VANCOUVER, BRITISH COLUMBIA--(Marketwire - June 19, 2012) - International Tower Hill Mines Ltd. (News - Market indicators)(NYSE Amex:THM)(NYSE MKT:THM)(FRANKFURT:IW9) ("ITH" or the "Company") announces an update regarding the optimization review of its Livengood project, which was announced on May 15, 2012. The Company has determined that the most efficient and cost-effective path to permitting is to incorporate results from current engineering and metallurgical test work directly into a definitive feasibility study, which ITH expects to complete in the first half of 2013. The Company has also implemented a cost reduction program and is evaluating financial de-risking options for the development of the Livengood project. Additionally, the Board of Directors is reviewing a list of qualified candidates for the position of the Company's Chief Executive Officer.

Project Review - Fast Track to Feasibility

Over the past nine months, the Company's management team has been examining all potential options for the Livengood gold deposit to address key process and development opportunities. This work has focused in large part on metallurgical testing aimed at defining the recovery process. To date, the test work has produced encouraging results and suggests the potential for a more efficient gold recovery system than the one proposed in the August 2011 Preliminary Economic Assessment (PEA). The advanced level of this work is expected to enable the Company to bypass the preparation of a prefeasibility study and move directly to completion of a feasibility study, with a view to more cost-effectively advancing the project.

Key elements of this plan for completion of a feasibility study are described below:

  • Since the August 2011 PEA, the development team has made significant advancements on project design which are being driven by an extensive metallurgical test program. Determining the most cost-effective extraction method is critical to the Livengood gold project's success, given its significant resource size but lower gold grade.
  • In February 2012, 10,800 kg from approximately 3,000 samples selected from throughout the Livengood deposit were sent to SGS Canada Inc. for the final stage of optimization testing and analysis. To date, SGS has completed gravity test work and results are pending.
  • Remaining engineering work is focused on determining the secondary system that will be used to complete the gold recovery process. This has been narrowed down to either whole-ore Cyanide in Leach (CIL) or flotation-CIL (the proposed system in the August 2011 PEA). The whole-ore CIL process is being evaluated as it would offer operational simplification opportunities.
  • Grinding studies have begun and may have significant impacts on equipment selection, power demands and resulting operating costs. Initial results from testing on a more extensive sample base indicate that mineralization at the Livengood project could have better grinding characteristics than those published in the August 2011 PEA. This could have a potentially positive impact on the project.
  • A number of other trade-off studies and project design alternatives have been evaluated over the last six months, including various grinding circuits, heap leaching and various reagent additions. At present, the large mill concept has generated superior results to all alternatives.
  • New mine design work is ongoing to re-examine cut-off grades and the optimum grade to the mill, which will produce the most economically robust project. In addition, geotechnical work for surface facility sites has significantly progressed with a key focus being potential tailing and overburden locations.

This test work program and the ongoing engineering studies have significantly advanced the Livengood project and are expected to produce the optimum project from an economic and permitting perspective. Once all work has been completed, the Company plans to begin permitting discussions with various agencies and look at project financing work necessary to advance the project towards production.

Rationalization of Costs

A comprehensive cost and organizational review is being undertaken by the Board of Directors to establish the most cost-effective structure. As a result, the Company has decided to postpone much of its district-wide exploration drilling program and reduce a portion of its condemnation drill program. The Company will focus on completing all the necessary field work and drilling to support the completion of a feasibility study and the environmental work needed to keep its permitting schedule on track. The Company believes that is has sufficient funds to complete the revised 2012 work program.

In addition, the Board of Directors is reviewing all options that could de-risk the project financially, including possible discussions with third parties on joint venture opportunities.

Qualified Person

Allen Thabit (SME # 4101531RM), a qualified person as defined by National Instrument 43-101, has supervised the preparation of the scientific and technical information that forms the basis of this news release, and has approved the disclosure herein. Mr. Thabit is not independent of ITH.

About International Tower Hill Mines Ltd.

International Tower Hill Mines Ltd. controls a 100% interest in the world-class Livengood Gold Project accessible by paved highway 70 miles north of Fairbanks, Alaska. In 2012, ITH is focused on the rapid advancement of the Livengood project into a compelling potential development scenario.

On behalf of International Tower Hill Mines Ltd.

Donald C. Ewigleben, Chairman of the Board

Cautionary Note Regarding Forward-Looking Statements

This press release contains forward-looking statements and forward-looking information (collectively, "forward-looking statements") within the meaning of applicable Canadian and U.S. securities legislation. All statements, other than statements of historical fact, included herein, including, without limitation, statements regarding the anticipated content, commencement, completion and cost of exploration programs, anticipated exploration program results and the timing thereof, the size and characteristics of, or the discovery and delineation of, mineral deposits, resources or reserves, the potential for the expansion of the estimated resources at the Livengood property, the preparation or completion of a feasibility study, the optimization of mine or gold recovery plans, the permitting of a mine at the Livengood project, the potential for a production decision to be made, the potential commencement of any development of a mine at Livengood following a production decision, the Company's business strategy and the potential for a joint venture in respect of the Livengood project, and the Company's other business and financing plans and business trends, are forward-looking statements. Information concerning mineral resource estimates and the preliminary economic analysis thereof also may be deemed to be forward-looking statements in that it reflects a prediction of the mineralization that would be encountered, and the results of mining it, if a mineral deposit were developed and mined.

Although the Company believes that such statements are reasonable, it can give no assurance that such expectations will prove to be correct. Forward-looking statements are typically identified by words such as: believe, expect, anticipate, intend, estimate, postulate, proposed, planned, potential and similar expressions, or are those, which, by their nature, refer to future events. The Company cautions investors that any forward-looking statements by the Company are not guarantees of future results or performance, and that actual results may differ materially from those in forward looking statements as a result of various factors, including, but not limited to, variations in the nature, quality and quantity of any mineral deposits that may be located at the Livengood property, variations in the market price of any mineral products the Company may produce or plan to produce, the inability of the Company to obtain any necessary permits, consents or authorizations required for its activities, the inability of the Company to produce minerals from its properties successfully or profitably, to continue its projected growth, to raise necessary capital or to be fully able to implement its business strategies, and other risks and uncertainties disclosed in the Company's Annual Information Form filed with certain securities commissions in Canada and the Company's annual report on Form 40-F filed with the United States Securities and Exchange Commission (the "SEC"), and other information released by the Company and filed with the appropriate regulatory agencies. All of the Company's Canadian public disclosure filings may be accessed via www.sedar.com and its United States public disclosure filings may be accessed via www.sec.gov, and readers are urged to review these materials, including the technical reports filed with respect to the Company's mineral properties.

This press release is not, and is not to be construed in any way as, an offer to buy or sell securities in the United States.

NR12-15



International Tower Hill Mines Ltd.
Shirley Zhou
Vice-President - Corporate Communications
604-343-4799 or Toll-Free: 1-855-208-4642 Ext. 213
szhou@ithmines.com
www.ithmines.com
Data and Statistics for these countries : Canada | All
Gold and Silver Prices for these countries : Canada | All

Intl. Tower Hill Mines

DEVELOPMENT STAGE
CODE : ITH.TO
ISIN : CA46051L1040
Follow and Invest
Add to watch list Add to your portfolio Add or edit a note
Add Alert Add to Watchlists Add to Portfolio Add Note
ProfileMarket
Indicators
VALUE :
Projects & res.
Press
releases
Annual
report
RISK :
Asset profile
Contact Cpy

Intl. Tower Hill is a gold development stage company based in Canada.

Intl. Tower Hill develops gold and silver in USA, and holds various exploration projects in USA.

Its main asset in development is LIVENGOOD in USA and its main exploration properties are BMP, PAINTED HILLS and COFFE DOME in USA.

Intl. Tower Hill is listed in Canada, in Germany and in United States of America. Its market capitalisation is CA$ 146.0 millions as of today (US$ 106.2 millions, € 99.8 millions).

Its stock quote reached its lowest recent point on April 29, 2005 at CA$ 0.25, and its highest recent level on February 25, 2011 at CA$ 9.99.

Intl. Tower Hill has 162 190 000 shares outstanding.

Your feedback is appreciated, please leave a comment or rate this article.
Rate : Average note :0 (0 vote) View Top rated
 
Financings of Intl. Tower Hill Mines
9/18/2012International Tower Hill Closes Second Tranche of Non-Broker...
7/19/2012International Tower Hill Increases Non-Brokered Private Plac...
7/12/2012International Tower Hill Announces Up To $25,000,000 Non-Bro...
2/17/2011International Tower Hill Receives Share Ownership Top-Up Not...
4/7/2010 Closes Final Tranche of CAD 30,000,000 Non-Brokered Equity ...
3/16/2010CAD 30,000,000 Non-Brokered Equity Financing
8/26/2009Closes AngloGold Ashanti Top Up Private Placement
3/5/2009Closes $10,500,000 Bought Deal Equity Financing
2/17/2009Increase in Bought Deal Equity Financing
2/12/2009 Announces Bought Deal Equity Financing
Option Grants of Intl. Tower Hill Mines
8/24/2012International Tower Hill Grants Incentive Options
Nominations of Intl. Tower Hill Mines
1/30/2013International Tower Hill Announces Resignation of a Director
1/9/2012International Tower Hill Mines Names Thomas E. Irwin as New ...
4/14/2010Appointment of Timothy Haddon and Daniel Carriere as new Dir...
Financials of Intl. Tower Hill Mines
8/15/2012International Tower Hill Files 2012 Second Quarter Financial...
5/11/2012International Tower Hill Files 2012 First Quarter Financial ...
Project news of Intl. Tower Hill Mines
7/23/2013(Livengood)International Tower Hill Mines Announces Livengood Gold Proj...
11/7/2012(Livengood)International Tower Hill Provides an Update on the Livengood...
6/19/2012(Livengood)International Tower Hill Mines Announces Update on the Liven...
1/26/2012(Livengood)International Tower Hill Mines Selects Engineering Firms for...
12/14/2011(Livengood)International Tower Hill Mines Acquires Mining Claims Near L...
6/9/2011(Livengood)International Tower Hill Mines Intersects 92.9 Metres of 1.6...
5/3/2011(Livengood)International Tower Hill Mines Intersects 33.5 Metres of 8.0...
3/30/2011(Livengood)International Tower Hill Mines Intersects Additional Zones o...
3/15/2011(Livengood)International Tower Hill Mines Hires Construction Manager fo...
2/5/2011(Livengood)International Tower Hill Intersects 13.7 metres of 5.45 g/t ...
6/16/2010(Livengood)Announces Resource Update, Livengood Gold Project, Alaska
5/11/2010(Livengood)Continues to Grow New High-Grade SW Zone, Livengood Project
4/26/2010(Livengood)Expands Higher Grade SW and Sunshine Zones at Livengood Proj...
3/22/2010(Livengood)Expands Livengood Deposit with First Results of Winter Drill...
3/10/2010(Livengood)Increases Indicated Resources at Livengood Gold Project
3/8/2010(Livengood)Announces Key Positive Metallurgical Test Results for Liveng...
3/4/2010(Terra) Signs LOI to Form Production Joint Venture on Terra Project
2/4/2010(Livengood)Begins 50,000 Metre 2010 Exploration Drill Program at Liveng...
12/4/2009Coffee Dome Drilling Intersects Gold System 17Km East of For...
11/30/2009(Livengood)Positive Preliminary Economic Assessment Results
11/12/2009(Livengood) Continues to Expand Livengood Gold Project, Alaska
11/5/2009(Chisna)Reaches JV Agreement on Chisna Copper
11/2/2009(Livengood)Continues to Expand the Livengood Gold Project
9/30/2009(Livengood)Expands the Sunshine Zone at Livengood
9/9/2009(Livengood)Latest Drill Results From Livengood Gold Project, Alaska
9/2/2009(Coffe Dome)Begins Drilling at Coffee Dome Project, Alaska
8/4/2009(North Bullfrog)Signs Agreement to Acquire 100% Interest in North Bullfrog
8/5/2009(Livengood)Delineates Major New Zone of Gold Mineralization at Livengoo...
6/26/2009(Livengood)Resource Update at Livengood, Alaska
6/10/2009(Livengood)Livengood Gold Project, Alaska Summer Drilling Program Comme...
3/10/2009(Livengood)Doubles Planned 2009 Drill Program for Livengood Gold Projec...
3/2/2009(Livengood)First Two Holes of 2009 Winter Drill Program
2/9/2009(Livengood)Livengood Gold Project, Alaska Winter Drilling Program Comme...
Corporate news of Intl. Tower Hill Mines
5/6/2016International Tower reports 1Q loss
3/16/2016International Tower reports 4Q loss
10/30/2015International Tower Hill Mines Files 2015 Third Quarter Fina...
8/6/2015International Tower reports 2Q loss
8/6/2015International Tower Hill Mines Files 2015 Second Quarter Fin...
3/26/2015International Tower Hill Mines Appoints Karl Hanneman as Chi...
3/11/2015International Tower Hill Mines Files 2014 Year End Financial...
1/6/2015International Tower Hill Mines Announces Progress on Livengo...
12/18/2014International Tower Hill Mines Announces Management Change
11/24/2014International Tower Hill Mines Announces CAD 8.4 Million Non...
11/5/2014International Tower Hill Mines Files 2014 Third Quarter Fina...
8/7/2014International Tower Hill Mines Files 2014 Second Quarter Fin...
8/7/2014International Tower Hill Mines Files 2014 Second Quarter Fin...
5/7/2014International Tower Hill Mines Files First Quarter 2014 Fina...
9/9/2013(Livengood)International Tower Hill Mines Files NI 43-101 Technical Rep...
8/8/2013International Tower Hill Mines Announces Addition to the Boa...
7/31/2013International Tower Hill Mines Files 2013 Second Quarter Fin...
6/7/2013International Tower Hill Mines Announces Results from Annual...
5/9/2013International Tower Hill Mines Files 2013 First Quarter Fina...
4/24/2013International Tower Hill Mines Comments on Recent Gold Marke...
3/13/2013International Tower Hill Mines Announces Corporate Update an...
12/11/2012(Livengood)International Tower Hill Announces Positive Metallurgical Te...
8/21/2012International Tower Hill Reports New High-Grade Gold Interce...
8/2/2012International Tower Hill Mines Announces New Manager of Inve...
6/29/2012International Tower Hill Mines Announces Interim Chief Execu...
4/4/2012International Tower Hill Recognizes Alaska Progress Made Tow...
3/21/2012International Tower Hill Mines Files Audited Annual Financia...
3/6/2012(Livengood)International Tower Hill Mines Validates Resource Estimate a...
2/27/2012International Tower Hill Mines Reports Historical Resource o...
1/16/2012International Tower Hill Mines Changes Fiscal Year End
1/4/2012International Tower Hill Mines Grants Options
12/20/2011International Tower Hill Mines Appoints Robert D. Comer as I...
8/29/2011International Tower Hill Mines Files 2011 Audited Annual Fin...
8/23/2011International Tower Hill Announces Surface Mine Measured & I...
8/16/2011International Tower Hill Mines Appoints Harold Galbriath as ...
7/28/2011International Tower Hill Mines Grants Stock Options
5/10/2011International Tower Hill Mines Appoints James Komadina as Ne...
5/6/2010 Signs Key Exploration Agreement with Ahtna
2/11/2010Receives Share Ownership Top-up Notice from AngloGold Ashant...
1/12/2010Hires Chief Operating Officer
11/26/2009to Begin Trading on Toronto Stock Exchange
11/18/2009Receives Conditional Toronto Stock Exchange Listing Approval
10/13/2009Expands Livengood Gold Resource by 64%
7/10/2009Receives Share Ownership Top-up Notice from AngloGold Ashant...
7/3/2009Retains Renmark Financial Communications Inc.
5/20/2009Receives Proceeds of $23,114,288 from Warrant/Broker Option ...
Comments closed
 
Latest comment posted for this article
Be the first to comment
Add your comment
TORONTO (ITH.TO)AMEX (THM)
0.900-3.23%0.675+0.75%
TORONTO
CA$ 0.900
04/19 14:57 -0.030
-3.23%
Prev close Open
0.930 0.920
Low High
0.900 0.920
Year l/h YTD var.
0.650 -  1.08 7.14%
52 week l/h 52 week var.
0.450 -  1.08 18.42%
Volume 1 month var.
1,500 -1.10%
24hGold TrendPower© : 4
Produces
Develops Gold
Explores for Bismuth - Copper - Gold - Nickel - Silver
 
 
 
Analyse
Interactive chart Add to compare
Interactive
chart
Print Compare Export
Last updated on : 1/27/2010
You must be logged in to use the porfolio and watchlists (free)
Top Newsreleases
MOST READ
Annual variation
DateVariationHighLow
202469.81%
2023-8.62%0.910.44
2022-40.21%1.560.51
2021-45.51%1.960.79
2020161.76%3.070.43
 
5 years chart
 
3 months chart
 
3 months volume chart
 
 
Mining Company News
Plymouth Minerals LTDPLH.AX
Plymouth Minerals Intersects Further High Grade Potash in Drilling at Banio Potash Project - Plannin
AU$ 0.12-8.00%Trend Power :
Santos(Ngas-Oil)STO.AX
announces expected non-cash impairment
AU$ 7.82+1.69%Trend Power :
Oceana Gold(Au)OGC.AX
RELEASES NEW TECHNICAL REPORT FOR THE HAILE GOLD MINE
AU$ 2.20+0.00%Trend Power :
Western Areas NL(Au-Ni-Pl)WSA.AX
Advance Notice - Full Year Results Conference Call
AU$ 3.86+0.00%Trend Power :
Canadian Zinc(Ag-Au-Cu)CZN.TO
Reports Financial Results for Q2 and Provides Project Updates
CA$ 0.12+4.55%Trend Power :
Stornoway Diamond(Gems-Au-Ur)SWY.TO
Second Quarter Results
CA$ 0.02+100.00%Trend Power :
McEwen Mining(Cu-Le-Zn)MUX
TO ACQUIRE BLACK FOX FROM PRIMERO=C2=A0
US$ 11.22+1.63%Trend Power :
Rentech(Coal-Ngas)RTK
Rentech Announces Results for Second Quarter 2017
US$ 0.20-12.28%Trend Power :
KEFIKEFI.L
Reduced Funding Requirement
GBX 0.55+2.59%Trend Power :
Lupaka Gold Corp.LPK.V
Lupaka Gold Receives First Tranche Under Amended Invicta Financing Agreement
CA$ 0.06+0.00%Trend Power :
Imperial(Ag-Au-Cu)III.TO
Closes Bridge Loan Financing
CA$ 2.48-1.59%Trend Power :
Guyana Goldfields(Cu-Zn-Pa)GUY.TO
Reports Second Quarter 2017 Results and Maintains Production Guidance
CA$ 1.84+0.00%Trend Power :
Lundin Mining(Ag-Au-Cu)LUN.TO
d Share Capital and Voting Rights for Lundin Mining
CA$ 15.84-1.31%Trend Power :
Canarc Res.(Au)CCM.TO
Canarc Reports High Grade Gold in Surface Rock Samples at Fondaway Canyon, Nevada
CA$ 0.24+0.00%Trend Power :
Havilah(Cu-Le-Zn)HAV.AX
Q A April 2017 Quarterly Report
AU$ 0.19-7.32%Trend Power :
Uranium Res.(Ur)URRE
Commences Lithium Exploration Drilling at the Columbus Basin Project
US$ 6.80-2.86%Trend Power :
Platinum Group Metals(Au-Cu-Gems)PTM.TO
Platinum Group Metals Ltd. Operational and Strategic Process ...
CA$ 1.85-2.63%Trend Power :
Devon Energy(Ngas-Oil)DVN
Announces $340 Million of Non-Core Asset Sales
US$ 51.83+0.78%Trend Power :
Precision Drilling(Oil)PD-UN.TO
Announces 2017Second Quarter Financial Results
CA$ 8.66-0.35%Trend Power :
Terramin(Ag-Au-Cu)TZN.AX
2nd Quarter Report
AU$ 0.03+0.00%Trend Power :