Troy Resources NL

Published : July 10th, 2015

Karouni Gold Project - Operational Update

( 0 vote, 0/5 ) Print article
  Article Comments Comment this article Rating Follow Company  
0
Send
0
comment
Keywords :   Australia | Consequence | Gold | Water |

Karouni Gold Project - Operational Update

ASX Release

10 July 2015

KAROUNI GOLD PROJECT - OPERATIONAL UPDATE

Perth, Western Australia: Troy Resources Limited (ASX: TRY) today announced an update on operational activities at its Karouni Gold project in Guyana, South America.

The past month or so has been an extremely busy period at Karouni as the construction team of over 500 employees and contractors worked through heavy seasonal rainfall to push completion of the plant as far as possible. The various pictures and associated remarks set out in this update show just how much progress has been achieved on site since construction started back in February this year.
Inevitably, under these conditions, there have been some difficulties that the team has had to address, including the Mill installation in particular, as well as delays experienced in clearing goods and containers held at the port. Whilst this process has improved, we are currently waiting on the last few containers and pallets of equipment and reagents held at the wharf to be cleared.
At the end of June, the only major items that were still under construction were the Mill and the Thickener, with all the other major components and site facilities ready for power connection and commissioning. All site infrastructure work is complete and all the Administration buildings are functioning.

Karouni Plant Site where construction commenced in February 2015

Mining

Mining activities are on schedule. Total ore placed on the ROM pad is now approaching 40,000 tonnes at an estimated grade of 2.3g/t. The majority of this initial material has been sourced from the Hicks Pit, which averages just over 2g/t, whilst production from the high grade Smarts Pit, averaging close to

5g/t, is gradually ramping up. The ROM pad now has a nominal capacity of just over

200,000 tonnes, which provides sufficient flexibility for blending as well as ensuring the contingency necessary to deal with the impact of future rainfall cycles.

Power Station

All generators have been mechanically commissioned and connected to transformers and the switch room. Operational High Voltage (HV) commissioning will only proceed once sufficient power load has been established - including the Mill and

Thickener circuits. The Low

Voltage (LV) circuit will be operated through separate generators in order to connect and test the site facility network and small operating units such as pumps.

The control room for the plant will be fully operational once power is available to enable electrical commissioning to occur.

ROM Pad & Reclaim Conveyor

ROM pad operational. Reclaim tunnel and conveyor systems complete. Installation of wear plates, cover and braces in the ROM bin underway. By the end of August there is expected to be more than 150,000 tonnes of ore on the ROM pad.

2

Conveyors

Structures complete. Belt installation about to commence.

Apron Feeder

Final alignment with Primary Crusher Station in progress.

Primary & Secondary Crusher

Structures complete. Final installation of walkway mesh and stairs in progress.

Raw Water Dam & Process Water Dam

Construction complete. Lining and pumps installed and tested.

3

CIL Tanks

Substantially complete. All agitators and walkway mesh installed. Some of the valves and pipework required to complete the leach circuit still in the process of being cleared through Customs.

Grinding Mill

Construction of the formwork foundation for the Mill commenced in April. Assembly of the component parts on the pedestals started in June. During the latter stages of assembly, a number of significant issues with the bearing shells, lubrication system and alignment of the Mill were identified. In order to address these issues, which could have impacted on the ongoing performance of the

Mill, site management engaged

a specialist installation team from Outotec, the manufacturer of the Mill. This team is currently on site and working to resolve the specified issues in order to ensure that all tolerances and design specifications are met, before the Mill is put into operation. It is now estimated that this additional work will take up to 5 weeks to complete. As a consequence, testing of the HV circuit will also be delayed by a similar period of time due to load constraints.

Gravity Circuit

Steelwork in place and both Knelson concentrators have been installed.

4

Thickener

All civils complete and petal steel-ring installed. The tank bridge, centre discharge box and weir are currently scheduled to clear Customs in the last week in July. Plant air compressors, low pressure blowers and air receivers ready to be commissioned.

Mobile Equipment Workshop

Complete and operational.

Elution Circuit

Ready to commission.

Gold Room & Laboratory

Building complete. Fit out in progress. Commissioning will occur once processing has started. The Sample, Prep and Assay Lab is complete and calibration and training programmes are underway.

5

Diesel Fuel Farm

Complete and operational.

Detox Tanks

Agitators have been installed in all tanks. Walkways and grating installation complete. Air blowers fitted.

Tailings Dam

Nearing completion. Stage 1 cell will be operational within scheduled requirements.

Camp/Medical Station/Offices/Exploration Buildings/Kitchen

Complete

All logistics relating to refining, security and transportation arrangements have been put in place.
Whilst the recent difficulties with the Mill installation and delays in clearing goods through Georgetown Port are disappointing, the fact that this fast-track construction project has been conducted with very few serious health and safety incidents stands as a noteworthy achievement.
With the prospect of better weather on the horizon and the entire focus of the construction crew on the few remaining major tasks to get the plant into full operation, the target now is to start wet commissioning in early September. The first gold pour is now expected to occur approximately 3 to 4 weeks after the start of wet commissioning.
The Company is in the process of awarding the contract for Air-core and RC drilling to enable exploration activities to commence at its priority targets. A further update on this will be provided in due course.
ENDS

For further information please contact:

Martin Purvis Stacey Apostolou CEO Company Secretary Troy Resources Limited Troy Resources Limited T: (61 8) 9481 1277 T: (61 8) 9481 1277

E: [email protected] E: [email protected]

6

Read the rest of the article at www.noodls.com
Data and Statistics for these countries : Australia | All
Gold and Silver Prices for these countries : Australia | All

Troy Resources NL

PRODUCER
CODE : TRY.AX
ISIN : AU000000TRY7
Follow and Invest
Add to watch list Add to your portfolio Add or edit a note
Add Alert Add to Watchlists Add to Portfolio Add Note
ProfileMarket
Indicators
VALUE :
Projects & res.
Press
releases
Annual
report
RISK :
Asset profile
Contact Cpy

Troy Res. is a gold producing company based in Australia.

Troy Res. produces gold, silver in Argentina, in Australia and in Brazil, develops gold in Australia, and holds various exploration projects in Argentina, in Australia, in Brazil and in Finland.

Its main assets in production are GOIAS VELHO / SERTAO MINE and ANDORINHAS in Brazil, BULCHINA MINE, CORNISHMAN & DOUBLE O, CORNISHMAN MINE, LORD NELSON and LORD HENRY in Australia and CASPOSO in Argentina, its main assets in development are SANDSTONE - LORD NELSON and SERTAO in Australia and its main exploration properties are DALY RIVER, THREE RIVERS, TWO MILE, THREE RIVERS and TROJAN JV in Australia and OIJARVI in Finland.

Troy Res. is listed in Australia, in Canada and in Germany. Its market capitalisation is AU$ 13.7 millions as of today (US$ 9.9 millions, € 9.1 millions).

Its stock quote reached its highest recent level on October 05, 2012 at AU$ 5.02, and its lowest recent point on September 01, 2023 at AU$ 0.03.

Troy Res. has 456 600 000 shares outstanding.

Your feedback is appreciated, please leave a comment or rate this article.
Rate : Average note :0 (0 vote) View Top rated
 
Corporate Presentations of Troy Resources NL
8/23/2016Investor Presentation
5/9/2016Gold Tour Presentation
7/27/2011Company Presentation-Investor Update
Annual reports of Troy Resources NL
: 2012 Annual Report to Shareholders
Annual Report 2011
Financings of Troy Resources NL
4/9/2013Provides Funding to Azimuth Pursuant to Convertible Note Fac...
Option Grants of Troy Resources NL
1/10/2012Payment of Dividend and Issuance of Shares Under the Troy Di...
Nominations of Troy Resources NL
7/29/2016Appointment of Independent Non-Executive Director
8/29/2013: Change to Directors
2/5/2013: Appointment of Company Secretary
3/14/2011Resignation of Company Director
2/1/2010Appointment of Mr David Dix
Financials of Troy Resources NL
7/29/2016Quarterly Activities Report - June 2016
4/28/2016Quarterly Activities Report - March 2016
9/27/2012: Full Year Statutory Financial Statements-30 June 2012
Project news of Troy Resources NL
5/21/2014Australian company to open gold mine in Guyana
8/29/2011Strong Production Growth Returns Troy to Profit
4/27/2011(Kamila)Follow-up Drilling at Kamila SE Extension Zone Produces Furt...
3/20/2011(Casposo)- High Grade Drill Intercept
5/17/2010(Casposo) NI-43101 Technical Report Casposo Project San Juan, Argenti...
5/11/2010(Casposo)Casposo financing complete
5/6/2010(Casposo)Casposo updated mining reserve and production schedule
3/8/2010(Sandstone - Lord Nelson)New Nickel Sulphide Discovery at Sandstone JV
2/23/2010(Andorinhas)Andorinhas Robbery
1/27/2010(Casposo)Casposo Update
10/9/2009(Casposo)Casposo Project Update
9/14/2009(Casposo)NI43-101 Updated Technical Reports for Casposo & Sandstone
8/18/2009(Casposo)Updated Mineral Reserves and Resources
7/31/2009(Two Mile)New Inferred Resource Two Mile Hill Prospect Sandstone WA
7/29/2009(Casposo)Significant (32%) Increase in Casposo
7/16/2009(Two Mile)High Grade Results at Two Mile Hill Prospect
6/12/2009(Casposo)Files technical report for the Casposo deposit
9/9/2008(Andorinhas)Andorinhas Iron Ore Resource
8/4/2008(Andorinhas)Troy Resources NL - Andorinhas Iron Drill Results
7/25/2008(Andorinhas)Colluvial Iron Ore Study Update - Andorinhas Project Brazil
Corporate news of Troy Resources NL
9/23/2016Becoming a substantial holder from CBA
7/13/2016Operational Update
6/27/2016Director Appointment/Resignation
5/27/2016Karouni Operational Update
5/13/2016Ceasing to be a substantial holder
5/4/2016 Troy Restructures Investec Facility
5/3/2016Troy Restructures Investec Facility
2/1/2016Change of Director's Interest Notices
2/1/2016Change of Director's Interest Notices
1/28/2016Appendix 3B and Cleansing Notice
1/28/2016Results of Meeting
1/28/2016Quarterly Activities Report - December 2015
12/28/2015Change in substantial holding
12/28/2015Change in substantial holding
12/24/2015Ceasing to be a substantial holder
12/23/2015Appendix 3B and Cleansing Notice
12/23/2015Notice of General Meeting/Proxy Form
12/17/2015Troy Announces Completion of $10 million Placement
12/17/2015Capital Raising Investor Presentation
12/17/2015Capital Raising Investor Presentation
12/15/2015Trading Halt
12/15/2015Trading Halt
10/30/2015Quarterly Activities Report - September 2015 (Relodge)
10/30/2015Quarterly Activities Report - September 2015
10/29/2015Change in substantial holding
10/26/2015Commissioning Complete at Karouni Gold Project
10/26/2015Commissioning Complete at Karouni Gold Project
10/23/2015Corporate Governance and Appendix 4G
10/23/2015Annual Report to shareholders
10/23/2015Notice of Annual General Meeting/Proxy Form
10/23/2015Annual Report to shareholders
10/23/2015Notice of Annual General Meeting/Proxy Form
9/25/2015Full Year Statutory Accounts - 30 June 2015
9/25/2015Full Year Statutory Accounts - 30 June 2015
9/14/2015TRY to Convert Currency of Loan Facility and Resets Hedging
9/10/2015Change to Securities
9/10/2015Change to Securities
8/31/2015Mineral Resources and Ore Reserves Update
8/31/2015Mineral Resources and Ore Reserves Update
8/31/2015Appendix 4E - Preliminary Final Report - 30 June 2015
8/31/2015Appendix 4E - Preliminary Final Report - 30 June 2015
8/31/20152015 Financial Year Results Announcement
8/13/2015Appendix 3Y - Change of Director's Interest Notice - Jones
8/13/2015Appendix 3Y - Change of Director's Interest Notice - Jones
8/4/2015Diggers and Dealers 2015 Presentation
8/4/2015Diggers and Dealers 2015 Presentation
7/31/2015Quarterly Activities Report - June 2015
7/31/2015Quarterly Activities Report - June 2015
7/22/2015Change in substantial holding
7/14/2015Troy Chairman Leave of Absence
7/10/2015Karouni Gold Project - Operational Update
7/9/2015Becoming a substantial holder
6/15/2015Appendix 3Y - Change of Director's Interest Notice - Jones
6/9/2015Successful Completion of Placement and Share Purchase Plan
6/9/2015Appendix 3B and Cleansing Notice
6/4/2015Results of General Meeting
4/27/2015Trading Halt
4/24/2015Quarterly Activities Report - March 2015
4/20/2015Appendix 3Z - Final Director's Interest Notice - Harvey
4/20/2015Resignation of Director
4/20/2015Resignation of Director
4/14/2015UK Investor Update Presentation - April 2015
4/14/2015UK Investor Update Presentation - April 2015
4/14/2015Voluntary Delisting from Toronto Stock Exchange
4/14/2015: Voluntary Delisting From Toronto Stock Exchange
3/25/2015Notice of Initial Substantial Holder for ALY
3/25/2015Half - Year Ended 31 December 2014 Financial Results
3/25/2015Half - Year Report for the Period Ended 31 December 2014
3/25/2015ALY: Purchase of Reserve Payment from Troy
3/25/2015S&P DJ Indices Announces March Quarterly Review
3/25/2015Appendix 3Y - Change of Director's Interest Notice - Parish
3/25/2015Change in substantial holding
3/25/2015Ceasing to be a Substantial Holder for ALY
3/25/2015Half - Year Report for the Period Ended 31 December 2014
3/25/2015ALY: Purchase of Reserve Payment from Troy
3/25/2015S&P DJ Indices Announces March Quarterly Review
3/25/2015Change in substantial holding
3/25/2015Ceasing to be a Substantial Holder for ALY
2/20/2015: Investor Update Presentation, February 2015
12/18/2014Appendix 3Y - Change of Director's Interest Notice - Purvis
12/18/2014Appendix 3B - Issue of Share Appreciation Rights
10/20/2014Troy Signs Minerals Agreement for the Karouni Gold Project
10/14/2014The Dollar Rally: Where Will The Buck Stop?
2/25/2014Troy Resources to Raise Up to A$28 Million by Way of Placeme...
2/25/2014Troy to Raise Up to A$28 Million by Way of Placement and Up ...
2/23/2014Troy Resources Limited: Half Year Ended 31 December 2013 Fin...
2/20/2014Troy Resources Limited: RIU Explorers Conference Presentatio...
2/17/2014Troy Reaches Agreement to Sell Its 70% Interest in the Serta...
2/2/2014Troy Resources Limited: Investor Update, February 2014
2/2/2014Troy Resources Limited: Exceptional Channel Sample Results a...
1/31/2014Troy Resources Limited: Quarterly Activities Report December...
10/29/2013Presentation-ASX Small to Mid Caps
10/25/2013-Notice of 2013 Annual General Meeting and Explanatory Memor...
9/26/2013Full Year Statutory Accounts-30 June 2013
9/16/2013Investor Presentations-September 2013
8/28/2013: Completion of Compulsory Acquisition of Ordinary Shares in...
8/6/2013Presentation-Diggers & Dealers 2013
7/29/2013: Quarterly Activities Report June 2013
7/29/2013: Quarterly Activities Report June 2013
7/9/2013Corporate and Operational Update-BRR Webcast
6/27/2013Cuts Costs in Decisive Response to Price Volatility
6/24/2013Takeover Bid by Troy Resources Limited for Azimuth Resources...
6/17/2013Takeover Bid By Troy Resources Limited for Azimuth Resources...
6/7/2013Takeover Bid by Troy Resources Limited for Azimuth Resources...
5/24/2013: Institutional Acceptance Facility and First Supplementary ...
5/8/2013: Change to Securities
4/30/2013on Progress of Troy Takeover Offer for Azimuth
4/22/2013Secures A$40 Million Funding from Investec
4/3/2013and Azimith Resources CEOs Discuss Proposed Takeover-BRR Web...
3/28/2013: Media Conference Call Recording
3/25/2013(Kamila)Casposo Exploration Drilling Update Kamila Southeast Trend I...
1/30/2013: Quarterly Report on Activities December 2012
10/25/2012: Notice of 2012 Annual General Meeting & Proxy Form
10/16/2012Presentation: ASX Small to Mid Caps Asia
8/14/2012Announces Agreement to Sell the Sandstone Property to Southe...
8/8/2012Presentation: Diggers & Dealers
7/27/2012: Quarterly Report on Activities June 2012
7/12/2012(Casposo): Dr. J.W. Hedenquist Casposo Site Visit and Report
6/25/2012: Presentation & Webcast-The Gold Coast Resources Showcase
6/20/2012(Casposo): Reserve and Mine Plan Updated Technical Report (NI 43-101)...
5/30/2012(Casposo): Casposo Mineral Reserve Update Gold Equivalent Production ...
4/13/2012to Be Included in the S&P ASX 200 Index
4/4/2012: Company Presentation
2/24/2012(Casposo)Doubles Production & Revenue as Low Cost Casposo Hits its St...
2/8/2012: Revised December 2011 Quarterly Report
1/30/2012: Quarterly Report on Activities December 2011
1/9/2012ASX Announcement - ASIC Approves Change of Company Type and ...
12/15/2011New Corporate Office and Registered Address
10/12/2011(Casposo)Resource Update Report Released for Casposo Project San Juan...
10/4/2011(Casposo)Casposo Achieves Nameplate Throughput
8/29/2011(Kamila): Initial Resource Estimate Kamila Southeast Discovery at Ca...
8/24/2011Introduces A Shareholder Dividend Re-Investment Plan
8/3/2011Public Announcement Media Speculation
8/2/2011(Kamila)Kamila Southeast Target Drilling Update-More High Grade Resu...
7/20/2011(Casposo)ASX Announcement - High Grade Intercepts Drilling at Casposo...
6/21/2011(Kamila)Kamila Southeast Zone Drilling Continues to Deliver High Gra...
6/7/2011(Casposo)Declares Dividend as Low Cost Casposo Mine Officially Opened
5/19/2011(Kamila)Kamila Southeast Zone Step-Out Drilling Delivers High Grade ...
2/28/2011Half Year Ended December 31, 2010 Financial Results
1/24/2011 Quarterly Report on Activities December 2010
8/2/2010Diggers & Dealers 2010 Company Presentation
7/29/2010Sales of Andorinhas Iron Ore
7/16/2010Initial Inferred Resource Julieta Prospect Casposo Project
4/30/2010Quarterly Report on Activities March 2010
3/17/2010Corporate Update Presentation
2/10/2010Financing Update
2/4/2010Moving to Where the Gold Is
1/29/2010Quarterly Report on Activities December 2009
1/29/2010Aztec Vein Initial Grade Control Drilling - Casposo Project
1/21/2010 Notice of Forfeited Shares Auction
1/20/2010 Sale of Mongolian Assets
12/14/2009Form 604 -Notice of change of interests of substantial holde...
12/7/2009Share Placement and Appendix 3B
12/4/2009Entitlements Issue - Under Subscription
12/2/2009Amended Constitution
11/9/2009Troy Resources NL - Chairman's Letter to Shareholders - EGM ...
11/5/2009Shareholder Letters Re Entitlements Issue
11/4/2009Entitlements Issue 708AA Notice & Appendix 3
11/4/2009Withdrawal of Request for EGM
10/28/2009Quarterly Report on Activities September 2009
10/2/2009Notice of Shareholder Meeting
9/30/2009Full Year Statutory Accounts
9/25/2009CALL ON PARTLY PAID SHARES
8/27/2009Profit of A$16.7 Million and Builds the Foundation for Futur...
8/10/2009Declares 10th Consecutive Fully Franked Dividend
7/30/2009Quarterly Report on Activities June 2009
2/9/2009Quarterly Report and Operations Update - Audio Broadcast
2/23/2009Half Year Report
2/3/2009ASX Release - Voluntary Annual Information Form
1/28/2009Quarterly Report
1/20/2009ASX Announcement
11/27/2008AGM Results November 2008
11/26/2008Resignation of Non-Executive Director T D McKeith
11/13/2008ASX Announcement
9/30/2008ASX Announcement
8/29/2008ASX Announcement
7/31/2008Quarterly Report
Comments closed
 
Latest comment posted for this article
Be the first to comment
Add your comment
AUSTRALIA (TRY.AX)TORONTO (TRY.TO)
0.030+0.00%0.430+1.18%
AUSTRALIA
AU$ 0.030
09/01 11:00 -
0%
Prev close Open
0.030 0.030
Low High
0.030 0.030
Year l/h YTD var.
 -  -
52 week l/h 52 week var.
- -  0.030 -%
Volume 1 month var.
0 -%
24hGold TrendPower© : -26
Produces Gold - Silver
Develops Gold
Explores for Copper - Gold - Lead - Silver - Zinc
 
 
 
Analyse
Interactive chart Add to compare
Interactive
chart
Print Compare Export
Last updated on : 11/24/2010
You must be logged in to use the porfolio and watchlists (free)
Top Newsreleases
MOST READ
Annual variation
DateVariationHighLow
20240.00%
20230.00%0.030.03
2022-18.92%0.040.03
2021-62.63%0.100.03
20208.79%0.200.06
 
5 years chart
 
3 months chart
 
3 months volume chart
 
 
Mining Company News
Plymouth Minerals LTDPLH.AX
Plymouth Minerals Intersects Further High Grade Potash in Drilling at Banio Potash Project - Plannin
AU$ 0.12-8.00%Trend Power :
Santos(Ngas-Oil)STO.AX
announces expected non-cash impairment
AU$ 7.30+0.07%Trend Power :
OceanaGold(Au)OGC.AX
RELEASES NEW TECHNICAL REPORT FOR THE HAILE GOLD MINE
AU$ 2.20+0.00%Trend Power :
Western Areas NL(Au-Ni-Pl)WSA.AX
Advance Notice - Full Year Results Conference Call
AU$ 3.86+0.00%Trend Power :
Stornoway Diamond(Gems-Au-Ur)SWY.TO
Second Quarter Results
 0.02+100.00%Trend Power :
McEwen Mining(Cu-Le-Zn)MUX
TO ACQUIRE BLACK FOX FROM PRIMERO=C2=A0
US$ 9.33+0.43%Trend Power :
Rentech(Coal-Ngas)RTK
Rentech Announces Results for Second Quarter 2017
US$ 0.20-12.28%Trend Power :
KEFIKEFI.L
Reduced Funding Requirement
GBX 0.59-2.00%Trend Power :
Lupaka Gold Corp.LPK.V
Lupaka Gold Receives First Tranche Under Amended Invicta Financing Agreement
CA$ 0.05-9.09%Trend Power :
Imperial(Ag-Au-Cu)III.TO
Closes Bridge Loan Financing
 2.23-0.89%Trend Power :
Guyana Goldfields(Cu-Zn-Pa)GUY.TO
Reports Second Quarter 2017 Results and Maintains Production Guidance
 1.84+0.00%Trend Power :
Lundin Mining(Ag-Au-Cu)LUN.TO
d Share Capital and Voting Rights for Lundin Mining
 14.42+3.30%Trend Power :
Canarc Res.(Au)CCM.TO
Canarc Reports High Grade Gold in Surface Rock Samples at Fondaway Canyon, Nevada
 0.32+1.59%Trend Power :
Havilah(Cu-Le-Zn)HAV.AX
Q A April 2017 Quarterly Report
 0.22+7.50%Trend Power :
Uranium Res.(Ur)URRE
Commences Lithium Exploration Drilling at the Columbus Basin Project
US$ 6.80-2.86%Trend Power :
Platinum Group Metals(Au-Cu-Gems)PTM.TO
Platinum Group Metals Ltd. Operational and Strategic Process ...
 2.11+5.50%Trend Power :
Devon Energy(Ngas-Oil)DVN
Announces $340 Million of Non-Core Asset Sales
US$ 42.42+1.51%Trend Power :
Precision Drilling(Oil)PD-UN.TO
Announces 2017Second Quarter Financial Results
CA$ 8.66-0.35%Trend Power :
Terramin(Ag-Au-Cu)TZN.AX
2nd Quarter Report
AU$ 0.04+0.00%Trend Power :
Sun Res.(Oil)SUR.AX
Released ASX Announcement: Quarterly Activities Report
AU$ 0.00+0.00%Trend Power :
Take advantage of rising gold stocks
  • Subscribe to our weekly mining market briefing.
  • Receive our research reports on junior mining companies
    with the strongest potential
  • Free service, your email is safe
  • Limited offer, register now !
Go to website.