Kvanefjeld Feasibility Study Developments: Mine and Concentrator Study Lowers Initial Start-Up Costs
Published : March 26, 2013
( 0 vote, 0/5 ) Print article
  Article Comments Comment this article Rating Follow Company  
0
Send
0
comment

PERTH, WESTERN AUSTRALIA--(Marketwire - March 26, 2013) - Greenland Minerals and Energy Ltd's (News - Market indicators)(PINKSHEETS:GDLNF) 100% owned Kvanefjeld multi-element project contains one of the world's largest undeveloped resources of rare earth metals and uranium (JORC-code compliant), and is ideally located near the southern tip of Greenland. Feasibility studies are well advanced and demonstrate Kvanefjeld's potential to be developed as a long term, low-cost uranium supply, and a large low-cost supplier of both heavy and light rare earth oxides (REOs).

GMEL is now focussed on a staged development strategy with an initial mine-throughput of 3Mtpa, expanding to 6Mtpa. There are two main steps in the processing of Kvanefjeld ores; a concentrator stage, and a refining stage. The Company has completed the testwork program for the concentrator stage with two successful pilot pant campaigns, and has now finalised a Mine and Concentrator Study.

Key Outcomes of the Mine and Concentrator Study:

The mine and concentrator (flotation circuit) will produce a high-grade REE-uranium mineral concentrate, along with zinc (6,180tpa) and fluorspar by-products (8,865tpa)
   
The REE-uranium mineral concentrate containing 14% total REO and 0.24% U3O8 will then be treated in a dedicated refinery to produce 23,000tpa of high purity mixed rare earth hydroxide, and 1.1 Mlbs U3O8
   
Significantly reduced capital costs:
     
  Overall start-up costs are now estimated at $810M
     
  The mine and concentrator capable of treating 3Mtpa is anticipated to cost $450M
     
  The refinery to produce marketable REE and U products is estimated to cost $360M
     
Unit costs of production are low; less than US$6.40/kg TREO (after by-product credits) which will make Kvanefjeld one of the lowest cost REE producers worldwide.
     
  Upon mine expansion from 3.0 Mtpa to 6.0 Mtpa, the unit cost of TREO production drops to less than US$4.90/kg TREO (after by-product credits)
     
  The incremental cost of recovering the uranium is less than US$37/lb U3O8. Following expansion to 6Mtpa the uranium unit production costs drop to less than US$31/lb U3O8. This will make Kvanefjeld one of the lowest cost uranium producers amongst projects that are being considered for development in the next 5-10 years.
     
The initial 3Mtpa Project generates a pre-tax, ungeared internal rate of return of 32% and a cash payback period of 3 years, based on long term prices of US$70/lb U3O8 and US$23/kg TREO*. The pre-tax NPV is US$1,913 M.
  (*assumes 60% value recognition in concentrate for a basket price of US$37.80)

Background

The Kvanefjeld multi-element project is ideally located in southern Greenland with direct year-round shipping access and an international airport nearby. The project is centred on the highly prospective northern Ilimaussaq Complex. To date approximately less than 20% of the prospective area has been evaluated with drill programs already unearthing a multi-element resource base of 956Mt (JORC-code compliant).

Importantly, the Company has rigorously developed a simple, highly effective process flow sheet for Kvanefjeld that presents the opportunity to develop a cost-competitive, long life and readily scalable poly-metallic mining operation. This provides the foundation for Kvanefjeld to be a cornerstone of future rare earth supply, as well as being an important source of uranium.

GMEL released a prefeasibility study on Kvanefjeld in May 2012 that presented a technically sound and economically robust mining project. Subsequent test work has continued to optimise the flowsheet, enhance metal recoveries and improve the economic metrics (Technical Update, August 2012). The process flowsheet developed for Kvanefjeld is technically advantageous in its relative simplicity. The concentrator circuit delivers a very high upgrade ratio using a single methodology, and also produces marketable zinc and fluorspar by-products. A refinery circuit then effectively extracts REEs and uranium from the mineral concentrate utilising a conventional atmospheric acid leach circuit to produce marketable rare earth and uranium products. Of significance is that the REE-U rich minerals at Kvanefjeld are non-refractory and do not require complex and costly, high temperature 'mineral cracking' that many RE-producing operations require.

The technical development for Kvanefjeld is now significantly de-risked. Test work for the concentrator circuit is complete, with two highly successful pilot plant operations. Continuous test work programs for the refining circuit have been completed, with patent applications lodged for the refining methodology developed by GMEL's technical team.

GMEL's recent focus has looked to identify the optimal means of implementing the Kvanefjeld project. As announced on February 28th, 2013, the Company has firmed up an initial start-up capacity of 3Mtpa, with a subsequent expansion to 6Mtpa, which mitigates both market and financing risk. In addition, the Company is evaluating the establishment of a dedicated refinery offshore. Investigations are currently underway into potential locations for a refinery, and discussions are advancing with potential partners interested in participating in establishing the refinery.

At 6Mtpa, Kvanefjeld will be a significant uranium producer, and one of the largest and lowest cost producers of rare earth concentrates. Notably Kvanefjeld will have significant output of both the important light and heavy REEs, including neodymium, dysprosium, terbium and yttrium.

With the Mine and Concentrator Study component of the Feasibility Study completed the Company can now finalise the Environmental and Social Impact Assessment studies and prepare an application to the Greenlandic Government for an Exploitation Licence. In the current project schedule construction is targetted to commence in 2015, with first production in 2017. The Company looks forward to working in co-operation with the newly elected Greenlandic Government to reach a successful conclusion to the planning and approvals stage of the project development.

SEE FULL ASX Announcement on site: http://www.ggg.gl/docs/ASX-announcements/Mine-and-Concentrator-study.pdf.

ABN 85 118 463 004



Greenland Minerals and Energy Ltd.
Roderick Mcillree
Managing Director
+61 8 9382 2322
www.ggg.gl
Data and Statistics for these countries : Australia | Greenland | All
Gold and Silver Prices for these countries : Australia | Greenland | All

Greenland Minerals and Energy Ltd.

EXPLORATION STAGE
CODE : GGG.AX
ISIN : AU000000GGG4
Follow and Invest
Add to watch list Add to your portfolio Add or edit a note
Add Alert Add to Watchlists Add to Portfolio Add Note
ProfileMarket
Indicators
VALUE :
Projects & res.
Press
releases
Annual
report
RISK :
Asset profile
Contact Cpy

Greenland Min. is a zinc and uranium exploration company based in Australia.

Greenland Min. holds various exploration projects in Greenland.

Its main exploration properties are KVANEFJELD and ZONE 2 in Greenland.

Greenland Min. is listed in Australia. Its market capitalisation is AU$ 56.3 millions as of today (US$ 40.6 millions, € 38.6 millions).

Its stock quote reached its highest recent level on February 18, 2011 at AU$ 1.37, and its lowest recent point on April 01, 2016 at AU$ 0.02.

Greenland Min. has 1 004 770 048 shares outstanding.

Your feedback is appreciated, please leave a comment or rate this article.
Rate : Average note :0 (0 vote) View Top rated
 
Nominations of Greenland Minerals and Energy Ltd.
2/8/2011Appoints New Commercial Manager
Financials of Greenland Minerals and Energy Ltd.
2/2/2011Quarterly Report - Q4 2010
Project news of Greenland Minerals and Energy Ltd.
10/16/2013(Kvanefjeld)Progress Environmental and Social Impact Assessments on the ...
3/26/2013(Kvanefjeld)Kvanefjeld Feasibility Study Developments: Mine and Concentr...
10/17/2012(Kvanefjeld)Acquisition of the Outstanding 39% of the Kvanefjeld Multi E...
2/23/2012(Kvanefjeld): Kvanefjeld Project-Major Technical Breakthrough: Atmospher...
12/5/2011(Kvanefjeld)Government Introduces Uranium Licensing Framework for Kvanef...
8/15/2011gains full control of world's largest rare earth project
5/3/2011(Kvanefjeld)Builds First-Class Team to Facilitate the Kvanefjeld Feasibi...
3/23/2011(Kvanefjeld)Releases an Upgraded Resource Estimate for the Kvanefjeld Mu...
2/17/2011(Zone 2)Confirms a Substantial New Rare Earth Element - Uranium Depo...
2/1/2011(Kvanefjeld)Greenland Minerals Awards Contracts for Key Social and Envir...
Corporate news of Greenland Minerals and Energy Ltd.
6/9/2016Greenland and Denmark Pass Uranium Export Legislation, Solid...
2/1/2016December 2015 Quarterly Report
1/26/2016Greenland rare earth mining to remain contentious due to ura...
1/25/2016Greenland and Denmark Reach Landmark Agreement on Uranium Ex...
10/14/2015Director Appointment
4/10/2015Notice of Annual General Meeting and Explanatory Statement
4/7/2015New Memorandum of Understanding Signed With NFC to Focus on ...
4/7/2015(Kvanefjeld)New Memorandum of Understanding Signed With NFC to Focus on ...
4/1/20152014 Annual Financial report – 20 Mar 2015
4/1/2015Outstanding 2% royalty purchase – 10 Mar 2013
4/1/2015Exploration license renewal – 1 Apr 2015
3/3/2015Company Presentation, March 2015
3/2/2015Company Presentation, March 2015
3/2/2015Update on Current Activities, Outlook and Funding
2/12/2015Kvanefjeld Project – Mineral Resource Update
12/17/2014Assay of Historic Drill Cores at Kvanefjeld Return High-Grad...
12/3/2014Greenland parties in coalition talks, mining in focus
10/23/2014Feasibility Study Progress
7/9/2014Greenland Minerals and Energy Limited: Fully Underwritten $8...
10/27/2013Repeals Zero-Tolerance Uranium Policy
7/25/2013Set for Key Role in EU-Backed Rare Earth Supply Chain Initia...
10/1/2012Completes Capital Raising and Launches Share Purchase Plan
9/25/2012GGG:ASX Bell Potter Securities Initiates Research Coverage o...
9/20/2012(Kvanefjeld)Kvanefjeld Feasibility Study Underway: Metallurgical Develop...
8/6/2012(Kvanefjeld)Finalises Full Ownership of Kvanefjeld Multi-Element Project...
7/4/2012Greenland Minerals Renames Zone 2 Rare Ear
6/6/2012(Kvanefjeld)Zone 3 Grows Kvanefjeld Project Resource Inventory to 575 Ml...
5/17/2012Shaw Stockbroking increases Greenland Minerals valuation to ...
5/4/2012(Kvanefjeld)Kvanefjeld Prefeasibility Study Confirms a Long-Life, Cost C...
4/19/2012RM Research Commences Coverage on Greenland Minerals:
4/12/2012Annual Report: Greenland Minerals and Energy And Controlled ...
3/27/2012'Zone 3' Rare Earth - Uranium Deposit Shapes Up With Solid D...
3/21/2012(Zone 2)Releases Initial 242 Million Tonne Mineral Resource Estimate...
10/6/2011Independent Investment Research - Greenland Minerals and Ene...
Comments closed
 
Latest comment posted for this article
Be the first to comment
Add your comment
AUSTRALIA (GGG.AX)
0.056+0.00%
AUSTRALIA
AU$ 0.056
01/06 10:00 -
0%
Prev close Open
0.056 0.057
Low High
0.055 0.057
Year l/h YTD var.
 -  -
52 week l/h 52 week var.
- -  0.056 -%
Volume 1 month var.
216,188 -%
24hGold TrendPower© : 34
Produces
Develops
Explores for Uranium - Zinc
 
 
 
Analyse
Interactive chart Add to compare
Interactive
chart
Print Compare Export
Last updated on : 1/16/2010
You must be logged in to use the porfolio and watchlists (free)
Top Newsreleases
MOST READ
Annual variation
DateVariationHighLow
20240.00%
2023-9.68%0.070.06
2022-25.30%0.090.05
2021-68.68%0.320.07
2020103.85%0.350.07
 
5 years chart
 
3 months chart
 
3 months volume chart
 
 
Mining Company News
Plymouth Minerals LTDPLH.AX
Plymouth Minerals Intersects Further High Grade Potash in Drilling at Banio Potash Project - Plannin
AU$ 0.12-8.00%Trend Power :
Santos(Ngas-Oil)STO.AX
announces expected non-cash impairment
AU$ 7.75+0.52%Trend Power :
Oceana Gold(Au)OGC.AX
RELEASES NEW TECHNICAL REPORT FOR THE HAILE GOLD MINE
AU$ 2.20+0.00%Trend Power :
Western Areas NL(Au-Ni-Pl)WSA.AX
Advance Notice - Full Year Results Conference Call
AU$ 3.86+0.00%Trend Power :
Canadian Zinc(Ag-Au-Cu)CZN.TO
Reports Financial Results for Q2 and Provides Project Updates
CA$ 0.12+4.55%Trend Power :
Stornoway Diamond(Gems-Au-Ur)SWY.TO
Second Quarter Results
CA$ 0.02+100.00%Trend Power :
McEwen Mining(Cu-Le-Zn)MUX
TO ACQUIRE BLACK FOX FROM PRIMERO=C2=A0
US$ 11.94+9.34%Trend Power :
Rentech(Coal-Ngas)RTK
Rentech Announces Results for Second Quarter 2017
US$ 0.20-12.28%Trend Power :
KEFIKEFI.L
Reduced Funding Requirement
GBX 0.54-2.55%Trend Power :
Lupaka Gold Corp.LPK.V
Lupaka Gold Receives First Tranche Under Amended Invicta Financing Agreement
CA$ 0.06+0.00%Trend Power :
Imperial(Ag-Au-Cu)III.TO
Closes Bridge Loan Financing
CA$ 2.69+13.03%Trend Power :
Guyana Goldfields(Cu-Zn-Pa)GUY.TO
Reports Second Quarter 2017 Results and Maintains Production Guidance
CA$ 1.84+0.00%Trend Power :
Lundin Mining(Ag-Au-Cu)LUN.TO
d Share Capital and Voting Rights for Lundin Mining
CA$ 15.60+1.83%Trend Power :
Canarc Res.(Au)CCM.TO
Canarc Reports High Grade Gold in Surface Rock Samples at Fondaway Canyon, Nevada
CA$ 0.24+0.00%Trend Power :
Havilah(Cu-Le-Zn)HAV.AX
Q A April 2017 Quarterly Report
AU$ 0.19+0.00%Trend Power :
Uranium Res.(Ur)URRE
Commences Lithium Exploration Drilling at the Columbus Basin Project
US$ 6.80-2.86%Trend Power :
Platinum Group Metals(Au-Cu-Gems)PTM.TO
Platinum Group Metals Ltd. Operational and Strategic Process ...
CA$ 1.87+5.65%Trend Power :
Devon Energy(Ngas-Oil)DVN
Announces $340 Million of Non-Core Asset Sales
US$ 52.61+0.98%Trend Power :
Precision Drilling(Oil)PD-UN.TO
Announces 2017Second Quarter Financial Results
CA$ 8.66-0.35%Trend Power :
Terramin(Ag-Au-Cu)TZN.AX
2nd Quarter Report
AU$ 0.04+0.00%Trend Power :