Orocobre Provides Olaroz Lithium Project Construction Update
Published : January 22, 2013
( 0 vote, 0/5 ) Print article
  Article Comments Comment this article Rating Follow Company  
0
Send
0
comment
Keywords :   Argentina | Australia | Boron | Lithium | Market | Report | Storage | Swift | Water |

BRISBANE, AUSTRALIA--(Marketwire - Jan. 21, 2013) - Orocobre Limited (News - Market indicators)(ASX:ORE) ("Orocobre" or "the Company") is pleased to provide a progress report on the construction of the Company's flagship Olaroz lithium project. 

Construction of the Olaroz lithium project officially began on 21st November 2012. Progress has been swift due in a large part to the preparation and planning that took place in the preceding year. Sinclair Knight Merz, with the assistance of INFA, a well respected Argentine engineering group, completed detailed engineering for all areas of the operation, including brine extraction, transport and evaporation, the lithium carbonate plant and key areas of the re-purification and micronizing circuits. The procurement process was also well advanced with all main suppliers identified and with many construction and supply contracts at an advanced stage of negotiation or ready for awarding by the construction commencement date.

In addition, prior to official construction start, various aspects of site preparation had been advanced, including the drilling of fresh water bores and pumping station and the time consuming removal of scrubby vegetation, "tolar", from the area of the evaporation ponds prior to earth moving. Since then, numerous contracts with a total value of US$45m have been executed, or are ready for execution. These include the earth moving contracts for the construction of the 4.2 square kilometres of evaporation pond and road construction for the bore field access road across the salt lake (which will allow production bores to be drilled), the drilling contract for sixteen 200m production bores, purchase of 37km of pipeline for gas supply, and the establishment of the construction camp, fuel and water supply. All major contracts awarded to this point have been on or under budget.

Since start of official construction, and taking into account the Christmas break, significant progress has been made on-site as follows:

  • The establishment of the construction camp at Olaroz, and the renting of supplementary accommodation at the nearby town of Susques for first stage construction crews
  • Mobilization of earth moving equipment and commencement of works
  • The clearing of tolar over approximately 50% of the evaporation pond area (2 sq km) and the commencement of earth works for evaporation pond construction. 
  • Establishment of a long term water supply to be used both for both domestic and construction purposes
  • Establishment of fuel supply/storage and telecommunications
  • The construction of 50% of the access roads on the salar to the bore - field area.

Currently 142 construction workers are at site with a peak maximum expected of 400 by mid 2013.

The project implementation is through EPCM (Engineering, Procurement and Construction Management) with a high proportion of local involvement through construction and supply contracts and local employment. The unique community and shared value policy continues as a key success factor, training local people with supervision by high quality experienced professionals.

The Olaroz lithium project is being developed by Orocobre (66.5%) with is partners Toyota Tsusho Corporation ("TTC") (25%) and the Jujuy Province mining and energy company, JEMSE (8.5%) with a construction budget of US$229m including contingency. The project is fully funded with up to US$275m of funding available via US$82.8m of equity funding from TTC and Orocobre and US$192m of project finance for Mizuho Corporate Bank. First production is scheduled for the end of second quarter, 2014.

To view "Figure 1 Building Road to Bore Field," please visit the following link: http://media3.marketwire.com/docs/ORL2101_Figure1.jpg.

To view "Figure 2 Plant Platform Lime Area," please visit the following link: http://media3.marketwire.com/docs/ORL2101_Figure2.jpg.

To view "Figure 3 Road Construction," please visit the following link: http://media3.marketwire.com/docs/ORL2101_Figure3.jpg.

To view "Figure 4 Removal of Vegetation," please visit the following link: http://media3.marketwire.com/docs/ORL2101_Figure4.jpg

To view "Figure 5 Fuel Storage," please visit the following link: http://media3.marketwire.com/docs/ORL2101_Figure5.jpg.

To view "Figure 6 Communications," please visit the following link: http://media3.marketwire.com/docs/ORL2101_Figure6.jpg.

About Orocobre Limited

Orocobre Limited is listed on the Australian Securities Exchange and Toronto Stock Exchange (News - Market indicators)(ASX:ORE), and is building a substantial Argentinian-based industrial minerals company through the construction and operation of its portfolio of lithium, potash and boron projects and facilities in the Puna region of northern Argentina. The Company is building in partnership with Toyota Tsusho Corporation the first large-scale, "greenfield" brine based lithium project in 20 years at its flagship Salar de Olaroz resource, with projected production of 17,500 tonnes per annum of low-cost battery grade lithium carbonate scheduled to commence in Q2 2014. The Company also wholly-owns Borax Argentina, an important regional borate producer. Orocobre has recently been included in the S&P/ASX 300 Index and was named 2012 Mining Company of the Year by Argentine mining magazine Panorama Minero and the Fundacion para el desarrollo de le Mineria Argentina ("Fundamin" or Foundation for Development of Argentina Mining). For further information, please visit www.orocobre.com.

Caution Regarding Forward-Looking Information

This news release contains "forward-looking information" within the meaning of applicable securities legislation. Forward-looking information contained in this release includes, but is not limited to, the draw down of finance for the Olaroz Project, the completion of construction at the Olaroz Project and the timing thereof, the commencement of commercial production at the Olaroz Project and the timing thereof, the cost of construction relative to the estimated capital cost of the Olaroz Project, the design production rate for lithium carbonate and potash at the Olaroz Project, the expected brine grade at the Olaroz Project, the expected operating costs at the Olaroz Project and the comparison of such expected costs to expected global operating costs, and the ongoing working relationship between Orocobre and the Province of Jujuy.

Such forward-looking information is subject to known and unknown risks, uncertainties and other factors that may cause actual results to be materially different from those expressed or implied by such forward-looking information, including but not limited to the risk of further changes in government regulations, policies or legislation; the possibility that required concessions may not be obtained, or may be obtained only on terms and conditions that are materially worse than anticipated; the risk that the conditions precedent to draw down the project financing with Mizuho Corporate Bank will not be met; that further funding may be required, but unavailable, for the ongoing development of the Company's projects; fluctuations or decreases in commodity prices; uncertainty in the estimation, economic viability, recoverability and processing of mineral resources; risks associated with weather patterns and impact on production rate; risks associated with construction and development of the Olaroz Project; unexpected capital or operating cost increases; uncertainty of meeting anticipated program milestones at the Olaroz Project; general risks associated with the feasibility and development of the Olaroz Project; as well as those factors disclosed in the Company's Annual Information Form for the year ended June 30, 2012 filed at www.sedar.com.

The Company believes that the assumptions and expectations reflected in such forward-looking information are reasonable. Assumptions have been made regarding, among other things: the timely receipt of required approvals and completion of agreements on reasonable terms and conditions; the ability of the Company to obtain financing as and when required and on reasonable terms and conditions; the prices of lithium and potash; and the ability of the Company to operate in a safe, efficient and effective manner. Readers are cautioned that the foregoing list is not exhaustive of all factors and assumptions which may have been used. There can be no assurance that forward-looking information will prove to be accurate, as actual results and future events could differ materially from those anticipated in such information. Accordingly, readers should not place undue reliance on forward-looking information. The Company does not undertake to update any forward-looking information, except in accordance with applicable securities laws.

ABN 31 112 589 910



Australia and Asia: Orocobre Limited
David Hall
Business Development Manager
M: +61 7 3871 3985
dhall@orocobre.com
or
North America: Orocobre Limited
James Calaway
Chairman
M: +1 (713) 818 1457
jcalaway@orocobre.com
Data and Statistics for these countries : Argentina | Australia | All
Gold and Silver Prices for these countries : Argentina | Australia | All

Oriel Resources PLC

CODE : ORL.TO
Follow and Invest
Add to watch list Add to your portfolio Add or edit a note
Add Alert Add to Watchlists Add to Portfolio Add Note
ProfileMarket
Indicators
VALUE :
Projects & res.
Press
releases
Annual
report
RISK :
Asset profile
Contact Cpy

Oriel Res. is a nickel development stage company based in United kingdom.

Oriel Res. is listed in Canada, in Germany, in United Kingdom and in United States of America. Its market capitalisation is CA$ 1.7 billions as of today (US$ 1.4 billions, € 1.2 billions).

Its stock quote reached its lowest recent point on December 30, 2005 at CA$ 0.43, and its highest recent level on December 03, 2021 at CA$ 9.30.

Oriel Res. has 209 479 867 shares outstanding.

Your feedback is appreciated, please leave a comment or rate this article.
Rate : Average note :0 (0 vote) View Top rated
 
Nominations of Oriel Resources PLC
7/1/2013Orocobre Limited: Resignation and Appointment of Company Sec...
1/21/2013Orocobre Announces Executive Appointments
7/27/2011Orocobre Appoints Bruce Rose, Vice President, Corporate Deve...
Project news of Oriel Resources PLC
8/23/2013Orocobre Limited: Amendment to Salinas Grandes Technical Rep...
1/25/2012Orocobre Announces Results of Long-Term Pumping Tests at Ola...
Corporate news of Oriel Resources PLC
11/4/2013Orocobre Limited: Boric Acid Plant Pre-Feasibility Study Com...
10/31/2013Orocobre Limited: Quarterly Report of Operations for the Per...
10/14/2013Orocobre Limited: Construction Update on the Olaroz Lithium ...
9/5/2013Orocobre Limited: August Update-First Brine Production at th...
7/15/2013Orocobre Limited: Cancellation of Securities
7/1/2013Orocobre Announces Borax Plant Relocation
6/11/2013Orocobre Completes Long-Term Pump Testing at the Cangrejillo...
5/7/2013Orocobre Finance Update
4/30/2013Orocobre Limited: Quarterly Report of Operations for the Per...
4/9/2013Orocobre Limited: Canadian Reporting Update
4/5/2013Orocobre Provides Olaroz Lithium Project Construction Update
3/20/2013Orocobre Limited: Borax Argentina Develops Nuclear Grade Bor...
3/19/2013Orocobre Limited: Celebration of the Official Opening of Ola...
1/31/2013Orocobre Limited: Quarterly Report of Operations For the Per...
1/22/2013Orocobre Provides Olaroz Lithium Project Construction Update
11/5/2012CORRECTION FROM SOURCE: Orocobre Announces Completion of A$2...
11/5/2012Orocobre Announces Completion of A$21 Million Institutional ...
11/1/2012Orocobre Limited: ASX/TSX Announcement
10/22/2012Orocobre Announces Maiden Resource at the Cauchari Lithium-P...
10/17/2012Orocobre Signs Agreement With Toyota Tsusho for Development ...
10/17/2012Orocobre Signs Agreement With Toyota Tsusho for Development ...
9/26/2012Toyota Tsusho Corporation Announces Positive Investment Deci...
8/21/2012BRR Webcast: "Orocobre Ltd Acquires Borax Argentina from Rio...
8/21/2012Orocobre Acquires Borax Argentina S.A.
8/1/2012CORRECTION FROM SOURCE: BRR Webcast: "Orocobre Limited follo...
8/1/2012BRR Webcast: "Orocobre Limited follow-up interview with Mr. ...
7/25/2012Orocobre Receives Project Approval and Mining Leases for Ola...
7/17/2012BRR Webcast: "Orocobre Limited Receives Approval to Develop ...
6/27/2012Orocobre Receives Expert Committee Approval to Develop the O...
5/31/2012Orocobre Provides Update on Olaroz Project Approvals
4/30/2012Orocobre Limited-Quarterly Report of Operations for the Peri...
3/7/2012Orocobre Announces the Maiden Resource for the Salinas Grand...
1/31/2012Orocobre Limited: Quarterly Report of Operations for the Per...
1/25/2012Orocobre Announces Results from Its Cauchari Lithium-Potash ...
12/28/2011Orocobre Announces Update on Company Activities
10/24/2011Orocobre Limited-Change of Director's Interest Notice
9/8/2011Orocobre Receives Approval for Exploration Drilling at Salar...
8/31/2011Orocobre Reports Progress on its Flagship Salar de Olaroz Pr...
8/8/2011Orocobre Awards Detailed Engineering Contract to SKM for Sal...
8/1/2011Orocobre Limited: Quarterly Report of Operations For The Per...
7/18/2011Orocobre Limited: ASX Announcement
7/18/2011Orocobre Completes Phase 1 Drilling at Salinas Grandes Lithi...
7/14/2011on Drilling Results from Salinas Grandes Lithium-Potash Proj...
6/20/2011Orocobre Limited: Addenda Approved for the Salar de Olaroz E...
5/27/2011Orocobre Limited: Progress With Olaroz Final Approvals Proce...
5/3/2011Orocobre Conference Call Invitation
5/3/2011Orocobre Receives Positive Results for Definitive Feasibilit...
4/27/2011Orocobre Limited: ASX/TSX Announcement-Quarterly Report of O...
4/8/2011Orocobre Limited: First Battery Grade Lithium Carbonate Prod...
4/1/2011Orocobre Limited: Increased and Upgraded Resource at Olaroz ...
3/7/2011Orocobre Limited: Approvals Process for Olaroz Lithium-Potas...
2/24/2011Orocobre Limited Completes $22 Million "Bought Deal" Financi...
Comments closed
 
Latest comment posted for this article
Be the first to comment
Add your comment
TORONTO (ORL.TO)LSE (ORI.L)
8.28+3.63%121.50-1.62%
TORONTO
CA$ 8.28
12/13 15:59 0.290
3.63%
Prev close Open
7.99 8.12
Low High
8.12 8.34
Year l/h YTD var.
 -  -
52 week l/h 52 week var.
- -  8.28 -%
Volume 1 month var.
19,462 -%
24hGold TrendPower© : 16
Produces
Develops
Explores for
 
 
 
Analyse
Interactive chart Add to compare
Interactive
chart
Print Compare Export
You must be logged in to use the porfolio and watchlists (free)
Top Newsreleases
MOST READ
Annual variation
DateVariationHighLow
202188.61%9.303.89
202089.22%4.441.60
 
5 years chart
 
3 months chart
 
3 months volume chart
 
 
Mining Company News
Plymouth Minerals LTDPLH.AX
Plymouth Minerals Intersects Further High Grade Potash in Drilling at Banio Potash Project - Plannin
AU$ 0.12-8.00%Trend Power :
Santos(Ngas-Oil)STO.AX
announces expected non-cash impairment
AU$ 7.82+1.69%Trend Power :
Oceana Gold(Au)OGC.AX
RELEASES NEW TECHNICAL REPORT FOR THE HAILE GOLD MINE
AU$ 2.20+0.00%Trend Power :
Western Areas NL(Au-Ni-Pl)WSA.AX
Advance Notice - Full Year Results Conference Call
AU$ 3.86+0.00%Trend Power :
Canadian Zinc(Ag-Au-Cu)CZN.TO
Reports Financial Results for Q2 and Provides Project Updates
CA$ 0.12+4.55%Trend Power :
Stornoway Diamond(Gems-Au-Ur)SWY.TO
Second Quarter Results
CA$ 0.02+100.00%Trend Power :
McEwen Mining(Cu-Le-Zn)MUX
TO ACQUIRE BLACK FOX FROM PRIMERO=C2=A0
US$ 11.29+2.30%Trend Power :
Rentech(Coal-Ngas)RTK
Rentech Announces Results for Second Quarter 2017
US$ 0.20-12.28%Trend Power :
KEFIKEFI.L
Reduced Funding Requirement
GBX 0.55+2.59%Trend Power :
Lupaka Gold Corp.LPK.V
Lupaka Gold Receives First Tranche Under Amended Invicta Financing Agreement
CA$ 0.06+0.00%Trend Power :
Imperial(Ag-Au-Cu)III.TO
Closes Bridge Loan Financing
CA$ 2.46-2.38%Trend Power :
Guyana Goldfields(Cu-Zn-Pa)GUY.TO
Reports Second Quarter 2017 Results and Maintains Production Guidance
CA$ 1.84+0.00%Trend Power :
Lundin Mining(Ag-Au-Cu)LUN.TO
d Share Capital and Voting Rights for Lundin Mining
CA$ 15.85-1.25%Trend Power :
Canarc Res.(Au)CCM.TO
Canarc Reports High Grade Gold in Surface Rock Samples at Fondaway Canyon, Nevada
CA$ 0.24+0.00%Trend Power :
Havilah(Cu-Le-Zn)HAV.AX
Q A April 2017 Quarterly Report
AU$ 0.19-7.32%Trend Power :
Uranium Res.(Ur)URRE
Commences Lithium Exploration Drilling at the Columbus Basin Project
US$ 6.80-2.86%Trend Power :
Platinum Group Metals(Au-Cu-Gems)PTM.TO
Platinum Group Metals Ltd. Operational and Strategic Process ...
CA$ 1.83-3.68%Trend Power :
Devon Energy(Ngas-Oil)DVN
Announces $340 Million of Non-Core Asset Sales
US$ 51.84+0.80%Trend Power :
Precision Drilling(Oil)PD-UN.TO
Announces 2017Second Quarter Financial Results
CA$ 8.66-0.35%Trend Power :
Terramin(Ag-Au-Cu)TZN.AX
2nd Quarter Report
AU$ 0.03+0.00%Trend Power :