First Majestic Silver Corp.

Published : January 19th, 2016

First Majestic Produces 16.1M Silver Eqv. Oz in 2015 (4.8M Silver Eqv. Oz in Q4); Announces 2016 Production Outlook and Cost Guidance

( 0 vote, 0/5 ) Print article
  Article Comments Comment this article Rating Follow Company  
0
Send
0
comment

First Majestic Produces 16.1M Silver Eqv. Oz in 2015 (4.8M Silver Eqv. Oz in Q4); Announces 2016 Production Outlook and Cost Guidance

January 19th, 2016

First Majestic Silver Corp. ('First Majestic' or the 'Company') is pleased to announce the Company's fourth quarter and full year 2015 production results, as well as production and cost guidance for 2016.

Total production reached a new record in 2015 of 16,086,272 equivalent ounces of silver, representing a 5% increase over 2014. The equivalent silver production for 2015 consisted of 11,142,109 ounces of silver, 25,467 ounces of gold, 40,149,170 pounds of lead and 17,524,223 pounds of zinc.

Total production in the fourth quarter also reached a new quarterly record of 4,820,408 equivalent ounces of silver consisting of 3,055,442 ounces of silver, 14,534 ounces of gold, 9,040,601 pounds of lead and 4,227,296 pounds of zinc.

As of December 31, 2015, the Company held US$51.0 million in cash.

'Our production results for the fourth quarter marked a strong finish to 2015 and were consistent with expectations,' said Keith Neumeyer, President & CEO. 'Despite some minor production decreases in our effort to produce profitable ounces in this distressed market, we still pulled off a record quarter and another record year. Our transformational strategy for reducing costs and improving operational procedures is working, and along with Santa Elena's successful integration, I feel that we have truly turned a corner in this challenging market. '

Production Details Table:

Quarterly Operational Review:

The total ore processed during the quarter at the Company's six operating silver mines: Santa Elena, La Encantada, La Parrilla, Del Toro, San Martin and La Guitarra, amounted to 883,377 tonnes, reflecting a 29% increase compared to the fourth quarter of 2014 and a 31% increase from the previous quarter. The increase in tonnes compared to the prior quarter was primarily due to the acquisition of Santa Elena on October 1, 2015.

Average silver grades in the quarter decreased by 28% to 146 g/t compared to 201 g/t in the fourth quarter of 2014 and a 13% decrease compared with the previous quarter. The decrease in grade compared to the prior quarter is primarily due to Santa Elena's reprocessing of lower grade heap leach material blended with fresh mined ore. Combined silver recoveries averaged 74% during the quarter, up from 70% compared to the same quarter in the prior year and a slight improvement over the third quarter average of 72%.

The Company's underground development in the fourth quarter consisted of 9,261 metres, reflecting a 13% increase compared to 8,231 metres completed in the previous quarter.

At quarter end, seven Diamond drill rigs were active at the Company's six operations. The Company completed 5,819 metres of Diamond drilling in the quarter compared to 8,586 metres in the prior quarter, representing a 32% decrease.

Mine by Mine Quarterly Production Table:

*Certain amounts shown in this news release may not add exactlytothetotal amount due to rounding differences .

*The following prices were used in the calculation of silver equivalent ounces: Silver: $14.76 per ounce; Gold: $1,105 per ounce; Lead: $0.76 per pound; Zinc $0.73 per pound.

At the Santa Elena Silver Mine:

  • During the quarter, Santa Elena exceeded guidance by producing 673,969 silver ounces and 11,110 ounces of gold for a total quarterly production of 1,506,405 silver equivalent ounces.
  • The mill processed a total of 254,625 tonnes during the quarter, consisting of 127,396 tonnes (1,385 tpd) of underground ore and 127,229 tonnes (1,383 tpd) from the above ground heap leach pad.
  • Silver recoveries increased to 86%, up 16% compared to the quarter prior to the Company's acquisition and a new mine record, primarily due to improvements made in fine grinding ore size, longer leach times and the addition of oxygen and lead nitrates into the circuit.
  • Gold grades and recoveries averaged 1.47 g/t and 92%, respectively.
  • Underground development completed in the fourthquarter totaled 1,738 metres.
  • One underground drill rig was active within the Santa Elena property during the quarter. Total metres drilled in the fourthquarter amounted to 198 metres.

At the La Encantada Silver Mine:

  • For the quarter, total silver production was 714,057 silver ounces representing a 7% increase over the previous quarter. The increase was primarily due to an 11% increase in silver grades offset but a 4% reduction in throughput.
  • During the quarter, the foundations and electrical wiring for the new natural gas power plant was completed. The generators arrived on site in mid-December and are currently being installed. Initial testing and commissioning is now expected to occur in late January.
  • A total of 960 metres of underground development were completed in the fourthquarter compared to 1,290 metres of development in the previous quarter.
  • One surface drill rig was active at La Encantada during the quarter. A total of 450 metres of exploration drilling was completed in the fourthquarter compared to 4,680 metres of drilling in the previous quarter.

At the La Parrilla Silver Mine:

  • During the quarter, the flotation circuit processed 107,450 tonnes (1,168 tpd) with an average silver grade of 165 g/t and an 87% recovery while the cyanidation circuit processed 42,053 tonnes (457 tpd) with an average silver grade of 133 g/t and a 61% recovery.
  • The ramp up of the flotation circuit to 1,200 tpd was achieved during the quarter and ahead of schedule.
  • The lead circuit processed an average lead grade of 2.1% with recoveries of 84% for total lead production of 4,187,628 lbs, representing a 62% increase compared to the previous quarter. The increase in lead production was primarily attributed to 5% higher recoveries, a 33% increase in grade and a 16% increase in throughput.
  • The zinc circuit processed an average zinc grade of 2.6% with recoveries of 68% for total zinc production of 4,227,296 lbs, representing a 35% increase compared to the previous quarter. The increase in zinc production was primarily due to an 11% increase in grades, a 5% increase in recoveries and a 16% increase in throughput.
  • Underground development completed in the quarter totaled 1,692 metres compared with 1,701 metres developed in the previous quarter.
  • Two underground drill rigs were active within the La Parrilla property during the quarter. A total of 2,145 metres were drilled in the fourth quarter compared to 1,367 metres in the previous quarter.

At the Del Toro Silver Mine:

  • For the quarter, Del Toro produced a total of 586,672 silver equivalent ounces representing a 22% decrease compared to the previous quarter. The decrease in production was primarily due to a 10% decrease in throughput and an 11% decrease in silver grades.
  • Lead grades and recoveries averaged 3.4% and 58%, respectively, producing a total of 4,852,973 pounds of lead, representing a 21% decrease compared to the previous quarter. The decrease was primarily related a 10% decrease in throughput, a 7% decrease in grade and a 6% decrease in recoveries.
  • Underground development completed in the quarter totaled 1,460 metres compared with 1,091 metres developed in the previous quarter.
  • One underground drill rig was active in the fourth quarter at Del Toro. Total exploration metres drilled in the quarter amounted to 55 metres compared to 1,644 metres drilled in the previousquarter.

At the San Martin Silver Mine:

  • During the quarter, San Martin achieved guidance by producing 485,227 silver ounces and 1,222 ounces of gold for a total quarterly production of 576,675 silver equivalent ounces. Compared to the previous quarter, total production decreased 25% due to an 18% decrease in silver grades and a 5% decrease in throughput.
  • In October, heavy winds and excessive rainfall occurred at San Martin due to Hurricane Patricia making landfall in southern Mexico. The Company took immediate precautions and evacuated the mine and processing plant as the eye of the storm was projected to pass directly over the operation. Fortunately, no property damage was recorded but throughput levels were 5% lower compared to the prior quarter as a result of the temporary disruption.
  • Underground development completed in the fourthquarter totaled 1,487 metres compared with 1,974 metres of development in the previous quarter.
  • Three underground drill rigs were active within the San Martin property during the quarter. Total metres drilled in the fourthquarter amounted to 2,059 metres compared to 482 metres of drilling in the previous quarter.

At the La Guitarra Silver Mine:

  • During the quarter, La Guitarra produced 245,358 silver ounces and 1,840 gold ounces for a total quarterly production of 382,953 silver equivalent ounces. Compared to the previous quarter, total production decreased 15% due to a 9% decrease in silver grades and a 4% decrease in throughput.
  • Approximately 70% of the production ore came from the Coloso area and the remaining 30% was extracted from the La Guitarra mine .
  • Recoveries of silver and gold increased in the quarter to 85% and 79%, respectively, primarily due to the installation of a gravimetric concentrator and use of new reagents.
  • A total of 1,924 metres of development were completed in the fourth quarter compared to 2,175 metres of development in the previous quarter.
  • Two underground drill rigs were active in the fourth quarter within the La Guitarra property. Total metres drilled in the quarter amounted to 912 metres compared to 414 metres drilled in the previous quarter.

2016 Production Outlook and Cost Guidance:

For 2016, the Company anticipates silver production will range between 12.0 to 13.3 million ounces (17.8 to 19.8 million silver equivalent ounces). This compares to 2015 silver production of 11.1 million ounces (16.1 million silver equivalent ounces). The increase is primarily due to the addition of a full year's worth of production from Santa Elena offset by lower production levels forecasted at Del Toro and San Martin.

A mine-by-mine breakdown of the 2016 production guidance is included in the table below. Cash cost and AISC guidance is shown per payable silver ounce. Metal price assumptions for calculating equivalents are: silver: $14.00/oz, gold: $1,000/oz, lead: $0.75 /lb, zinc: $0.75 /lb.

Mine

Silver Oz (M)

Silver Eqv Oz (M)

Cash Costs ($)

AISC ($)

Santa Elena

2.0 - 2.3

4.6 - 5.1

3.12 - 3.72

9.26 - 10.55

La Encantada

2.7 - 3.0

2.7 - 3.0

10.13 - 10.46

11.98 - 12.52

La Parrilla

2.6 - 2.9

3.9 - 4.3

6.25 - 6.68

9.58 - 10.38

Del Toro

1.9 - 2.1

3.1 - 3.5

8.39 - 8.99

11.12 - 12.03

San Martin

1.7 - 1.8

1.9 - 2.1

8.29 - 8.55

10.76 - 11.59

La Guitarra

1.1 - 1.2

1.6 - 1.7

5.01 - 5.56

10.37 - 11.52

Totals:

12.0 - 13.3

17.8 - 19.8

$7.11 - $7.60

$12.29 - $13.36*

*Consolidated AISC includes Corporate General & Administrative cost estimates of $1.24 to $1.37 per payable silver ounce.

The Company is projecting its 2016 All-In Sustaining Cost per Ounce ('AISC'), as defined by the World Gold Council, to be within a range of $12.29 to $13.36 consolidated on a per payable silver ounce basis. Excluding non-cash items, the Company anticipates its 2016 AISC to be within a range of $11.82 to $12.84 per payable silver ounce. An itemized AISC cost table is provided below:

All-In Sustaining Cost Calculation

FY 2016
($ /Ag oz)

Total Cash Costs per Payable Silver Ounce

7.11 - 7.60

General and Administrative Costs

1.24 - 1.37

Sustaining Development Costs

1.92 - 2.14

Sustaining Plant, Property and Equipment Costs

1.19 - 1.32

Sustaining Exploration Costs

0.37 - 0.42

Share-based Payments (non-cash)

0.38 - 0.42

Accretion of Reclamation Costs (non-cash)

0.09 - 0.10

All-In Sustaining Costs: (WGC definition)

$12.29 - $13.36

All-In Sustaining Costs: (WGC excluding non-cash items)

$11.82 - $12.84

  1. AISC is a non-GAAP measure and is calculated based on guidance provided by the World Gold Council ('WGC') in June 2013. AISC is used as a comprehensive measure for the Company's consolidated operating performance. WGC is a not a regulatory industry organization and does not have the authority to develop accounting standards for disclosure requirements. Other mining companies may calculate AISC differently as a result of differences in underlying accounting principles, the definition of 'sustaining costs' and the distinction between sustaining and expansionary capital costs.
  2. Total cash cost per payable silver ounce includes estimated royalties and 0.5% Mining Environmental Fee of $0.09 per ounce.

In 2016, the Company plans to invest a total of $63.8 million on capital expenditures consisting of $45.3 million for sustaining requirements and $18.5 million for expansionary projects. This total represents a significant reduction in budgeted capital expenditures compared to the prior year.

The 2016 annual budget includes a total of $16.7 million to be spent towards property, plant and equipment, $35.2 million towards underground development, $9.9 million in exploration and $2.0 million towards corporate projects. Management has the option to make adjustments to the 2016 budget should metal prices have any dramatic price changes in 2016.

First Majestic is a mining company focused on silver production in México and is aggressively pursuing the development of its existing mineral property assets and the pursuit through acquisition of additional mineral assets which contribute to the Company achieving its corporate growth objectives.

FOR FURTHER INFORMATION contact [email protected], visit our website at www.firstmajestic.com or call our toll free number 1.866.529.2807.

FIRST MAJESTIC SILVER CORP.
'signed'
Keith Neumeyer, President & CEO

Cautionary Note Regarding Forward Looking Statements

This press release contains 'forward-looking statements', within the meaning of the United States Private Securities Litigation Reform Act of 1995 and applicable Canadian securities legislation, concerning the business, operations and financial performance and condition of First Majestic Silver Corp. Forward-looking statements include, but are not limited to, statements with respect to the future price of silver and other metals, the estimation of mineral reserves and resources, the realization of mineral reserve estimates, the timing and amount of estimated future production, costs of production, capital expenditures, costs and timing of the development of new deposits, success of exploration activities, permitting time lines, hedging practices, currency exchange rate fluctuations, requirements for additional capital, government regulation of mining operations, environmental risks, unanticipated reclamation expenses, timing and possible outcome of pending litigation, title disputes or claims and limitations on insurance coverage. Generally, these forward-looking statements can be identified by the use of forward-looking terminology such as 'plans', 'expects' or 'does not expect', 'is expected', 'budget', 'scheduled', 'estimates', 'forecasts', 'intends', 'anticipates' or 'does not anticipate', or 'believes', or variations of such words and phrases or state that certain actions, events or results 'may', 'could', 'would', 'might' or 'will be taken', 'occur' or 'be achieved'. Forward-looking statements are subject to known and unknown risks, uncertainties and other factors that may cause the actual results, level of activity, performance or achievements of First Majestic Silver Corp. to be materially different from those expressed or implied by such forward-looking statements, including but not limited to: risks related to the integration of acquisitions; risks related to international operations; risks related to joint venture operations; actual results of current exploration activities; actual results of current reclamation activities; conclusions of economic evaluations; changes in project parameters as plans continue to be refined; future prices of metals; possible variations in ore reserves, grade or recovery rates; failure of plant, equipment or processes to operate as anticipated; accidents, labour disputes and other risks of the mining industry; delays in obtaining governmental approvals or financing or in the completion of development or construction activities, as well as those factors discussed in the section entitled 'Description of the Business - Risk Factors' in First Majestic Silver Corp.'s Annual Information Form for the year ended December 31, 2014, available on www.sedar.com, and Form 40-F on file with the United States Securities and Exchange Commission in Washington, D.C. Although First Majestic Silver Corp. has attempted to identify important factors that could cause actual results to differ materially from those contained in forward-looking statements, there may be other factors that cause results not to be as anticipated, estimated or intended. There can be no assurance that such statements will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements. Accordingly, readers should not place undue reliance on forward-looking statements. First Majestic Silver Corp. does not undertake to update any forward-looking statements that are incorporated by reference herein, except in accordance with applicable securities laws.
Read the rest of the article at www.noodls.com
Data and Statistics for these countries : Georgia | Mexico | All
Gold and Silver Prices for these countries : Georgia | Mexico | All

First Majestic Silver Corp.

PRODUCER
CODE : FR.TO
ISIN : CA32076R1029
CUSIP : 32076R1029
Follow and Invest
Add to watch list Add to your portfolio Add or edit a note
Add Alert Add to Watchlists Add to Portfolio Add Note
ProfileMarket
Indicators
VALUE :
Projects & res.
Press
releases
Annual
report
RISK :
Asset profile
Contact Cpy

First Majestic is a silver producing company based in Canada.

First Majestic produces silver, gold, lead and zinc in Mexico, and holds various exploration projects in Canada and in Mexico.

Its main assets in production are LA PARRILLA SILVER MINE, LA ENCANTADA (FIRST MAJESTIC SILVER), SAN MARTIN and LA ENCANTADA SILVER MINE in Mexico and its main exploration properties are REAL DE CATORCE, DEL TORO and CUITABOCA in Mexico and PITT ISLAND, PINCOURT, DOMPIERRE and DESJARDINS in Canada.

First Majestic is listed in Canada, in Germany and in United States of America. Its market capitalisation is CA$ 1.6 billions as of today (US$ 1.1 billions, € 1.1 billions).

Its stock quote reached its lowest recent point on November 02, 2001 at CA$ 0.01, and its highest recent level on December 22, 2017 at CA$ 9.99.

First Majestic has 164 340 000 shares outstanding.

Your feedback is appreciated, please leave a comment or rate this article.
Rate : Average note :0 (0 vote) View Top rated
 
In the News and Medias of First Majestic Silver Corp.
8/13/2018First Majestic shares hammered after reporting $40 million-l...
1/21/2009Follow up N° 1
Annual reports of First Majestic Silver Corp.
Files Form 40-F Annual Report
2008 Annual report
2007 Annual Report
Financings of First Majestic Silver Corp.
8/20/2009Tranche of Non-Brokered Private Placement Closes
8/12/2009Non-Brokered Private Placement and Debt Settlement
Nominations of First Majestic Silver Corp.
4/4/2014Appoints VP of Technical Services
12/24/2013Announces Retirement of Robert Young from Board of Directors
1/5/2012Appoints Chief Information Officer
12/30/2011Names Douglas Penrose as Chairman
Financials of First Majestic Silver Corp.
2/25/2016First Majestic Announces Financial Results for Q4 and Year E...
2/3/2014Fourth Quarter and Year End Financial Results to be Released...
11/12/2013Reports Third Quarter Financial Results
10/31/2013Third Quarter Financial Results to be Released on November 1...
7/15/2013Second Quarter Financial Results to be Released on August 13...
5/15/2013Reports First Quarter Earnings of $26.5 million on Revenues ...
5/7/2013Quarter Financial Results to be Released on May 15th
11/14/2012Earns $24.9M in Third Quarter; Revenues of $63.6M, an Increa...
11/7/2012Third Quarter Financial Results to Be Released on November 1...
8/7/2012Second Quarter Financial Results to be Released on August 14...
5/10/2012Reports Strong Earnings of $26.4M in Q1 2012, Up 10% Compare...
5/4/2012First Quarter Financial Results to Be Released on May 10th
3/5/2012Announces New Record Earnings & Cash Flows for 2011
2/24/2012to Announce Fourth Quarter and Year End 2011 Financial Resul...
10/26/2011Third Quarter Financial Results to be Released on November 9...
8/3/2011Second Quarter Financial Results to be Released on August 11...
5/17/2011Earns a Record $23.9 million in First Quarter of 2011
5/11/2011Quarter Financial Results to Be Released on May 16, 2011-Con...
3/1/20112010 Audited Financial Results show Record Earnings & Cash F...
3/23/2010Year End & Fourth Quarter Financial Results
11/12/2009Record Third Quarter Financial Results
8/14/2009Second Quarter Financial Results
8/15/2008Second Quarter Financial Results
5/16/2008CORRECTION- MISSING TEXT - Record First Quarter Financial Re...
4/18/20082007 Year End Financial Results
Project news of First Majestic Silver Corp.
1/14/2014becomes a Senior Silver Producer; Produces 10.64M Ounces of ...
12/4/2013(Del Toro)Dor=E9 Production Commences at the Del Toro SilverMine
4/9/2013(Del Toro)Del Toro Silver Mine Flotation Circuit Deemed Commercial
1/9/2013Achieved Record Production of 2.6M Silver Eqv. Ounces (2.3M ...
9/27/2012Mine Videos - Just Released
1/24/2012(Del Toro)-La Parrilla Mill Expansion to 2,000 tpd Completed: Del Toro...
1/12/2012Achieved Record Production of 1.96M Silver Ounces (2.1M Silv...
10/13/2011(La Parrilla Silver Mine)Announces Q3 Production Results and Commences Commercial Pro...
9/22/2011(La Parrilla Silver Mine)First Stage of Expansion at the La Parrilla Processing Plant...
9/13/2011(La Parrilla Silver Mine)Mill Capacity at La Parrilla to Reach 2,000 tpd Following Po...
3/1/2011(San Martin)2010 Audited Financial Results show Record Earnings & Cash F...
4/8/2010(La Encantada (first Majestic Silver))La Encantada Achieves Commercial Production
11/26/2009(La Encantada (first Majestic Silver))La Encantada Opening Ceremony & Production of First Silver P...
10/13/2009(La Encantada (first Majestic Silver))La Encantada Expansion Nearing Completion
10/6/2009Third Quarter Production Results
2/17/2009(La Parrilla Silver Mine)La Parrilla Silver Mine Updates NI 43-101 Resource
1/20/2009(San Martin)San Martin Updated NI 43-101 Report Increasing Reserves/Reso...
7/17/2008(San Juan Silver Mine)Major Intersection At San Juan Silver Mine Drill Hole Inters...
4/29/20081st Quarter Production Results
4/23/2008(San Martin Silver Mine)Commissioning of Flotation Circuit at the San Martin Silver ...
4/1/2008(La Parrilla Silver Mine)Discovery of New High Grade Ore Shoot on the Vacas Vein at t...
1/8/2008(La Encantada Silver Mine)La Encantada Silver Mine Update and New NI 43-101 Resource
7/2/2007(La Parrilla Silver Mine)La Parilla Technical Report
Corporate news of First Majestic Silver Corp.
7/27/2016Coverage Initiated on Silver Stocks First Majestic Silver, S...
7/25/2016Second Quarter Financial Results to be Released on August 10
7/20/2016Here’s Why These Five Stocks Are on the Move on Wednesday
7/12/2016First Majestic Produces 4.7 Million Silver Eqv. Ounces in Se...
1/29/2016Silver Could Spike $10 In A Day In Global Collapse Scenario
11/28/2015How Top Traders Are Shifting Western Asst High Incm Opprtnty...
10/14/2015First Majestic Produces 3.6 Million Silver Eqv. Ounces in Q3...
10/14/2015First Majestic Produces 3.6 Million Silver Eqv. Ounces in Q3...
10/13/2015A Silver Lining in October 2015?
10/2/2015First Majestic Completes Acquisition of Silvercrest
10/1/2015First Majestic Completes Acquisition of SilverCrest
9/25/2015First Majestic and SilverCrest Announce Shareholder Approval...
9/15/2015Leading Independent Advisory Firms ISS and Glass Lewis Recom...
8/27/2015First Majestic and SilverCrest Announce Receipt of Interim O...
8/27/2015First Majestic and SilverCrest Announce Receipt of Interim O...
8/11/2015First Majestic reports 2Q loss
8/11/2015First Majestic Reports Second Quarter Financial Results and ...
8/10/2015Why Earnings Season Could Be Great for First Majestic Silver...
7/30/2015Second Quarter Financial Results to be Released on August 11
7/30/2015First Majestic Silver: Second Quarter Financial Results to B...
7/27/2015First Majestic Announces Friendly Acquisition of Silvercrest...
7/27/2015announces friendly acquisition of Silvercrest Mines
7/9/2015First Majestic Produces 3.8 Million Silver Eqv. Ounces in Q2...
4/23/2015NYSE stocks posting largest percentage decreases
4/23/2015First Quarter Financial Results to be Released on May 7
4/23/2015First Majestic Silver Corp. First Quarter Financial Results ...
4/22/2015First Majestic Silver Corp. Announces Closing of C$30 Millio...
4/20/2015NYSE stocks posting largest percentage decreases
4/13/2015NYSE stocks posting largest percentage decreases
4/13/2015First Majestic Produces 3.9 Million Silver Eqv. Ounces in Q1...
4/9/2015NYSE stocks posting largest percentage decreases
4/6/2015First Majestic Silver Corp. Announces C$30 Million Bought De...
4/6/2015Announces C$30 Million Bought Deal Financing
4/6/2015First Majestic Announces Promotion of Martin Palacios to Chi...
4/6/2015First Majestic Announces Acquisition of Shares of First Mini...
4/1/2015NYSE stocks posting largest percentage increases
4/1/2015First Majestic Updates Mineral Reserve and Resource Estimate...
3/31/2015Announces New La Guitarra NI 43-101 Technical Report
3/31/2015First Majestic Announces New La Guitarra NI 43-101 Technical...
3/11/2015First Majestic Renews Share Repurchase Program
3/11/2015First Majestic Renews Share Repurchase Program
8/22/2014to List on the Mexican Stock Exchange
10/24/2013Appeal Against First Majestic Dismissed
9/30/2013Applies to Dismiss Appeal of Positive Judgment for US$93.84 ...
7/10/2013Produces a New Quarterly Record of 3.27 Million Silver Eqv. ...
7/2/2013Payment of CDN$14.85 million Received in Court Litigation
5/2/2013Announces Completion of La Guitarra's Expansion to 500 tpd
4/26/2013Receives Positive Judgment for US$89.6 in Court Litigation
4/17/2013Earns Socially Responsible Business Distinction Award for Fi...
4/15/2013Produces Another Quarterly Record 2.73 Million Silver Eqv. O...
3/11/2013Announces Share Repurchase Program
2/19/2013Elects Not to Exercise Right to Match Coeur's Offer for Orko
2/14/2013Considering Superior Offer from Coeur to Acquire Orko Silver
1/25/2013(Del Toro)Production Commences at the Del Toro Silver Mine
10/10/2012Produces a Record 2.44 Million Silver Equivalent Ounces in T...
9/26/2012New Look! New Features! First Majestic Bullion Store
9/6/2012Keith Neumeyer's Interview With Minesite.com
8/27/2012Announces Appointment of VP of Exploration
8/21/2012(Del Toro)Updated Del Toro NI 43-101 Technical Report & Final Permit R...
8/16/2012Recognized as a Leader in Corporate Social Responsibility
7/17/2012Produces 2.1 Million Silver Equivalent Ounces in Second Quar...
7/3/2012Completes Acquisition of Silvermex Resources
6/26/2012mex Securityholders Approve Plan of Arrangement With First M...
5/22/2012(Del Toro)Del Toro NI 43-101 Technical Report & Pre-Feasibility Study
4/16/2012First Quarter Production Results and Full Commencement of Co...
4/3/2012Announces Friendly Acquisition of Silvermex Resources
3/30/2012Files Form 40-F Annual Report
10/7/2011Third Quarter Production Results to Be Released on October 1...
8/11/2011Record Earnings of $30.6 million in Second Quarter
7/7/2011Another Record Quarter of Silver Production
4/8/2011Silver Production Up 25%; Reaches 97% Pure Silver and Mainta...
8/16/2010Record Earnings and Cash Flows. Purest Silver Producer with ...
4/22/20102nd Year Running for Mexican Distinction as a "Socially Resp...
4/12/2010Production Increases by 30% to 1,619,403 Equivalent Ounces S...
1/12/2010Production Increases by 18%, Reaches New Record
11/13/2009Completes Acquisition of Normabec Mining Resources; Normabec...
9/14/2009to Acquire Normabec Mining Resources
8/13/2009Joins OTCQX
6/26/2009offering for purchase 0.999 fine 1oz. silver rounds, and 5oz...
3/5/2009Closing of $21.2 Million Offering
11/19/2008Operations Update
9/11/2008Many Positive Developments Underway
7/15/20082nd Quarter Production Shows Continued Ramp-up
3/25/2008Closing of $45,475,000 Offering
1/17/2008Another Record Quarter of Silver Production
12/14/2007TSX Conditional Approval
12/5/2007Update on the Chalchihuites Group of Properties
Comments closed
 
Latest comment posted for this article
Be the first to comment
Add your comment
TORONTO (FR.TO)OTHER OTC (FRMSF)
9.47+1.72%
TORONTO
CA$ 9.47
04/25 17:00 0.160
1.72%
Prev close Open
9.31 9.30
Low High
9.14 9.57
Year l/h YTD var.
5.74 -  10.95 18.67%
52 week l/h 52 week var.
5.74 -  10.95 -1.66%
Volume 1 month var.
899,785 30.80%
24hGold TrendPower© : -17
Produces Lead - Silver - Zinc
Develops
Explores for Gold - Lead - Silver - Zinc
 
 
 
Analyse
Interactive chart Add to compare
Interactive
chart
Print Compare Export
Last updated on : 12/27/2010
You must be logged in to use the porfolio and watchlists (free)
Top Newsreleases
MOST READ
Annual variation
DateVariationHighLow
202424.77%
2023-32.71%9.9510.07
2022-23.32%9.9610.00
2021-13.88%30.7512.74
20209.63%9.8610.08
 
5 years chart
 
3 months chart
 
3 months volume chart
 
 
Mining Company News
Plymouth Minerals LTDPLH.AX
Plymouth Minerals Intersects Further High Grade Potash in Drilling at Banio Potash Project - Plannin
AU$ 0.12-8.00%Trend Power :
Santos(Ngas-Oil)STO.AX
announces expected non-cash impairment
AU$ 7.75+0.52%Trend Power :
Oceana Gold(Au)OGC.AX
RELEASES NEW TECHNICAL REPORT FOR THE HAILE GOLD MINE
AU$ 2.20+0.00%Trend Power :
Western Areas NL(Au-Ni-Pl)WSA.AX
Advance Notice - Full Year Results Conference Call
AU$ 3.86+0.00%Trend Power :
Canadian Zinc(Ag-Au-Cu)CZN.TO
Reports Financial Results for Q2 and Provides Project Updates
CA$ 0.12+4.55%Trend Power :
Stornoway Diamond(Gems-Au-Ur)SWY.TO
Second Quarter Results
CA$ 0.02+100.00%Trend Power :
McEwen Mining(Cu-Le-Zn)MUX
TO ACQUIRE BLACK FOX FROM PRIMERO=C2=A0
US$ 11.94+9.34%Trend Power :
Rentech(Coal-Ngas)RTK
Rentech Announces Results for Second Quarter 2017
US$ 0.20-12.28%Trend Power :
KEFIKEFI.L
Reduced Funding Requirement
GBX 0.54-2.55%Trend Power :
Lupaka Gold Corp.LPK.V
Lupaka Gold Receives First Tranche Under Amended Invicta Financing Agreement
CA$ 0.06+0.00%Trend Power :
Imperial(Ag-Au-Cu)III.TO
Closes Bridge Loan Financing
CA$ 2.69+13.03%Trend Power :
Guyana Goldfields(Cu-Zn-Pa)GUY.TO
Reports Second Quarter 2017 Results and Maintains Production Guidance
CA$ 1.84+0.00%Trend Power :
Lundin Mining(Ag-Au-Cu)LUN.TO
d Share Capital and Voting Rights for Lundin Mining
CA$ 15.60+1.83%Trend Power :
Canarc Res.(Au)CCM.TO
Canarc Reports High Grade Gold in Surface Rock Samples at Fondaway Canyon, Nevada
CA$ 0.24+0.00%Trend Power :
Havilah(Cu-Le-Zn)HAV.AX
Q A April 2017 Quarterly Report
AU$ 0.19+0.00%Trend Power :
Uranium Res.(Ur)URRE
Commences Lithium Exploration Drilling at the Columbus Basin Project
US$ 6.80-2.86%Trend Power :
Platinum Group Metals(Au-Cu-Gems)PTM.TO
Platinum Group Metals Ltd. Operational and Strategic Process ...
CA$ 1.87+5.65%Trend Power :
Devon Energy(Ngas-Oil)DVN
Announces $340 Million of Non-Core Asset Sales
US$ 52.61+0.98%Trend Power :
Precision Drilling(Oil)PD-UN.TO
Announces 2017Second Quarter Financial Results
CA$ 8.66-0.35%Trend Power :
Terramin(Ag-Au-Cu)TZN.AX
2nd Quarter Report
AU$ 0.04+0.00%Trend Power :