Please find below a link to our June Quarter Activities Report which we have today lodged with the ASX:
http://www.malachite.com.au/pdf/quarterly/MAR%20-%20Quarterly%20Activity%20Report%20June%20%2008%20240708.pdf
CONRAD SILVER PROJECT, NSW
� Drilling to increase resources has continued successfully, with two rigs operating;
� A total of 21 holes, totalling 7,368 metres, were drilled in the Quarter;
� Drill hole intersections continue to be in line with expectations;
� The deepest lode intersection is now 500m below surface;
� A new resource estimate is underway, based on drilling to the end of June;
� A major upgrade to the existing resource is expected by early August, with a further upgrade in October;
� Metallurgical testwork continues to show positive results.
OTHER PROJECTS
� Evaluation of the Karaula Tin Deposit at ELSMORE continues to provide much encouragement;
� Scout drilling at TOOLOOM has identi?ed additional mineralised breccia at the Phoenix Prospect;
� Further drilling at the MT LIDSTER and VOLGA copper projects near Mount Isa was also completed in the June Quarter.
Regards
Andrew J. Cooke
Company Secretary
Malachite Resources NL
Tel: +61 2 9411 6033
Fax: +61 2 9411 6066
Mob: 0412 090 826
Email: acooke@malachite.com.au