PROGRESS UPDATE ON PILOT PLANT WORK AT ARAGUAIA NICKEL PROJECT, BRAZIL

9 March 2015 - Horizonte Minerals Plc, (AIM: HZM, TSX: HZM) ('Horizonte' or 'the Company'), the nickel development company, is pleased to announce positive results following completion of first stage testing of the Rotary Kiln Electric Furnace Pilot Plant ('RKEF Pilot Plant') for its 100% owned Araguaia nickel project ('Araguaia') in Para State, north central Brazil.

Highlights

Completed commissioning of the 'Dryer/Agglomerator' module ahead of full

RKEF Pilot Plant launch targeted for April 2015

Good drying and agglomeration performance achieved over three sets of test conditions

Excellent product quality - well agglomerated material obtained with low dust

generation while meeting target moisture level in the dryer product (18% H2O)

Kiln pre-commissioning and testing showed excellent calcination with no

evidence of sticking or sintering up to discharge temperatures of 1,000oC
Horizonte Minerals CEO Jeremy Martin said, "The dryer tests, which is the first stage of the process flow sheet for the full scale RKEF Pilot Plant campaign have been positive marking another successful milestone in Araguaia's development. It's important to create the right blend of ore feed at this first stage in the process flow sheet to negate problems occurring with the feed throughout the process once in commercial production. To this end, the Araguaia material tested formed excellent ore feed, low dust levels and optimum particle size to be fed into the kiln and subsequently into the electric arc furnace to produce ferronickel.
"We will be delivering a further 200 tonnes of bulk sample of Araguaia ore to the RKEF
pilot facility in April 2015 to provide feed for the next stage of testing, the continuous
20 day RKEF pilot plant metallurgical campaign. The aim is to produce ferronickel to commercial specification on a continual basis. This will be another significant de-

26 Dover Street, London, W1S 4LY . T-44 (0) 207 763 7157 . [email protected] . www.horizonteminerals.com

risking step for the project and a principal part of the Feasibility Study. We look forward to providing regular updates as this work progresses."

Further Information

Araguaia has a current NI 43-101 compliant Mineral Resource of 71.98Mt grading
1.33% Ni (Indicated) and 25.4Mt at 1.21% Ni (Inferred) at a 0.95% nickel cut-off; included in the resource is a Probable Mineral Reserve of 21.2Mt at 1.66%Ni. Furthermore a Pre-Feasibility study ('PFS') has outlined robust economics for a 'base case' 15,000tpa nickel in ferro-nickel output with a 20% Fe-Ni product over a 25 year mine life.
As part of the on-going testwork for the Feasibility Study, Horizonte has successfully completed commissioning of the 'Dryer/Agglomerator' module during late January and February 2015 as part of first stage testing of the Pilot Plant, ahead of the full Pilot Plant launch targeted for April 2015.

Ore Preparation. A 20 tonne (wet) bulk sample of Araguaia ore for Drying/Agglomeration pre-testing was delivered to the IGEO testwork facility at the Morro Azul pilot plant in Minas Gerais, Brazil on 22 January 2015. The bulk sample had been selected for the purposes of drying/agglomeration commissioning/pre- testing from ore representative of a blend of 60% saprolite and 40% transition material i.e. the same proportions as the scheduled feed for the 'base case' life of mine used in the PFS. Crushing to

Drying/Agglomeration. Drying and agglomeration testing has been carried out over a range of test conditions in the 1 m diameter by 14 m long LPG-fired dryer at the Morro Azul pilot plant. At steady state conditions, drying and agglomeration performance was very good over the range of three test conditions, with well agglomerated material being obtained while meeting the target moisture level in the dryer product (18% H2O).
Kiln Pre-testing. Kiln pre-commissioning and testing has been carried out on the diesel fired long kiln (1.3 m diameter by 9.4 m) at the Morro Azul pilot plant. The dryer product from each of the three dryer runs was mixed with coal and processed in the kiln. The kiln temperature was allowed to slowly increase so that calcine discharge temperature increased from approximately 900oC to 1000oC. Observations of the movement of the calcine material inside the kiln showed that over the above

26 Dover Street, London, W1S 4LY . T-44 (0) 207 763 7157 . [email protected] . www.horizonteminerals.com

temperature range the feed showed no evidence of sticking or sintering. The calcine product had good granulometry and averaged reduction (Fe2+ /Fet) = 54% and the calcine contained an average of 1.8% carbon.

Full RKEF Pilot Plant Testwork. Preparations are at an advanced stage with the collection of a 200 tonne bulk sample underway to provide feed for full Pilot Plant metallurgical testwork planned for April 2015. The 200 tonne (wet) bulk sample of Araguaia ore will be representative of the PFS 'base case' feed for the first nine years of operation.

* * ENDS * *

For further information visit www.horizonteminerals.com or contact:
Jeremy Martin Horizonte Minerals plc Tel: +44 (0) 20 7763 7157
David Hall Horizonte Minerals plc Tel: +44 (0) 20 7763 7157
Joanna Weaving Christopher Raggett
Felicity Winkles
Lottie Brocklehurst
finnCap Ltd (Corporate Broking)
finnCap Ltd (Corporate Finance)
St Brides Partners Ltd (PR) St Brides Partners Ltd
Tel: +44 (0) 20 7220 0500
Tel: +44 (0) 20 7220 0500
Tel: +44 (0) 20 7236 1177
Tel: +44 (0) 20 7236 1177

About Horizonte Minerals:

Horizonte Minerals plc is an AIM and TSX-listed nickel development company focused in Brazil, which wholly owns the advanced Araguaia nickel laterite project located to the south of the Carajas mineral district of northern Brazil.
The Company is developing Araguaia as the next major nickel mine in Brazil, with targeted production by late 2017 or early 2018.
The Project, which has excellent infrastructure in place including rail, road, water and power, has a current NI 43-101 compliant Mineral Resource of 71.98Mt grading 1.33% Ni (Indicated) and 25.4Mt at 1.21% Ni (Inferred) at a 0.95% nickel cut-off; included in Resources is a Probable Reserve base of 21.2Mt at 1.66%Ni.
A Pre-Feasibility Study has been completed which underpins the robust economics of developing a mine with a targeted 15,000tpa nickel in ferro-nickel output with a 20%

26 Dover Street, London, W1S 4LY . T-44 (0) 207 763 7157 . [email protected] . www.horizonteminerals.com

Fe-Ni product over a 25 year mine life utilising the proven pyrometallurgical process of Rotary Kiln Electric Furnace technology. At these production rates, the project has a post-tax NPV of US$519m at a discount rate of 8% and an IRR of 20%, with a capital cost of US$582m which puts this project in the lowest quartile of the cost curve.
Horizonte has a strong shareholder structure including Teck Resources Limited 38.5%, Henderson Global Investors 14%, Anglo Pacific Group 7%.

CAUTIONARY STATEMENT REGARDING FORWARD LOOKING INFORMATION

Except for statements of historical fact relating to the Company, certain information contained in this press release constitutes "forward-looking information" under Canadian securities legislation. Forward-looking information includes, but is not limited to, statements with respect to the potential of the Company's current or future property mineral projects; the success of exploration and mining activities; cost and timing of future exploration, production and development; the estimation of mineral resources and reserves and the ability of the Company to achieve its goals in respect of growing its mineral resources; and the realization of mineral resource and reserve estimates. Generally, forward-looking information can be identified by the use of forward-looking terminology such as "plans", "expects" or "does not expect", "is expected", "budget", "scheduled", "estimates", "forecasts", "intends", "anticipates" or "does not anticipate", or "believes", or variations of such words and phrases or statements that certain actions, events or results "may", "could", "would", "might" or "will be taken", "occur" or "be achieved". Forward-looking information is based on the reasonable assumptions, estimates, analysis and opinions of management made in light of its experience and its perception of trends, current conditions and expected developments, as well as other factors that management believes to be relevant and reasonable in the circumstances at the date that such statements are made, and are inherently subject to known and unknown risks, uncertainties and other factors that may cause the actual results, level of activity, performance or achievements of the Company to be materially different from those expressed or implied by such forward-looking information, including but not limited to risks related to: exploration and mining risks, competition from competitors with greater capital; the Company's lack of experience with respect to development-stage mining operations; fluctuations in metal prices; uninsured risks; environmental and other regulatory requirements; exploration, mining and other licences; the Company's future payment obligations; potential disputes with respect to the Company's title to, and the area of, its mining concessions; the Company's dependence on its ability to obtain sufficient financing in the future; the Company's dependence on its relationships with third parties; the Company's joint ventures; the potential of currency fluctuations and political or economic instability in countries in which the Company operates; currency exchange fluctuations; the Company's ability to manage its growth effectively; the trading market for the ordinary shares of the Company; uncertainty with respect to the Company's plans to continue to develop its operations and new projects; the Company's dependence on key personnel; possible conflicts of interest of directors and officers of the Company, and various risks associated with the legal and

regulatory framework within which the Company operates.


26 Dover Street, London, W1S 4LY . T-44 (0) 207 763 7157 . [email protected] . www.horizonteminerals.com

Although management of the Company has attempted to identify important factors that could cause actual results to differ materially from those contained in forward-looking information, there may be other factors that cause results not to be as anticipated, estimated or intended. There can be no assurance that such statements will prove

to be accurate, as actual results and future events could differ materially from those anticipated in such statements.


26 Dover Street, London, W1S 4LY . T-44 (0) 207 763 7157 . [email protected] . www.horizonteminerals.com

Read the rest of the article at www.noodls.com
Data and Statistics for these countries : Brazil | All
Gold and Silver Prices for these countries : Brazil | All

Horizonte Minerals Plc.

CODE : HZM.L
ISIN : GB00B11DNM70
Follow and Invest
Add to watch list Add to your portfolio Add or edit a note
Add Alert Add to Watchlists Add to Portfolio Add Note
ProfileMarket
Indicators
VALUE :
Projects & res.
Press
releases
Annual
report
RISK :
Asset profile
Contact Cpy

Horizonte Min. is a nickel exploration company based in United kingdom.

Horizonte Min. holds various exploration projects in Brazil and in Peru.

Its main exploration properties are TANGARA, LONTRA and ARAGUAIA BRAZIL in Brazil.

Horizonte Min. is listed in Canada and in United Kingdom. Its market capitalisation is GBX 644.6 millions as of today (US$ 752.5 millions, € 703.3 millions).

Its stock quote reached its highest recent level on November 18, 2022 at GBX 99.00, and its lowest recent point on April 26, 2024 at GBX 0.45.

Horizonte Min. has 1 432 521 800 shares outstanding.

Your feedback is appreciated, please leave a comment or rate this article.
Rate : Average note :0 (0 vote) View Top rated
 
Annual reports of Horizonte Minerals Plc.
2007 annual report
Project news of Horizonte Minerals Plc.
7/26/2016(Araguaia Brazil)awarded three new concession areas at Araguaia - the next ma...
9/28/2015Horizonte consolidates Araguaia nickel project through acqui...
7/29/2013Horizonte Minerals awards Pre-Feasibility Study Contract to ...
6/11/2013Horizonte Minerals: Successfully raises =A33.08M to fund Ara...
5/22/2013Horizonte Minerals Plc: Completion of met testing at Araguai...
2/7/2012completes acquisition of 100% of Vila Oito and Floresta Nick...
2/21/2011(Araguaia Brazil)Drilling returns 15.9 metres grading 1.56% Nickel from the A...
Corporate news of Horizonte Minerals Plc.
8/2/2016Glencore Final Closing
7/26/2016Three New Concession Areas
6/15/20166 Monthly Block Listing Return
6/8/2016Award of LP
5/11/2016Q1 Results Press release
4/21/2016AGM voting results
3/22/2016Mailing of annual disclosures
10/29/2015Horizonte Minerals plc - Notice of General Meeting of Shareh...
10/28/2015Notice of Meeting
10/14/2015Placing Update
10/9/2015Horizonte Minerals Plc: Placing Update
10/8/2015Tranche 2 Receipt
10/1/2015Private Placement
9/28/2015Director share purchase
9/27/2015Glencore transaction
9/27/2015HZM Presentation Q3 2015
9/13/2015Concession Areas
8/13/2015Interim Financial Statements June 2015
4/16/2015Drill Results
4/16/2015New High Grade Drill Results from Infill Mineral Resource Dr...
4/1/2015AGM Results
3/26/2015AGM & Presentation
3/9/2015Pilot Plant 1st Stage
2/24/20152014 Annual Results
2/1/2015Public Hearing
1/25/2015Operations Update
11/14/2014Q3 Results
10/28/2014TR1 - Notification
7/23/2014Horizonte announces filing in Canada of financial statements
6/19/2014Social Environmental Impact Assesment Completed and Filed wi...
2/20/2014Horizonte Minerals Final Results highlight major milestones ...
8/14/2013Horizonte Minerals Interim Results highlight significant pro...
3/14/2013Northland Capital and Fox Davies notes on Horizonte Minerals...
2/22/2013Horizonte Minerals: Final Results - Araguaia continues to be...
6/16/2011 Listing on Toronto Stock Exchange
6/8/2011Horizonte Minerals plc - Bill Fisher Appointed to the Board ...
10/8/2007Signs Option Agreement - Mara Rosa Gold Project in Brazil
9/25/2007Positive drill results from its Tangara gold project in Braz...
7/17/2007raises £2.19 million - develop resource projects in Brazil a...
6/12/2007Defines five new gold targets
4/30/2007Preliminary Results
4/3/2007acquires Nickel Project in Brazil
Comments closed
 
Latest comment posted for this article
Be the first to comment
Add your comment
LSE (HZM.L)TORONTO (HZM.TO)
0.450-2.17%0.010+0.00%
LSE
GBX 0.450
04/26 17:35 -0.010
-2.17%
Prev close Open
0.460 0.460
Low High
0.406 0.460
Year l/h YTD var.
0.390 -  18.00 -96.00%
52 week l/h 52 week var.
0.390 -  172.00 -99.68%
Volume 1 month var.
4,156,473 -70.00%
24hGold TrendPower© : 9
Produces
Develops
Explores for
 
 
 
Analyse
Interactive chart Add to compare
Interactive
chart
Print Compare Export
You must be logged in to use the porfolio and watchlists (free)
Top Newsreleases
MOST READ
Annual variation
DateVariationHighLow
2024-99.66%
2023-11.26%172.00126.20
20222168.52%99.00100.00
2021-11.84%9.825.80
202093.42%8.001.33
 
5 years chart
 
3 months chart
 
3 months volume chart
 
 
Mining Company News
Plymouth Minerals LTDPLH.AX
Plymouth Minerals Intersects Further High Grade Potash in Drilling at Banio Potash Project - Plannin
AU$ 0.12-8.00%Trend Power :
Santos(Ngas-Oil)STO.AX
announces expected non-cash impairment
AU$ 7.70-0.65%Trend Power :
Oceana Gold(Au)OGC.AX
RELEASES NEW TECHNICAL REPORT FOR THE HAILE GOLD MINE
AU$ 2.20+0.00%Trend Power :
Western Areas NL(Au-Ni-Pl)WSA.AX
Advance Notice - Full Year Results Conference Call
AU$ 3.86+0.00%Trend Power :
Canadian Zinc(Ag-Au-Cu)CZN.TO
Reports Financial Results for Q2 and Provides Project Updates
CA$ 0.12+4.55%Trend Power :
Stornoway Diamond(Gems-Au-Ur)SWY.TO
Second Quarter Results
CA$ 0.02+100.00%Trend Power :
McEwen Mining(Cu-Le-Zn)MUX
TO ACQUIRE BLACK FOX FROM PRIMERO=C2=A0
US$ 12.26+2.68%Trend Power :
Rentech(Coal-Ngas)RTK
Rentech Announces Results for Second Quarter 2017
US$ 0.20-12.28%Trend Power :
KEFIKEFI.L
Reduced Funding Requirement
GBX 0.53-1.87%Trend Power :
Lupaka Gold Corp.LPK.V
Lupaka Gold Receives First Tranche Under Amended Invicta Financing Agreement
CA$ 0.06+0.00%Trend Power :
Imperial(Ag-Au-Cu)III.TO
Closes Bridge Loan Financing
CA$ 2.64-1.86%Trend Power :
Guyana Goldfields(Cu-Zn-Pa)GUY.TO
Reports Second Quarter 2017 Results and Maintains Production Guidance
CA$ 1.84+0.00%Trend Power :
Lundin Mining(Ag-Au-Cu)LUN.TO
d Share Capital and Voting Rights for Lundin Mining
CA$ 16.23+4.04%Trend Power :
Canarc Res.(Au)CCM.TO
Canarc Reports High Grade Gold in Surface Rock Samples at Fondaway Canyon, Nevada
CA$ 0.24+4.26%Trend Power :
Havilah(Cu-Le-Zn)HAV.AX
Q A April 2017 Quarterly Report
AU$ 0.20+2.63%Trend Power :
Uranium Res.(Ur)URRE
Commences Lithium Exploration Drilling at the Columbus Basin Project
US$ 6.80-2.86%Trend Power :
Platinum Group Metals(Au-Cu-Gems)PTM.TO
Platinum Group Metals Ltd. Operational and Strategic Process ...
CA$ 1.88+0.53%Trend Power :
Devon Energy(Ngas-Oil)DVN
Announces $340 Million of Non-Core Asset Sales
US$ 52.71+0.19%Trend Power :
Precision Drilling(Oil)PD-UN.TO
Announces 2017Second Quarter Financial Results
CA$ 8.66-0.35%Trend Power :
Terramin(Ag-Au-Cu)TZN.AX
2nd Quarter Report
AU$ 0.04+5.56%Trend Power :