Brockman Resources Limited (ASX:
BRM)
ASX RELEASE
10
August 2009
Moves to Definitive Feasibility Study Following Completion of Positive Pre-Feasibility
Study at Marillana
Net Present Value Estimated to Be Up
to A$1.64 billion
4 Pre-Feasibility
Study confirms the (Marillana Project) is financially
and technically positive, positioning Brockman to become the most substantial
producer amongst the Pilbara’s emerging iron ore miners
4 Potential
NPV’s in the range from A$1.39 billion to A$1.64 billion with
accompanying internal rates of return ranging from 19.5% to 25.1% for
four alternative Project development options
4
Subject to securing
port and rail access agreements under state or federal government
regimes, production is forecasted to start in Q4 2012 at a nominal rate
of up to 17 Mtpa of 58-62% Fe beneficiated product
with a minimum mine life of 20 years
4 Upfront
capital costs estimated to range from A$705 million to A$1.35 billion
4 Total
operating costs estimated to range from A$31.50 to A$34.10 a tonne FOB
(excluding state royalties)
4 Environmental Impact Assessment on schedule with EPA approval of Scoping Document
pending
4 The
Brockman Board has endorsed the Study and approved the decision to proceed to a
Definitive Feasibility Study
Brockman Resources Limited (ASX:
BRM Brockman
or the Company) is pleased to announce the positive outcomes of the Pre-Feasibility Study (PFS) on its 100%-owned Marillana Iron Ore Project in the
Pilbara region of Western Australia.
The
Pre-Feasibility Study found that
the Net Present Value (NPV) of the Marillana Project ranges from
A$1.4 billion to A$1.64 billion using an 8% real
discount rate, with Internal
Rates of Return (IRR) ranging from
19.5% to 25.1% and capital paybacks ranging from 5 to 6 years.
Upfront capital costs are forecast to range from A$705
million to A$1.35 billion depending on different logistical, development and ore transportation options. These are based on a nominal
production rate of 17 million tonnes per annum (Mtpa).
The
Study reviewed four
principal development options for the Marillana Project with varying rail and port infrastructure logistics
and construction programs:
37.5Mtpa plant feed commencing in
2012 and utilising BHP Billiton rail and NWIOA port infrastructure (base case);
37.5Mtpa plant feed commencing in
2012 and utilising TPI rail and NWIOA port infrastructure;
37.5Mtpa plant feed commencing in
2012 and utilising TPI rail and TPI port infrastructure; and
18.75Mtpa plant feed commencing in
2012, increasing to 37.5Mtpa feed in 2015, utilising BHP Billiton rail and
NWIOA port infrastructure.
Total operating costs for the
four scenarios reviewed are forecast
to range from A$31.50 to A$34.80 a tonne on a Free on
Board (FOB) basis (excluding
state royalties). The capital and operating costs were developed to a plus or minus
25 per cent accuracy and include
all direct and indirect costs, EPCM costs, contingency and accuracy provisions.
The Pre-Feasibility
Study shows that the Marillana Project stands to be a financially rewarding project with robust
operating margins, strong
rates of return and simple mining and processing technologies, said Brockman’s Managing Director, Wayne Richards.
The findings of the Study pave the way for the execution of a Definitive Feasibility Study (DFS) to get underway later
this quarter, putting Brockman
firmly on track to become a major iron ore producer within the Pilbara, he added.
Pre-Feasibility Study Overview
The Pre-Feasibility
Study was commenced in December 2008 by Ausenco, as the principle
consultant, in consultation with specialist
service groups and sub-consultants including:
- Geology and
Resources
Coffey Mining
- Mine
Scheduling
Coffey Mining
- Processing
Plant
Ausenco
- Rail
Infrastructure
Engenium
- Metallurgy
Ammtec/Nagrom/Coffey
- Capital Cost
Estimate
Ausenco
- Operating Cost Estimate
Ausenco
- Financial
Analysis
CS Consulting
- Environmental
Ecologia
- Hydrology/Hydrogeology
Aquaterra
- Land Access/Native Title/Heritage
ACHM/PNTS
Pre-Feasibility Study Outcomes
Based on the base case total feed
rate of 37.5Mtpa (2 x 18.75Mtpa capacity front-end
plants), the Marillana Project will
be capable of producing between 17 to 20Mtpa of product
(i.e. beneficiated detritals
and/or CID fines), depending upon
the modus operandi of the two
processing plants (hereby known as the processing facility) and the overall net weight recovery of iron ore fines.
The
Study has been initially developed and modelled on the
basis of a minimum mine life of 20 years at a nominal production (output) rate of 17Mtpa.
The
Marillana Project has assumed
an average weight recovery of Run of Mine (ROM) feed of 45% and the processing facility has been designed to produce a fines only product.
All operating and capital costs
have been modelled on the basis of concurrent mining and processing of both the Channel Iron Deposit (CID) and Detrital Ore with initial production from the
mine scheduled to commence by late
2012.
Project Financials
Financial analysis of the four development options was conducted utilising price forecasts for iron ore and currency exchange
rates provided by a number
of independent international banking
and research groups.
For the purposes of conservatism, Brockman adopted a long term iron ore pricing forecast for the Study (see table below) well below recently
executed benchmark pricing agreements between Rio Tinto and
a number of Japanese and Korean steel groups of US$0.97/dry
metric tonne unit (dmtu),
and significantly below those prices currently
being achieved on the international
spot market.
The adoption of either 2009 contract or current spot prices would have an extremely positive impact on the valuation
range for the Marillana Project, as demonstrated by the table below:
|
2013 (Long Term)
BRM Forecast
|
2009 Contract Price
|
Current Spot
Price
|
Hamersley Fines (USc/dmtu) FOB
|
81.2
|
97.0
|
132.3*
|
Exchange Rates $A/$US
|
0.75
|
0.82
|
0.82
|
NPV - base case (A$M)
|
1,643
|
2,226
|
4,573
|
*Source ?
FIS Iron Ore Swap Report ? 29 July 2009
Capital costs were developed by Ausenco in accordance with their industry experience and
benchmarked against other major iron ore projects currently being undertaken
within the Pilbara district. A post-tax real discount rate of 8% has been used
in determining the NPV for the Project. The capital cost estimates are in
Q2 2009 dollars and are fully inclusive of direct and indirect costs and a 10%
contingency.
Total
upfront capital investment
in the Marillana Project is
estimated to be $997
million (base case), which represents
the total direct and indirect costs for the development of the project. This
figure includes $166 million for mine pre-strip, infrastructure and
civil works; $532 million for processing
plants, stockyards and support facilities;
and $299 million in indirect costs and contingency
The mining and processing operating
cost estimate includes all site-related costs associated with processing of two
types of ore from the ROM pad. The operating costs for haulage and shipping of
the products via rail infrastructure to stockyard and loading facilities in
Port Hedland include a capital payback charge plus the operating costs for rail
haulage, unloading and stockpiling, and ship loading. The averages of life of
mine pre-tax operating costs (excluding depreciation) were utilised in the
financial model to calculate the per unit tonne cost on a Free on Board (FOB)
basis.
Approvals
The final Environmental Scoping
Document has been submitted to the Environmental Protection Authority (EPA) and
approval is expected shortly. Preparation of the full Environmental
Impact Assessment (EIA) documentation is well advanced and is expected to be
lodged in October, 2009.
Final ethnographic and
archaeological heritage surveys are being completed over the mine and
infrastructure areas with no restrictions identified to date. The Company
expects to finalise a mining agreement with the Nyiyaparli
native title claimant group. Once this agreement is signed, the Mining
Leases can be granted. A mining agreement with the Martu
Idja Banjima people was
executed in October last year.
Resources and Mining
The Pre-Feasibility Study was based
on the existing Indicated and Inferred Mineral Resources for the Marillana Project of 1.4 billion tonnes as summarised in
Tables 1 and 2. After applying specific
Fe (> 40% Fe) and Al2O3 (<7.0%) cut off
grades, pit optimisation delivered an initial robust pit(s) containing
approximately 723Mt of DSO - CID and beneficiation feed detrital
mineralisation. The pit optimisation used conservative 27 degree (south wall)
and 37 degree (north wall) overall pit slope angles and resulted in a Waste:
Ore stripping ratio of 1.4: 1. Mining was assumed to be performed by
conventional truck and shovel open pit mining methods, and a contract mining
fleet/operation was valued in the financial
model.
Table 1 Beneficiation Feed Mineral
Resource Summary (Cut-off grade: 40% Fe)
Marillana Deposit All Zones
|
Tonnes
(Mt)
|
Grade
(% Fe)
|
Total Indicated Resources
|
551
|
44.6
|
Total Inferred Resources
|
773
|
42.2
|
TOTAL INDICATED AND INFERRED
MINERAL RESOURCES
|
1325
|
43.2
|
Table 2 Marillana
Project Direct-Shipping Mineral Resource Summary (Cut-off grade: 54% Fe)
DSO CID Mineralisation
? All Zones
|
Tonnes
(Mt)
|
Fe
(%)
|
Fe-Cal
(%)
|
Al2O3
(%)
|
SiO2
(%)
|
P
(%)
|
LOI
(%)
|
Indicated Mineral Resources
|
54.2
|
57.4
|
63.0
|
3.6
|
4.0
|
0.086
|
8.91
|
Inferred Mineral Resources
|
13.6
|
56.1
|
62.8
|
3.0
|
4.7
|
0.133
|
10.64
|
TOTAL INDICATED AND INFERRED
MINERAL RESOURCES ? DSO
|
67.8
|
57.1
|
62.9
|
3.4
|
4.1
|
0.095
|
9.25
|
Fe-Cal represents calcined Fe and is calculated by Brockman using the formula
Fe(Cal) = Fe% / ((100-LOI)/100)
Processing
The Pre-Feasibility Study model is
based on a nominal 37.5Mtpa processing facility consisting of twin primary
crushing stations located along strike at the North West and South Eastern
extremities of the proposed initial pits. The crushing stations transfer ore to
the beneficiation plants utilising standard gravity separation methodology to
yield approximately 17Mtpa of beneficiated iron ore fines product.
The mining schedule identifies that
a significant volume of Detrital Ore will be mined
before CID can be accessed, resulting in a number of years where only Detrital Ore will be processed. CID production will
vary between 2Mtpa and 5Mtpa once the CID mineralisation has been
accessed. Detritals and CID will be processed
as fines only (-8mm) products, with the CID material being processed on a
campaign basis. When either of the beneficiation plants are processing CID Ore, certain sections of the plant will
be shut-down, and the recovery rate of the CID will be as high as 100% of the
feed rate. For the purpose of the study, a conservative recovery rate of 90%
was assumed for all CID feed to the Plant(s).
Inert waste rock and fines generated
from mining and processing operations will be placed back in the pit via mine
backfilling operations from year seven of the operation. In addition to
beneficiated detrital ore, the study has initially
been developed on the basis of generating in excess of 40 million tonnes of CID
fines from year five of the proposed mining schedule.
Recent laboratory metallurgical
beneficiation test work on samples of Marillana detrital iron ore, reflective of the head grades and
cut-off parameters incorporated into the project design criteria, produced the
following results and specification ranges for iron fines:
Table 3 - Post-Beneficiation Iron
Fines Quality Parameters
Fe%
|
SiO2 %
|
Al2O3 %
|
P%
|
S%
|
%LOI1000
|
58.3 - 62.1
|
3.6 - 9.9
|
2.7 - 3.2
|
0.05 - 0.09
|
0.01 - 0.02
|
2.6 - 3.2
|
These results are based on heavy
liquid separations and tabling results. Further metallurgical work is
currently in progress to upgrade the detrital ore
resource classification (Inferred/Indicated to Indicated/Measured), verify
metallurgical variability across the mineralised zones and establish the final
process flow sheet option for use in the definitive pit optimisation and
process plant equipment selection.
Development Schedule
The development of the Marillana Project will be via a conventional mining and
processing operation with a nominal production output of up to 17Mtpa over a
minimum period of 20 years.
The operating philosophy includes
the flexibility of both ROM and stockyard blending. A stacking and
reclaiming operation will be utilised to load trains via a dedicated rail loop
servicing the stock yard. Beneficiated iron ore will then be transported from
the Marillana site to a Port Hedland Port Facility by
rail for subsequent ship loading and transport to overseas customers.
The
preliminary Project implementation
plan has been developed with
the key milestones identified as follows:
- Commencement of
DFS
Q3, 2009
- Completion of
DFS
Q3, 2010
- Brockman project
funding approval
Q4, 2010
- Final Public Environmental Review (PER) approval
Q4, 2010
- Commence
Construction
Q1, 2011
- Operations
commence
Q4, 2012
With first production scheduled
for the end of 2012, Brockman is
now focused on upgrading the resource classification,
verifying metallurgical variability and establishing rail
and port infrastructure operating terms and
conditions. These activities
will be the main focus for
the project team over the forthcoming
quarters and will support
the Definitive Feasibility Study.
Infrastructure
There
are two primary options considered for rail haulage in
the Pre-Feasibility Study. These are either the construction of a rail loading
loop on the Marillana site connected to BHP Billiton rail infrastructure or the
construction of a 110km spur line (including a site rail loop) connected to FMG (TPI) rail infrastructure at a point north of the
Chichester ranges and approximately 150km south-west of Port Hedland.
Brockman is actively pursuing access
to appropriate rail services. Options being pursued include both above rail
access and haulage services.
The
technical and cost analysis of these two options supports the potential
to transport the Marillana production output via existing third party rail
infrastructure to Port Hedland. An estimate of rail haulage
operating and capital costs has been included in the project operating
costs.
Brockman, as a founding
member of the North West Iron Ore Alliance (NWIOA), is engaged in the completion of a Pre-feasibility Study for the development of the
multi-user iron ore export facilities
at South West Creek within
the inner-harbour of Port Hedland. These two berths within
the south west creek have
been allocated to the NWIOA (and other
iron ore juniors) by the Port Hedland
Port Authority. The recent
NWIOA Scoping Study identified the potential capital cost for the development of the
port facilities, including
a rail unloading facility, stockyards and shiploading berths. An estimate of the
port facility’s capital and operating costs per tonne FOB has been factored
into the Marillana project’s operating costs
The
development of the port berths
and unloading/stockpile facilities will ensure the end-to-end delivery of
the ore from the Marillana
mine to the ship and complement
the growth potential of the
Marillana Project and Brockman
Resources.
Brockman’s Board has endorsed
the results of the PFS and the Company will now proceed with a full Definitive
Feasibility Study. Initial scoping and tender preparation will commence
later this quarter, ensuring there will be ongoing rapid progress in the
development of the Pilbara’s next major iron ore producer. The DFS
is expected to be completed in the third quarter of 2010.
Wayne Richards
Managing Director
ENDS
Released by:
Nicholas Read
Read Corporate
Phone: +61 8 9388 1474
|
On behalf of:
Wayne Richards
Managing Director
Brockman Resources
Phone: +61 8 9389 3000
|
Competent Person’s Statement
The information in this report that
relates to Mineral Resources east of local grid 13000 East based on information
compiled by Mr Iain Macfarlane and Mr Alex Virisheff,
who are full time employees of Coffey Mining Pty Ltd and are Members of the
Australasian Institute of Mining and Metallurgy. Iain Macfarlane and Alex
Virisheff have sufficient experience relevant to the
style of mineralisation and type of deposit under consideration and to the
activity which they are undertaking to qualify as Competent Persons as defined
in the 2004 Edition of the Australasian Code for Reporting of Mineral resources
and Reserves. Iain Macfarlane and Alex Virisheff
consent to the inclusion in the report of the matters based on the information
in the form and context in which it appears.
The information in this report that
relates to Mineral Resources at North-West Sector and Rockhole Bore (west of
local grid 13000 East) is based on information compiled by Mr M Nimmo and Mr A Zhang.
Mr M Nimmo,
who is a Member of the Australasian Institute of Geoscientists and a full-time
employee of Snowden Mining Industry Consultants Pty Ltd, produced the Mineral
Resource estimates for the North-West Sector and Rockhole Bore deposits based
on the data and geological interpretations provided by Brockman. Mr Nimmo has sufficient experience that is relevant to the
style of mineralisation, type of deposit under consideration and to the
activity that he is undertaking to qualify as a Competent Person as defined in
the 2004 edition of the ?Australasian Code for Reporting of Exploration,
Results, Mineral Resource and Ore Reserves. Mr Nimmo
consents to the inclusion in this report of the matters based on his
information in the form and context that the information appears.
Mr A Zhang, who is a Member of the
Australasian Institute of Mining and Metallurgy and a full-time employee of
Brockman Resources Limited, provided the geological interpretations and the drillhole data used for the Mineral Resource
estimation. Mr Zhang has sufficient experience that is relevant to the
style of mineralisation, type of deposit under consideration and to the
activity that he is undertaking to qualify as a Competent Person as defined in
the 2004 edition of the ?Australasian Code for Reporting of Exploration, Results,
Mineral Resource and Ore Reserves. Mr Zhang consents to the inclusion in
this report of the matters based on his information in the form and context
that the information
appears.
The information in this report that
relates to mineralisation and exploration results is based on information
compiled by Mr Colin Paterson, who is a Member of the Australian Institute of
Geoscientists. Mr Paterson is a full time employee of Brockman Resources Ltd
and has sufficient experience which is relevant to the style of mineralisation
and type of deposit under consideration and to the activity which he is
undertaking to qualify as a Competent Person as defined in the 2004 edition of the ?Australasian Code for Reporting of Exploration Results,
Mineral Resources and Ore Reserves?. Mr Paterson consents to the inclusion in
the report of the matters based on his information in the form and context in
which it appears.