COPPER FOX PROVIDES UPDATE ON 2011 PLANS FOR SCHAFT CREEK, Diamond DRILLING EXPECTED TO COMMENCE MID-MAY
("Copper Fox" or the "Company") (TSXV: CUU) is pleased to provide its shareholders an update of activities as well as its 2011 plans for the Schaft Creek project.

Highlights:

a)  Copper Fox has been advised by AMEC to expect the updated resource estimate on the Schaft Creek deposit later this month,
b)  The high resolution airborne survey of the Schaft Creek project has commenced and is expected to be completed within 10 days subject to weather conditions, and
c) Diamond drilling is expected to commence later this month subject to snow conditions. The first drill hole of the 2011 season will be the completion of DDH CF2101-406 which had to be capped due to weather conditions at the end of the 2010 season.

Elmer B. Stewart President and CEO of Copper Fox stated "The objectives of the 2011 program are to expand the limits of the mineralization in the Paramount zone of the Schaft Creek deposit and to try and locate another deposit of copper-gold-molybdenum-silver mineralization. In addition to the Schaft Creek deposit, two large zones of copper-gold mineralization and a large chargeability anomaly are located within the Schaft Creek project none of which have ever been tested by Diamond drilling. The potential for any one of these zones to host a large copper-gold-molybdenum-silver deposit is considered to be high".

Resource Estimate:
Copper Fox has been advised by AMEC Americas Limited ("AMEC") to expect an updated resource estimate on the Schaft Creek deposit later this month. Mr. Stewart, President and CEO of Copper Fox stated, "While it is disappointing the resource estimate has taken longer than originally anticipated, we are pleased to report that AMEC continues to diligently work towards finalizing this report. It is important always to keep in mind, that given the nature of the work, it will continue to be difficult to predict the precise date that AMEC will complete its work, and it may well take until later in May before the Company receives delivery of the report. We very much look forward to receiving the updated resource estimate from AMEC as it marks a major milestone for Copper Fox and a very important step in the development of the Schaft Creek project".

Airborne Geophysical Survey:
The drilling completed in 2010 demonstrated that the copper-gold-molybdenum-silver mineralization in the Paramount zone of the Schaft Creek deposit has a positive magnetic signature.  A compilation of historical exploration results has identified a 15 kilometre long zone of favourable geology, alteration and copper mineralization referred to as the Schaft Creek mineral trend.  In addition to the Schaft Creek deposit, this trend hosts:

a) the recently acquired ES zone (see News Release dated April13, 2011) located approximately 3 kms north of the Paramount zone of the Schaft Creek deposit measures at least 1,100m long by 300m wide. The average of 32 chip and grab samples collected from this zone was 0.87% copper and 0.31 g/t gold,
b) the recently acquired GK zone located approximately 3 kms north of the ES zone measures at least 1,700m long by 250m wide.  Reconnaissance sampling on the GK zone in 2008 consisted of 17 grab and chip samples that averaged 1.24% copper, 16 g/t silver and 0.07g/t gold according to a property assessment report filed in 2008, and
c) a large chargeability anomaly located north of the Paramount zone. The limits of the zone of chargeability have not been defined and this target has not yet been tested by Diamond drilling.

The mineral claims on which the ES and GK zones of copper mineralization occur are contiguous to the Schaft Creek project.  These claims were acquired (see News Release dated March 24, 2011) by Copper Fox due to the geological setting, widespread copper-gold mineralization and associated alteration exposed on surface. These features are very similar to those of the higher-grade mineralization in the Paramount zone of the Schaft Creek deposit.

To better define the three zones listed above and to identify additional targets that may occur within the Schaft Creek mineral trend, a high resolution aeromagnetic survey has commenced as scheduled on the Schaft Creek project. The exposed mineralization alteration and geology on the ES and GK targets indicate potential for discovery of large zones of copper-gold-molybdenum-silver mineralization Preliminary exploration of magnetic targets in the aeromagnetic survey, will be included in the 2011 program.

Diamond Drilling Program:
As previously announced, Copper Fox plans to complete an 8,000m Diamond drilling program on the Schaft Creek project in 2011.  Two Diamond drill contractors have been retained to complete the work.  The primary objectives of the 2011 program are:

a) to expand the limits of the zone of higher-grade copper-gold-molybdenum-silver mineralization located in 2010 in the Paramount zone of the Schaft Creek deposit,
b) to complete geophysical surveying of (Titan-24 surveys) and initial Diamond drill testing of the ES and GK zones of mineralization, and
c) to complete geophysical surveying of (Titan-24) and initial Diamond drill testing of the large chargeability anomaly located north of the Paramount zone.

The majority of the 2011 drilling program is expected to be completed in the Paramount zone.  The 2011 drilling program also contemplates completing one or two Diamond drill holes into the ES and GK zones and the large chargeability anomaly to test each zone for its copper-gold potential.

About Copper Fox
Copper Fox is a Canadian based resource company listed on the TSX-Venture Exchange (CUU-TSX-V). Copper Fox was recently recognized by TSX Venture Inc. as a member of the distinguished TSX Venture 50® group where it had the distinction of being ranked first overall for 2010.

The Company is working on completing a Feasibility Study on the Schaft Creek deposit, one of the largest undeveloped copper, gold, molybdenum and silver deposits in North America.  Categorized as a "giant porphyry deposit" this project is at the advanced development stage with a Preliminary Feasibility Study ("PFS") prepared by Samuel Engineering, Inc. of Denver, Colorado, in September 2008.  The results of the PFS were extremely "robust" reporting a NPV @ 8% (before tax) of $2.8 billion dollars over a 23 year mine life.  They contemplated processing 100,000 tonne per day ("tpd") from an open pit mine using a standard flotation recovery process.  The PFS estimated the current Mineral Resources (using a 0.2% copper equivalent cutoff) at Schaft Creek includes; Measured Resources of 463.5 million tonnes grading 0.30% copper, 0.23 g/t gold, 0.02% molybdenum and 1.55 g/t silver, Indicated Resources of 929.8 million tonnes grading 0.23% copper, 0.15 g/t gold, 0.02% molybdenum and 1.56 g/t silver.

A Feasibility Study is being led by Wardrop, A Tetra Tech Company on a minimum 120,000 tpd open pit mine and the study is expected to be completed by the end of June 2011.

Copper Fox holds title and a 100% working interest in a contiguous 24,003.5 hectare (59,311 acre) property which includes the Schaft Creek deposit subject to certain royalty agreements, a 30% carried interest held by Liard Copper and an earn back option held by Teck Resources Limited ("Teck"). Copper Fox is currently earning a 78% interest in Liard Copper from Teck. Teck's earn back option to acquire 20%, 40% or 75% of the Schaft Creek project is triggered upon completion of a positive Feasibility Study.  Should Teck elect to exercise its option for 75% they are required to fund subsequent property expenditures up to a total of 400% of those incurred by Copper Fox ($58.1 million as of March 29, 2011) and arrange for project financing, including the Copper Fox portion.  For full details of the option please refer to the Company's website www.copperfoxmetals.com.

Additionally Copper Fox holds mineral claims totaling 3,947 hectares (9,752 acres) in the Liard mining district of BC not subject to the Teck earn-back.

Elmer B. Stewart, MSc. P. Geol., President of Copper Fox, is the Company's nominated Qualified Person pursuant to National Instrument 43-101, Standards for Disclosure for Mineral Projects, has reviewed the technical information disclosed in this news release.

*United States investors are advised that current Mineral Resources are not current Mineral Reserves and do not have demonstrated economic viability.  All figures are rounded to reflect the relative accuracy of the estimate and in keeping with "best practice principles".

On behalf of the Board of Directors

Elmer B. Stewart
President & Chief Executive Officer

Copper Fox Metals Inc.

DEVELOPMENT STAGE
CODE : CUU.V
ISIN : CA21749Q1046
Follow and Invest
Add to watch list Add to your portfolio Add or edit a note
Add Alert Add to Watchlists Add to Portfolio Add Note
ProfileMarket
Indicators
VALUE :
Projects & res.
Press
releases
Annual
report
RISK :
Asset profile
Contact Cpy

Copper Fox is a copper development stage company based in Canada.

Copper Fox develops copper, gold, molybdenum and silver in Canada.

Its main asset in development is SCHAFT CREEK in Canada.

Copper Fox is listed in Canada. Its market capitalisation is CA$ 104.8 millions as of today (US$ 76.7 millions, € 71.7 millions).

Its stock quote reached its highest recent level on April 21, 2011 at CA$ 2.63, and its lowest recent point on March 13, 2020 at CA$ 0.01.

Copper Fox has 427 809 984 shares outstanding.

Your feedback is appreciated, please leave a comment or rate this article.
Rate : Average note :0 (0 vote) View Top rated
 
Annual reports of Copper Fox Metals Inc.
2007 Annual report
2006 Annual report
Financings of Copper Fox Metals Inc.
7/1/2016Announces Closing of the Second placement
4/8/2013Announces Closing of a $2,653,000 Financing
2/22/2013announces a $2,500,000 Private Placement Unit Offering, insi...
1/22/2013ANNOUNCES the Closing of a $1,500,000 Financing by an Inside...
1/16/2013Announces a $1,500,000 Private Placement Unit Offering, Insi...
1/16/2013Announces a $1,500,000 Private Placement Unit Offering, Insi...
10/24/2012ANNOUNCES the Closing of a $2,500,000 Financing by an Inside...
9/14/2012Announces the Closing of a $4,025,000 Financing by an Inside...
7/23/2012ANNOUNCES a $4,025,000 Private Placement Unit Offering, Insi...
6/18/2012Announces A $4,480,000 Private Placement Unit Offering Insid...
1/30/2012Announces The Closing Of $2,200,000 Financing By An Insider
1/19/2012Announces a $2,200,000 Private Placement Unit Offering Insid...
12/14/2011Announces the Closing of $4,000,000 Financing by an Insider
12/7/2011Announces Increase of $2,000,000 to previously announced Pri...
10/5/2011Announces the Closing of $5,000,000 Financing by an Insider
9/13/2011Announces an Additional $2,000,000 Private Placement Unit Of...
9/8/2011announces a $3,000,000 Private Placement Unit Offering. Ins...
3/31/2011ANNOUNCES THE ACCELERATION TERM TO BE APPLIED TO THE EXPIRY ...
3/17/2011CLOSING OF A $3,750,000 NON BROKERED PRIVATE PLACEMENT FLOW-...
2/17/2011Announces a $3,750,000 Non Brokered Private Placement Flow-T...
10/22/2009closing of a $2,000,000 Private Placement Unit Offering
9/28/2009$2,000,000 Private Placement
6/23/2009Provides Update on its $6,000,000 Private Placement
6/19/2009 Updates on its $6,000,000 private placement
6/2/2009announces a $6,000,000 non-brokered Private Placement of whi...
12/16/2008Announces the Withdrawal of a Private Placement Financing
11/7/2008ANNOUNCES PRIVATE PLACEMENT FINANCING
11/7/2008Announces Private Placement Financing
5/15/2008closes Non Brokered Private Placement Financing of $12,398,2...
7/17/2007to raise $10,000,000 in flow-through and non-flow-through fu...
7/17/2007Intends to offer a brokered private placement
Option Grants of Copper Fox Metals Inc.
4/30/2012Announces Incentive Stock Option Grants
3/14/2011Grant of 1,700,000 shares at $ 1,69 par share
6/26/2008grant of incentive stock options to Employees, Officers, Con...
Nominations of Copper Fox Metals Inc.
5/3/2011ANNOUNCES RESIGNATION OF CFO, APPOINTMENT OF AN INTERIM CFO
7/16/2009Announces Executive Changes and the Appointment of a Directo...
9/17/2007Announces the appointment of Shane Uren as Vice President
Financials of Copper Fox Metals Inc.
9/22/2016Announces 2016 Third Quarter Financial Results
3/31/2016Announces 2016 First Quarter Financial Results
9/29/2015Announces Third Quarter Results
9/28/2013Announces Third Quarter Results
6/24/2013Announces Second Quarter Results
9/27/2012Announces Third Quarter Results
6/18/2012Announces Second Quarter Results
4/25/2012Announces First Quarter Results
2/29/2012Reports 2011 Annual Financial Results and a Corporate Update
9/29/2011Reports 2011 Third Quarter Financial Results and a Corporate...
6/30/2011Advances Feasibility Study and Reports 2011 Second Quarter F...
3/31/2011Announces First Quarter 2011 Highlights and Financial Result...
2/16/2011Announces Fourth Quarter Highlights and 2010 Year-End Financ...
2/25/2010Announces 2009 Year-End Financial Results
3/6/20092008 Year-end Financial Results
6/4/2008Second Quarter Results Three and Six Months Ended April 30, ...
6/3/2008Second Quarter Results
3/31/2008First Quarter Financials
3/27/2008First Quarter Results Three Months Ended January 31, 2008
2/11/20082007 Year-End Financial Results
9/24/2007Announces third quarter results
3/28/2007announces its first quarter results for the three months en...
Project news of Copper Fox Metals Inc.
1/9/2014Outlines 2014 Diamond Drilling Plans for Van Dyke Copper Pro...
11/19/2013Sampling Locates Two Large Areas Of Porphyry Style Copper-M...
4/12/2013Acquires Van Dyke Copper Deposit in Arizona
3/25/2013(Schaft Creek)Enters Into Facilities Study Agreement with BC Hydro for Sch...
2/4/2013(Schaft Creek)Files Positive Feasibility Study on Schaft Creek Project
9/10/2012Completes Acquisition Of Sombrero Butte Copper Project And V...
7/9/2012To Acquire From Bell Copper The Van Dyke Copper Deposit And ...
5/31/2012(Schaft Creek)Schaft Creek Resource Estimate Update
5/24/2012(Schaft Creek)Provides Update on Schaft Creek Project
5/10/2012(Schaft Creek)Announces 2012 Exploration Program And Acquires Additional M...
3/27/2012(Schaft Creek)Completes Land Acquisitions Covering Positive Magnetic Linea...
3/19/2012(Schaft Creek)s Activities on the Schaft Creek-Copper-Gold-Molybdenum-Silv...
2/3/2012(Schaft Creek)Announces Drilling Intersect of 0.96% CuEq Over 110m and Rep...
12/12/2011Drilling Expands Paramount Zone with Intersection of 1.10% C...
10/13/2011(Schaft Creek)Secures Shipping Facilities for Concentrate at Port of Stewa...
9/23/2011(Schaft Creek)Extends Mineralized Zone to the East And Completes Strategic...
9/6/2011Welcomes the Awarding of the Construction Contract for the N...
7/26/2011(Schaft Creek)Drilling Intersects 1.18% Copper Equivalent Over 161M at Sch...
5/31/2011(Schaft Creek)Commences 2011 Drilling Program, Updates Other Activities ...
5/10/2011(Schaft Creek)Welcomes the Federal Government of Canada's Approval of the ...
5/6/2011(Schaft Creek)Provides Update on 2011 Plans for Schaft Creek, Diamond Dril...
5/5/2011(Schaft Creek)FOX PROVIDES UPDATE ON 2011 PLANS FOR SCHAFT CREEK, DIAMOND ...
3/24/2011(Schaft Creek)Announces Strategic Acquisitions to Enlarge Schaft Creek Pro...
2/28/2011(Schaft Creek)Copper Fox Metals Applauds the Announcement of the Province ...
2/23/2011(Schaft Creek)DDH CF405 Tests Chargeability Anomaly And Expands Zone Of De...
2/14/2011(Schaft Creek)News Release
2/3/2011(Schaft Creek)Latest Assay Results Expands Zone of Deep, Higher Grade Mine...
6/18/2010files an amended Preliminary Feasibility Study on SEDAR
4/1/2010s Status of Feasibility Study and Reports 2010 First Quarter...
1/21/2010(Schaft Creek)Awards Feasibility Study On Schaft Creek Project
11/18/2009(Schaft Creek)Geophysical Survey Outlines "8" IP Anomalies at Schaft Creek...
9/15/2008Positive Results of Preliminary Feasibility Study on Schaft ...
9/15/2008Announces Positive Results of Preliminary Feasibility Study ...
7/14/2008(Schaft Creek)Strategic Drilling Program and Greenfield Camp Expansion Hig...
6/26/2008(Schaft Creek)2007 Drilling And Geophysical Results All Show Increased Pot...
3/20/2008(Schaft Creek)Announces Schaft Creek progress
1/14/2008(Schaft Creek)Releases Positive Preliminary Economic Assessment on its Sch...
11/27/2007(Schaft Creek)continues development of its Schaft Creek British Columbia m...
10/22/2007(Schaft Creek)'Pit Optimization Study Demonstrates 65,000-tonne per-day Op...
7/10/2007(Schaft Creek)Updates 2007 Schaft Creek Work Program
7/4/2007(Schaft Creek)Significantly Increases Resources at Schaft Creek
Corporate news of Copper Fox Metals Inc.
6/29/2016Copper Fox Announces 2016 Second Quarter Financial Results
6/10/2016Copper Fox Announces a $1,000,000 Non-Brokered Private Place...
3/31/2016Copper Fox Announces 2016 First Quarter Financial Results
3/30/2016Copper Fox Annnounces 2016 Schaft Creek Program
1/25/2016Copper Fox Announces Mineral Mountain Copper Project in Ariz...
12/24/2015Copper Fox Files Van Dyke Technical Report on SEDAR
12/22/2015Copper Fox Announces $1,650,000 Non-Brokered Private Placeme...
11/6/2015Copper Fox Provides Update of Activities
9/29/2015Copper Fox Announces Third Quarter Results
9/25/2015Copper Fox Extends Size of Exploration Target on Sombrero Bu...
9/8/2015Copper Fox Reports Large Chargeablity Signature on Sombrero ...
7/28/2015Copper Fox Provides Update of Activities
7/13/2015Copper Fox Commences Titan-24 DCIP Survey at Sombrero Butte ...
4/15/2015Copper Fox Announces Preliminary Results of Metallurgical Te...
4/8/2015Copper Fox Announces Commencement of Preliminary Economic As...
3/31/2015Copper Fox Annnounces First Quarter Results
3/17/2015Copper Fox Annnounces 2015 Schaft Creek Program
3/13/2015Copper Fox Receives $3.63 Million Cash Refund
3/12/2015Copper Fox Extends Warrant Expiry Dates and Announces AGM Da...
2/27/2015Copper Fox Announces Annual Results
2/9/2015Copper Fox Updates Schaft Creek Project Activities
2/3/2015Copper Fox Files Van Dyke Technical Report on SEDAR
1/15/2015Copper Fox Completes Top-Up Investmentin Carmax Mining Corp.
12/24/2014Copper Fox Provides Corporate Update on Project Activities
12/19/2014Copper Fox Completes Inferred Mineral Resource Estimate for ...
12/3/2014Copper Fox Announces Preliminary In-Situ Leach Test Results ...
10/28/2014Copper Fox Announces Commencement of Resource Estimate at Va...
10/23/2014Copper Fox Announces Update on Schaft Creek Project
9/25/2014Copper Fox Completes Top-Up Investment in Carmax Mining Corp...
9/23/2014Copper Fox Announces Third Quarter Results
9/10/2014Copper Fox Announces Van Dyke Drill Results and Provides Oth...
8/7/2014Copper Fox Announces Van Dyke Drill Results and Provides Cor...
7/21/2014Copper Fox Completes Van Dyke Drilling Program and Provides ...
6/18/2014Copper Fox Announces Second Quarter Results
5/29/2014Copper Fox Closes Carmax Investment
5/23/2014Copper Fox Announces Carmax Shareholders Approve Private Pla...
5/15/2014Copper Fox Adds Second Drill to Van Dyke Project and Provide...
12/3/2013s Activities on Van Dyke Copper Deposit in Arizona
11/19/2013Sampling locates two large areas of porphyry style copper-mo...
8/30/2013announces a corporate reorganization
8/12/2013provides update on corporate activities
7/16/2013(Schaft Creek)And Teck Resources Form Schaft Creek Joint Venture
6/5/2013(Schaft Creek)provides update on discussions regarding Schaft Creek
2/7/2013(Schaft Creek)Completes Land Acquisitions at Schaft Creek & Sombrero Butte...
1/17/2013Announces Extension Of Expiry Date Of Certain Stock Options
10/17/2012(Schaft Creek)Reports Diamond Drill Results From the 2012 Drilling Program...
9/25/2012(Schaft Creek)Reports the Status of the Schaft Creek Feasibility Study and...
9/25/2012(Schaft Creek)Reports the Status of the Schaft Creek Feasibility Study and...
9/4/2012Drilling Indicates Widespread Mineralization in the Discover...
8/2/2012(Schaft Creek)Drilling Extends Mineralization In Discovery Zone And Acquir...
2/16/2012(Schaft Creek)Locates a New Zone of Copper Mineralization 1,200M North of ...
1/23/2012Announces The Issuance Of 1,272,727 Shares For Outstanding ...
1/13/2012Announces Shares For Debt Agreement
9/6/2011(Schaft Creek)Drilling Intersects 0.81% Copper Equivalent Over 154m at Sch...
7/11/2011(Schaft Creek)Measured and Indicated Resource Estimate Exceeds 1 Billion T...
6/21/2011(Schaft Creek)High Resolution Magnetic Survey at Schaft Creek Confirms Sim...
4/13/2011Announces Completion of 3D Model and Award of High-Resolutio...
4/13/2011ANNOUNCES COMPLETION OF 3D MODEL AND AWARD OF HIGH-RESOLUTIO...
6/17/2010June 17 2010 news release
6/1/2010June 1 2010 News release
2/2/2010Feb 2 2010 news release
1/21/2010Jan 21, 2010
10/23/2009New release attached
10/22/2009announces the closing of a $2,000,000 Private Placement Unit...
9/17/2009Applauds Federal Government’s Support for British Columbia N...
9/17/2009Applauds Federal Government's Support for British Columbia N...
7/13/2009Special Shareholders Meeting Approves a New control Person -...
7/13/2009July 13, 2009 News release
6/30/2009Three and Six Months Ended April 30, 2009
6/26/2009June 25, 2009 news release
3/3/2009Annual Financial
2/27/2009Feb 26, 2009 News release
2/27/2009Lions Gate Metals Inc. and Copper Fox Metals Inc. Announce B...
2/12/2009Correct News release
2/12/2009Feb 11 09 News release
2/12/2009provides an update of Corporate Activities
2/3/2009Highway 37 Power Line Coalition Applauds Premier for Express...
1/22/2009Cambridge House Invitation - Vancouver
12/18/2008December 17 2008 News release
12/18/2008Announces Resignation Of A Director
9/30/2008Sept 30/08
9/29/2008Applauds Advancement of Northwest Power Line
9/29/2008Applauds Advancement of Northwest Power Line
9/26/2008Northwest Power Line Could Create Thousands of Jobs, Attract...
9/17/2008Schaft not Galore says Copper Fox president
9/2/2008LV Hard Assets Conference Personalized Html
7/17/2008from the Ministry of Energy, Mines and Petroleum Resources r...
6/26/2008June 26 2008 Options
6/26/2008June 26, 2008
5/26/2008Register Today for a Discounted Rate to the New Orleans 2008...
4/4/2008Applauds Advancement of Northwest Power Line Study
3/31/2008$16mm offering
11/15/2007announces the renewal of the engagement of Jason Shepherd fo...
10/12/2007Announces is has earned a 70% Direct Interest in the World C...
10/2/2007$400 million to empower B.C.'s far northwest
8/8/2007Drilling to Commence at Copper Flats
7/12/2007Press Release: Augusta Files Plan of Operations for Rosemont...
7/3/2007 2nd Quarter Financials
6/11/2007announces its request for a trading halt
5/4/2007and the Tahltan Nation Development Corporation complete a "M...
4/22/2007Adopts a Shareholder Rights Plan.
2/27/2007Welcomes New Executive to the Team
Comments closed
 
Latest comment posted for this article
Be the first to comment
Add your comment
TSX-V (CUU.V)
0.245+4.26%
TSX-V
CA$ 0.245
04/25 16:59 0.010
4.26%
Prev close Open
0.235 0.235
Low High
0.235 0.250
Year l/h YTD var.
0.160 -  0.250 6.52%
52 week l/h 52 week var.
0.150 -  0.300 -10.91%
Volume 1 month var.
91,000 44.12%
24hGold TrendPower© : 40
Produces
Develops Copper - Gold - Molybdenum - Silver
Explores for
 
 
 
Analyse
Interactive chart Add to compare
Interactive
chart
Print Compare Export
Last updated on : 7/8/2010
You must be logged in to use the porfolio and watchlists (free)
Top Newsreleases
MOST READ
Annual variation
DateVariationHighLow
202425.64%
202321.88%0.310.15
2022-36.00%0.320.13
2021-25.37%0.660.20
2020346.67%0.470.01
 
5 years chart
 
3 months chart
 
3 months volume chart
 
 
Mining Company News
Plymouth Minerals LTDPLH.AX
Plymouth Minerals Intersects Further High Grade Potash in Drilling at Banio Potash Project - Plannin
AU$ 0.12-8.00%Trend Power :
Santos(Ngas-Oil)STO.AX
announces expected non-cash impairment
AU$ 7.75+0.52%Trend Power :
Oceana Gold(Au)OGC.AX
RELEASES NEW TECHNICAL REPORT FOR THE HAILE GOLD MINE
AU$ 2.20+0.00%Trend Power :
Western Areas NL(Au-Ni-Pl)WSA.AX
Advance Notice - Full Year Results Conference Call
AU$ 3.86+0.00%Trend Power :
Canadian Zinc(Ag-Au-Cu)CZN.TO
Reports Financial Results for Q2 and Provides Project Updates
CA$ 0.12+4.55%Trend Power :
Stornoway Diamond(Gems-Au-Ur)SWY.TO
Second Quarter Results
CA$ 0.02+100.00%Trend Power :
McEwen Mining(Cu-Le-Zn)MUX
TO ACQUIRE BLACK FOX FROM PRIMERO=C2=A0
US$ 11.94+9.34%Trend Power :
Rentech(Coal-Ngas)RTK
Rentech Announces Results for Second Quarter 2017
US$ 0.20-12.28%Trend Power :
KEFIKEFI.L
Reduced Funding Requirement
GBX 0.54-2.55%Trend Power :
Lupaka Gold Corp.LPK.V
Lupaka Gold Receives First Tranche Under Amended Invicta Financing Agreement
CA$ 0.06+0.00%Trend Power :
Imperial(Ag-Au-Cu)III.TO
Closes Bridge Loan Financing
CA$ 2.69+13.03%Trend Power :
Guyana Goldfields(Cu-Zn-Pa)GUY.TO
Reports Second Quarter 2017 Results and Maintains Production Guidance
CA$ 1.84+0.00%Trend Power :
Lundin Mining(Ag-Au-Cu)LUN.TO
d Share Capital and Voting Rights for Lundin Mining
CA$ 15.60+1.83%Trend Power :
Canarc Res.(Au)CCM.TO
Canarc Reports High Grade Gold in Surface Rock Samples at Fondaway Canyon, Nevada
CA$ 0.24+0.00%Trend Power :
Havilah(Cu-Le-Zn)HAV.AX
Q A April 2017 Quarterly Report
AU$ 0.19+0.00%Trend Power :
Uranium Res.(Ur)URRE
Commences Lithium Exploration Drilling at the Columbus Basin Project
US$ 6.80-2.86%Trend Power :
Platinum Group Metals(Au-Cu-Gems)PTM.TO
Platinum Group Metals Ltd. Operational and Strategic Process ...
CA$ 1.87+5.65%Trend Power :
Devon Energy(Ngas-Oil)DVN
Announces $340 Million of Non-Core Asset Sales
US$ 52.61+0.98%Trend Power :
Precision Drilling(Oil)PD-UN.TO
Announces 2017Second Quarter Financial Results
CA$ 8.66-0.35%Trend Power :
Terramin(Ag-Au-Cu)TZN.AX
2nd Quarter Report
AU$ 0.04+0.00%Trend Power :