1%
7. Tailings Dam (Initial and Ongoing Capital) +90.7%
8. Resettlement Costs +15.9%

Project Economics and Financial Analysis

As part of this Feasibility Study, the following three separate options were investigated to determine the most viable financial return:
  • Treating all of the ore as and when it gets mined;
  • Delaying and stockpiling the refractory portion of the ore for treatment in later years;
  • Treating only the oxides and fresh porphyry ore.
This Feasibility Study concludes that the most attractive option is to treat all of the ore as and when it gets mined, and the financial analysis reflects these findings accordingly.

SENET has produced a cash flow valuation model for the Twangiza Project based on the geological and engineering work completed to date and incorporating the hydroelectric power source. The base case was developed using a long-term gold price of US$850 per ounce. The financial model also reflects the favourable fiscal aspects of the Mining Convention governing the Twangiza Project, which includes 100% equity interest and a 10 year tax holiday from the start of production. An administrative tax of 5% for the importation of plant, machinery and consumables has been included in the projected capital and operating costs. The Hydroelectric Project costs have been run through the financial model at 50% of the overall capital costs, assuming a 50% third party investment, being repaid at a kWh rate over the first 10 years of the project life. Further savings could be achieved through the potential of recouping some of the capital investment through carbon credits, the benefits of which have not been included in these financials.

Calculated sensitivities show the upside leverage to gold prices and the robust nature of the projected economics to operating assumptions.

Sensitivities
Table VIII - Gold Price (Base Case: US$850/oz)

Gold Price
US$/oz

IRR

NPV US$ million
at different discount rates

%

0%

5%

10%

750

12.7%

328

154

44

850

20.5%

593

342

185

950

27.4%

858

530

325


Table IX - Capex (Base Case: US$476.543 Million)

CAPEX Change
%

IRR

NPV US$ million
at different discount rates

%

0%

5%

10%

-10%

24.4%

641

388

229

+10%

17.3%

545

296

140


Table X - Operating Cash Costs (Base Case: US$429/oz)

OPEX Change
%

IRR

NPV US$ million
at different discount rates

%

0%

5%

10%

-10%

23.0%

707

419

239

+10%

17.8%

479

265

130


Table XI - Fuel Price (Base Case: US$ 1.20 /litre)

Fuel Price Change
%

IRR

NPV US$ million
at different discount rates

%

0%

5%

10%

-10%

20.8%

605

350

191

+10%

20.2%

581

334

178


Project Opportunities

Project estimates are based on costs received during the period of October to December 2008, before the full impact of the global economic crisis could have been translated into lower commodity input prices for mining projects. In light of this, it is believed that, going forward, further economic savings could be achieved as a result of supply and demand shifts within the mining project environment (due to cancelation and/or delay of numerous projects worldwide).

"This Feasibility Study can be reviewed and further optimized going forward as input parameters change. Banro believes that contractor rates, civil and earthwork rates, steel prices, diesel prices and transport costs will become more favourable compared to the inputs to this Study," observed Mr. Prinsloo.

Gold prices have continued to improve and consensus estimates have risen in recent months, with potential upside to the base case view of $850/oz, taken in this Feasibility Study.

In order to achieve further reductions, the supply of diesel, lime and cement will be explored, with the objective of sourcing suppliers from within the DRC and/or in neighboring countries.

Project Risks

Apart from the risks captured within the cautionary and forward looking statements in this press release, an additional risk as described under the "Site Selection and Related Infrastructure" heading above, associated with the outcomes of the outstanding geotechnical investigation and geohydrological investigation could, either favorably or adversely, impact on the following areas of the project:

  • Civil design criteria for the process plant and related infrastructure;
  • Civil design criteria for the tailings disposal facility site selection and containment design;
  • Civil design criteria for the tunnel of the hydroelectric power facility;
  • Environmental impact.
Development Timetable

Construction of the process plant and associated infrastructure for the Twangiza Project is expected to take between 24 to 30 months. Development of the Hydro Electric or Ulindi II Project, which will be done in parallel to the mine development, has an expected timeline of approximately 28 months.

Banro intends to refresh and optimize this Feasibility Study and to initiate discussions with potential strategic partners and project finance lenders, including both multilateral agencies and commercial banks, on the above development timetable.

Details of this Feasibility Study in the form of a National Instrument 43-101 technical report will be filed on SEDAR in due course.

Additional information with respect to the Twangiza Project is contained in the technical report of SENET dated August 13, 2008 and entitled "Pre-Feasibility Study NI 43-101 Technical Report, Twangiza Gold Project, South Kivu Province, Democratic Republic of Congo". A copy of this report can be obtained from SEDAR at www.sedar.com.

Qualified Person

This Feasibility Study was prepared under the supervision of Neil Senior, Joint Managing Director of SENET and a "Qualified Person," as such term is defined in National Instrument 43-101. Mr. Senior has reviewed and approved the contents of this press release. Mr. Senior was also the qualified person throughout the preparation of the pre-feasibility study.

A list of other "Qualified Persons" working on the feasibility study includes:
  • Martin Pittuck, SRK (UK) (Mineral Resources)
  • Wally Waldeck, SRK (SA) (Mining and Mineral Reserves)
  • Mark Sturgeon, SRK (SA) (Mining and Mineral Reserves)
  • Jeremy Haile, Knight Piesold (Hydroelectric Power)
  • Ciaran Molloy, AMEC (Tailings and Water Dams)
Cautionary Statement
The findings contained in this Feasibility Study reflect an ongoing analysis and therefore there is no certainty that all the conclusions reached in this study will be realized.

Cautionary Note to U.S. Investors
The United States Securities and Exchange Commission (the "SEC") permits U.S. mining companies, in their filings with the SEC, to disclose only those mineral deposits that a company can economically and legally extract or produce. Certain terms are used by the Company, such as "measured", "indicated", and "inferred" "resources", that the SEC guidelines strictly prohibit U.S. registered companies from including in their filings with the SEC. U.S. Investors are urged to consider closely the disclosure in the Company's Form 40-F Registration Statement, File No. 001-32399, which may be secured from the Company, or from the SEC's website at http://www.sec.gov/edgar.shtml.

Cautionary Note Concerning Forward-Looking Statements
This press release contains forward-looking statements. All statements, other than statements of historical fact, that address activities, events or developments that the Company believes, expects or anticipates will or may occur in the future (including, without limitation, statements regarding estimates and/or assumptions in respect of production, revenue, cash flow and costs, estimated Twangiza project economics, mineral resource and mineral reserve estimates, potential mineralization, potential mineral resources and mineral reserves, projected timing of possible production and the Company's exploration and development plans and objectives with respect to its Twangiza project) are forward-looking statements. These forward-looking statements reflect the current expectations or beliefs of the Company based on information currently available to the Company. Forward-looking statements are subject to a number of risks and uncertainties that may cause the actual results of the Company to differ materially from those discussed in the forward-looking statements, and even if such actual results are realized or substantially realized, there can be no assurance that they will have the expected consequences to, or effects on the Company. Factors that could cause actual results or events to differ materially from current expectations include, among other things: uncertainties relating to the availability and costs of financing needed in the future; uncertainty of estimates of capital and operating costs, production estimates and estimated economic return; the possibility that actual circumstances will differ from the estimates and assumptions used in the Twangiza study and mine plan; failure to establish estimated mineral resources or mineral reserves; fluctuations in gold prices and currency exchange rates; inflation; gold recoveries for Twangiza being less than those indicated by the metallurgical test work carried out to date (there can be no assurance that gold recoveries in small scale laboratory tests will be duplicated in large tests under on-site conditions or during production); changes in equity markets; political developments in the DRC; lack of infrastructure; failure to procure or maintain, or delays in procuring or maintaining, permits and approvals; lack of availability at a reasonable cost or at all, of plants, equipment or labour; inability to attract and retain key management and personnel; changes to regulations affecting the Company's activities; the uncertainties involved in interpreting drilling results and other geological data; and the other risks disclosed under the heading "Risk Factors" and elsewhere in the Company's annual information form dated March 28, 2008 filed on SEDAR at www.sedar.com. Any forward-looking statement speaks only as of the date on which it is made and, except as may be required by applicable securities laws, the Company disclaims any intent or obligation to update any forward-looking statement, whether as a result of new information, future events or results or otherwise. Although the Company believes that the assumptions inherent in the forward-looking statements are reasonable, forward-looking statements are not guarantees of future performance and accordingly undue reliance should not be put on such statements due to the inherent uncertainty therein.

Cautionary Note Concerning Resource and Reserve Estimates
The mineral resource and mineral reserve figures referred to in this press release are estimates and no assurances can be given that the indicated levels of gold will be produced. Such estimates are expressions of judgment based on knowledge, mining experience, analysis of drilling results and industry practices. Valid estimates made at a given time may significantly change when new information becomes available. While the Company believes that the resource and reserve estimates included in this press release are well established, by their nature resource and reserve estimates are imprecise and depend, to a certain extent, upon statistical inferences which may ultimately prove unreliable. If such estimates are inaccurate or are reduced in the future, this could have a material adverse impact on the Company.

Mineral resources are not mineral reserves and do not have demonstrated economic viability. There is no certainty that mineral resources can be upgraded to mineral reserves through continued exploration.

Due to the uncertainty that may be attached to inferred mineral resources, it cannot be assumed that all or any part of an inferred mineral resource will be upgraded to an indicated or measured mineral resource as a result of continued exploration. Confidence in the estimate is insufficient to allow meaningful application of the technical and economic parameters to enable an evaluation of economic viability worthy of public disclosure (except in certain limited circumstances). Inferred mineral resources are excluded from estimates forming the basis of a feasibility study.


Banro is a Canadian-based gold exploration and development company focused on the development of four major, wholly-owned gold projects, each with mining licenses, along the 210 kilometre-long Twangiza-Namoya gold belt in the South Kivu and Maniema provinces of the DRC. Led by a proven management team with extensive gold and African experience, Banro's strategy is to unlock shareholder value by increasing and developing its significant gold assets in a socially and environmentally responsible manner.

For further information, please visit our website at www.banro.com, or contact: Mike Prinsloo, President and C.E.O., South Africa, Tel: + 27 (0) 11 958-2885; Arnold T. Kondrat, Executive Vice-President, Toronto, Ontario, or Martin Jones, Vice-President, Corporate Development, Toronto, Ontario, Tel: (416) 366-2221 or 1-800-714-7938.

You can also view this News Release on our website at:
http://www.banro.com/s/NewsReleases.asp?ReportID=335716
 

Home Corporate Info Properties Investors Contact Us
 
<
Data and Statistics for these countries : Burundi | Canada | Kenya | South Africa | Tanzania | Uganda | United Kingdom | Zambia | All
Gold and Silver Prices for these countries : Burundi | Canada | Kenya | South Africa | Tanzania | Uganda | United Kingdom | Zambia | All

Banro Corporation

PRODUCER
CODE : BAA
Follow and Invest
Add to watch list Add to your portfolio Add or edit a note
Add Alert Add to Watchlists Add to Portfolio Add Note
ProfileMarket
Indicators
VALUE :
Projects & res.
Press
releases
Annual
report
RISK :
Asset profile
Contact Cpy

Banro is a gold producing company based in Canada.

Banro holds various exploration projects in Congo Dem. Rep. of.

Its main assets in production are LUGUSHWA and KAMITUGA in Congo Dem. Rep. of and its main assets in development are TWANGIZA and NAMOYA in Congo Dem. Rep. of.

Banro is listed in Canada and in United States of America. Its market capitalisation is US$ 120.8 millions as of today (€ 102.0 millions).

Its stock quote reached its highest recent level on August 31, 2007 at US$ 9.96, and its lowest recent point on May 26, 2017 at US$ 0.07.

Banro has 1 098 579 968 shares outstanding.

Your feedback is appreciated, please leave a comment or rate this article.
Rate : Average note :0 (0 vote) View Top rated
 
Annual reports of Banro Corporation
2008 Annual report
Annual Report 2007
Financings of Banro Corporation
7/18/2016Enters Into Gold Dore Purchase and Financing Arrangement wit...
2/26/2016Closes Balance of US$98.75 Million Financing
2/16/2016Closes US$67.5 Million Stream Financing
12/31/2015Announces US$98.75 Million Financing With Resource FinanceWo...
8/18/2014Announces Financing Plan and Certain Senior Management Chang...
2/28/2014Closes US$40 Million Financing
4/25/2013Closes US$100 Million Financing
4/12/2013Announces Pricing of Previously Announced Financing Plan
3/27/2013Announces Financing Plan for US$100 Million
2/21/2013Announces Financing Package for up to US$90 Million
3/29/2011Receives Receipt for Final Short Form Prospectus
2/24/2011Announces Closing of C$56,875,000 Financing
2/4/2011Announces C$56,875,000 Private Placement
Nominations of Banro Corporation
6/30/2016Announces Election of Directors
6/28/2013Announces Election of Directors
3/28/2013Appoints Peter V. Gundy to Board of Directors
11/30/2009Appoints Michael Beckett to Board of Directors
9/10/2007Announces Senior Appointments For Its Operations In D.R.Cong...
8/21/2007Appoints Mike Prinsloo Chief Executive Officer
Financials of Banro Corporation
11/8/2016Announces Q3 2016 Financial and Operating Results
5/11/2016Announces Q1 2016 Financial Results
3/28/2016Announces Year End 2015 Financial Results
11/12/2013Announces Q3 2013 Financial Results
11/11/2013Provides Notice of Q3 2013 Financial Results Release & Inves...
8/13/2013Announces Q2 2013 Financial Results
8/8/2013Provides Notice of Q2 2013 Financial Results Release & Inves...
5/8/2013Announces Q1 2013 Financial Results
5/3/2013Provides Notice of Q1 2013 Financial Results Release & Inves...
3/27/2013Announces Year End 2012 Financial Results
Project news of Banro Corporation
1/9/2014(Twangiza)Provides Q4 2013 Production Update for =?ISO-8859-1?Q?=20its...
12/31/2013(Namoya)Pours First Gold at Namoya Mine, Democratic Republic of the ...
10/10/2013(Twangiza)Provides Q3 2013 Production Update for =?ISO-8859-1?Q?=20its...
7/15/2013Intersects High Grade Gold Mineralization Including 39=2E60 ...
7/10/2013(Twangiza)Provides Q2 2013 Production Update for =?ISO-8859-1?Q?=20Its...
3/18/2013Files 43-101 Technical Report on Lugus =?ISO-8859-1?Q?hwa=20...
10/11/2011(Twangiza)Corp's Twangiza Mine Pours First Gold in the Democratic Repu...
3/14/2011(Twangiza)Phase 1 Mining Of The Oxide Cap At Twangiza Indicates Annual...
1/24/2011(Namoya)Preliminary Assessment of its Namoya Heap Leach Gold Project...
7/20/2009(Twangiza)Files NI 43-101 Technical Report on Twangiza Updated Feasibi...
6/8/2009(Twangiza)Update of Twangiza Feasibility Study Increases Proven and Pr...
3/2/2009(Twangiza)Files NI 43-101 Technical Report On Twangiza Feasibility Stu...
1/26/2009(Twangiza)Feasibility Study Of Twangiza Gold Project Indicates Gold Pr...
11/17/2008(Lugushwa)Intercepts Broad Zones of Gold Mineralization at its Lugushw...
8/19/2008(Namoya)intersects 29.00 metres grading 5.59 g/t Au, 7.70 metres gra...
8/18/2008(Twangiza)Files NI 43-101 Technical Report on Twangiza Pre-feasibility...
7/16/2008Moves Ahead With Bankable Feasibility Study Of Twangiza And ...
7/7/2008(Twangiza)Pre-Feasibility Study of its Twangiza Gold Project Indicates...
6/6/2008(Twangiza)Outlines Major New Mineralized Gold Structure At Mufwa Withi...
5/29/2008(Twangiza)Intersects 16.60 metres grading 8.03 g/t Au and 47 metres gr...
4/29/2008(Namoya)Intersects 18.62 metres Grading 20.15 g/t Au and 7.25 metres...
8/23/2007(Lugushwa)Intersects Wide Zones of Gold Mineralization at its Lugushwa...
6/8/2007(Namoya)Increases Indicated Mineral Resource At Namoya By 36% To 938...
5/8/2007(Twangiza)Continues to Interesect Wide Zones of Gold Mineralisation at...
2/20/2007(Namoya) Announces Further Drilling Results from its Namoya Project
Corporate news of Banro Corporation
7/26/2016Provides Corporate Update
7/26/2016Banro Provides Corporate Update
7/11/2016Banro Achieves Record Gold Production Results in Q2 as Namoy...
6/30/2016Banro Announces Election of Directors
6/18/2016Banro and Banro Group (Barbados) Limited Declare Dividends P...
6/16/2016Banro Provides Information for Holders of Series A Preferenc...
6/13/2016Banro Foundation Wins "Community Development and Local Conte...
5/20/2016Banro Declares Dividends Payable on Series A Preference Shar...
5/11/2016Banro Announces Q1 2016 Financial Results
5/11/2016Banro reports 1Q loss
4/19/2016Banro Announces Reserve Growth of 9% to 3.18 Million Ounces ...
4/11/2016Banro Announces Q1 Production Results
3/30/2016Banro and Banro Group (Barbados) Limited Declare Dividends P...
3/28/2016Banro reports 4Q loss
3/28/2016Banro Announces Year End 2015 Financial Results
3/24/2016Banro Provides a Corporate Update
12/31/2015Banro Announces US$98.75 Million Financing With Resource Fin...
12/17/2015Sustainable Agriculture and Infrastructure Construction High...
10/19/2015Banro Wins "Best Performer in Social Investment" Award at th...
10/13/2015Banro Announces Q3 Production Results
9/30/2015Banro Provides a Corporate Update
9/30/20159:25 pm Banro receives notice from NYSE MKT regarding its lo...
9/18/2015Banro Reports High Grade Drill Results at Namoya and Provide...
8/12/2015Banro Announces Q2 2015 Financial Results; Achieves Record Q...
8/12/2015Banro reports 2Q loss
7/30/2015Banro Files NI 43-101 Technical Report for Twangiza Relating...
7/9/2015Banro Announces Q2 Production Results
6/20/2015Banro and Banro Group (Barbados) Limited Declare Dividends P...
4/16/2015Pan American Silver Enters Into New $300M Credit Facility - ...
4/15/2015Gold Fields (GFI) Issues Cost and Production Outlook for Q1 ...
4/13/2015Gold Field Inks Wage Agreement with South Deep for 3 Years -...
4/9/2015Newmont (NEM) to Construct Phase 1 of Long Canyon Mine - Ana...
4/7/2015Banro Announces Record Q1 Production Results
4/7/2015Banro Announces Year End 2014 Financial Results
4/6/2015Banro Announces Record Q1 Production Results
4/1/2015Banro Provides Notice of Year End 2014 Financial Results Rel...
3/13/2015Banro and Banro Group (Barbados) Limited Declare Dividends P...
3/13/2015Banro and Banro Group (Barbados) Limited Declare Dividends P...
3/12/2015Banro Provides Update on Note Indenture Consent Solicitation
3/12/2015Banro Provides Update on Note Indenture Consent Solicitation
3/6/2015Banro Announces US$100 Million Financing and Provides Brief ...
3/6/2015Banro Provides Information for Holders of Series A Preferenc...
3/6/2015Banro Provides Information for Holders of Series A Preferenc...
2/27/2015Banro Announces US$100 Million Financing and Provides Brief ...
1/5/2015Banro Provides Q4 2014 Gold Production and Brief Operations ...
1/5/2015Banro Provides Q4 2014 Gold Production and Brief Operations ...
12/8/2014Barrick Closes Copper Joint Venture Deal with Ma'aden
12/3/2014Vale Unveils Capital Expenditure Budget for 2015
12/2/2014Paramount Gold and Silver (PZG) Surges: Stock Up 22.7%
12/2/2014AuRico Gold (AUQ) Jumps: Stock Adds 11.3% in Session
12/2/2014Alamos Gold (AGI) Shows Strength: Stock Moves Up 7.7%
12/1/2014Agnico Eagle Closes Acquisition of Cayden Resources
11/25/2014Should You Get Rid of Gold Resource (GORO) Now?
11/20/2014Weakness Seen in Allied Nevada Gold (ANV): Stock Plunges 27%
11/20/2014Primero Mining (PPP) Falls: Stock Goes Down 7.2%
12/12/2013Announces Corporate and Board Appointments and Provides a Br...
9/13/2013Provides Information for Holders of Series A Preference Shar...
4/24/2013Job Creation and Community Development Highlight Banro's 201...
4/10/2013(Twangiza)Provides Q1 2013 Production Update for Its Twangiza Gold Min...
3/19/2013Provides an Operations Personnel Update
1/31/2013Increases Oxide and Free-milling Ounces of Gold by 45%
1/14/2013(Twangiza)Provides Q4 2012 Production Update for its Twangiza Gold Min...
9/25/2012Foundation's "Celebrate the Congo" =?ISO-8859-1?Q?=20Event=2...
8/29/2012(Twangiza)Declares Commercial Production at Twangiza Gold Mine and Pro...
9/15/2011to be Added to the S&P/TSX Composite Index
8/15/2011(Twangiza)Corp's Twangiza Phase I Gold Mine Plant Entering Cold Commis...
7/12/2011CEO Simon Village presents corporate overview at Objective C...
6/27/2011(Namoya)Intercepts Further Significant Gold Mineralization While Fea...
6/13/2011Foundation and Co-Sponsors Raise $80,000 in Charitable Fundi...
5/5/2011to Host Investor Meetings on West Coast and South East Unite...
4/21/2011Signs Memorandum of Understanding with China Gold Internatio...
4/19/2011Provides Update
7/26/2010The Arrival Of Its Refurbished Gold Plant At Twangiza And P...
5/11/2010Announces Financing
10/14/2009Foundation and the Saramabila Community Celebrate Handover o...
8/11/2009Welcomes The DRC Government's Final Ratification Of The Fisc...
6/26/2009Closes CDN$100,001,700 Financing
6/17/2009Announces Terms of CDN $100,001,700 Financing
6/1/2009Provides Update on Share Trading Activity
2/25/2009Mining Convention And Titles Confirmed By DRC Government
9/23/2008Announces Exercise of Over-Allotment Option
9/17/2008Announces Closing Of Financing
9/11/2008Announces Pricing For Financing
9/2/2008Files Preliminary Short-Form Prospectus For Proposed Financi...
8/1/2008intercepts 192 metres grading 2.02 g/t Au,...at its Twangiza...
7/28/2008Provides Update On Share Trading Activity
3/4/2008Issues Corporate Update
2/19/2008Comments on Correspondence Received from the DRC Minister of...
2/6/2008 and CARE International to partner for sustainable community...
12/24/2007Peter Cowley to Retire as President
9/20/2007Continues to Interesect Significant Near Surface Gold Minera...
7/3/2007Preliminary Economic Assessment of Namoya Gold Project Indic...
3/21/2007Responds To Statements Regarding Status Of Properties Applie...
Comments closed
 
Latest comment posted for this article
Be the first to comment
Add your comment
AMEX (BAA)TORONTO (BAA.TO)
0.110+0.00%0.150-63.86%
AMEX
US$ 0.110
12/21 15:59 -
0%
Prev close Open
0.110 0.110
Low High
0.100 0.110
Year l/h YTD var.
 -  -
52 week l/h 52 week var.
- -  0.110 -%
Volume 1 month var.
1,400,074 -%
24hGold TrendPower© : -28
Produces Gold
Develops Gold
Explores for
 
 
 
Analyse
Interactive chart Add to compare
Interactive
chart
Print Compare Export
Last updated on : 11/18/2010
You must be logged in to use the porfolio and watchlists (free)
Top Newsreleases
MOST READ
Annual variation
DateVariationHighLow
 
5 years chart
 
3 months chart
 
3 months volume chart
 
 
Mining Company News
Plymouth Minerals LTDPLH.AX
Plymouth Minerals Intersects Further High Grade Potash in Drilling at Banio Potash Project - Plannin
AU$ 0.12-8.00%Trend Power :
Santos(Ngas-Oil)STO.AX
announces expected non-cash impairment
AU$ 7.82+1.69%Trend Power :
Oceana Gold(Au)OGC.AX
RELEASES NEW TECHNICAL REPORT FOR THE HAILE GOLD MINE
AU$ 2.20+0.00%Trend Power :
Western Areas NL(Au-Ni-Pl)WSA.AX
Advance Notice - Full Year Results Conference Call
AU$ 3.86+0.00%Trend Power :
Canadian Zinc(Ag-Au-Cu)CZN.TO
Reports Financial Results for Q2 and Provides Project Updates
CA$ 0.12+4.55%Trend Power :
Stornoway Diamond(Gems-Au-Ur)SWY.TO
Second Quarter Results
CA$ 0.02+100.00%Trend Power :
McEwen Mining(Cu-Le-Zn)MUX
TO ACQUIRE BLACK FOX FROM PRIMERO=C2=A0
US$ 11.22+1.63%Trend Power :
Rentech(Coal-Ngas)RTK
Rentech Announces Results for Second Quarter 2017
US$ 0.20-12.28%Trend Power :
KEFIKEFI.L
Reduced Funding Requirement
GBX 0.55+2.59%Trend Power :
Lupaka Gold Corp.LPK.V
Lupaka Gold Receives First Tranche Under Amended Invicta Financing Agreement
CA$ 0.06+0.00%Trend Power :
Imperial(Ag-Au-Cu)III.TO
Closes Bridge Loan Financing
CA$ 2.47-1.98%Trend Power :
Guyana Goldfields(Cu-Zn-Pa)GUY.TO
Reports Second Quarter 2017 Results and Maintains Production Guidance
CA$ 1.84+0.00%Trend Power :
Lundin Mining(Ag-Au-Cu)LUN.TO
d Share Capital and Voting Rights for Lundin Mining
CA$ 15.79-1.62%Trend Power :
Canarc Res.(Au)CCM.TO
Canarc Reports High Grade Gold in Surface Rock Samples at Fondaway Canyon, Nevada
CA$ 0.24+0.00%Trend Power :
Havilah(Cu-Le-Zn)HAV.AX
Q A April 2017 Quarterly Report
AU$ 0.19-7.32%Trend Power :
Uranium Res.(Ur)URRE
Commences Lithium Exploration Drilling at the Columbus Basin Project
US$ 6.80-2.86%Trend Power :
Platinum Group Metals(Au-Cu-Gems)PTM.TO
Platinum Group Metals Ltd. Operational and Strategic Process ...
CA$ 1.82-4.21%Trend Power :
Devon Energy(Ngas-Oil)DVN
Announces $340 Million of Non-Core Asset Sales
US$ 51.74+0.60%Trend Power :
Precision Drilling(Oil)PD-UN.TO
Announces 2017Second Quarter Financial Results
CA$ 8.66-0.35%Trend Power :
Terramin(Ag-Au-Cu)TZN.AX
2nd Quarter Report
AU$ 0.03+0.00%Trend Power :