Nevada Copper Project Update

VANCOUVER, BRITISH COLUMBIA--(Marketwired - Nov 4, 2014) - Nevada Copper Corp. (NCU.TO) ("Nevada Copper" or the "Company") is pleased to provide an update on its 100% owned Pumpkin Hollow Copper Project ("the Project"), located near Yerington, Nevada. The update focusses on production shaft progress, the Stage 2 open pit optimization, the Land Bill and project financing.

Highlights

  • The production shaft is at a current depth of 1,475 feet: over 77% completed towards the main 1906 foot haulage level;
  • Access to the 1906 haulage level for lateral development expected in Q1-2015;
  • Sinking rates increased to a rate of 6-7 feet per day;
  • Stage 2 Open Pit optimization and updated feasibility study commenced with a target date for release of Q1-2015; and,
  • Land Bill unanimously passed in the House of Representatives with passage expected in the Senate.

Giulio Bonifacio, President and CEO, stated: "We continue to make substantial progress in our key focus areas of shaft sinking, open pit optimization, permitting and financing. Our decision to temporarily reduce non-shaft sinking expenditures has allowed us the time to fully optimize and consider the funding mix for the balance of Stage 1 project capital. We have also continued to review the Stage 2 open pit project data with a view toward optimization, and now have sufficient encouragement to move forward with the completion of an updated and optimized feasibility study for Stage 2. The updated feasibility study will also incorporate a further 32,000 feet of drilling completed since the last published mineral resource estimate in 2012.

On the Land Bill we recently saw passage of our Bill in the House of Representatives which is the most significant milestone to date and we are optimistic that passage of the Land Bill in the Senate may occur before year end. We have been advised that this remains one of the top priorities of Senator Heller (R-NV) and Senate Majority Leader Harry Reid (D-NV)."

Stage 1 Main Shaft Progress

The circular 24-foot diameter concrete-lined production shaft is currently at the 1,475 foot level - over 77% of the way towards the main 1906 haulage level. Since April 1, 2014, 804 feet of shaft have been sunk. During this time period a mid-shaft pump station was also excavated at the 960 level. The shaft continues to progress through dry ground with water inflows controlled by two fully-commissioned dewatering wells.

The 1906 foot haulage level is expected to be reached in January 2015 at which point lateral development will commence to provide setup locations for development drilling as well as access to the East ore zones. The last drilling in the East deposit was completed from surface in 2010, with the deposit remaining open in several directions. The planned underground drill program will focus on enlarging the high grade zones within the current reserve and will provide additional data for mine development designs while expanding the open mineralized areas.

Stage 2 Open Pit Engineering and Feasibility Study Update

After the Stage 2 Open Pit Feasibility Study was completed in 2013, results from 9,880 meters (32,414 feet) of additional drilling on the North Deposit were received. In Q2-2014, the Company decided to incorporate these drill results and ascertain if the data would improve the present mine design. In particular, drill hole NC12-34 as previously disclosed in a news release dated September, 13, 2012, on the southwestern edge of the North Deposit ultimate pit intersected 690 feet (210.3 meters), 625.3 feet (190.6 meters) true thickness, grading 1.17% copper, including 150 feet grading 3.8% (The North-South cross section and open pit perspective is available at http://www.nevadacopper.com/i/maps/2014-11-04_NRMB_L8bHsX.jpg). Another drill hole, NC13-05, disclosed in a news release dated June 17, 2013, along the western edge of the North deposit and not included in the 2013 Feasibility Study, intersected several zones including 125 feet (38.1 meters), true thickness, grading 1.45% copper.

The new information resulted in an opportunity to significantly improve the grade profile and reduce mine waste rock quantities by re-evaluating the pit shell in the North Deposit. Preliminary work to date on the mineral resource calculations and production schedule has demonstrated extremely positive results with respect to the copper grades and copper production in the early years, as well as overall life-of-mine copper grades. Management believes that the positive initial results support completion of an updated and optimized feasibility study for the Stage 2 open pit operation. The updated feasibility study will incorporate the new and updated technical and cost information on the Stage 2 project. The results of this updated Feasibility Study are targeted for release in Q1-2015.

Readers are cautioned that until the updated feasibility study is completed, the implications of the copper grade, production increases and cost updates on the Project, including the impact on Project economics, cannot be fully determined.

Land Bill Status

As previously announced on September 16, 2014, the U.S. House of Representatives unanimously passed H.R. 5205, the Northern Nevada Land Conservation and Economic Development Act. That bill includes the Lyon County Economic Development and Conservation Act ("the Bill"). With this major milestone having been reached, attention is focused on passage of the equivalent Bill in the Senate. Senate Majority Leader Harry Reid (D-NV) and Senator Dean Heller (R-NV) co-sponsored the legislation in the Senate and it passed unanimously in the Senate Energy and Natural Resources Committee on a bi-partisan basis in June 2013. Local and state officials are now urging quick passage in the full Senate, considering that the Bill is non-controversial, has overwhelming public support and would have major economic benefits in one of the most economically stressed communities in Nevada and the nation. Therefore management and their advisors believe that the Bill will pass in the Senate after the mid-term US elections on November 4, 2014 and before the end of the 113th Congress at year-end.

Once signed into law by President Obama, the legislation requires that the land acquisition must be completed by the Bureau of Land Management within six months. During this period, Nevada Copper would work to complete the remaining Stage 2 State permitting, setting the stage for issuance of all key Stage 2 permits by Q2-2015.

Financing Update

Nevada Copper has a current cash balance of US$15.3 million. The Company also has an undrawn US$10 million balance of its US$20 million credit facility with Pala Investments (see the August 26, 2014 news release), plus US$149 million remaining as the undrawn portion of its Red Kite/Orion secured loan facility (see the March 28, 2013 news release). The final draw of the latter loan facility is subject to certain conditions, including completion of the shaft and arrangement of the balance of funding of Stage 1 project capital. Nevada Copper also has an available US$24 million Caterpillar Financial equipment lease finance facility available for mobile equipment purchases.

The Company continues to advance several project financing opportunities. These include additional debt, precious metal streams, joint ventures and off-take structures to provide the remaining funding for both Stage 1 and Stage 2. Multiple proposals have been received for the Stage 1 underground financing, and potential transactions are currently being discussed and advanced. Completion of Stage 1 funding is targeted by Q1-2015.

About Nevada Copper

The Company's advanced stage Pumpkin Hollow project in Nevada consists of a fully permitted, 6,500 tons/day Stage 1 underground copper mine development, currently in construction, and a nearby Stage 2, 70,000 tons/day open pit mine copper project in the advanced permitting phase. Expected average copper production for the first five years is 75 million lbs./year from the Stage 1 underground mine, and 221 million lbs./year from the Stage 2 open pit mine. The project is located near Yerington, Nevada, close to road, rail, and power infrastructure, and with all future water supply requirements met.

For further information please visit the Nevada Copper corporate website (www.nevadacopper.com) and the Pumpkin Hollow project website (www.pumpkinhollowcopper.com).

Qualified Persons

The technical information in this release has been reviewed and approved by Gregory French, P.G., Vice-President, Exploration & Project Development, Timothy Arnold, P.E., Vice President Operations, and Robert McKnight, P. Eng., Executive Vice-President and CFO of Nevada Copper, all of whom are Non-independent Qualified Persons within the meaning of NI 43-101.

NEVADA COPPER CORP.

Giulio T. Bonifacio, President & CEO

We seek safe harbour.

Read the rest of the article at finance.yahoo.com

Nevada Copper

DEVELOPMENT STAGE
CODE : NCU.TO
ISIN : CA64128F1099
CUSIP : 64128F
Follow and Invest
Add to watch list Add to your portfolio Add or edit a note
Add Alert Add to Watchlists Add to Portfolio Add Note
ProfileMarket
Indicators
VALUE :
Projects & res.
Press
releases
Annual
report
RISK :
Asset profile
Contact Cpy

Nevada Copper is a copper exploration company based in Canada.

Nevada Copper develops copper, gold, iron and silver in USA.

Its main asset in development is PUMPKIN HOLLOW in USA.

Nevada Copper is listed in Canada and in Germany. Its market capitalisation is CA$ 7.9 millions as of today (US$ 5.8 millions, € 5.4 millions).

Its stock quote reached its highest recent level on April 08, 2011 at CA$ 6.42, and its lowest recent point on November 06, 2020 at CA$ 0.06.

Nevada Copper has 88 170 000 shares outstanding.

Your feedback is appreciated, please leave a comment or rate this article.
Rate : Average note :0 (0 vote) View Top rated
 
In the News and Medias of Nevada Copper
5/9/2019Nevada Copper inks $115m deal to construct Pumpkin Hollow
8/31/2018Nevada Copper shares jump on construction decision
5/16/2018Nevada copper provides positive update on drill program: int...
Financings of Nevada Copper
4/19/2016Amends Red Kite and Pala Loan Terms
4/27/2010Closes $23,7 Million Bough-Deal Private Placement Financing
4/9/2010$20.6 Million Bought-Deal Private Placement Financement
10/27/2009$11,250,000 Private Placement with Capstone Mining Corp.
Nominations of Nevada Copper
8/8/2013Appoints Director
2/28/2012Appoints New Director and Launches Project Website
Project news of Nevada Copper
9/9/2013Receives All Permits For Stage 1 Underground Mine
7/28/2011(Pumpkin Hollow)Obtains 100% of Water Needs for the Pumpkin Hollow Project
4/28/2011(Pumpkin Hollow)Provides Update on Feasibility Study & Engages Merit for Pre...
4/12/2011INTERSECTS 415 FEET OF 1.84% COPPER
3/31/2011(Pumpkin Hollow)s Mineral Resource Estimate and Clarifies Technical Disclosu...
2/8/2011S FEASIBILITY STUDY PROGRESS
8/4/2010(Pumpkin Hollow)Intersects 230 Feet of 1.46% Copper in The Open Pittable Nor...
7/8/2010(Pumpkin Hollow)E2 Deposit Drilling Intersects 145 Feet of 2.37% Copper and ...
6/16/2010(Pumpkin Hollow)Mineralization Remains Open at North Deposit: Intersecting 9...
5/27/2010(Pumpkin Hollow)Increases Drilling Program
5/18/2010(Pumpkin Hollow)Discovers Two New Zones Intersecting 275 Feet of 0.98% Coppe...
5/6/2010(Pumpkin Hollow)Step Out Drilling Expands the Open Pittable North Deposit: I...
4/23/2010(Pumpkin Hollow)Drills Over 650 Feet Of Greater Than 0.70% Copper In Three S...
2/16/2010(Pumpkin Hollow)Continues to Intersect High Grade Copper
1/21/2010(Pumpkin Hollow)Intersects 31.1 Meters of 2.45% Copper
1/14/2010Files NI 43-101 Preliminary Economic Assessment
12/8/2009(Pumpkin Hollow)Commences Pre-Feasibility & 25,000 Meter Drilling Program
8/25/2009(Pumpkin Hollow)Files resource update NI 43-101 on Sedar
7/15/2009(Pumpkin Hollow)Reports Significant Resource Increase to 9.3 Billion Pounds ...
Corporate news of Nevada Copper
6/9/2016Nevada Copper Closes Cdn$4.6 Million Equity Offering
6/3/2016Nevada Copper Closes Cdn$ 10.5 Million Financing With Red Ki...
6/1/2016Nevada Copper Solar Zoning Approved
5/27/2016Nevada Copper Annual Meeting Results
5/27/2016Nevada Copper Announces Red Kite Funding Commitment And Equi...
5/3/2016Nevada Copper and City of Yerington Advance Solar Zoning
4/22/2016Nevada Copper Announces Filing Of Amended Prospectus And Exe...
4/5/2016Nevada Copper Amends Red Kite and Pala Loan Terms
1/28/2016Nevada Copper Appoints Directors
11/3/2015Nevada Copper Intersects 105 Feet of 2.55% Copper in the Eas...
10/13/2015Nevada Copper Acquires Private Land & Completes Federal Land...
9/30/2015Nevada Copper Provides Corporate and Project Update
9/10/2015Nevada Copper Intersects 462 Feet of 0.64% Copper
8/21/2015IIROC Trade Resumption - NCU
8/21/2015Federal Land Conveyance Complete at Nevada Copper's Pumpkin ...
8/20/2015IIROC Trading Halt - NCU
8/17/2015Nevada Copper Fully Permitted
7/31/2015Nevada Copper Extends and Increases Bridge Loan Facility
7/31/2015Nevada Copper Receives Air Pollution Control Permit
7/17/2015Nevada Copper Receives Decision Record on Yerington Land Con...
7/15/2015Nevada Copper Intersects 448 Feet Grading 1.0% Copper
7/9/2015Nevada Copper Files Integrated Feasability Study on SEDAR
6/29/2015Nevada Copper Election of New Director and Annual Meeting Re...
6/24/2015Nevada Copper Continues to Expand Open Pit Mineralization In...
4/23/2015Nevada Copper Pumpkin Hollow Project Update
2/10/2015Nevada Copper Pumpkin Hollow Project Update
12/30/2014Nevada Copper Closes US$200 Million Loan Facility
12/22/2014President Signs National Defense Authorization Act That Incl...
12/3/2014Nevada Copper Project Update
11/4/2014Nevada Copper Project Update
7/30/2014Nevada Copper Advances Lyon County Bill
7/16/2014Nevada Copper Provides 2014 Update
7/2/2014Nevada Copper Provides Update & AGM Results
5/12/2014Nevada Copper Update on Lyon County Land Bill
1/23/2014NCU - Nevada Copper featured on KTVN - Channel 2 News
10/28/2013Announces Management Additions
10/9/2013Receives Additional US$15 Million Under Its US$200 Million S...
10/1/2013Announces $24 Million Equipment Financing
8/26/2013Receives Water Pollution Control Permit
7/16/2013Remaining Stage One Permits Issued for Public Comment
6/25/2013Receives Special Use Permit and Provides Update on Land Bill
6/17/2013North Deposit Drilling Intersects Multiple Zones of Minerali...
6/10/2013Receives Reclamation Permit
5/28/2013Provides Update on State Permits
5/7/2013s Lyon County Bill Status
4/23/2013(Pumpkin Hollow)to Proceed With Two-Stage Approach to Building Pumpkin Hollo...
4/17/2013s Permitting and Yerington Land Bill Status
4/17/2013s Permitting and Yerington Land Bill Status
3/28/2013Closes US$200 Million Loan Facility and Concentrate Off-Take...
3/11/2013North Deposit Mineralization Continues to Expand Intersectin...
2/15/2013-Permitting and Feasibility Study Update
1/3/2013Status of Congressional Action-Lyon County Land Bill
10/30/2012North Deposit Mineralization Remains Open Intersecting 119 F...
10/19/2012Files Resource Update NI 43-101 Technical Report on SEDAR
10/5/2012to Purchase 17.8% of Mercator Minerals
9/5/2012Governor Sandoval's Trade Mission to China and South Korea
8/9/2012Drilling Continues to Expand Shallow Mineralization in the S...
7/10/2012Submits Mine Development Permit Applications and Announces D...
6/20/2012-Project Update/Land Bill Passed by the House
6/5/2012s Permitting and Yerington Land Conveyance
5/29/2012Intersects 470 Feet at 0.73% Copper in the North Deposit
4/19/2012Provides an Update on House Subcommitee Hearing on Yerington...
4/10/2012Mineralization Continues to Expand in the North Deposit; Lan...
3/26/2012Announces Introduction of Land Conveyance Bill in the United...
3/13/2012Intersects 9.08% Copper in Open Pittable North Deposit
2/27/2012Appoints New Director & Launches Project Website
2/22/2012Breaks Ground on Underground Shaft
2/16/2012Announces Introduction Of Yerington Land Conveyance Bill
2/7/2012Files Feasibility Study on SEDAR
1/23/2012Announces Positive Feasibility Study Results
1/17/2012(Pumpkin Hollow)Hosts Conference Call to Discuss Pumpkin Hollow Definitive F...
1/9/2012North Deposit Continues to Expand-NC1127 Intersects Minerali...
12/16/2011Announces Selection of Underground Contractor
11/29/2011Coppper-Update on Underground Contractor Selection & Feasibi...
9/29/2011Annnounces Management Addition and Shaft Contract Update
9/19/2011-Feasibility Study Update and Land Transfer
9/7/2011Mineralization Continues to Expand, Intersecting Over 600 Fe...
8/16/2011North Deposit Continues to Expand, Drilling Multiple Interva...
6/14/2011Expands North Deposit Intersecting 785 Feet of 0.73% Copper ...
5/25/2011Steps Out and Drills 126 Feet of 1.26% Copper/Definitive Fea...
5/3/2011(Pumpkin Hollow)Intersects 1,164 Feet of 0.49% Copper in the Pumpkin Hollow ...
12/1/2009Robust Economic Results
12/1/2009Reports robust economic results
11/3/2009Capstone Mining Makes Strategic Investment in Nevada Copper
6/29/2009US$2,000,000 Convertible Debenture
5/2/2007Press Release: Augusta Files Q1 Financials - Negotiates Sale...
Comments closed
 
Latest comment posted for this article
Be the first to comment
Add your comment
TORONTO (NCU.TO)FRANKFURT (ZYT.F)
0.090+0.00%0.045-4.26%
TORONTO
CA$ 0.090
04/26 16:59 -
0%
Prev close Open
0.090 0.090
Low High
0.085 0.090
Year l/h YTD var.
0.060 -  0.140 -35.71%
52 week l/h 52 week var.
0.060 -  0.345 -74.65%
Volume 1 month var.
324,008 -10.00%
24hGold TrendPower© : 20
Produces
Develops Copper - Gold - Silver
Explores for
 
 
 
Analyse
Interactive chart Add to compare
Interactive
chart
Print Compare Export
Last updated on : 3/23/2010
You must be logged in to use the porfolio and watchlists (free)
Top Newsreleases
MOST READ
Annual variation
DateVariationHighLow
2024-40.00%
2023-48.28%0.420.14
2022-53.23%0.790.20
2021327.59%1.220.07
2020-60.27%0.380.06
 
5 years chart
 
3 months chart
 
3 months volume chart
 
 
Mining Company News
Plymouth Minerals LTDPLH.AX
Plymouth Minerals Intersects Further High Grade Potash in Drilling at Banio Potash Project - Plannin
AU$ 0.12-8.00%Trend Power :
Santos(Ngas-Oil)STO.AX
announces expected non-cash impairment
AU$ 7.70-0.65%Trend Power :
Oceana Gold(Au)OGC.AX
RELEASES NEW TECHNICAL REPORT FOR THE HAILE GOLD MINE
AU$ 2.20+0.00%Trend Power :
Western Areas NL(Au-Ni-Pl)WSA.AX
Advance Notice - Full Year Results Conference Call
AU$ 3.86+0.00%Trend Power :
Canadian Zinc(Ag-Au-Cu)CZN.TO
Reports Financial Results for Q2 and Provides Project Updates
CA$ 0.12+4.55%Trend Power :
Stornoway Diamond(Gems-Au-Ur)SWY.TO
Second Quarter Results
CA$ 0.02+100.00%Trend Power :
McEwen Mining(Cu-Le-Zn)MUX
TO ACQUIRE BLACK FOX FROM PRIMERO=C2=A0
US$ 12.26+2.68%Trend Power :
Rentech(Coal-Ngas)RTK
Rentech Announces Results for Second Quarter 2017
US$ 0.20-12.28%Trend Power :
KEFIKEFI.L
Reduced Funding Requirement
GBX 0.53-1.87%Trend Power :
Lupaka Gold Corp.LPK.V
Lupaka Gold Receives First Tranche Under Amended Invicta Financing Agreement
CA$ 0.06+0.00%Trend Power :
Imperial(Ag-Au-Cu)III.TO
Closes Bridge Loan Financing
CA$ 2.64-1.86%Trend Power :
Guyana Goldfields(Cu-Zn-Pa)GUY.TO
Reports Second Quarter 2017 Results and Maintains Production Guidance
CA$ 1.84+0.00%Trend Power :
Lundin Mining(Ag-Au-Cu)LUN.TO
d Share Capital and Voting Rights for Lundin Mining
CA$ 16.23+4.04%Trend Power :
Canarc Res.(Au)CCM.TO
Canarc Reports High Grade Gold in Surface Rock Samples at Fondaway Canyon, Nevada
CA$ 0.24+4.26%Trend Power :
Havilah(Cu-Le-Zn)HAV.AX
Q A April 2017 Quarterly Report
AU$ 0.20+2.63%Trend Power :
Uranium Res.(Ur)URRE
Commences Lithium Exploration Drilling at the Columbus Basin Project
US$ 6.80-2.86%Trend Power :
Platinum Group Metals(Au-Cu-Gems)PTM.TO
Platinum Group Metals Ltd. Operational and Strategic Process ...
CA$ 1.88+0.53%Trend Power :
Devon Energy(Ngas-Oil)DVN
Announces $340 Million of Non-Core Asset Sales
US$ 52.71+0.19%Trend Power :
Precision Drilling(Oil)PD-UN.TO
Announces 2017Second Quarter Financial Results
CA$ 8.66-0.35%Trend Power :
Terramin(Ag-Au-Cu)TZN.AX
2nd Quarter Report
AU$ 0.04+5.56%Trend Power :