Orocobre Limited: Quarterly Report of Operations for the Period Ended 31 December 2011
Published : January 31, 2012
( 0 vote, 0/5 ) Print article
  Article Comments Comment this article Rating Follow Company  
0
Send
0
comment

BRISBANE, AUSTRALIA--(Marketwire - Jan. 31, 2012) - Orocobre Limited (News - Market indicators)(ASX:ORE) -

HIGHLIGHTS AND SIGNIFICANT DEVELOPMENTS

Salar de Olaroz Lithium-Potash Project: 

  • Completion of management negotiations on investment terms of Toyota Tsusho Corp. Ltd., Mizuho Corporate Bank mandated as lead arranger for debt component of project
  • Pumping tests and 3-D modelling suggest possible expansions beyond 16,400 tpa of battery grade lithium carbonate.
  • Orocobre and its engineering partner, Sinclair Knight Merz, focused on detailed engineering and procurement to allow construction to commence in early 2Q 2012.

Salar de Cauchari Lithium-Potash Project: 

  • Six hole exploratory drilling program completed yielding encouraging results
  • Brine body expected to allow integration with planned Olaroz lithium carbonate production facility. 

Salinas Grandes Lithium-Potash Project: 

  • Grid auger drilling program completed - provides key resource modelling data 

Corporate 

  • Strong cash position of A$27.7 million at end of the quarter. 

Salar De Olaroz Lithium-Potash Project 

The Olaroz Project is Orocobre's flagship project located in Jujuy province of Argentina, on which a definitive Feasibility Study for a 16,400 tonnes per annum battery-grade lithium carbonate operation was completed earlier in 2011.

During the quarter, the company has made substantial progress on key activities required to commence construction of commercial operations at the Olaroz Lithium-Potash project in northwest Argentina including completion of management negotiations on investment term of Toyota Tsusho Corporation Ltd, debt financing arrangements with Mizuho Corporate Bank Ltd and Japan Oil, Gas and Metals National Corporation (JOGMEC) and advancement of the project's approval process with the Provincial Government of Jujuy, Argentina. In addition, the detailed engineering design and procurement process has advanced including the ordering of critical path items.

Project Financing

Orocobre and Toyota Tsusho mandated Mizuho Corporate Bank Ltd as lead arranger for the debt component of the project development. This is expected to be for 60% of the capital cost which was estimated in the feasibility study at US$207 million. The facility is planned to be guaranteed by JOGMEC. 

The company has also completed management negotiations with Toyota Tsusho Corporation regarding the terms of its investment and for the project financing arrangements together with associated shareholders' and marketing agreements. The process has now moved to the drafting of definitive agreements and finalization of financing and subsequent investment approval process for both companies. Funding is contingent on the completion of all definitive agreements, Mizuho and JOGMEC's approval of project loans and guarantees respectively, the finalization of bank loan documents and final investment approval by Toyota Tsusho Corporation and Orocobre.

Orocobre expects project financing agreements to be completed by the end of February 2012 and construction to commence in the second quarter of 2012 subject to receiving final Jujuy provincial government approval.

Final Provincial Government Approval

As of December 10th, the new administration of Governor Eduardo Fellner has assumed control of the provincial government. Gabriel Romanosky has been appointed Production Minster and is responsible for the function of the Committee of Experts and approval. With changes in place, the Company now enters what management expects will be the final phase of approval for the project with the Jujuy government. While it is difficult to predict the exact timing, we remain optimistic that this approval will materialize within a timeframe that correlates with the completion of key financing agreements. Assuming the likely completion of these financing and governmental agreements, the company remains on track to commence construction early in the second quarter of 2012.

Olaroz Long-term Pumping Tests and 3-D Model Simulations

Subsequent to the end of the quarter, on January 24th, the Company announced preliminary results of a long-term pumping test on the Olaroz salar. The pumping test was located in the area of the proposed extraction well field. The well produced consistently high grade brine throughout the test, with average lithium concentrations of 875±10 mg/L, 22% higher than the adjacent Diamond drill hole used in the resource estimate that gave 717±80 mg/L Li. The test has run for over three months at a flow rate of 14 litres per second. Interpretation of the data suggests that preferential flow is taking place to the well from specific geological units, where the permeability and grade are higher. The information obtained will allow these specific units to be targeted during production. The flow rate was limited by the capacity of the pump, not by the well or aquifer, so that under production conditions average well flow rates may be expected to be significantly better than the design of 15 litres per second.

The results from the long-term pumping test - together with the data on aquifer geometry, permeability, porosity, groundwater pressures, brine compositions, as well as the water balance incorporating rainfall and surface water inputs and evaporation outputs obtained during the earlier drilling and testing phase - are being used by company consultant Dr. Noel Merrick to build and calibrate a 3-D finite difference model of fluid flow and solute transport that incorporates the known variation in fluid density across the salar. The model is being built using the well-known and validated USGS Modflow-Surfact Version 4, which is at the cutting edge for this task. Dr. Merrick is a former associate professor at the National Centre for Groundwater Management at the University of Technology in Sydney.

The preliminary results from the model indicate that the cone of depression resulting from the well field pumping will be limited in extent, and the grade will decline only slowly over the project life, well within the capacity of the solar ponds to ensure a consistent feed to the plant. The model will be used to forecast and control production throughout the project life, as well as to investigate potential production increases.

Management is confident that the proposed well field design will deliver the initial annual production rate of 16,400 tonnes of battery grade lithium carbonate as outlined in the Olaroz project definitive feasibility study. The slow predicted declines in grade coupled with excellent flow rates, suggest the possibility of future project expansions.

Project Engineering Update

Orocobre and its engineering partner, Sinclair Knight Merz (SKM), continued during the quarter to focus on key detailed project engineering and procurement issues to allow construction to commence at Olaroz in the second quarter of 2012 subject to financing and governmental approvals. In addition, the company has ordered certain critical path items for the operation. Earlier, in August 2011, the Company awarded the Olaroz Project's detailed engineering contract to Sinclair Knight Merz ("SKM"), a large international engineering projects firm. SKM has been involved in the Olaroz Project for over a year and previously completed the engineering and capital and operating cost estimates for the Feasibility Study. SKM has significant lithium-potash industry experience. It is the only company that has ever designed and managed the construction of a complete lithium brine operation, at FMC's Salar de Hombre Muerto facility in Argentina.

Further information on the Company's activities at The Olaroz project is given in the Company's news releases of 28th December 2011 and 25th January 2012.

Salar de Cauchari Project Results from Drilling Exploratory Wells (Orocobre 85%)

Subsequent to the end of the quarter, on January 25th, Orocobre announced encouraging results from exploratory well drilling completed during the quarter at the company's Salar de Cauchari property, located five kilometres south of the company's Olaroz project. The company's South American Salars subsidiary (85%) holds rights to over 30,000 hectares of property at Cauchari.

The objective of the drilling program was to delineate a brine body at the Cauchari project and to allow a resource estimate to be undertaken. The company's drill program tested the area on the company's leases directly to the southeast of the highest-grade part of the brine body drill tested by Lithium Americas Corp. on its Cauchari lithium project.

The drilling program consisted of six holes, comprising five triple-tube Diamond core holes and one rotary drill hole drilled vertically to between 46 and 249 metres depth. Four drill holes (CAU002D to CAU005D) terminated in units of halite (salt) and interbedded clastic sediments, suggesting this sequence continues at depth (as observed in CAU001). Holes CAU002D to CAU005D did not reach the target depths of 200 metres due to problems with drilling equipment.

The drilling program analytical results confirmed that the elevated values identified in the lithium resource defined by Lithium Americas Corp. extend into Orocobre's properties along the east portion of the Cauchari salar. Assay results received to date from CAU001D and CAU002D show elevated lithium values in areas previously predicted from publicly released Lithium Americas data.

Results received from four holes give values that include 244 metres in CAU001D 548 milligrams per litre lithium in CAU001D (from 5-249 metres) and 177 metres at 403 milligrams per litre lithium (9-186 metres) in CAU002D.

Lithium geochemistry is similar to the Olaroz project, with average magnesium-to-lithium ratios of 2.6 to 4.9 in the three holes for which results have been received. The sulphate-to-lithium ratio is higher than Olaroz, with values from 44 to 177 for these same three drill holes.

Results are pending from drill holes in the southern portion of Orocobre's properties (CAU003 through CAU006) when received these will help define the extent of elevated lithium values and the SO4/Li ratios in this area.

The spacing between the six holes averages 2.9 kilometres. Results suggest the lithium brine body extends over an area of approximately 26 square kilometres within Orocobre's Cauchari properties. It is expected that the brine body could extend well beneath the current drilling depth, as Lithium America Corporation's deepest reported hole (PE10/DDH07) had not intersected basement at 450 metres.

Porosity data are being collected from the Diamond drill cores by the British Geological Survey sedimentological laboratories that previously undertook this work for the company on the Olaroz project. Specific yield porosity determinations have not yet been received for core samples analysed. An estimate of the project resource is planned to be undertaken in the second quarter of 2012 once the remaining chemical analyses and specific yield porosity determinations are received from the British Geological Survey laboratories.

If sufficient resource is delineated in the Cauchari project, the Cauchari brines could be developed and processed at the planned Olaroz project facilities for relatively small incremental capital cost. This development strategy would require a capacity expansion of the Olaroz processing facilities beyond the currently planned rate of 16,400 tonnes per year of battery-grade lithium carbonate. Similarities in brine type are expected to allow Cauchari brine to be integrated into the planned operation with minor modifications to the processing route. Orocobre has been producing battery-grade lithium carbonate at its Olaroz pilot plant since early 2011.

Further technical information from this drilling program and mapping of the Salar de Cauchari resource areas are available in the Company's January 25, 2012 news release.

Salar de Salinas Grandes Potassium-Lithium Project (Orocobre 85 per cent) 

During the quarter, the company completed a grid auger drilling program on the Salinas Grandes lithium-potash project in Salta province, northwest Argentina. Salinas Grandes is located 70 kilometres southeast of the company's flagship Salar de Olaroz project. The auger program complements the Diamond drilling program completed earlier in 2011 that indicated the presence of two brine bodies with good grades and significant exploration potential. Diamond drilling holes were to between 60 and 75 m depth, with one hole drilled to 71 m with a Diamond core and to 180 m total depth with a tricone. Further technical information on the Diamond drilling program is contained in the company's news releases of 31 October 2011 and 18 July 2011. 

The auger drilling program consisted of 47 solid stem auger holes drilled on a north-south oriented grid, with an average spacing of 1.7 kilometres between holes. Holes were drilled vertically to between two and twenty metres depth, depending on access conditions within the salar. Geological samples were logged and results compiled on geological sections, which show a significant increase in sand on the northern margins of the salar where sand has been sourced from the northern alluvial fan.

Samples were collected during the drilling by bailing brine from the hole every four metres (and at two metres in four-metre-deep holes). The upper four-metre sample is representative of the interval zero to four metres, the deeper samples (four to eight metres, eight to 12 metres, 12 to 16 metres and 16 to 20 metres) are composites from the hole to the depth at the point of sampling. Further information on the auger drilling program, including average results for each auger hole, are provided in the Company's news release of 21 November 2011.

Composite values are influenced by the lithium concentrations in each lithological unit and the permeability of individual lithological units, with higher permeability units influencing brine-sample compositions more than lower permeability units. The shallow brine body occurs over an area of approximately 170 square kilometres, of which approximately 110 square kilometres is located within Orocobre's properties.

Samples in the shallow brine body exhibit attractively low magnesium-lithium ratios, averaging 2.7 for all samples. Sulphate levels are low, ranging from 947 mg/l on the margins of the salar to an isolated maximum of 11,978 mg/l within the salar, with an average of 3,628 mg/l. Within the zone of greater than 1,000 mg/l lithium, in the zero-to-four-metre samples sulphate averages 3,572 mg/l.

The shallow brine body is hosted in a sequence of sand, silt and clay units, with an increase in sand content in the north of the salar. Halite is limited to a maximum thickness of 0.5 metre from surface in the centre-south of the salar. The elevated lithium brine concentrations encountered during auger sampling correlate well with the distribution of elevated lithium values from previous pit sampling.

Specific yield porosity determinations have been received for core samples analysed by the British Geological Survey. The results are similar to those obtained at the company's Olaroz project for the same types of sediments. The specific yield porosity data, auger drilling and previous Diamond drilling results will be used to undertake a resource estimate on the shallow brine body. Guidance on the potential for extraction of the brine will be released with the resource estimate.

The close proximity of Salinas Grandes to the Company's Salar de Olaroz project provides potential operational synergies. One potential synergy could be the processing of concentrated Salinas Grandes lithium brine at an expanded Olaroz lithium carbonate plant following potash recovery at Salinas Grandes. 

The Company's current focus is to complete an analysis of the resource estimate and to establish an understanding of the brine extractability through pumping tests. Pump testing of the auger drill holes is now under way to gather data on permeability and flow rates, and to assess the extractability of the brine.

Corporate 

New Argentine Foreign Currency Transfer Regulations

In late October, Argentina's national government decreed that export revenues from mining projects must be repatriated and converted to Argentine currency prior to being distributed either locally or overseas. This overturned oil and mining companies' pre-existing exemption from Argentina's currency repatriation laws that apply to all other sectors' primary producers.

A preliminary analysis by the company's Argentine legal counsel indicates that this decree does not affect regulations allowing purchase and transfer of foreign currency to offshore destinations in consideration for the purchase of equipment or supplies, debt repayment, or dividend payments.

Management current assessment is that this decree does not have a material effect on Orocobre's current and proposed Argentine operations. The company will continually assess implications on the financial and operational aspects of the company that may arise from the new regulations.

Cash Position 

At the end of the quarter, the company had a strong cash position of A$27.7m. 

About Orocobre Limited 

Orocobre Limited is listed on the Australian Securities Exchange (ASX:ORE) and the Toronto Stock Exchange (News - Market indicators), and is the leading lithium-potash developer in the lithium and potassium rich Puna region of Argentina. For further information, please visit www.orocobre.com.

Technical Information, Competent Persons' and Qualified Persons Statements 

The technical information in this announcement has been reviewed and approved by Mr. Neil Stuart, a non-executive director of Orocobre. Neil Stuart is a geologist and is a Fellow of The Australasian Institution of Mining and Metallurgy. Neil has sufficient relevant experience to qualify as a competent person as defined in the 2004 edition of the Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves. He is also a "Qualified Person" as defined in NI 43-101. 

Additional information relating to the Company's projects is available in "Technical Report - Salar de Olaroz Lithium-Potash Project, Argentina" dated May 30, 2011, (the Olaroz Report), the "Technical Report - Salinas Grandes Project" dated April 30, 2010 and the "Technical Report - Salar de Cauchari Project, Argentina" dated April 30, 2010, respectively, which have each been prepared by John Houston, Consulting Hydrogeologist, together with, in the case of the Olaroz Report, Mike Gunn, Consulting Processing Engineer, in accordance with NI 43-101.

Information in this news release relating to the testing results of Lithium Americas Corp. has not been verified by Orocobre, and such information is not necessarily indicative of results that will be obtained by Orocobre at the Cauchari Project.

Caution Regarding Forward-Looking Information

This report contains "forward-looking information" within the meaning of applicable securities legislation. Forward-looking information may include, but is not limited to, the results of the Olaroz feasibility study, the estimation and realization of mineral resources at the Company's projects, the viability, recoverability and processing of such resources, costs and timing of development of the Olaroz project, timing of future exploration at the Company's projects, the forecasts relating to the lithium and potash markets provided by Roskill in the Olaroz feasibility study, timing and receipt of approvals for the Company's projects, consents and permits under applicable legislation, adequacy of financial resources, production and other milestones for the Olaroz project, the Olaroz project's future financial and operating performance including production, rates of return, operating costs, capital costs and cash flows, the finalization of a joint venture agreement with Toyota Tsusho Corporation, the completion of project financing for the Olaroz Project, approval from the Jujuy provincial government of the Olaroz Project, potential operating synergies between the Salinas Grandes and Cauchari projects and the Olaroz project, the implications of the changes to foreign currency transfer regulations in Argentina that are described herein, the delineation of a brine body at the Cauchari Project, the processing route for brines from the Cauchari Project and the incremental capital cost of such processing, and other matters related to the development of the Olaroz project, Cauchari Project and the Salinas Grandes project. 

Forward-looking information is subject to known and unknown risks, uncertainties and other factors that may cause actual results to be materially different from those expressed or implied by such forward-looking information, including but not limited to the risk that further funding may be required, but unavailable, for the ongoing development of the Company's projects; changes in government regulations, policies or legislation; fluctuations or decreases in commodity prices; the possibility that required permits or approvals may not be obtained; uncertainty in the estimation, economic viability, recoverability and processing of mineral resources; general risks associated with the feasibility of the Company's projects; risks associated with construction and development of the Olaroz project; unexpected capital or operating cost increases; the risk that a definitive joint venture agreement with Toyota Tsusho Corporation may not be completed and/or that project financing will not be arranged; uncertainty of meeting anticipated program milestones at the Company's projects; as well as those factors disclosed in the Company's Annual Information Form for the year ended June 30, 2011 filed at www.sedar.com

The Company believes that the assumptions and expectations reflected in such forward-looking information are reasonable. Assumptions have been made regarding, among other things: the Company's ability to carry on its exploration and development activities, the timely receipt of required approvals, the prices of lithium and potash, the ability of the Company to operate in a safe, efficient and effective manner and the ability of the Company to obtain financing as and when required and on reasonable terms. Readers are cautioned that the foregoing list is not exhaustive of all factors and assumptions which may have been used. There can be no assurance that forward-looking information will prove to be accurate, as actual results and future events could differ materially from those anticipated in such information. Accordingly, readers should not place undue reliance on forward-looking information. The Company does not undertake to update any forward-looking information, except in accordance with applicable securities laws.

ABN 31 112 589 910



Australia & Asia
Orocobre Limited
Richard Seville, Managing Director
M +61 419 916 338
rseville@orocobre.com
or
North America
Orocobre Limited
Bruce Rose, VP- Corporate Development
M + 1 (604) 377 1423
brose@orocobre.com
www.orocobre.com
Data and Statistics for these countries : Argentina | Japan | All
Gold and Silver Prices for these countries : Argentina | Japan | All

Oriel Resources PLC

CODE : ORL.TO
Follow and Invest
Add to watch list Add to your portfolio Add or edit a note
Add Alert Add to Watchlists Add to Portfolio Add Note
ProfileMarket
Indicators
VALUE :
Projects & res.
Press
releases
Annual
report
RISK :
Asset profile
Contact Cpy

Oriel Res. is a nickel development stage company based in United kingdom.

Oriel Res. is listed in Canada, in Germany, in United Kingdom and in United States of America. Its market capitalisation is CA$ 1.7 billions as of today (US$ 1.4 billions, € 1.2 billions).

Its stock quote reached its lowest recent point on December 30, 2005 at CA$ 0.43, and its highest recent level on December 03, 2021 at CA$ 9.30.

Oriel Res. has 209 479 867 shares outstanding.

Your feedback is appreciated, please leave a comment or rate this article.
Rate : Average note :0 (0 vote) View Top rated
 
Nominations of Oriel Resources PLC
7/1/2013Orocobre Limited: Resignation and Appointment of Company Sec...
1/21/2013Orocobre Announces Executive Appointments
7/27/2011Orocobre Appoints Bruce Rose, Vice President, Corporate Deve...
Project news of Oriel Resources PLC
8/23/2013Orocobre Limited: Amendment to Salinas Grandes Technical Rep...
1/25/2012Orocobre Announces Results of Long-Term Pumping Tests at Ola...
Corporate news of Oriel Resources PLC
11/4/2013Orocobre Limited: Boric Acid Plant Pre-Feasibility Study Com...
10/31/2013Orocobre Limited: Quarterly Report of Operations for the Per...
10/14/2013Orocobre Limited: Construction Update on the Olaroz Lithium ...
9/5/2013Orocobre Limited: August Update-First Brine Production at th...
7/15/2013Orocobre Limited: Cancellation of Securities
7/1/2013Orocobre Announces Borax Plant Relocation
6/11/2013Orocobre Completes Long-Term Pump Testing at the Cangrejillo...
5/7/2013Orocobre Finance Update
4/30/2013Orocobre Limited: Quarterly Report of Operations for the Per...
4/9/2013Orocobre Limited: Canadian Reporting Update
4/5/2013Orocobre Provides Olaroz Lithium Project Construction Update
3/20/2013Orocobre Limited: Borax Argentina Develops Nuclear Grade Bor...
3/19/2013Orocobre Limited: Celebration of the Official Opening of Ola...
1/31/2013Orocobre Limited: Quarterly Report of Operations For the Per...
1/22/2013Orocobre Provides Olaroz Lithium Project Construction Update
11/5/2012CORRECTION FROM SOURCE: Orocobre Announces Completion of A$2...
11/5/2012Orocobre Announces Completion of A$21 Million Institutional ...
11/1/2012Orocobre Limited: ASX/TSX Announcement
10/22/2012Orocobre Announces Maiden Resource at the Cauchari Lithium-P...
10/17/2012Orocobre Signs Agreement With Toyota Tsusho for Development ...
10/17/2012Orocobre Signs Agreement With Toyota Tsusho for Development ...
9/26/2012Toyota Tsusho Corporation Announces Positive Investment Deci...
8/21/2012BRR Webcast: "Orocobre Ltd Acquires Borax Argentina from Rio...
8/21/2012Orocobre Acquires Borax Argentina S.A.
8/1/2012CORRECTION FROM SOURCE: BRR Webcast: "Orocobre Limited follo...
8/1/2012BRR Webcast: "Orocobre Limited follow-up interview with Mr. ...
7/25/2012Orocobre Receives Project Approval and Mining Leases for Ola...
7/17/2012BRR Webcast: "Orocobre Limited Receives Approval to Develop ...
6/27/2012Orocobre Receives Expert Committee Approval to Develop the O...
5/31/2012Orocobre Provides Update on Olaroz Project Approvals
4/30/2012Orocobre Limited-Quarterly Report of Operations for the Peri...
3/7/2012Orocobre Announces the Maiden Resource for the Salinas Grand...
1/31/2012Orocobre Limited: Quarterly Report of Operations for the Per...
1/25/2012Orocobre Announces Results from Its Cauchari Lithium-Potash ...
12/28/2011Orocobre Announces Update on Company Activities
10/24/2011Orocobre Limited-Change of Director's Interest Notice
9/8/2011Orocobre Receives Approval for Exploration Drilling at Salar...
8/31/2011Orocobre Reports Progress on its Flagship Salar de Olaroz Pr...
8/8/2011Orocobre Awards Detailed Engineering Contract to SKM for Sal...
8/1/2011Orocobre Limited: Quarterly Report of Operations For The Per...
7/18/2011Orocobre Limited: ASX Announcement
7/18/2011Orocobre Completes Phase 1 Drilling at Salinas Grandes Lithi...
7/14/2011on Drilling Results from Salinas Grandes Lithium-Potash Proj...
6/20/2011Orocobre Limited: Addenda Approved for the Salar de Olaroz E...
5/27/2011Orocobre Limited: Progress With Olaroz Final Approvals Proce...
5/3/2011Orocobre Conference Call Invitation
5/3/2011Orocobre Receives Positive Results for Definitive Feasibilit...
4/27/2011Orocobre Limited: ASX/TSX Announcement-Quarterly Report of O...
4/8/2011Orocobre Limited: First Battery Grade Lithium Carbonate Prod...
4/1/2011Orocobre Limited: Increased and Upgraded Resource at Olaroz ...
3/7/2011Orocobre Limited: Approvals Process for Olaroz Lithium-Potas...
2/24/2011Orocobre Limited Completes $22 Million "Bought Deal" Financi...
Comments closed
 
Latest comment posted for this article
Be the first to comment
Add your comment
TORONTO (ORL.TO)LSE (ORI.L)
8.28+3.63%121.50-1.62%
TORONTO
CA$ 8.28
12/13 15:59 0.290
3.63%
Prev close Open
7.99 8.12
Low High
8.12 8.34
Year l/h YTD var.
 -  -
52 week l/h 52 week var.
- -  8.28 -%
Volume 1 month var.
19,462 -%
24hGold TrendPower© : 16
Produces
Develops
Explores for
 
 
 
Analyse
Interactive chart Add to compare
Interactive
chart
Print Compare Export
You must be logged in to use the porfolio and watchlists (free)
Top Newsreleases
MOST READ
Annual variation
DateVariationHighLow
202188.61%9.303.89
202089.22%4.441.60
 
5 years chart
 
3 months chart
 
3 months volume chart
 
 
Mining Company News
Plymouth Minerals LTDPLH.AX
Plymouth Minerals Intersects Further High Grade Potash in Drilling at Banio Potash Project - Plannin
AU$ 0.12-8.00%Trend Power :
Santos(Ngas-Oil)STO.AX
announces expected non-cash impairment
AU$ 7.70-0.58%Trend Power :
Oceana Gold(Au)OGC.AX
RELEASES NEW TECHNICAL REPORT FOR THE HAILE GOLD MINE
AU$ 2.20+0.00%Trend Power :
Western Areas NL(Au-Ni-Pl)WSA.AX
Advance Notice - Full Year Results Conference Call
AU$ 3.86+0.00%Trend Power :
Canadian Zinc(Ag-Au-Cu)CZN.TO
Reports Financial Results for Q2 and Provides Project Updates
CA$ 0.12+4.55%Trend Power :
Stornoway Diamond(Gems-Au-Ur)SWY.TO
Second Quarter Results
CA$ 0.02+100.00%Trend Power :
McEwen Mining(Cu-Le-Zn)MUX
TO ACQUIRE BLACK FOX FROM PRIMERO=C2=A0
US$ 11.94+9.34%Trend Power :
Rentech(Coal-Ngas)RTK
Rentech Announces Results for Second Quarter 2017
US$ 0.20-12.28%Trend Power :
KEFIKEFI.L
Reduced Funding Requirement
GBX 0.54-2.55%Trend Power :
Lupaka Gold Corp.LPK.V
Lupaka Gold Receives First Tranche Under Amended Invicta Financing Agreement
CA$ 0.06+0.00%Trend Power :
Imperial(Ag-Au-Cu)III.TO
Closes Bridge Loan Financing
CA$ 2.69+13.03%Trend Power :
Guyana Goldfields(Cu-Zn-Pa)GUY.TO
Reports Second Quarter 2017 Results and Maintains Production Guidance
CA$ 1.84+0.00%Trend Power :
Lundin Mining(Ag-Au-Cu)LUN.TO
d Share Capital and Voting Rights for Lundin Mining
CA$ 15.60+1.83%Trend Power :
Canarc Res.(Au)CCM.TO
Canarc Reports High Grade Gold in Surface Rock Samples at Fondaway Canyon, Nevada
CA$ 0.24+0.00%Trend Power :
Havilah(Cu-Le-Zn)HAV.AX
Q A April 2017 Quarterly Report
AU$ 0.20+5.26%Trend Power :
Uranium Res.(Ur)URRE
Commences Lithium Exploration Drilling at the Columbus Basin Project
US$ 6.80-2.86%Trend Power :
Platinum Group Metals(Au-Cu-Gems)PTM.TO
Platinum Group Metals Ltd. Operational and Strategic Process ...
CA$ 1.87+5.65%Trend Power :
Devon Energy(Ngas-Oil)DVN
Announces $340 Million of Non-Core Asset Sales
US$ 52.61+0.98%Trend Power :
Precision Drilling(Oil)PD-UN.TO
Announces 2017Second Quarter Financial Results
CA$ 8.66-0.35%Trend Power :
Terramin(Ag-Au-Cu)TZN.AX
2nd Quarter Report
AU$ 0.04+5.56%Trend Power :